Planning Application Status

PL2011061




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2011061
EMERGENT CARE PLUS - SUITE ADDITION
Commercial Final Development Plan
Commercial Final Development Plan
Approved
05/16/2011
EMERGENT CARE ASSET HOLDINGS LLC
PRIMARY CARE SUITE ADDITION
Locations
Contacts
EMERGENT CARE ASSET HOLDINGS LLC, Address:2741 NE MCBaine Dr  
THE HOLLIS & MILLER GROUP, Address:1828 WALNUT ST STE 922, Phone:(816) 525-5600  
SCHLAGEL & ASSOC., P.A., Address:14920 W. 107TH STREET  
KCBJ PROPERTIES LEE'S SUMMIT LLC, Address:10701 NALL AVE STE 200  
Reviews
Review Type Outcome Est. Completion Date Completed
Planning Review No Comments 08/04/2011 07/29/2011
Chris Hughey
Fire Review Complete 08/04/2011 07/29/2011
Chris Hughey
Corrective Action Required
07/29/2011

Fire Department-All building and life safety issues shall comply with the 2006 International Fire Code and local amendments as adopted by the City of Lee’s Summit.
Engineering Review No Comments 08/04/2011 07/28/2011
Gene Williams, P.E.
Planning Review Corrections 07/12/2011 07/28/2011
Chris Hughey
Corrective Action Required
07/08/2011

The minor plat for the Lots 5A and 6A of "I-470 Business and Technology Center" has been received and is currently under review by the City. A Temporary or Full Certificate of Occupancy for the Emergent Care Addition will not be issued until the plat has been approved by the City, and recorded at Jackson County.
Corrective Action Required
07/08/2011

The proposed signage on the Final Development Plan sets exceeds the permitted signage quantity and size limitations. A Sign Application shall be submitted for review by the Planning Commission if the applicant would like to pursue the signage as shown. The Sign Application can be found at http://cityofls.net/LinkClick.aspx?fileticket=%2bjM1RL1OuH4%3d&tabid=718 . If you have any questions about the Sign Application process contact Chris Hughey at the above number. Approval of the Final Development Plan does not constitute approval of the proposed signage.
Corrective Action Required
07/08/2011

Staff is supportive of the pre-finished metal panel material for the screening of the new roof-top mounted mechanical units. However, staff requests that the color be changed from red to a color that complements the dominate colors of the building facade.
Engineering Review No Comments 07/12/2011 07/28/2011
Chris Hughey
Traffic Review No Comments 08/04/2011 07/28/2011
Chris Hughey
Fire Review Complete 07/12/2011 07/12/2011
Jim Eden
Code Statement
Corrective Action Required
07/12/2011

Fire Department-All building and life safety issues shall comply with the 2006 International Fire Code and local amendments as adopted by the City of Lee’s Summit.
Traffic Review No Comments 07/12/2011 07/11/2011
Michael Park
Engineering Review Corrections 06/28/2011 06/28/2011
Gene Williams, P.E.
Corrective Action Required
06/28/2011

All engineering review and inspection fees must be paid prior to approval of the Final Development Plan. Please see attached schedule of fees.
Fire Review Complete 06/28/2011 06/28/2011
Jim Eden
Code Statement
Corrective Action Required
06/28/2011

Fire Department-All building and life safety issues shall comply with the 2006 International Fire Code and local amendments as adopted by the City of Lee’s Summit.
Planning Review Corrections 06/28/2011 06/27/2011
Chris Hughey
Corrective Action Required
06/27/2011

The minor plat for the Lots 5A and 6A of "I-470 Business and Technology Center" has been received and is currently under review by the City. A Temporary or Full Certificate of Occupancy for the Emergent Care Addition will not be issued until the plat has been approved by the City, and recorded at Jackson County.
Corrective Action Required
06/27/2011

Provide an example of the "pre-finished metal wall panel system" shown on sheet A2 with color photos.
Traffic Review No Comments 06/28/2011 06/22/2011
Michael Park
Fire Review Complete 05/31/2011 06/01/2011
Jim Eden
Code Statement
Corrective Action Required
06/01/2011

Fire Department-All building and life safety issues shall comply with the 2006 International Fire Code and local amendments as adopted by the City of Lee’s Summit.
Imposed Loads
Corrective Action Required
06/01/2011

Fire Department- IFC 503.2.3 Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Planning Review Corrections 06/01/2011
Chris Hughey
Corrective Action Required
05/31/2011

Lots 5 and 6 of "I-470 Business and Technology Center" shall be replated, approved by the City, and recoreded at Jackson County prior to the approval of the Final Development Plan.
Corrective Action Required
06/01/2011

All new evergreen trees shall have a minimum height of 8 feet at the time of planting and all deciduous trees shall have a minimum caliper of 3 inches at the time of planting. Correct the plant schedule accordingly.
Corrective Action Required
06/01/2011

Add a note stating that all parking lot screening shrubbery (along NE McBaine Dr.) shall have a minimum height of 2.5 feet at the time of planting.
Corrective Action Required
06/01/2011

Incorporate the footcandles of the wall mounted light fixtures into the photometric site plan.
Corrective Action Required
06/01/2011

The new pole lights shall use LED light fixtures. Refer to Article 7 of the City's Unified Development Ordinance (UDO).
Corrective Action Required
06/01/2011

Provide the manufacturer's specification sheets for the roof mounted mechanical units.
Engineering Review Corrections 05/31/2011 05/31/2011
Tony Reames
Corrective Action Required
05/31/2011

A sealed Engineer’s Opinion of Probable Construction Costs should accompany your final submittal copies. Public Works’ review and inspection fee is based on that cost. The following items, both materials and installation, should be included in the itemized estimate • Any water line larger than 2” in diameter, valves, hydrants, and backflow preventer with vault, if outside the building • All storm water piping 6” or larger, structures, and detention/retention facilities • All grading for detention/retention ponds • All sanitary sewer manholes and piping between manholes, including private mains • The connection of the building sewer stub to the public main • All public infrastructure, both onsite and offsite • All private street construction, excluding parking lots, drive approaches and sidewalks • All erosion control devices
Traffic Review No Comments 05/31/2011 05/27/2011
Michael Park
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Final Development Plan fee $600.00 $600.00 Paid 05/16/2011
Outstanding Fees Amount Paid Owing Date Paid


$0.00
Hearings
Title Location Date Time
Documents & Images
Date Uploaded File Type Document Name
05/16/2011 Letter Admin Route Sheet FDP
06/01/2011 Letter Applicant Letter (FDP)
06/21/2011 Letter Admin Re-Route FDP
06/28/2011 Letter ENGINEERING PLAN REVIEW FEE / INSPECTION FEE
06/30/2011 Letter Applicant Letter (FDP)
07/28/2011 Letter Admin Re-Route FDP
07/28/2011 Letter Approval Letter (Administrative)
07/28/2011 Letter Approval Letter (Administrative)
06/28/2013 Letter Applicant Letter - FDP (DFDP)
06/28/2013 Letter Applicant Letter - FDP (DFDP)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home