Permit Application Status

PRSUBD20250004


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSUBD20250004
Public Infrastructure
Issued
PREMIER RE OF LEES SUMMIT LLC
DEVELOPMENT COMPLETE
Hyundai - Public sanitary sewer plans, Street improvements, and Traffic signal
01/02/2025
07/15/2025
Locations
Contacts
Falk Architects, Address:1520 Clay St, Phone:(785) 691-9958  
United Engineering Group, Address:4501 NW Oakley Ave, Ste 232, Phone:(785) 806-2806  
PREMIER RE OF LEES SUMMIT LLC, Address:13040 I 10 SERVICE RD  
MCP Development, Inc. , Address:3501 SW Fairlawn Rd. Ste 70, Phone:(785) 273-3880  
Alyx Griffin - MCP Development, Phone:(785) 260-6233  
WALSER REAL ESTATE LLC, Address:7700 FRANCE AVE S STE 410N  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review - Sanitary Approved with Conditions 02/28/2025 02/27/2025
Gene Williams, P.E.
Miscellaneous Correction
Resolved
02/27/2025

Manhole MH1 does not have enough fall. Minimum fall is 0.50 feet at skewed angles. Recommend 0.60 feet to acccount for construction tolerance. Correction required.
Miscellaneous Correction
Resolved
02/27/2025

Provide a callout of the existing City manhole #22-098. Correction required.
Miscellaneous Correction
Resolved
02/27/2025

Addtional fall is required (see comment #1 above) at the existing City manhole 22-098. Re-design the incoming pipe to achieve the minimum fall of 0.50 feet, with 0.60 feet recommended to account for construction tolerance. Correction required.
Miscellaneous Correction
Resolved
02/27/2025

Cost estimate for all work shown within the plans is required prior to formal approval. Informational comment.
Miscellaneous Correction
Resolved
02/27/2025

MDNR construction permit shall not be required due to length being less than 1000 feet. Informational comment.
DE Engineers Estimate
Corrective Action Required
02/27/2025

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $3,623.70
DE Contact Field Eng. Inspector
Corrective Action Required
02/27/2025

Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to schedule a project coordination meeting with the assigned Field Engineering Inspector.
DE Future Repair Work
Corrective Action Required
02/27/2025

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
DE Wetland or Jurisdictional Waterway
Corrective Action Required
02/27/2025

The applicant shall provide either proper documentation that no wetlands or jurisdictional waterways exist on the subject property or copies of all required documentation and / or permits associated with the wetland or jurisdictional waterway prior to approval of any final development or associated engineering plans.
Miscellaneous Correction
Corrective Action Required
02/27/2025

No MDNR construction permit shall be required for the sanitary sewer extension due to the length being less than 1000 feet. Informational comment.
Engineering Review - Sanitary Corrections 01/16/2025 01/16/2025
Gene Williams, P.E.
Miscellaneous Correction
Corrective Action Required
01/16/2025

Manhole MH1 does not have enough fall. Minimum fall is 0.50 feet at skewed angles. Recommend 0.60 feet to acccount for construction tolerance. Correction required.
Miscellaneous Correction
Corrective Action Required
01/16/2025

Provide a callout of the existing City manhole #22-098. Correction required.
Miscellaneous Correction
Corrective Action Required
01/16/2025

Addtional fall is required (see comment #1 above) at the existing City manhole 22-098. Re-design the incoming pipe to achieve the minimum fall of 0.50 feet, with 0.60 feet recommended to account for construction tolerance. Correction required.
Miscellaneous Correction
Corrective Action Required
01/16/2025

Cost estimate for all work shown within the plans is required prior to formal approval. Informational comment.
Miscellaneous Correction
Corrective Action Required
01/16/2025

MDNR construction permit shall not be required due to length being less than 1000 feet. Informational comment.
Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Insp Fees $3,023.70 $3,023.70 Paid 07/14/2025
Water Test Fee $600.00 $600.00 Paid 07/14/2025
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Grading/Excavation/Fill Inspection Pending
Punch List Inspection Pending
Erosion Control Inspection Pending
Site Visit Pending
Misc
Informational
01/21/2026
1/21/26 Wednesday JMJ (MCP Group, Design Pro) Contractor is waiting for the completion of sanitary camera, and testing shutting water main for tie-in.
Sanitary Sewer Construction Inspection Partial 11/12/2025 11/12/2025 11/12/2025
Misc
Informational
11/12/2025
11/12/25 Wednesday JMJ (Sub. Pro Design) Contractor excavated existing sanitary manhole approximately 15' plus fee. Manhole will be cored into tomorrow @ 8:00AM 8" sanitary SDR-26 line will tie into existing manhole. Contractor is still trying to ID conduit line that are in the surrounding area.
Sanitary Sewer Construction Inspection Partial 11/13/2025
Misc
Informational
11/12/2025
11/12/25 Wednesday JMJ (Sub. Pro Design) Contractor excavated existing sanitary manhole approximately 15' plus fee. Manhole will be cored into tomorrow @ 8:00AM 8" sanitary SDR-26 line will tie into existing manhole. Contractor is still trying to ID conduit line that are in the surrounding area. 11/13/25 Thursday JMJ (Sub. Pro Design) Contractor installed approximately 60' of 8" sanitary SDR-26 from existing to newly installed sanitary manhole. see C101
Sanitary Sewer Construction Inspection Partial 11/17/2025 11/17/2025 11/17/2025
Misc
Informational
11/13/2025
11/12/25 Wednesday JMJ (Sub. Pro Design) Contractor excavated existing sanitary manhole approximately 15' plus fee. Manhole will be cored into tomorrow @ 8:00AM 8" sanitary SDR-26 line will tie into existing manhole. Contractor is still trying to ID conduit line that are in the surrounding area. 11/13/25 Thursday JMJ (Sub. Pro Design) Contractor installed approximately 60' of 8" sanitary SDR-26 from existing to newly installed sanitary manhole. see C101 11/17/25 Monday JMJ (Sub. Pro Design) Contractor installed approximately 84' of 8" sanitary SDR-26 on 11/14/25 Friday and backfilled excavation. Contractor continued to install 8" sanitary SDR-26.
Sanitary Sewer Construction Inspection Partial 11/18/2025 11/18/2025 11/18/2025
Misc
Informational
11/17/2025
11/12/25 Wednesday JMJ (Sub. Pro Design) Contractor excavated existing sanitary manhole approximately 15' plus fee. Manhole will be cored into tomorrow @ 8:00AM 8" sanitary SDR-26 line will tie into existing manhole. Contractor is still trying to ID conduit line that are in the surrounding area. 11/13/25 Thursday JMJ (Sub. Pro Design) Contractor installed approximately 60' of 8" sanitary SDR-26 from existing to newly installed sanitary manhole. see C101 11/17/25 Monday JMJ (Sub. Pro Design) Contractor installed approximately 84' of 8" sanitary SDR-26 on 11/14/25 Friday and backfilled excavation. Contractor continued to install 8" sanitary SDR-26. 11/18/25 Tuesday JMJ (Sub. Pro Design) Contractor installed approximately 140' of SDR-26 sanitary sewer pipe. The base of the sanitary manhole was set today.
Sanitary Sewer Construction Inspection Partial 11/19/2025 11/19/2025 11/19/2025
Misc
Informational
11/18/2025
11/12/25 Wednesday JMJ (Sub. Pro Design) Contractor excavated existing sanitary manhole approximately 15' plus fee. Manhole will be cored into tomorrow @ 8:00AM 8" sanitary SDR-26 line will tie into existing manhole. Contractor is still trying to ID conduit line that are in the surrounding area. 11/13/25 Thursday JMJ (Sub. Pro Design) Contractor installed approximately 60' of 8" sanitary SDR-26 from existing to newly installed sanitary manhole. see C101 11/17/25 Monday JMJ (Sub. Pro Design) Contractor installed approximately 84' of 8" sanitary SDR-26 on 11/14/25 Friday and backfilled excavation. Contractor continued to install 8" sanitary SDR-26. 11/18/25 Tuesday JMJ (Sub. Pro Design) Contractor installed approximately 140' of SDR-26 sanitary sewer pipe. The base of the sanitary manhole was set today. 11/19/25 Wednesday JMJ (Sub. Pro Design) Contractor finished laying 8" pipe on the public sanitary & manholes bases also the first two manhole lids were placed. Contractor plans to pour inverts and collars tomorrow.
Sanitary Sewer Construction Inspection Partial 11/20/2025
Misc
Informational
11/19/2025
11/12/25 Wednesday JMJ (Sub. Pro Design) Contractor excavated existing sanitary manhole approximately 15' plus fee. Manhole will be cored into tomorrow @ 8:00AM 8" sanitary SDR-26 line will tie into existing manhole. Contractor is still trying to ID conduit line that are in the surrounding area. 11/13/25 Thursday JMJ (Sub. Pro Design) Contractor installed approximately 60' of 8" sanitary SDR-26 from existing to newly installed sanitary manhole. see C101 11/17/25 Monday JMJ (Sub. Pro Design) Contractor installed approximately 84' of 8" sanitary SDR-26 on 11/14/25 Friday and backfilled excavation. Contractor continued to install 8" sanitary SDR-26. 11/18/25 Tuesday JMJ (Sub. Pro Design) Contractor installed approximately 140' of SDR-26 sanitary sewer pipe. The base of the sanitary manhole was set today. 11/19/25 Wednesday JMJ (Sub. Pro Design) Contractor finished laying 8" pipe on the public sanitary & manholes bases also the first two manhole lids were placed. Contractor plans to pour inverts and collars tomorrow. 11/20/25 Thursday JMJ (Sub. Pro Design) Contractor continued construct the manholes. Inverts were poured for the manholes on newly installed sanitary mains. Rubber boots were used on all manholes when connecting to sanitary pipe line.
Sanitary Sewer Construction Inspection Partial 11/24/2025 11/24/2025 11/24/2025
Misc
Informational
11/20/2025
11/12/25 Wednesday JMJ (Sub. Pro Design) Contractor excavated existing sanitary manhole approximately 15' plus fee. Manhole will be cored into tomorrow @ 8:00AM 8" sanitary SDR-26 line will tie into existing manhole. Contractor is still trying to ID conduit line that are in the surrounding area. 11/13/25 Thursday JMJ (Sub. Pro Design) Contractor installed approximately 60' of 8" sanitary SDR-26 from existing to newly installed sanitary manhole. see C101 11/17/25 Monday JMJ (Sub. Pro Design) Contractor installed approximately 84' of 8" sanitary SDR-26 on 11/14/25 Friday and backfilled excavation. Contractor continued to install 8" sanitary SDR-26. 11/18/25 Tuesday JMJ (Sub. Pro Design) Contractor installed approximately 140' of SDR-26 sanitary sewer pipe. The base of the sanitary manhole was set today. 11/19/25 Wednesday JMJ (Sub. Pro Design) Contractor finished laying 8" pipe on the public sanitary & manholes bases also the first two manhole lids were placed. Contractor plans to pour inverts and collars tomorrow. 11/20/25 Thursday JMJ (Sub. Pro Design) Contractor continued construct the manholes. Inverts were poured for the manholes on newly installed sanitary mains. Rubber boots were used on all manholes when connecting to sanitary pipe line. 11/24/25 Monday JMJ (Sub. Pro Design) The construction of the underground sanitary sewer main was backfilled completely and the 30 day before testing has began (Sub. Pro Design) (Sub. Pro Design)11/20/25 Thursday.
Sanitary Sewer - Mandrel Partial 12/22/2025 12/22/2025 12/22/2025
Misc
Informational
12/22/2025
12/22/25 Monday JMJ (Gen. MCP, Sub. Pro Design Contractors ) The mandrel successfully through MH3 to MH2, MH2 to MH4, MH4 to MH1, MH1 to Existing MH.
Sanitary Sewer - Air Test Partial 12/22/2025 12/22/2025 12/22/2025
Misc
Informational
12/22/2025
12/22/25 Monday JMJ (Gen. MCP, Sub. Pro Design Contractor) Air testing 0+00 to 10+56, 10+56 to 12+76, 12+76 to 14+64, & 14+64 to 16+84 sanitary sewer passed on the public line.
Sanitary Sewer - Vacuum Partial 12/22/2025 12/22/2025 12/22/2025
Misc
Informational
12/22/2025
12/22/25 Monday JMJ (Gen. MCP, Sub. Pro Design Contractor) MH1, MH4, MH2, & MH3 passed sanitary sewer-vacuum test.
Site Visit Partial 1/21/2026 1/21/2026 01/21/2026
Misc
Informational
01/21/2026
1/21/26 Wednesday JMJ (MCP Group, Design Pro) Contractor is waiting for the completion of sanitary camera, and testing shutting water main for tie-in.
Sanitary Sewer Construction Inspection Partial 2/5/2026 2/5/2026 02/05/2026
Misc
Informational
11/24/2025
11/12/25 Wednesday JMJ (Sub. Pro Design) Contractor excavated existing sanitary manhole approximately 15' plus fee. Manhole will be cored into tomorrow @ 8:00AM 8" sanitary SDR-26 line will tie into existing manhole. Contractor is still trying to ID conduit line that are in the surrounding area. 11/13/25 Thursday JMJ (Sub. Pro Design) Contractor installed approximately 60' of 8" sanitary SDR-26 from existing to newly installed sanitary manhole. see C101 11/17/25 Monday JMJ (Sub. Pro Design) Contractor installed approximately 84' of 8" sanitary SDR-26 on 11/14/25 Friday and backfilled excavation. Contractor continued to install 8" sanitary SDR-26. 11/18/25 Tuesday JMJ (Sub. Pro Design) Contractor installed approximately 140' of SDR-26 sanitary sewer pipe. The base of the sanitary manhole was set today. 11/19/25 Wednesday JMJ (Sub. Pro Design) Contractor finished laying 8" pipe on the public sanitary & manholes bases also the first two manhole lids were placed. Contractor plans to pour inverts and collars tomorrow. 11/20/25 Thursday JMJ (Sub. Pro Design) Contractor continued construct the manholes. Inverts were poured for the manholes on newly installed sanitary mains. Rubber boots were used on all manholes when connecting to sanitary pipe line. 11/24/25 Monday JMJ (Sub. Pro Design) The construction of the underground sanitary sewer main was backfilled completely and the 30 day before testing has began (Sub. Pro Design) (Sub. Pro Design)11/20/25 Thursday. 02/05/26 Thursday JMJ (Sub. Pro Design) The cut and grinded down the sewer pipe. Water was called to com and re-inspect sanitary line.
Documents & Images
Date Uploaded File Type Document Name
01/02/2025 Plans Sanitary Sewer plans_Rev 0_PRSUBD20240004
01/21/2025 Letter SUBD Comment Letter_Rev 0_PRSUBD20250004
02/13/2025 Letter Response to Comments_Rev 0_PRSUB20250004
02/13/2025 Plans Sanitary Sewer plans_Rev 1_PRSUBD20250004
02/13/2025 Engineers Estimate Cost Estimate_Rev 1_PRSUBD20250004
02/27/2025 Activity Document Copy of FeeWorksheetSAN
06/09/2025 Approved Plans APPROVED PLANS
07/14/2025 Receipt Receipt for transaction:2025-005480
07/15/2025 Letter DE-Permit
06/09/2025 Approved Plans Approved traffic plans_Hyundai Premier Auto Outlet_PL2025001_6.9.2025
11/12/2025 Letter INSPECTION SUMMARY
11/13/2025 Letter INSPECTION SUMMARY
11/17/2025 Letter INSPECTION SUMMARY
11/18/2025 Letter INSPECTION SUMMARY
11/19/2025 Letter INSPECTION SUMMARY
11/24/2025 Letter INSPECTION SUMMARY
12/22/2025 Letter INSPECTION SUMMARY
12/22/2025 Letter INSPECTION SUMMARY
12/22/2025 Letter INSPECTION SUMMARY
01/21/2026 Letter INSPECTION SUMMARY
02/05/2026 Letter SUBD Comment Letter
02/05/2026 Letter INSPECTION SUMMARY
02/27/2026 Letter INSPECTION SUMMARY
02/27/2026 Letter INSPECTION SUMMARY
02/27/2026 Letter INSPECTION SUMMARY
02/27/2026 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home