| Review Type |
Outcome |
Est. Completion Date |
Completed |
|
Engineering Review - Sanitary
|
Approved with Conditions
|
02/28/2025
|
02/27/2025
|
|
|
Gene Williams, P.E.
|
|
|
Miscellaneous Correction
Manhole MH1 does not have enough fall. Minimum fall is 0.50 feet at skewed angles. Recommend 0.60 feet to acccount for construction tolerance. Correction required.
|
|
|
Miscellaneous Correction
Provide a callout of the existing City manhole #22-098. Correction required.
|
|
|
Miscellaneous Correction
Addtional fall is required (see comment #1 above) at the existing City manhole 22-098. Re-design the incoming pipe to achieve the minimum fall of 0.50 feet, with 0.60 feet recommended to account for construction tolerance. Correction required.
|
|
|
Miscellaneous Correction
Cost estimate for all work shown within the plans is required prior to formal approval. Informational comment.
|
|
|
Miscellaneous Correction
MDNR construction permit shall not be required due to length being less than 1000 feet. Informational comment.
|
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $3,623.70
|
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to schedule a project coordination meeting with the assigned Field Engineering Inspector.
|
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
|
DE Wetland or Jurisdictional Waterway
Corrective Action Required
The applicant shall provide either proper documentation that no wetlands or jurisdictional waterways exist on the subject property or copies of all required documentation and / or permits associated with the wetland or jurisdictional waterway prior to approval of any final development or associated engineering plans.
|
|
|
Miscellaneous Correction
Corrective Action Required
No MDNR construction permit shall be required for the sanitary sewer extension due to the length being less than 1000 feet. Informational comment.
|
|
|
|
|
Engineering Review - Sanitary
|
Corrections
|
01/16/2025
|
01/16/2025
|
|
|
Gene Williams, P.E.
|
|
|
Miscellaneous Correction
Corrective Action Required
Manhole MH1 does not have enough fall. Minimum fall is 0.50 feet at skewed angles. Recommend 0.60 feet to acccount for construction tolerance. Correction required.
|
|
|
Miscellaneous Correction
Corrective Action Required
Provide a callout of the existing City manhole #22-098. Correction required.
|
|
|
Miscellaneous Correction
Corrective Action Required
Addtional fall is required (see comment #1 above) at the existing City manhole 22-098. Re-design the incoming pipe to achieve the minimum fall of 0.50 feet, with 0.60 feet recommended to account for construction tolerance. Correction required.
|
|
|
Miscellaneous Correction
Corrective Action Required
Cost estimate for all work shown within the plans is required prior to formal approval. Informational comment.
|
|
|
Miscellaneous Correction
Corrective Action Required
MDNR construction permit shall not be required due to length being less than 1000 feet. Informational comment.
|
|
|
|