Permit Application Status

PRSUBD20232901


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSUBD20232901
Public Infrastructure
Issued
DEVELOPMENT COMPLETE
REUNION AT BLACKWELL - PUBLIC WATER, SANITARY STREET AND STORM ASSOCIATED WITH THIS DEVELOPMENT - PLANNING APPLICATION PL2023044, PL2023045, PL2023046 AND PL2023047
06/20/2023
10/16/2024
Locations
Contacts
Selby Excavating LLC, Address:16212 Cameron Road  
Jake McClung, Address:16212 Cameron Road, Phone:(816) 820-0956  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 06/20/2023 11/15/2023
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
9110068-Storm Fee $9,624.30 $9,624.30 Paid 10/16/2024
9110071-Site Grading Fee $234.00 $234.00 Paid 10/15/2024
9110072-Water Test Fee $1,200.00 $1,200.00 Paid 11/14/2023
9110081-Paved Surface Inspection Fee $16,901.94 $16,901.94 Paid 10/15/2024
91100C8-Sanitary Sewer Insp Fees $7,662.00 $7,662.00 Paid 06/05/2024
91100C9-Water Insp Fee $9,985.50 $9,985.50 Paid 11/14/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Pending
Sanitary Sewer Construction Inspection Pending
Misc
Informational
07/16/2024
7-16-24 BR Contractor (Selby Excavation) installed 40' of 8'' PVC pipe from MH A-7 before running into heavy rock.
Water Line - Construction Inspection Pending
Misc
Informational
09/18/2024
9-18-24 BR Contractor (Selby Excavation) installed 200' of 8'' water main on line F from Sta. 0+00 - Sta. 2+00.
Grading/Excavation/Fill Inspection Pending
Water Line - Construction Inspection Pending
Sanitary - Material Verification Pending
Sanitary Sewer Construction Inspection Pending
Pavement-Proof Roll Pending
Pavement-Surface Pending
Install Street and Stop Signs Pending
Pavement-Curb Construction Pending
Storm Sewer Construction Inspection Pending
Sanitary Sewer Construction Inspection Pending
Pavement-Stabilized Subgrade Pending
Misc
Informational
11/14/2024
11-14-24 BR Contractor installed 9'' subgrade aggregate base on Lindberg Lane.
Sanitary Sewer - Mandrel Pending
Misc
Informational
12/02/2024
12-2-24 BR Contractor preformed mandrel test on MH A-7, MH A-1, MH A-2, MH A-3, MH A-4 Pass.
Sanitary Sewer - Air Test Pending
Misc
Informational
12/02/2024
12-2-24 BR Contractor preformed air test on MH A-7 / MH A-1, MH A-1 / MH A-2, MH A-2 / MH A-3, MH A-3 / MH A-4. Pass
Sanitary Sewer - Vacuum Pending
Misc
Informational
12/13/2024
12-11-24 BR Contractor preformed vacuum test on MH A-5, MH A-4, MH C-1, MH C-2, MH G-1, MH C-3 pass. 12/13/24 Friday JMJ (Selby) MH-A10 passed around 12:00PM.
Pavement-Stabilized Subgrade Partial 11/14/2024 11/14/2024 11/14/2024
Misc
Informational
11/14/2024
11-14-24 BR Contractor installed 9'' subgrade aggregate base on Lindberg Lane.
Sanitary Sewer - Air Test Partial 12/2/2024 12/2/2024 12/02/2024
Misc
Informational
12/02/2024
12-2-24 BR Contractor preformed air test on MH A-7 / MH A-1, MH A-1 / MH A-2, MH A-2 / MH A-3, MH A-3 / MH A-4. Pass
Water Line - Construction Inspection Partial 12/3/2024 12/3/2024 12/03/2024
Misc
Informational
09/18/2024
9-18-24 BR Contractor (Selby Excavation) installed 200' of 8'' water main on line F from Sta. 0+00 - Sta. 2+00. 9-19-24 BR Contractor (Selby Excavation) installed 270' of 8'' water main on line F from Sta. 2+00 - Sta. 5+00. 9-23-24 BR Contractor (Selby Excavation) installed 200' of 8'' water main on line F from Sta. 5+00 - Sta. 7+00. 9-24-24 BR Contractor (Selby Excavation) installed 300' of 8'' water main on line F from Sta. 7+00 - Sta. 11+00. 9-25-24 BR Contractor (Selby Excavation) installed 350' of 8'' water main on line F from Sta. 11+00 - Sta. 14+30. 10-2-24 BR Contractor (Selby Excavation) installed 500' of 8'' water main on line B from Sta. 0+00 - Sta. 5+00. From Sta. 0+00 - Sta. 2+00 contractor didn't install any bends do to water main is in line with gps coordinates. 10-3-24 BR Contractor (Selby Excavation) installed 300' of 8'' water main on line B from Sta. 5+00 - Sta. 7+50. 12-3-24 BR Contractor (Selby Excavation) installed 300' of 8'' water main on line A to connect to existing 12'' water on SE Wood Lane at STA. 3+00 to STA. 0+00 with fire hydrant assembly installed.
Sanitary Sewer - Vacuum Partial 12/12/2024 12/12/2024 12/12/2024
Misc
Informational
12/12/2024
12-11-24 BR Contractor preformed vacuum test on MH A-5, MH A-4, MH C-1, MH C-2, MH G-1, MH C-3 pass.
Sanitary Sewer - Vacuum Partial 12/13/2024 12/13/2024 12/13/2024
Misc
Informational
12/12/2024
12-11-24 BR Contractor preformed vacuum test on MH A-5, MH A-4, MH C-1, MH C-2, MH G-1, MH C-3 pass. 12/13/24 Friday JMJ (Selby) MH-A10 passed around 12:00PM. MH-A9 pass @ 1:35PM.
Sanitary Sewer - Mandrel Passed 12/2/2024 12/2/2024 01/15/2025
Misc
Informational
12/02/2024
12-2-24 BR Contractor preformed mandrel test on MH A-7, MH A-1, MH A-2, MH A-3, MH A-4 Pass.
Sanitary Sewer Construction Inspection Partial 3/14/2025 3/14/2025 03/14/2025
Misc
Informational
07/16/2024
7-16-24 BR Contractor (Selby Excavation) installed 40' of 8'' PVC pipe from MH A-7 before running into heavy rock. 7-17-24 BR Contractor (Selby Excavation) installed 280' f 8'' PVC pipe from MH A-7 to MH A-1 with MH A-1 structure installed. 7-18-24 BR Contractor (Selby Excavation) installed 220' of 8'' PVC pipe from MH A-1 to MH A-2 with MH A-2 structure installed. 7-19-24 BR Contractor (Selby Excavation) installed 170' of 8'' PVC pipe from MH A-1 to MH A-2 with MH A-2 structure installed. 7-22-24 BR Contractor (Selby Excavation) installed 300' of 8'' PVC pipe from MH A-2 to MH A-4 with MH A-3 & MH A-4 structure installed. 7-24-24 DA Contractor (Selby Excavation) installed 220' of 8'' PVC pipe from MH A-4. 7-25-24 BR Contractor (Selby Excavation) installed 250' of 8'' PVC pipe to MH C-1 with structure installed. 7-29-24 BR Contractor (Selby Excavation) installed 230' of 8'' PVC pipe from MH C-1 heading to MH C-2. 7-30-24 DA Contractor (Selby Excavation) installed 220' of 8'' PVC pipe from MH C-1 to MH C-2 with structure installed. 7-31-24 DA Contractor (Selby Excavation) installed 200' of 8'' PVC pipe from MH C-2 to MH G-1. 8-1-24 BR Contractor (Selby Excavation) installed 100' of service wyes. 8-7-24 JMJ Contractor (Selby Excavation) installed 220' of 8" PVC pipe and MH C-3. 6 service laterals were installed between MH A-6 & MH A-5, 2 more service laterals between MH A-5 and MH A-4. CFS test was onsite doing compaction testing. 8-9-24 BR Contractor (Selby Excavation) installed 6 service laterals on MH G-1 thru MH C-3. 2-6-25 BR Contractor excavating on 8'' PVC pipe between MH A-8 & MH A-7 to remove 10% sag in pipe do to sewer bond inspection. 2-10-25 BR Contractor excavated service wye between MH A-7 & MH A-7 to lowering tap to 45% do to tap is to high. 2-11-25 BR Contractor excavated service wye between MH A-2 & MH A-3, MH A-3 & MH A-4 to raise tap to 45% do to tap is to low. 3-14-25 BR Contractor fix 2 out 6 Manholes adjustment rings.
Documents & Images
Date Uploaded File Type Document Name
11/14/2023 Receipt Receipt for transaction:2023-008496
09/26/2023 Activity Document WATER FeeWorksheetReunionBlackwellWATER
09/19/2023 Engineers Estimate 22-097 - REUNION AT BLACKWELL - PUBLIC WATER - EOPC 2023_09_06
11/15/2023 Letter SUBD Building Permit
01/17/2024 Approved Plans APPROVED STAMPED PLANS - REUNION AT BLACKWELL PUBLIC SANITARY
06/05/2024 Receipt Receipt for transaction:2024-004408
11/14/2023 Approved Plans STAMPED PLANS - REUNION AT BLACKWELL PUBLIC WATER
06/05/2024 Letter DE-Permit
07/16/2024 Letter INSPECTION SUMMARY
07/17/2024 Letter INSPECTION SUMMARY
07/17/2024 Letter INSPECTION SUMMARY
07/18/2024 Letter INSPECTION SUMMARY
07/18/2024 Letter INSPECTION SUMMARY
07/19/2024 Letter INSPECTION SUMMARY
07/19/2024 Letter INSPECTION SUMMARY
07/22/2024 Letter INSPECTION SUMMARY
07/22/2024 Letter INSPECTION SUMMARY
07/25/2024 Letter INSPECTION SUMMARY
07/25/2024 Letter INSPECTION SUMMARY
07/29/2024 Letter INSPECTION SUMMARY
07/29/2024 Letter INSPECTION SUMMARY
08/01/2024 Letter INSPECTION SUMMARY
08/01/2024 Letter INSPECTION SUMMARY
08/07/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
09/18/2024 Letter INSPECTION SUMMARY
09/19/2024 Letter INSPECTION SUMMARY
09/19/2024 Letter INSPECTION SUMMARY
09/24/2024 Letter INSPECTION SUMMARY
09/24/2024 Letter INSPECTION SUMMARY
09/24/2024 Letter INSPECTION SUMMARY
09/24/2024 Letter INSPECTION SUMMARY
09/25/2024 Letter INSPECTION SUMMARY
09/25/2024 Letter INSPECTION SUMMARY
10/02/2024 Letter INSPECTION SUMMARY
10/02/2024 Letter INSPECTION SUMMARY
10/03/2024 Letter INSPECTION SUMMARY
10/03/2024 Letter INSPECTION SUMMARY
10/15/2024 Receipt Receipt for transaction:2024-008351
10/16/2024 Receipt Receipt for transaction:2024-008396
10/16/2024 Letter SUBD Building Permit
11/14/2024 Letter INSPECTION SUMMARY
12/02/2024 Letter INSPECTION SUMMARY
12/02/2024 Letter INSPECTION SUMMARY
12/03/2024 Letter INSPECTION SUMMARY
12/03/2024 Letter INSPECTION SUMMARY
12/12/2024 Letter INSPECTION SUMMARY
12/13/2024 Letter INSPECTION SUMMARY
01/15/2025 Letter INSPECTION SUMMARY
01/15/2025 Letter INSPECTION SUMMARY
02/06/2025 Letter INSPECTION SUMMARY
02/06/2025 Letter INSPECTION SUMMARY
02/10/2025 Letter INSPECTION SUMMARY
02/10/2025 Letter INSPECTION SUMMARY
02/11/2025 Letter INSPECTION SUMMARY
02/11/2025 Letter INSPECTION SUMMARY
03/14/2025 Letter INSPECTION SUMMARY
03/14/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home