Summary


PRSUBD20202286
Public Infrastructure
Final Acceptance
HUNT MIDWEST REAL ESTATE DEV INC
DEVELOPMENT COMPLETE
Full subdivision development.
08/12/2020
09/17/2020
09/15/2023
Locations
Address
2826 SW HEARTHSTONE PL, LEES SUMMIT, MO 64082

Address
2822 SW HEARTHSTONE PL, LEES SUMMIT, MO 64082

Address
2816 SW HEARTHSTONE PL, LEES SUMMIT, MO 64082

Address
2812 SW HEARTHSTONE PL, LEES SUMMIT, MO 64082

Address
2808 SW HEARTHSTONE PL, LEES SUMMIT, MO 64082

Address
2804 SW HEARTHSTONE PL, LEES SUMMIT, MO 64082

Address
2206 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2202 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2122 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2118 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2114 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2110 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2106 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2102 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2042 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2038 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2034 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2030 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2026 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2022 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2018 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2014 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2010 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2017 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2029 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2033 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2037 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2103 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2107 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2111 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2805 SW HEARTHSTONE PL, LEES SUMMIT, MO 64082

Address
2809 SW HEARTHSTONE PL, LEES SUMMIT, MO 64082

Address
2813 SW HEARTHSTONE PL, LEES SUMMIT, MO 64082

Address
2112 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2108 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2104 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2038 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2034 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2030 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2026 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2022 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2021 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2025 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2029 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2033 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2037 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2103 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2107 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2111 SW HARVEST MOON LN, LEES SUMMIT, MO 64082

Address
2015 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2829 SW HEARTHSTONE PL, LEES SUMMIT, MO 64082

Address
2126 SW RED BARN LN, LEES SUMMIT, MO 64082

Address
2830 SW HEARTHSTONE PL, LEES SUMMIT, MO 64082

Address
2207 SW RED BARN LN, LEES SUMMIT, MO 64082

Property
69200083500000000

Property
69200083400000000

Property
69200083300000000

Property
69200083200000000

Property
69200083100000000

Property
69200083600000000

Property
69200082900000000

Property
69200082800000000

Property
69200081900000000

Property
69200082000000000

Property
69200082100000000

Property
69200082200000000

Property
69200082300000000

Property
69200082400000000

Property
69200082500000000

Property
69200082600000000

Property
69200081800000000

Property
69200081000000000

Property
69200081100000000

Property
69200081200000000

Property
69200081300000000

Property
69200081400000000

Property
69200081500000000

Property
69200081600000000

Property
69200081700000000

Property
69200100200000000

Property
69200100300000000

Property
69200090200000000

Property
69200090300000000

Property
69200090400000000

Property
69200100400000000

Property
69200090100000000

Property
69200100900000000

Property
69200100800000000

Property
69200100700000000

Property
69200100600000000

Property
69200090700000000

Property
69200100500000000

Property
69200090900000000

Property
69200090800000000

Property
69200090600000000

Property
69200090500000000

Property
69200080900000000

Property
69200080800000000

Property
69200080700000000

Property
69200080600000000

Property
69200080500000000

Property
69200080200000000

Property
69200080300000000

Property
69200080400000000

Property
69200100100000000

Property
69200082700000000

Property
69200083700000000

Property
69200083000000000

Property
69200080100000000

Address
2006 SW RED BARN LN, LEES SUMMIT, MO 64082

Contacts
HUNT MIDWEST REAL ESTATE DEV INC, Address:8300 UNDERGROUND DR STE 200  
HUNT MIDWEST REAL EST DEV INC, Address:8300 NE UNDERGROUND DR  
CARDELLO ANGELICA NICOLE, Address:2006 SW RED BARN LN  
AHMED AHMED AHMED IBRAHLM & MOHAMED AHMED MAHA MAHMOUD, Address:2010 SW RED BARN LN  
ZHENG TINGBAO & LI LIN, Address:2014 SW RED BARN LN  
JULY ALYSSA MARIE & MATTHEW MICHAEL, Address:2018 SW RED BARN LN  
SAB CONSTRUCTION LLC, Address:200 NW COMMERCE CT  
BLOCKER WILLIE, Address:2026 SW RED BARN LN  
BAKER STEVEN & GINNETTE, Address:2030 SW RED BARN LN  
VOGEL RICHARD N & KIMBERLY D, Address:2034 SW RED BARN LN  
YANG PENGSUE & THAO CASSANDRA, Address:2038 SW RED BARN LN  
ASPEN HOMEBUILDERS LLC, Address:6618 ROYAL ST STE B  
NELSON LEIANN H & STEVEN F, Address:2102 SW RED BARN LN  
BAHR KYLE MICHEAL & BUTLER ASHLEY LYNN, Address:2106 SW RED BARN LN  
BILES LIVING TRUST DATED 10-21-2020, Address:2110 SW RED BARN LN  
HACHINSKY WADE A, Address:2114 SW RED BARN LN  
ASHTON MICHAEL & LINDA, Address:2118 SW RED BARN LN  
COMO ANTHONY J & JANET L, Address:2122 SW RED BARN LN  
HUNT MIDWEST RESIDENTIAL LLC, Address:8300 NE UNDERGROUND DR STE 100  
WERNSMAN FAMILY TRUST DATED MAY 9, 2022, Address:1049 SW ARGYL ST  
CRAVEN ALEX & TARA, TRUSTEES, Address:2206 SW RED BARN LN  
MAJEED AMJAD & FAZAL SAHMERA, Address:2029 SW RED BARN LN  
DOWELL RYAN & BINGHAM KELSEY, Address:2107 SW RED BARN LN  
WALKER CUSTOM HOMES INC, Address:PO BOX 3194  
COFFEY MICHAEL & SALLY COFFEY, Address:2804 SW HEARTHSTONE PL  
GATLIN MICHAEL A & DANIELLE L, Address:2808 SW HEARTSTONE PL  
BOWLES DUSTIN & JENNIFER, Address:2812 SW HEARTHSTONE PL  
SYLVESTER AUGUSTIN & TONASHA, Address:2816 SW HEARTSTONE PL  
ACCURSO CRAIG, Address:2822 SW HEARTHSTONE PL  
KO EUN SOOK, Address:2826 SW HEARTHSTONE PL  
ULRICH DUSTIN J & MADISON L, Address:2022 SW HARVEST MOON LN  
DAYNA L REIN TRUST DATED 11-29-2017, Address:2026 SW HARVEST MOON LN  
ECHOLS TERANCE L & TERESA M, Address:2030 SW HARVEST MOON LN  
GROFF MICHAEL & JUSTINE, Address:2104 SW HARVEST MOON LN  
BARRY JAY, Address:2112 SW HARVEST MOON LN  
ALUMBAUGH LUCAS R & OLIVIA M, Address:2037 SW HARVEST MOON LN  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 08/12/2020 09/17/2020
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
91100C9-Water Insp Fee $6,388.44 $6,388.44 Paid 09/14/2020
9110072-Water Test Fee $1,200.00 $1,200.00 Paid 09/14/2020
91100C8-Sanitary Sewer Insp Fees $6,377.10 $6,377.10 Paid 09/14/2020
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 09/14/2020
9110068-Storm Fee $6,713.22 $6,713.22 Paid 09/14/2020
9110081-Paved Surface Inspection Fee $9,407.10 $9,407.10 Paid 09/14/2020
9110071-Site Grading Fee $4,574.65 $4,574.65 Paid 09/14/2020
Outstanding Fees Amount Paid Owing Date Paid


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sanitary Sewer Construction Inspection Partial 04/05/2021
Misc
Informational
04/05/2021
Installing sasnitary main. 2 crews working. Will check back with Robert. Talked about compaction testing in roads and trench checks.
Sanitary Sewer Construction Inspection Partial 04/05/2021
Miscellaneous Correction
Informational
04/05/2021
John DiiMauro witnessed the core drill and connection to the existing MH. The contractors have installed MH 1-1, 1-2, and 1-3. They will have a tester out doin g companion test when they backfill.
Sanitary Sewer Construction Inspection Partial 04/06/2021
Miscellaneous Correction
Informational
04/05/2021
John DiiMauro witnessed the core drill and connection to the existing MH. The contractors have installed MH 1-1, 1-2, and 1-3. They will have a tester out doin g companion test when they backfill.
Misc
Informational
04/06/2021
Contractors have hit rock. They have installed wyes between MH 1-2 and 1-3. Installing pipe fron 1-3 to 1-4.
Sanitary Sewer Construction Inspection Partial 04/12/2021
Miscellaneous Correction
Informational
04/06/2021
John DiiMauro witnessed the core drill and connection to the existing MH. The contractors have installed MH 1-1, 1-2, and 1-3. They will have a tester out doin g companion test when they backfill.
Misc
Informational
04/06/2021
Contractors have hit rock. They have installed wyes between MH 1-2 and 1-3. Installing pipe fron 1-3 to 1-4.
Miscellaneous Correction
Partial Correction
04/12/2021
MH 2-1 has been installed. The service lines for 55,56,and 57 have been installed. MH 3-1 has been installed. The service lines between 1-3 and 3-1 have been installed. Line 1 has 2 sticks of pipe installed, they have hit a lot of rock.
Sanitary Sewer Construction Inspection Partial 04/13/2021
Miscellaneous Correction
Informational
04/12/2021
John DiiMauro witnessed the core drill and connection to the existing MH. The contractors have installed MH 1-1, 1-2, and 1-3. They will have a tester out doin g companion test when they backfill.
Misc
Informational
04/12/2021
Contractors have hit rock. They have installed wyes between MH 1-2 and 1-3. Installing pipe fron 1-3 to 1-4.
Miscellaneous Correction
Partial Correction
04/12/2021
MH 2-1 has been installed. The service lines for 55,56,and 57 have been installed. MH 3-1 has been installed. The service lines between 1-3 and 3-1 have been installed. Line 1 has 2 sticks of pipe installed, they have hit a lot of rock.
Miscellaneous Correction
Informational
04/13/2021
Crew is installing service stubs and wyes between MH 1-3 and 1-4. They are working toward MH 1-4.. Hitting rock so not getting much pipe installed.
Sanitary Sewer Construction Inspection Partial 4/14/2021 04/14/2021
Miscellaneous Correction
Informational
04/13/2021
John DiiMauro witnessed the core drill and connection to the existing MH. The contractors have installed MH 1-1, 1-2, and 1-3. They will have a tester out doin g companion test when they backfill.
Misc
Informational
04/13/2021
Contractors have hit rock. They have installed wyes between MH 1-2 and 1-3. Installing pipe fron 1-3 to 1-4.
Miscellaneous Correction
Partial Correction
04/13/2021
MH 2-1 has been installed. The service lines for 55,56,and 57 have been installed. MH 3-1 has been installed. The service lines between 1-3 and 3-1 have been installed. Line 1 has 2 sticks of pipe installed, they have hit a lot of rock.
Miscellaneous Correction
Informational
04/13/2021
Crew is installing service stubs and wyes between MH 1-3 and 1-4. They are working toward MH 1-4.. Hitting rock so not getting much pipe installed.
Misc
Informational
04/14/2021
Redford is working on service line wyes between MH 1-3 and 1-4. They are still hitting rock. I spoke to them about making sure the backfill is in good condition. Compaction tests are going to be done tomorrow. We will be doing them every 50 feet in the road over the maiin and on every service stub.
Sanitary Sewer Construction Inspection Partial 4/15/2021 04/15/2021
Miscellaneous Correction
Informational
04/14/2021
John DiiMauro witnessed the core drill and connection to the existing MH. The contractors have installed MH 1-1, 1-2, and 1-3. They will have a tester out doin g companion test when they backfill.
Misc
Informational
04/14/2021
Contractors have hit rock. They have installed wyes between MH 1-2 and 1-3. Installing pipe fron 1-3 to 1-4.
Miscellaneous Correction
Partial Correction
04/14/2021
MH 2-1 has been installed. The service lines for 55,56,and 57 have been installed. MH 3-1 has been installed. The service lines between 1-3 and 3-1 have been installed. Line 1 has 2 sticks of pipe installed, they have hit a lot of rock.
Miscellaneous Correction
Informational
04/14/2021
Crew is installing service stubs and wyes between MH 1-3 and 1-4. They are working toward MH 1-4.. Hitting rock so not getting much pipe installed.
Misc
Informational
04/14/2021
Redford is working on service line wyes between MH 1-3 and 1-4. They are still hitting rock. I spoke to them about making sure the backfill is in good condition. Compaction tests are going to be done tomorrow. We will be doing them every 50 feet in the road over the maiin and on every service stub.
Misc
Informational
04/15/2021
The compaction test have been put off until next Tuesday. They are still hitting rock, installed a few sticks of pipe.
Sanitary Sewer Construction Inspection Partial 04/19/2021
Miscellaneous Correction
Informational
04/15/2021
John DiiMauro witnessed the core drill and connection to the existing MH. The contractors have installed MH 1-1, 1-2, and 1-3. They will have a tester out doin g companion test when they backfill.
Misc
Informational
04/15/2021
Contractors have hit rock. They have installed wyes between MH 1-2 and 1-3. Installing pipe fron 1-3 to 1-4.
Miscellaneous Correction
Partial Correction
04/15/2021
MH 2-1 has been installed. The service lines for 55,56,and 57 have been installed. MH 3-1 has been installed. The service lines between 1-3 and 3-1 have been installed. Line 1 has 2 sticks of pipe installed, they have hit a lot of rock.
Miscellaneous Correction
Informational
04/15/2021
Crew is installing service stubs and wyes between MH 1-3 and 1-4. They are working toward MH 1-4.. Hitting rock so not getting much pipe installed.
Misc
Informational
04/15/2021
Redford is working on service line wyes between MH 1-3 and 1-4. They are still hitting rock. I spoke to them about making sure the backfill is in good condition. Compaction tests are going to be done tomorrow. We will be doing them every 50 feet in the road over the maiin and on every service stub.
Misc
Informational
04/15/2021
The compaction test have been put off until next Tuesday. They are still hitting rock, installed a few sticks of pipe.
Misc
Informational
04/19/2021
MH 3-1, 3-2 and the service lines are being installed. They are working on installing the wyes too.
Sanitary Sewer Construction Inspection Partial 04/22/2021
Miscellaneous Correction
Informational
04/19/2021
John DiiMauro witnessed the core drill and connection to the existing MH. The contractors have installed MH 1-1, 1-2, and 1-3. They will have a tester out doin g companion test when they backfill.
Misc
Informational
04/19/2021
Contractors have hit rock. They have installed wyes between MH 1-2 and 1-3. Installing pipe fron 1-3 to 1-4.
Miscellaneous Correction
Partial Correction
04/19/2021
MH 2-1 has been installed. The service lines for 55,56,and 57 have been installed. MH 3-1 has been installed. The service lines between 1-3 and 3-1 have been installed. Line 1 has 2 sticks of pipe installed, they have hit a lot of rock.
Miscellaneous Correction
Informational
04/19/2021
Crew is installing service stubs and wyes between MH 1-3 and 1-4. They are working toward MH 1-4.. Hitting rock so not getting much pipe installed.
Misc
Informational
04/19/2021
Redford is working on service line wyes between MH 1-3 and 1-4. They are still hitting rock. I spoke to them about making sure the backfill is in good condition. Compaction tests are going to be done tomorrow. We will be doing them every 50 feet in the road over the maiin and on every service stub.
Misc
Informational
04/19/2021
The compaction test have been put off until next Tuesday. They are still hitting rock, installed a few sticks of pipe.
Misc
Informational
04/19/2021
MH 3-1, 3-2 and the service lines are being installed. They are working on installing the wyes too.
Misc
Informational
04/22/2021
MH 3-3 has been instlled.All the wyes and service lines has been installed on line 3 up to 3-3. The trench checks and tracer wire has also been installed. Structure 4-1 is not here so they skipped this one.
Misc
Informational
04/27/2021
On Tuesday, 4-26-2020. Redford Excavating completed laterals for line 33 between MH# 3-3 & 3-4. Crew #2 worked on line #4 install aging MH#4-1 and completed lateral between MH#4-1 and #3-3 and compacted. On Thursday, 4-29-2021. Redford Excavating resumed Sanitary Sewer installation. Contractor installed MH #3-2 and laterals on the south side of main between MH #3-6 and #3-7. Back fill was placed over lines.
Sanitary Sewer Construction Inspection Partial 04/30/2021
Miscellaneous Correction
Informational
04/22/2021
John DiiMauro witnessed the core drill and connection to the existing MH. The contractors have installed MH 1-1, 1-2, and 1-3. They will have a tester out doin g companion test when they backfill.
Misc
Informational
04/22/2021
Contractors have hit rock. They have installed wyes between MH 1-2 and 1-3. Installing pipe fron 1-3 to 1-4.
Miscellaneous Correction
Partial Correction
04/22/2021
MH 2-1 has been installed. The service lines for 55,56,and 57 have been installed. MH 3-1 has been installed. The service lines between 1-3 and 3-1 have been installed. Line 1 has 2 sticks of pipe installed, they have hit a lot of rock.
Miscellaneous Correction
Informational
04/22/2021
Crew is installing service stubs and wyes between MH 1-3 and 1-4. They are working toward MH 1-4.. Hitting rock so not getting much pipe installed.
Misc
Informational
04/22/2021
Redford is working on service line wyes between MH 1-3 and 1-4. They are still hitting rock. I spoke to them about making sure the backfill is in good condition. Compaction tests are going to be done tomorrow. We will be doing them every 50 feet in the road over the maiin and on every service stub.
Misc
Informational
04/22/2021
The compaction test have been put off until next Tuesday. They are still hitting rock, installed a few sticks of pipe.
Misc
Informational
04/22/2021
MH 3-1, 3-2 and the service lines are being installed. They are working on installing the wyes too.
Misc
Informational
04/22/2021
MH 3-3 has been instlled.All the wyes and service lines has been installed on line 3 up to 3-3. The trench checks and tracer wire has also been installed. Structure 4-1 is not here so they skipped this one.
Misc
Informational
04/30/2021
On Friday, 4-30-2021. Redford Excavation installed laterals for sewer for MH #3-6 and #3-7 and #3-8. Set MH #3-7. Contractor back filled sewer System installed days previous.
Misc
Informational
05/04/2021
On Tuesday 5-04-2021. Redford Excavating began installing 16” Y laterals for line #1. A correction on the size of the sewer size. It was a 15” sewer and not a 16”.
Misc
Informational
05/06/2021
On Tuesday 5-04-2021. Redford Excavating began installing 15” Y laterals for 15” main. On Thursday, 5-05-2021. Redford resumed sewer installation for taps for 15” main for laterals on north side of project. Two (2) taps were installed.
Misc
Informational
05/06/2021
On Thursday 5-06-2021. RedFord Excavating resumed sewer installation. Contractor installed (5) 15” Y taps and began lateral installations. On Saturday, 5-08-2021. Redford Excavating resumed Sanitary Sewer installation. Contractor installing Laterals for lots, 63 and 78. Contractor has hit heavy rock for lateral installation. On Monday, 5-10-2021. Redford Excavating resumed Sanitary Sewer installation. Contractor worked installation Structure MH 1-5. Contractor also installed lateral at lots 66 and 72.
Storm - Material Verification Passed 05/12/2021
Misc
Informational
05/12/2021
On Wednesday, 5-12-2021. I gave a visual on the Storm Sewer Pipe, Boxes and lids on the project site and found them to meet city standards
Storm Sewer Construction Inspection Partial 05/24/2021
Misc
Informational
05/12/2021
On Wednesday, 5-12-2021. Redford Excavating began installation of the Storm Sewer system. The contractor started at structure CI 1-1, 1-2 and 1-3. Contractor installed approx 170LF of 36” HDPE pipe. And back filled. JJACKSON On Friday, 5-21-2021. Redford Excavating installed CI 2-3 & 2-4 and storm pipe from 2-2 to approximately ten foot short of where structure 2-5 will be installed. On Monday, 5-24-2021. Redford Excavating set storm structure 1-5 and began pipe installation. CI 3-1 & 3-2 were installed along with the 18” HDPE storm pipe. On Tuesday, 5-25-2021. Redford Excavating resumed storm sewer installation. Contractor pour concrete inverts. Also installed storm sewer for pipe between CI 3-1 and CI 3-2. On Monday, 6-01-2021. Redford Excavating resumed Storm Sewer Installation setting structure 6-1, and 6-2 including approx 200LF of 18” HDPE Pipe. Contractor also set structure 1-8 & 1-9 CI’s on line #1. Contractor also placed 155LF of 18” pipe. On Wednesday, 6-02-2021. Redford Excavating resumed storm sewer installation. Contractor placed structures MH 4-3, FI 4-5, 4-4 on line (4). Line (3) CI 2-5, 2-6 and all pipe in between all structures and backfilled except around boxes where inverts and dog houses need to be poured.
Sanitary Sewer - Air Test Passed 06/11/2021
Misc
Informational
06/11/2021
On Thursday, 6-10-2021. Redford Excavating sewer testing crew and I performed all necessary testing on sanitary sewers. Contractor performed Manderl, pipe air testing and Man Hole vacuum testing. All test passed city standards. I will sign off on Sanitary Sewers as completed and request Water Services to video.
Grading/Excavation/Fill Inspection Partial 06/18/2021
Misc
Informational
06/18/2021
On Friday 6-18-2021. Spalding Excavating resumes mass final grading. Contractor completing clean up of debris and removals of trash.
Misc
Informational
07/14/2021
On Monday and Tuesday, 7-13 and 7-14-2021. The contractor resumed rock fill for subgrade and compacted.
Pavement-Aggregate Base Passed 07/06/2021
Pavement-Proof Roll Passed 07/12/2021
Misc
Informational
07/12/2021
On Monday, 7-12-2021. Spalding and I completed a sub-grade proof roll for the placement of rock subgrade and it passed city standards. 7/23/21 Friday ( Field Inspector- John M. Jackson) Proof Roll for rock passed.
Curb - Proof Roll Passed 07/15/2021
Misc
Informational
07/15/2021
On Wednesday, 7-14-2021. Spalding Excavating performed a Curb proof roll for curb installation set for next day’s business. Proof Roll Passed for curb placement.
Street - Surface Course Passed 07/25/2021
Misc
Informational
07/24/2021
7/24/21 Saturday (Field Inspector John M. Jackson) Contractor (Superior Bowen Paving Super) began installing base asphalt approximately 4” depth onsite. Talked with Rhett Klinksick of (SB) about the arrival of third party testing for base asphalt. Third party testing contractor CMTE arrived onsite, and testing density have been good. Contractor stopped asphalt paving around 6:20PM, they resume on Monday 7/26/21. The entrance street to project will need base asphalt. Then (SB) will be able to start with surface asphalt. I talked with Rhett Klinksick of (SB) about the Tacking between the base & surface asphalt, he assured me that will have that done. On Monday, 7-26-2021. Superior-Bowen completed Base asphalt and installed all surface pavement for project.
Water Line - Construction Inspection Passed 08/12/2021
Misc
Informational
06/09/2021
On Wednesday, 6-09-2021 Spalding Excavating Had surveyor place stakes for final roadway elevation. Contractor placed geo-grid and began placement of rock sub base and compacted.
Misc
Informational
07/30/2021
On Thursday, 7-29-2021 Red Ford Excavating began placement of the 8” waterline. Contractor worked on line And placed (1) fire hydrant and sta. . And back filled system living fitting excess-able to pour restraints.
Misc
Informational
07/30/2021
On Thursday, 7-29-2021 Red Ford Excavating began placement of the 8” waterline. Contractor worked on line And placed (1) fire hydrant and sta. . And back filled system living fitting excess-able to pour restraints. On Friday, 7-30-2021. Red Ford Excavating Resumed waterline installation. Contractor placed line #3 with inline hydrant. Contractor back field waterline but left fittings open to pour restraints.
Misc
Informational
08/09/2021
On Thursday, 7-29-2021 Red Ford Excavating began placement of the 8” waterline. Contractor worked on line And placed (1) fire hydrant and sta. . And back filled system living fitting excess-able to pour restraints. On Friday, 7-30-2021. Red Ford Excavating Resumed waterline installation. Contractor placed line #3 with inline hydrant. Contractor back field waterline but left fittings open to pour restraints. On Tuesday, 8-03-2021. RedFord Excavating resumed 8”water main installation. Contractor installed line #2 from sta 13+14/w 10+25 line #2 to 17+51. This includes all fittings and hydrant at sta 16+47.
Misc
Informational
08/09/2021
On Thursday, 7-29-2021 Red Ford Excavating began placement of the 8” waterline. Contractor worked on line And placed (1) fire hydrant and sta. . And back filled system living fitting excess-able to pour restraints. On Friday, 7-30-2021. Red Ford Excavating Resumed waterline installation. Contractor placed line #3 with inline hydrant. Contractor back field waterline but left fittings open to pour restraints. On Tuesday, 8-03-2021. RedFord Excavating resumed 8”water main installation. Contractor installed line #2 from sta 13+14/w 10+25 line #2 to 17+51. This includes all fittings and hydrant at sta 16+47. On Wednesday, 8-04-2021. Redford Excavating resumes water line installation for line #2 & #3. Contractor poured all restraints from areas that were installed previous. On Thursday, 8-05-2021. Contractor resumed water line installation for line #2 and poured restraints and backfilled waterlines,
Misc
Informational
08/10/2021
On Thursday, 7-29-2021 Red Ford Excavating began placement of the 8” waterline. Contractor worked on line And placed (1) fire hydrant and sta. . And back filled system living fitting excess-able to pour restraints. On Friday, 7-30-2021. Red Ford Excavating Resumed waterline installation. Contractor placed line #3 with inline hydrant. Contractor back field waterline but left fittings open to pour restraints. On Tuesday, 8-03-2021. RedFord Excavating resumed 8”water main installation. Contractor installed line #2 from sta 13+14/w 10+25 line #2 to 17+51. This includes all fittings and hydrant at sta 16+47. On Wednesday, 8-04-2021. Redford Excavating resumes water line installation for line #2 & #3. Contractor poured all restraints from areas that were installed previous. On Thursday, 8-05-2021. Contractor resumed water line installation for line #2 and poured restraints and backfilled waterlines, On Monday, 8-09-2021. Redford Excavating resumed water main installation on line #2. Contractor completed line #2, backfilled and poured all restraints for that line. Also 2nd crew constructed valve connections for construction taps on 16” main for Wednesday morning, both locations.
Misc
Informational
08/12/2021
On Thursday, 7-29-2021 Red Ford Excavating began placement of the 8” waterline. Contractor worked on line And placed (1) fire hydrant and sta. . And back filled system living fitting excess-able to pour restraints. On Friday, 7-30-2021. Red Ford Excavating Resumed waterline installation. Contractor placed line #3 with inline hydrant. Contractor back field waterline but left fittings open to pour restraints. On Tuesday, 8-03-2021. RedFord Excavating resumed 8”water main installation. Contractor installed line #2 from sta 13+14/w 10+25 line #2 to 17+51. This includes all fittings and hydrant at sta 16+47. On Wednesday, 8-04-2021. Redford Excavating resumes water line installation for line #2 & #3. Contractor poured all restraints from areas that were installed previous. On Thursday, 8-05-2021. Contractor resumed water line installation for line #2 and poured restraints and backfilled waterlines, On Monday, 8-09-2021. Redford Excavating resumed water main installation on line #2. Contractor completed line #2, backfilled and poured all restraints for that line. Also 2nd crew constructed valve connections for construction taps on 16” main for Wednesday morning, both locations. On Wednesday, 8-11-2021, Redford Excavating worked installing the water line at the entrance of the project and contractor put together the 12” valves for the 12” main tie-in for tomorrow. The lone property that would have been affected was notified of the shut. On Thursday, 8-12-2021. The contractor completed both main tap and restored the water main back by 11;00 am. Water Services came out to assist with restoring the water in service.
Water Line - Coliform Test 1 Passed 09/16/2021
Misc
Informational
08/18/2021
On Monday, 8- 16-2021. Red Ford Excavating completed Pressure testing for the 8”water line. 175 pounds of Pressure was placed into the water line for 4 hours and held the Pressure for the time limit passing the test . Red Ford Excavating performed the chlorination of water line. On Tuesday, 8-17-2021. Red Ford Excavating D —Chlorinated water line and flushed water line. On Wednesday, 8-18-2021. Red Ford Excavating provided water sample for (3) locations and were taken to Keystone lab. On Friday, 8-20-2021. Test results for water sample (1) came back and failed location #1. Contractor taking sample again! Diana Johnson took the sample to Keystone Lab. On Tuesday, 9-8-2021 test results for water sample (1) came back and passed. On Wednesday, 9-9-2021 test results for water sample (2) came back and passed.
Sidewalk Inspection Partial 08/23/2022
Misc
Informational
08/23/2022
8-23-22 RH. Sidewalk is formed up and aggregate is placed and compacted at the entrance to the subdivision.
Sidewalk Inspection Passed 8/30/2022 8/30/2022 08/24/2022
Misc
Informational
08/23/2022
8-23-22 RH. Sidewalk is formed up and aggregate is placed and compacted at the entrance to the subdivision. 8-24-22 RH. Sidewalk meets LS and ADA specification.
Documents & Images
Date Uploaded File Type Document Name
09/14/2020 Receipt Receipt for transaction:2020-006218
09/15/2020 Approved Plans The Retreat at Hook Farms Water Plans Approved 9.15.20
09/15/2020 Approved Plans The Retreat at Hook Farms Sanitary Sewer Plans Approved 9.15.20
09/15/2020 Approved Plans The Retreat at Hook Farms Street and Storm Sewer Plans Approved 9.15.20
09/15/2020 Approved Plans The Retreat at Hook Farms Site Disturbance Plans Approved 9.15.20
04/05/2021 Letter INSPECTION SUMMARY
04/05/2021 Letter INSPECTION SUMMARY
04/06/2021 Letter INSPECTION SUMMARY
04/12/2021 Letter INSPECTION SUMMARY
04/13/2021 Letter INSPECTION SUMMARY
04/14/2021 Letter DE-Daily Inspection Summary
04/15/2021 Letter DE-Daily Inspection Summary
04/15/2021 Letter DE-Daily Inspection Summary
04/19/2021 Letter INSPECTION SUMMARY
04/19/2021 Letter INSPECTION SUMMARY
04/19/2021 Letter INSPECTION SUMMARY
04/22/2021 Letter INSPECTION SUMMARY
04/30/2021 Letter INSPECTION SUMMARY
05/06/2021 Letter INSPECTION SUMMARY
05/06/2021 Letter INSPECTION SUMMARY
05/12/2021 Letter INSPECTION SUMMARY
05/20/2021 Approved Plans The Retreat at Hook Farms Street and Storm Sewer Plans Approved 5.20.21
05/24/2021 Letter INSPECTION SUMMARY
05/24/2021 Letter INSPECTION SUMMARY
06/09/2021 Letter INSPECTION SUMMARY
06/11/2021 Letter INSPECTION SUMMARY
06/11/2021 Letter INSPECTION SUMMARY
07/06/2021 Letter INSPECTION SUMMARY
07/15/2021 Letter INSPECTION SUMMARY
07/15/2021 Letter INSPECTION SUMMARY
07/15/2021 Letter INSPECTION SUMMARY
07/24/2021 Letter INSPECTION SUMMARY
07/24/2021 Letter INSPECTION SUMMARY
07/24/2021 Letter INSPECTION SUMMARY
07/24/2021 image.jpg
07/24/2021 image.jpg0
07/24/2021 Letter INSPECTION SUMMARY
07/24/2021 image.jpg1
07/24/2021 image.jpg2
07/24/2021 image.jpg3
07/24/2021 image.jpg4
07/25/2021 Letter INSPECTION SUMMARY
07/25/2021 Letter INSPECTION SUMMARY
07/25/2021 Letter INSPECTION SUMMARY
07/27/2021 Letter INSPECTION SUMMARY
07/27/2021 Letter INSPECTION SUMMARY
08/12/2021 Letter INSPECTION SUMMARY
08/18/2021 Letter INSPECTION SUMMARY
08/18/2021 Letter INSPECTION SUMMARY
08/20/2021 Letter INSPECTION SUMMARY
09/16/2021 Hook Farms Retreat water test #2 passed .pdf
09/16/2021 Hook Farms Retreat water test #1 passed .pdf
09/16/2021 Hook Farms Retreat water test #1 passed .pdf0
09/16/2021 Letter INSPECTION SUMMARY
09/20/2021 Letter INSPECTION SUMMARY
09/20/2021 Letter INSPECTION SUMMARY
09/21/2021 Plans Approved Water Asbuilts (Full Set)
09/21/2021 Plans Approved Sanitary Sewer Asbuilts (Full Set)
09/21/2021 Plans not approved Street & Storm Sewer Asbuilts (Full Set)
09/27/2021 Letter INSPECTION SUMMARY
10/20/2021 Letter INSPECTION SUMMARY
12/10/2021 Letter DE-Certificate of Substantial Completion Multiple Lot
12/10/2021 Letter DE-Punch List
08/23/2022 Letter INSPECTION SUMMARY
08/24/2022 Letter INSPECTION SUMMARY
09/15/2023 Final Acceptance Hook Farms 1rst Plat
09/15/2023 Maintenace Bond
09/15/2023 Letter DE-Certificate of Final Acceptance (Commercial)
09/25/2024 Letter PW ROW Inspections Report
12/20/2024 Letter PW ROW Inspections Report
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home