Summary


PRSUBD20162865
Public Infrastructure
Final Acceptance
FISHER CHRISTINE A
DEVELOPMENT COMPLETE
MONTICELLO 3RD PLAT - STREET, STORM, MDP, ESC, WATER LINE
11/03/2016
12/26/2019
05/08/2020
Locations
Address
1245 NE GOSHEN DR, LEES SUMMIT, MO 64064

Address
1241 NE GOSHEN DR, LEES SUMMIT, MO 64064

Address
1237 NE GOSHEN DR, LEES SUMMIT, MO 64064

Address
1233 NE GOSHEN DR, LEES SUMMIT, MO 64064

Address
1229 NE GOSHEN DR, LEES SUMMIT, MO 64064

Address
1225 NE GOSHEN DR, LEES SUMMIT, MO 64064

Address
1221 NE GOSHEN DR, LEES SUMMIT, MO 64064

Address
1217 NE GOSHEN DR, LEES SUMMIT, MO 64064

Address
1213 NE GOSHEN DR, LEES SUMMIT, MO 64064

Address
1209 NE GOSHEN DR, LEES SUMMIT, MO 64064

Address
1121 NE GOSHEN CT, LEES SUMMIT, MO 64064

Address
1117 NE GOSHEN CT, LEES SUMMIT, MO 64064

Address
1113 NE GOSHEN CT, LEES SUMMIT, MO 64064

Address
1109 NE GOSHEN CT, LEES SUMMIT, MO 64064

Address
1105 NE GOSHEN CT, LEES SUMMIT, MO 64064

Address
1101 NE GOSHEN CT, LEES SUMMIT, MO 64064

Address
1104 NE GOSHEN CT, LEES SUMMIT, MO 64064

Address
1108 NE GOSHEN CT, LEES SUMMIT, MO 64064

Address
1112 NE GOSHEN CT, LEES SUMMIT, MO 64064

Address
1116 NE GOSHEN CT, LEES SUMMIT, MO 64064

Address
1200 NE GOSHEN DR, LEES SUMMIT, MO 64064

Address
1204 NE GOSHEN DR, LEES SUMMIT, MO 64064

Address
1208 NE GOSHEN DR, LEES SUMMIT, MO 64064

Address
4701 NE FREEHOLD DR, LEES SUMMIT, MO 64064

Address
4700 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
4701 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
4705 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
4709 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
4713 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
4717 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
4721 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
4725 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
4729 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
4728 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
4724 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
4720 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
4716 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
4712 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
4708 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
4704 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
4726 NE SARATOGA CT, LEES SUMMIT, MO 64064

Address
1102 NE GOSHEN CT, LEES SUMMIT, MO 64064

Property
43130011000000000

Property
43130011100000000

Property
43130011200000000

Property
43130011300000000

Property
43130011400000000

Property
43130011500000000

Property
43130011600000000

Property
43130011700000000

Property
43130020100000000

Property
43240016400000000

Property
43240016500000000

Property
43130063500000000

Property
43130063300000000

Property
43130063400000000

Property
43130040300000000

Property
43130040200000000

Property
43130040100000000

Property
43130030300000000

Property
43130030200000000

Property
43130063600000000

Property
43130030100000000

Property
43130064900000000

Property
43240016600000000

Property
43240016700000000

Property
43130063700000000

Property
43130064800000000

Property
43130063800000000

Property
43130064700000000

Property
43130063900000000

Property
43130064600000000

Property
43130064500000000

Property
43130064000000000

Property
43130064100000000

Property
43130064400000000

Property
43130066800000000

Property
43130064200000000

Property
43130064300000000

Property
43240016800000000

Property
43130020400000000

Property
43130020300000000

Property
43130020200000000

Property
43130010900000000

Property
43130011800000000

Address
1100 NE GOSHEN CT, LEES SUMMIT, MO 64064

Contacts
SILVERSTONE DEVELOPMENT LLC, Address:PO BOX 346  
FISHER CHRISTINE A, Address:1100 NE GOSHEN CT  
VANHORN JEFFERY L JR, Address:1101 NE GOSHEN CT  
ROBINSON RYAN T & KRYSTAL L, Address:1105 NE GOSHEN CT  
MEREDITH WILLIAM W & MELYNDA, Address:1109 NE GOSHEN CT  
PATRICIA GAIL COTTEN TRUST DATED 12/12/2019, Address:1113 NE GOSHEN CT  
HUNTLEY WADE T, Address:508 NW MANOR DR  
GOLDSTEIN AMY & JEFFREY, Address:1121 NE GOSHEN CT  
CURRY ERIN CATHLEEN, Address:1209 NE GOSHEN DR  
RAGSDALE KELLY, Address:1213 NE GOSHEN DR  
HAGOPIAN KIRSTEN M, Address:1217 NW GOSHEN DR  
RICHARDS HOUSTON & ASHTON, Address:1221 NE GOSHEN DR  
WEBBER DUSTIN & ALLISON, Address:4420 NE HIDEAWAY DR  
ZEFFIRO GEORGE, Address:1229 NE GOSHEN DR  
TRUMARK CUSTOM HOMES LLC, Address:2924 NW THOREAU DR  
HUBER DANA MICHELLE, Address:1241 NE GOSHEN DR  
MILLER DANIEL ALAN & BARTSHE TRACI NICOLE, Address:1245 NE GOSHEN DR  
MONTICELLO PROPERTY ASSOCIATION INC, Address:PO BOX 346  
LEIBOLD MARY LOU, Address:1104 NE GOSHEN CT  
TWIGG BRADLEE M & STEPHANIE M, Address:1108 NE GOSHEN CT  
RADER RYAN K, Address:1112 NE GOSHEN CT  
HENCEY TRAVIS & ANAID, Address:1116 NE GOSHEN CT  
SOJKA ROBERT J JR & AMBER L, Address:1200 NE GOSHEN DR  
JORDAN KERRIE J & KEARNEY JASON, Address:1204 NE GOSHEN DR  
LIMPUS LINDA K, Address:1208 NE GOSHEN DR  
PEC JOSEPH J & CATHY WILSON PEC, Address:4701 NE FREEHOLD DR  
VANFLEET RYAN & LINDSEY M, Address:4700 NE SARATOGA CT  
ANDERSON LOLA PATRICE, Address:4704 NE SARATOGA CT  
SEVILLA CYNTHIA, Address:4708 NE SARATOGA CT  
FRAZIER ANDREW S & STACIA R, Address:4712 NE SARATOGA CT  
RAPS-EK JANET, Address:4716 NE SARATOGA CT  
PETERS BRYAN & ASHTON, Address:4720 NE SARATOGA CT  
MIX ROBERT C & MICHELLE, Address:4724 NE SARATOGA CT  
BAIER BEN M & SUZANNE R, Address:4728 NE SARATOGA CT  
CROWL RANDY G & KAREN K, Address:4701 NE SARATOGA CT  
YOUNG JEREMY & AMANDA, Address:4705 NE SARATOGA CT  
JONES DAVID, Address:4709 NE SARATOGA CT  
HOEPPNER TIMOTHY K & PHILECIA L, Address:4713 NE SARATOGA CT  
MCCAFFREY JANET & MARK, Address:4717 NE SARATOGA CT  
SPOTTS MICHAEL J & MELISSA A, Address:4721 NE SARATOGA CT  
CHAPIN-PATCH GRANT & SIMMONS JENNIFER, Address:4725 NE SARATOGA CT  
ROCKHOLD JACOB & SALLY, Address:4729 NE SARATOGA CT  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 11/03/2016 12/12/2016
Bart Reese
Fees
Paid Fees Amount Paid Owing Date Paid
Storm Sewer Inspection Fee $10,753.95 $10,753.95 Paid 11/03/2016
Paved Surface Inspection Fee $12,008.28 $12,008.28 Paid 11/03/2016
Site Grading Fee $760.56 $760.56 Paid 11/03/2016
Sanitary Sewer Insp Fees $6,695.39 $6,695.39 Paid 07/30/2018
$6,695.40
Water Insp Fee $2,250.94 $2,250.94 Paid 09/05/2018
Water Test Fee $600.00 $600.00 Paid 09/05/2018
Outstanding Fees Amount Paid Owing Date Paid


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sanitary Sewer Construction Inspection Partial 8/2/2018 at 8:00 AM 08/02/2018
PW-Main inspection
Informational
08/02/2018
Holthouse has started with MH c-10, they installed 8" sdr 26 pipe to Mh c-11. They are going toward c-12 . I have checked the materials and everything appears to be correct. Steve Robbins 08/02/2018 9:01 AM
Sanitary Sewer Construction Inspection Partial 8/3/2018 at 10:30 AM 08/03/2018
PW-Main inspection
Informational
08/02/2018
Holthouse has started with MH c-10, they installed 8" sdr 26 pipe to Mh c-11. They are going toward c-12 . I have checked the materials and everything appears to be correct. Steve Robbins 08/02/2018 9:01 AM
PW-Main inspection
Informational
08/03/2018
A-12 and A-13 has been installed. They are installing the wyes for the service lines as they go along. They are just installing the wyes now, they will come back and install the service line. I also talked to them about making sure the wyes are at least 4ft. apart and 4ft from the main. Steve Robbins 08/03/2018 11:48 AM
Sanitary Sewer Construction Inspection Partial 8/6/2018 at 8:30 AM 08/06/2018
PW-Main inspection
Informational
08/03/2018
Holthouse has started with MH c-10, they installed 8" sdr 26 pipe to Mh c-11. They are going toward c-12 . I have checked the materials and everything appears to be correct. Steve Robbins 08/02/2018 9:01 AM
PW-Main inspection
Informational
08/03/2018
A-12 and A-13 has been installed. They are installing the wyes for the service lines as they go along. They are just installing the wyes now, they will come back and install the service line. I also talked to them about making sure the wyes are at least 4ft. apart and 4ft from the main. Steve Robbins 08/03/2018 11:48 AM
PW-Main inspection
Informational
08/06/2018
MH A-14 has been set, they are working to get the last 2 wyes installed on line c. They are planning on going back and working on the service lines and trench checks after they finish with A-14.Steve Robbins 08/06/2018 9:15 AM
Sanitary Sewer Construction Inspection Partial 8/16/2018 at 11:15 AM 08/16/2018
PW-Main inspection
Informational
08/06/2018
Holthouse has started with MH c-10, they installed 8" sdr 26 pipe to Mh c-11. They are going toward c-12 . I have checked the materials and everything appears to be correct. Steve Robbins 08/02/2018 9:01 AM
PW-Main inspection
Informational
08/06/2018
A-12 and A-13 has been installed. They are installing the wyes for the service lines as they go along. They are just installing the wyes now, they will come back and install the service line. I also talked to them about making sure the wyes are at least 4ft. apart and 4ft from the main. Steve Robbins 08/03/2018 11:48 AM
PW-Main inspection
Informational
08/06/2018
MH A-14 has been set, they are working to get the last 2 wyes installed on line c. They are planning on going back and working on the service lines and trench checks after they finish with A-14.Steve Robbins 08/06/2018 9:15 AM
PW-Main inspection
Informational
08/16/2018
iImade a mistake on the previous logs, they are on Cl Line, not A Line. To make the correction it is C-11 to C-14 has been installed. John Jackson has been helping me out here as he has been staying out here observing what is gong on. They have now installed F-Line MH F-1 and F-2. Today they are working on the service lines. Lots 78-88 have been installed with service lines and the trench checks with anodes have been installed.Steve Robbins 08/16/2018 11:48 AM
Sanitary Sewer Construction Inspection Partial 8/21/2018 at 10:45 AM 08/21/2018
PW-Main inspection
Informational
08/16/2018
Holthouse has started with MH c-10, they installed 8" sdr 26 pipe to Mh c-11. They are going toward c-12 . I have checked the materials and everything appears to be correct. Steve Robbins 08/02/2018 9:01 AM
PW-Main inspection
Informational
08/16/2018
A-12 and A-13 has been installed. They are installing the wyes for the service lines as they go along. They are just installing the wyes now, they will come back and install the service line. I also talked to them about making sure the wyes are at least 4ft. apart and 4ft from the main. Steve Robbins 08/03/2018 11:48 AM
PW-Main inspection
Informational
08/16/2018
MH A-14 has been set, they are working to get the last 2 wyes installed on line c. They are planning on going back and working on the service lines and trench checks after they finish with A-14.Steve Robbins 08/06/2018 9:15 AM
PW-Main inspection
Informational
08/16/2018
iImade a mistake on the previous logs, they are on Cl Line, not A Line. To make the correction it is C-11 to C-14 has been installed. John Jackson has been helping me out here as he has been staying out here observing what is gong on. They have now installed F-Line MH F-1 and F-2. Today they are working on the service lines. Lots 78-88 have been installed with service lines and the trench checks with anodes have been installed.Steve Robbins 08/16/2018 11:48 AM
PW-Main inspection
Informational
08/21/2018
There was rain yesterday, they worked till about 2. They have been installing the service lines up to MH F-1. Olsen has been testing for all the road crossings of the main and the service lines. John Jackson has been helping on this project. The Goshen ct. service lines has been completley finished.Steve Robbins 08/21/2018 11:41 AM
Sanitary Sewer - Wye / Insert-A-Tee Installation Partial 8/21/2018 at 11:45 AM 08/21/2018
PW-Misc
Informational
08/21/2018
The service lines/wyes for lots 78-88 have all been installed with trench checks and tracer wire with anodes.They are now working on 77-89 now. They are also getting compaction tests from olson.Steve Robbins 08/21/2018 11:49 AM
Sanitary Sewer Construction Inspection Partial 8/29/2018 at 10:00 AM 08/30/2018
PW-Main inspection
Informational
08/21/2018
Holthouse has started with MH c-10, they installed 8" sdr 26 pipe to Mh c-11. They are going toward c-12 . I have checked the materials and everything appears to be correct. Steve Robbins 08/02/2018 9:01 AM
PW-Main inspection
Informational
08/21/2018
A-12 and A-13 has been installed. They are installing the wyes for the service lines as they go along. They are just installing the wyes now, they will come back and install the service line. I also talked to them about making sure the wyes are at least 4ft. apart and 4ft from the main. Steve Robbins 08/03/2018 11:48 AM
PW-Main inspection
Informational
08/21/2018
MH A-14 has been set, they are working to get the last 2 wyes installed on line c. They are planning on going back and working on the service lines and trench checks after they finish with A-14.Steve Robbins 08/06/2018 9:15 AM
PW-Main inspection
Informational
08/21/2018
iImade a mistake on the previous logs, they are on Cl Line, not A Line. To make the correction it is C-11 to C-14 has been installed. John Jackson has been helping me out here as he has been staying out here observing what is gong on. They have now installed F-Line MH F-1 and F-2. Today they are working on the service lines. Lots 78-88 have been installed with service lines and the trench checks with anodes have been installed.Steve Robbins 08/16/2018 11:48 AM
PW-Main inspection
Informational
08/21/2018
There was rain yesterday, they worked till about 2. They have been installing the service lines up to MH F-1. Olsen has been testing for all the road crossings of the main and the service lines. John Jackson has been helping on this project. The Goshen ct. service lines has been completley finished.Steve Robbins 08/21/2018 11:41 AM
Informational
08/30/2018
C-10 to C-14 and all the service lines has been completed and the compaction tests for road crossings. F-1 and F-2 has also been completed and so have the service lines and the compaction tests. Last week when it rained the contractor did lifts and backfilled without the tester from olsen doing any compaction tests while it was raining. The next day we got it figured out and they dug up the ones they didnt get tested , no pot holing. They have now started on line G, they have the core drill and boot installed on the existing MH next to line C. They have installed G-1, 2 and 3. They also have service lines for lot 103 and 102. Steve Robbins 08/30/2018 10:22 AM
Sanitary Sewer Construction Inspection Partial 8/31/2018 at 11:00 AM 08/31/2018
PW-Main inspection
Informational
08/30/2018
Holthouse has started with MH c-10, they installed 8" sdr 26 pipe to Mh c-11. They are going toward c-12 . I have checked the materials and everything appears to be correct. Steve Robbins 08/02/2018 9:01 AM
PW-Main inspection
Informational
08/30/2018
A-12 and A-13 has been installed. They are installing the wyes for the service lines as they go along. They are just installing the wyes now, they will come back and install the service line. I also talked to them about making sure the wyes are at least 4ft. apart and 4ft from the main. Steve Robbins 08/03/2018 11:48 AM
PW-Main inspection
Informational
08/30/2018
MH A-14 has been set, they are working to get the last 2 wyes installed on line c. They are planning on going back and working on the service lines and trench checks after they finish with A-14.Steve Robbins 08/06/2018 9:15 AM
PW-Main inspection
Informational
08/30/2018
iImade a mistake on the previous logs, they are on Cl Line, not A Line. To make the correction it is C-11 to C-14 has been installed. John Jackson has been helping me out here as he has been staying out here observing what is gong on. They have now installed F-Line MH F-1 and F-2. Today they are working on the service lines. Lots 78-88 have been installed with service lines and the trench checks with anodes have been installed.Steve Robbins 08/16/2018 11:48 AM
Informational
08/31/2018
The contractors have now installed G-3 and are working on the 2 service lines.They got a late start because of the rain.Steve Robbins 08/31/2018 4:00 PM
Sanitary Sewer Construction Inspection Partial 9/4/2018 at 2:30 PM 09/04/2018
PW-Main inspection
Informational
08/31/2018
Holthouse has started with MH c-10, they installed 8" sdr 26 pipe to Mh c-11. They are going toward c-12 . I have checked the materials and everything appears to be correct. Steve Robbins 08/02/2018 9:01 AM
PW-Main inspection
Informational
08/31/2018
A-12 and A-13 has been installed. They are installing the wyes for the service lines as they go along. They are just installing the wyes now, they will come back and install the service line. I also talked to them about making sure the wyes are at least 4ft. apart and 4ft from the main. Steve Robbins 08/03/2018 11:48 AM
PW-Main inspection
Informational
08/31/2018
MH A-14 has been set, they are working to get the last 2 wyes installed on line c. They are planning on going back and working on the service lines and trench checks after they finish with A-14.Steve Robbins 08/06/2018 9:15 AM
PW-Main inspection
Informational
09/04/2018
G-1,2,3,and 4 MH has all been installed. They are also installing the wyes as they go.Steve Robbins 09/04/2018 3:58 PM
Sanitary Sewer Construction Inspection Partial 9/5/2018 at 10:30 AM 09/05/2018
PW-Main inspection
Informational
09/04/2018
Holthouse has started with MH c-10, they installed 8" sdr 26 pipe to Mh c-11. They are going toward c-12 . I have checked the materials and everything appears to be correct. Steve Robbins 08/02/2018 9:01 AM
PW-Main inspection
Informational
09/04/2018
A-12 and A-13 has been installed. They are installing the wyes for the service lines as they go along. They are just installing the wyes now, they will come back and install the service line. I also talked to them about making sure the wyes are at least 4ft. apart and 4ft from the main. Steve Robbins 08/03/2018 11:48 AM
PW-Main inspection
Informational
09/04/2018
MH A-14 has been set, they are working to get the last 2 wyes installed on line c. They are planning on going back and working on the service lines and trench checks after they finish with A-14.Steve Robbins 08/06/2018 9:15 AM
PW-Main inspection
Informational
09/04/2018
G-1,2,3,and 4 MH has all been installed. They are also installing the wyes as they go.Steve Robbins 09/04/2018 3:58 PM
PW-Main inspection
Informational
09/05/2018
The contractors are working on the main installing the wyes for the service lines, they are not doing any road crossings now , just wyes. They are wanting to do backfilling in the rain today because the ground has been so dry. I spoke with Dan and he said a very light misty rain is ok for the ROW but not road crossings. The tester for the Olson will not test in the rain. I spoke with Chad from Holthouse and he is not going to backfill if it rains hard or more than a mist. It has now started to rain too hard and they have left.Steve Robbins 09/05/2018 2:20 PM
Sanitary Sewer Construction Inspection Partial 9/6/2018 at 10:20 AM 09/06/2018
PW-Main inspection
Informational
09/05/2018
Holthouse has started with MH c-10, they installed 8" sdr 26 pipe to Mh c-11. They are going toward c-12 . I have checked the materials and everything appears to be correct. Steve Robbins 08/02/2018 9:01 AM
PW-Main inspection
Informational
09/05/2018
A-12 and A-13 has been installed. They are installing the wyes for the service lines as they go along. They are just installing the wyes now, they will come back and install the service line. I also talked to them about making sure the wyes are at least 4ft. apart and 4ft from the main. Steve Robbins 08/03/2018 11:48 AM
PW-Main inspection
Informational
09/05/2018
MH A-14 has been set, they are working to get the last 2 wyes installed on line c. They are planning on going back and working on the service lines and trench checks after they finish with A-14.Steve Robbins 08/06/2018 9:15 AM
PW-Main inspection
Informational
09/05/2018
G-1,2,3,and 4 MH has all been installed. They are also installing the wyes as they go.Steve Robbins 09/04/2018 3:58 PM
PW-Main inspection
Informational
09/05/2018
The contractors are working on the main installing the wyes for the service lines, they are not doing any road crossings now , just wyes. They are wanting to do backfilling in the rain today because the ground has been so dry. I spoke with Dan and he said a very light misty rain is ok for the ROW but not road crossings. The tester for the Olson will not test in the rain. I spoke with Chad from Holthouse and he is not going to backfill if it rains hard or more than a mist. It has now started to rain too hard and they have left.Steve Robbins 09/05/2018 2:20 PM
PW-Main inspection
Informational
09/06/2018
MH G-5 has been installed, this now completes all the MH and main for G-line. The contractors did not backfill in the rain yesterday. Today they are working on the service line. All the wyes have been installed and today they are working on the service lines. They are leaving a space for the trench checks. They have been installing tracer wire.Steve Robbins 09/06/2018 11:08 AM
Storm - Pipe Partial 9/20/2018 at 1:00 PM 09/21/2018
Informational
09/21/2018
Contractor installed Approximately 275 feet of 30 inch HDPE storm sewer.John Jackson 09/21/2018 9:04 AM
Storm - Inlets Clean Partial 9/20/2018 09/21/2018
Informational
09/21/2018
Three 5X4 curb inlet were installed. Curb inlet 13-1, 13-2, & 13-3.John Jackson 09/21/2018 9:16 AM
Storm - Rip Rap Partial 9/20/2018 09/21/2018
Informational
09/21/2018
Began the intial installation of Rip Rap apron at station 0+00 on storm line 13.John Jackson 09/21/2018 9:30 AM
Storm - Pipe Partial 9/21/2018 09/21/2018
Informational
09/21/2018
Contractor installed Approximately 340 feet of 30 inch HDPE storm sewer. John Jackson 09/21/2018 3:57 PM
Storm - Pipe Partial 9/21/2018 09/21/2018
Informational
09/21/2018
Contractor installed Approximately 340 feet of 30 inch HDPE storm sewer & Inlet 13-5. 13-2,13-3,13-4 & (began 13-1 Flared end with w/ toe wall installation.) was installed on 9/20/18 John Jackson 09/21/2018 4:14 PM
Sanitary Sewer Construction Inspection Partial 9/24/2018 at 8:30 AM 09/24/2018
PW-Main inspection
Informational
09/06/2018
Holthouse has started with MH c-10, they installed 8" sdr 26 pipe to Mh c-11. They are going toward c-12 . I have checked the materials and everything appears to be correct. Steve Robbins 08/02/2018 9:01 AM
PW-Main inspection
Informational
09/06/2018
A-12 and A-13 has been installed. They are installing the wyes for the service lines as they go along. They are just installing the wyes now, they will come back and install the service line. I also talked to them about making sure the wyes are at least 4ft. apart and 4ft from the main. Steve Robbins 08/03/2018 11:48 AM
PW-Main inspection
Informational
09/06/2018
MH A-14 has been set, they are working to get the last 2 wyes installed on line c. They are planning on going back and working on the service lines and trench checks after they finish with A-14.Steve Robbins 08/06/2018 9:15 AM
PW-Main inspection
Informational
09/06/2018
G-1,2,3,and 4 MH has all been installed. They are also installing the wyes as they go.Steve Robbins 09/04/2018 3:58 PM
PW-Main inspection
Informational
09/06/2018
The contractors are working on the main installing the wyes for the service lines, they are not doing any road crossings now , just wyes. They are wanting to do backfilling in the rain today because the ground has been so dry. I spoke with Dan and he said a very light misty rain is ok for the ROW but not road crossings. The tester for the Olson will not test in the rain. I spoke with Chad from Holthouse and he is not going to backfill if it rains hard or more than a mist. It has now started to rain too hard and they have left.Steve Robbins 09/05/2018 2:20 PM
PW-Main inspection
Informational
09/06/2018
MH G-5 has been installed, this now completes all the MH and main for G-line. The contractors did not backfill in the rain yesterday. Today they are working on the service line. All the wyes have been installed and today they are working on the service lines. They are leaving a space for the trench checks. They have been installing tracer wire.Steve Robbins 09/06/2018 11:08 AM
Informational
09/24/2018
All of the sanitary line hase been installed, all the wyes, tracer wire and trench checks have been completed. The contractors are now working on C-line that does not have any wyes, this line is for the next phase. They have installed C-1 to C-5 and are working toward C-6. Steve Robbins 09/24/2018 10:36 AM
Sanitary Sewer - Wye / Insert-A-Tee Installation Passed 9/24/2018 at 9:15 AM 09/24/2018
PW-Misc
Informational
08/21/2018
The service lines/wyes for lots 78-88 have all been installed with trench checks and tracer wire with anodes.They are now working on 77-89 now. They are also getting compaction tests from olson.Steve Robbins 08/21/2018 11:49 AM
Informational
09/24/2018
All the wyes have been installed, the anode, tracer wire, and trench checks have also been installed.Steve Robbins 09/24/2018 10:40 AM
Sanitary Sewer Construction Inspection Partial 9/24/2018 09/25/2018
PW-Main inspection
Informational
09/24/2018
Holthouse has started with MH c-10, they installed 8" sdr 26 pipe to Mh c-11. They are going toward c-12 . I have checked the materials and everything appears to be correct. Steve Robbins 08/02/2018 9:01 AM
PW-Main inspection
Informational
09/24/2018
A-12 and A-13 has been installed. They are installing the wyes for the service lines as they go along. They are just installing the wyes now, they will come back and install the service line. I also talked to them about making sure the wyes are at least 4ft. apart and 4ft from the main. Steve Robbins 08/03/2018 11:48 AM
PW-Main inspection
Informational
09/24/2018
MH A-14 has been set, they are working to get the last 2 wyes installed on line c. They are planning on going back and working on the service lines and trench checks after they finish with A-14.Steve Robbins 08/06/2018 9:15 AM
PW-Main inspection
Informational
09/24/2018
G-1,2,3,and 4 MH has all been installed. They are also installing the wyes as they go.Steve Robbins 09/04/2018 3:58 PM
PW-Main inspection
Informational
09/24/2018
The contractors are working on the main installing the wyes for the service lines, they are not doing any road crossings now , just wyes. They are wanting to do backfilling in the rain today because the ground has been so dry. I spoke with Dan and he said a very light misty rain is ok for the ROW but not road crossings. The tester for the Olson will not test in the rain. I spoke with Chad from Holthouse and he is not going to backfill if it rains hard or more than a mist. It has now started to rain too hard and they have left.Steve Robbins 09/05/2018 2:20 PM
Informational
09/25/2018
Installed approximately 80' feet of 30" HDPE pipe and Inlets 13-6 & 13-7 on 9/22/18. Created an opening on existing Field Inlet 3-5 to install 164' feet of 18" storm sewer on storm line 3. Installed Curb Inlet 3-6 and approximately 150' feet 15" HDPE pipe on 9/24/18. Contractor had to halt installation of HPDE 30 inch sewer line due to the existing straddle blocks interference on strorm line 13. Talked with Contractor about submit alternative plans to the City of Lee's Summit for review. John Jackson 09/25/2018 8:57 AM
Sanitary Sewer Construction Inspection Partial 9/25/2018 09/25/2018
PW-Main inspection
Informational
09/25/2018
Holthouse has started with MH c-10, they installed 8" sdr 26 pipe to Mh c-11. They are going toward c-12 . I have checked the materials and everything appears to be correct. Steve Robbins 08/02/2018 9:01 AM
PW-Main inspection
Informational
09/25/2018
A-12 and A-13 has been installed. They are installing the wyes for the service lines as they go along. They are just installing the wyes now, they will come back and install the service line. I also talked to them about making sure the wyes are at least 4ft. apart and 4ft from the main. Steve Robbins 08/03/2018 11:48 AM
PW-Main inspection
Informational
09/25/2018
MH A-14 has been set, they are working to get the last 2 wyes installed on line c. They are planning on going back and working on the service lines and trench checks after they finish with A-14.Steve Robbins 08/06/2018 9:15 AM
PW-Main inspection
Informational
09/25/2018
G-1,2,3,and 4 MH has all been installed. They are also installing the wyes as they go.Steve Robbins 09/04/2018 3:58 PM
Informational
09/25/2018
Contractor installed approximately 110' feet of 15" HDPE pipe on Storm Line 3 and Curb Inlets 3-7 & 3-8 on 9/25/18. John Jackson 09/25/2018 3:59 PM
Sanitary Sewer Construction Inspection Partial 9/27/2018 09/28/2018
PW-Main inspection
Informational
09/25/2018
Holthouse has started with MH c-10, they installed 8" sdr 26 pipe to Mh c-11. They are going toward c-12 . I have checked the materials and everything appears to be correct. Steve Robbins 08/02/2018 9:01 AM
PW-Main inspection
Informational
09/25/2018
A-12 and A-13 has been installed. They are installing the wyes for the service lines as they go along. They are just installing the wyes now, they will come back and install the service line. I also talked to them about making sure the wyes are at least 4ft. apart and 4ft from the main. Steve Robbins 08/03/2018 11:48 AM
PW-Main inspection
Informational
09/25/2018
MH A-14 has been set, they are working to get the last 2 wyes installed on line c. They are planning on going back and working on the service lines and trench checks after they finish with A-14.Steve Robbins 08/06/2018 9:15 AM
Informational
09/28/2018
Began pouring inverts on sanitary sewer Inlets that were installed 9/26/18. John Jackson 09/28/2018 3:02 PM
Storm - Pipe Partial 9/27/2018 09/28/2018
PW-Misc
Informational
09/28/2018
Poured inverts on storm sewer inlets that were installed completely 9/26/18. Backfilled storm sewer pipes and inlets9/27/18. John Jackson 09/28/2018 3:09 PM
Sanitary Sewer Construction Inspection Partial 10/1/2018 10/02/2018
PW-Main inspection
Informational
09/28/2018
Holthouse has started with MH c-10, they installed 8" sdr 26 pipe to Mh c-11. They are going toward c-12 . I have checked the materials and everything appears to be correct. Steve Robbins 08/02/2018 9:01 AM
PW-Main inspection
Informational
09/28/2018
A-12 and A-13 has been installed. They are installing the wyes for the service lines as they go along. They are just installing the wyes now, they will come back and install the service line. I also talked to them about making sure the wyes are at least 4ft. apart and 4ft from the main. Steve Robbins 08/03/2018 11:48 AM
Informational
10/02/2018
Contractor installed approximately 130' feet of 8" SDR-26 piping & manhole C-9. John Jackson 10/02/2018 7:39 AM
Storm - Pipe Partial 10/3/2018 10/04/2018
PW-Misc
Informational
09/28/2018
Poured inverts on storm sewer inlets that were installed completely. Backfilled storm sewer pipes and inlets. John Jackson 09/28/2018 3:09 PM
Informational
10/04/2018
Contractor installed approved modication Storm Sewer revised storm line 13 new storm line 17 pg C. 304 . Approximately 100' feet of 18" HDPE pipe was installed on storm line 17 & New 5'X4' Curb Inlet.
Storm - Pipe Partial 10/4/2018 10/04/2018
Informational
10/04/2018
Contractor installed Approximately 300" feet of 15" HDPE pipe on Storm line 13 & Curb Inlet 3-9
Storm - Pipe Partial 10/5/2018 10/05/2018
Informational
10/05/2018
John Jackson 10/05/2018 2:31 PMContractor poured invert for newly installed Strom Inlet boxes. Installed storm approximately line 14 30' feet of 15" HDPE and storm line 15 30' feet of 15" HDPE. Curb Inlet 14-1 & 15-1 were installed.
Storm - Pipe Partial 10/05/2018
Water Line - Construction Inspection Partial 10/5/2018 10/05/2018
Informational
10/05/2018
Contractor completed water line installation for 8' water line piping for Street Crossing per plans.
Sanitary Sewer Construction Inspection Partial 10/16/2018 10/17/2018
Informational
10/17/2018
Contractor installed approximately 100' feet of 8" SDR-26 Sanitary Sewer main on Line C. from sta 0+00 to 1+00 John Jackson 10/17/2018 3:27 PM
Erosion Control Inspection Partial 10/12/2018 at 3:00 PM 10/23/2018
PW-Devices for Erosion and Sediment Control
Corrective Action Required
10/23/2018
There are problems with the erosion control devices on your site. On friday 10/12/18 we had an on-site meeting at the church on Lakewood Way that backs up to the Montcello Project. During the heavey rains that occured over the past weekend the temporary sediment basin overflowed and a lot of silt washed off the Monticello property onto the church property. The silt ran into the church detention basin . Troy Bellah , Chad Holthouse, Dan Harper , myself and John Jackson met on-sight and determined that the Montecello representitives have to clean out the detention basin on the church property. The church and the contractors agreed to have it done in the next few weeks. They have also installed all new erosion control devices around the entire property. Steve Robbins 10/23/2018 7:13 AM
Pavement-Aggregate Base Partial 10/22/2018 at 2:00 PM 10/23/2018
Misc
Informational
10/23/2018
Spalding is installing fly -ash for the subgrade. They are using a tiller and a water truck for the installation of the fly-ash. Olsen has been on site doing the testing. Steve Robbins 10/23/2018 7:38 AM
Sanitary Sewer Construction Inspection Partial 10/25/2018 10/26/2018
PW-Main inspection
Informational
10/02/2018
Holthouse has started with MH c-10, they installed 8" sdr 26 pipe to Mh c-11. They are going toward c-12 . I have checked the materials and everything appears to be correct. Steve Robbins 08/02/2018 9:01 AM
Informational
10/26/2018
Contractor completed the instalation of sanitary sewer line. Installing apporximately 140' feet of 8" SDR-26 PVC on line C Sta 1+90 to 3+30.
Pavement-Aggregate Base Passed 10/24/2018 10/26/2018
Misc
Informational
10/23/2018
Spalding is installing fly -ash for the subgrade. They are using a tiller and a water truck for the installation of the fly-ash. Olsen has been on site doing the testing. Steve Robbins 10/23/2018 7:38 AM
Misc
Informational
10/26/2018
The fly ash has been installed for all the roads. Olsen has been on-sight doing the testing. They had a tiller on sight and was tilling in the fly ash.Steve Robbins 10/26/2018 7:44 AM
Pavement-Proof Roll Failed 10/25/2018 at 10:00 AM 10/26/2018
Misc
Informational
10/26/2018
This was a proofroll for the subgrade. The fly ash did not have time to set up, it was pumping in several spots on the first street. Steve Robbins 10/26/2018 7:50 AM
Sanitary Sewer - Air Test Partial 10/24/2018 10/26/2018
Informational
10/26/2018
Air test passed on lines F,G & C from Manhole 10-14. Air tested on the remaining portion of line C will be performed after the required 30 days after installation As per Spec. .
Sanitary Sewer - Mandrel Partial 10/24/2018 10/26/2018
Informational
10/26/2018
Mandrel passed on line F,G & C from Manhole 10-14. Line C will be completed after the required 30 days, after installation as per Spec. .
Sanitary Sewer - Vacuum Partial 10/24/2018 10/26/2018
Informational
10/26/2018
Vacuum test passed on Manholes on Line F,G & C on Maholes 10-14. The remaining portion of Line C will tested after it clears the 30 days after installation as per Spec. .
Sanitary Sewer Construction Inspection Partial 10/24/2018 10/26/2018
Informational
10/26/2018
Tracer wire passed on line F,G & C from Manholes 10-14. The test on the remaining tracer wire will be performed when the rest of Line C has passed the 30 day interval after installation as per Spec. .
Pavement-Proof Roll Partial 10/30/2018 at 9:00 AM 11/01/2018
Misc
Informational
10/26/2018
This was a proofroll for the subgrade. The fly ash did not have time to set up, it was pumping in several spots on the first street. Steve Robbins 10/26/2018 7:50 AM
PW-Misc
Corrective Action Required
11/01/2018
The proofroll failed again, it was doing much better, the problem now is over 3 sewer lateral crossings. Dan Harper was out sick so I spoke with Kent and Gene about this as the e-mails were coming in from the developer. On wednesday morning Gene spoke with George Binger about what to do for these crossings, I also spoke with Dan on wednesday morning and he thought if it was not too deep to fill in with MO type- and do it in 6" lifts and compact. John Jackson and I observed that is was only a few feet deep and allowed to fill with Mo-Type-5. John Jackson stayed out and observed what was going on. John says we are doing a proofroll on monday. The only part that has not passed is the three road crossings in question. Steve Robbins 11/01/2018 10:11 AM
Storm - Rip Rap Partial 11/1/2018 11/01/2018
Miscellaneous Correction
Corrective Action Required
11/01/2018
Contractor installed rip-rap around storm outlet as per projct plans.
Miscellaneous Correction
Corrective Action Required
11/01/2018
Contractor installed rip-rap around storm outlet as per projct plans.
Storm - Outlet Structure Partial 11/1/2018 11/01/2018
Misc
Corrective Action Required
11/01/2018
Storm outlet structures were installed completely on 10/31/18. If further work is required on Storm outlet structures it will be done before completion of project.
Pavement-Proof Roll Partial 11/2/2018 11/05/2018
Misc
Informational
11/01/2018
This was a proofroll for the subgrade. The fly ash did not have time to set up, it was pumping in several spots on the first street. Steve Robbins 10/26/2018 7:50 AM
PW-Misc
Corrective Action Required
11/01/2018
The proofroll failed again, it was doing much better, the problem now is over 3 sewer lateral crossings. Dan Harper was out sick so I spoke with Kent and Gene about this as the e-mails were coming in from the developer. On wednesday morning Gene spoke with George Binger about what to do for these crossings, I also spoke with Dan on wednesday morning and he thought if it was not too deep to fill in with MO type- and do it in 6" lifts and compact. John Jackson and I observed that is was only a few feet deep and allowed to fill with Mo-Type-5. John Jackson stayed out and observed what was going on. John says we are doing a proofroll on monday. The only part that has not passed is the three road crossings in question. Steve Robbins 11/01/2018 10:11 AM
Informational
11/05/2018
On 11/2/2018 Proof Roll passed over the sanitary sewer line crossings on line F between Station 4+00 and 7+00. Placing 18" of 2" clean rock and 18" of Missouri 5 over 3 sanitary sewer line crossing corrected areas of concern and allowed proof roll to pass (As per Specs).
Curb - Proof Roll Passed 11/15/2018 11/16/2018
Informational
11/16/2018
Proof roll passed inspection areas of concern dried out with rising temperatures 11/15/16. Ticket # 2324459 was taken for the Dump Truck used to proof roll John Jackson 11/16/2018 3:38 PM
Public Curb Inspection Partial 11/19/2018 11/20/2018
Informational
11/16/2018
Contractor installed approximately 60% of curb on newly constructed roads. All curbs were blanketed due to the forecasting of overnite freezing temperatures.
Informational
11/20/2018
Contractor installed 60% of curbs on 11/16/18 Friday & blanketed curbs. Contractor continued installation of curbs Monday 11/19/18 & blanketed curbs as section 502.4.1 Porland cement concrete base pavement Cold Weather Concrete. John Jackson 11/20/2018 8:27 AM
Public Curb Inspection Partial 11/20/2018 11/20/2018
Misc
Informational
11/20/2018
All storm inlet were poured and covered with blankets inaccrodance to cold weather concrete spec.
Water Line - Construction Inspection Partial 12/4/2018 12/04/2018
Informational
12/05/2018
Contractor installed 8" C-900 Class 200 PVC from sta 1+25 to Sta 6+00 on line 9. John Jackson 12/05/2018 9:29 AM
Water Line - Fire Hydrant Partial 12/4/2018 12/04/2018
Informational
12/05/2018
Hydrants installed @ Sta 1+57.50 & 5+85.47. John Jackson 12/05/2018 9:25 AM
Grading/Excavation/Fill Inspection Partial 12/4/2018 12/05/2018
Informational
12/05/2018
Contractor began grading streets. Temperature above 30 degrees. John Jackson 12/05/2018 9:49 AM
Water Line - Construction Inspection Partial 12/5/2018 12/05/2018
Informational
12/05/2018
Contractor secured installation of fire hydrants on line 9 and installed approximately 200' of 8" C-900 Class 200 PVC Water Main on Line 8 From 0+30 to 2+00. John Jackson 12/05/2018 4:01 PM
Water Line - Construction Inspection Partial 12/7/2018 12/07/2018
Informational
12/07/2018
Contractor installed approximately 100' on line 7 & 300' on line 6 of 8" PVC. John Jackson 12/07/2018 4:01 PM
Water Line - Fire Hydrant Partial 12/7/2018 12/07/2018
Informational
12/07/2018
Contractor installed new temporary fire hydrant assembly on line 7 sta 1+46.39, and a fire hydrant was installed at sta 3+02.24 on line 6.
Water Line - Fire Hydrant Partial 12/10/2018 12/10/2018
Informational
12/10/2018
Contractor installed final hydrant on Line 6 @ sta 8+33.59. John Jackson 12/10/2018 3:45 PM
Water Line - Construction Inspection Partial 12/10/2018 12/10/2018
Informational
12/10/2018
Contractor installed approximately 500' of 8" C-900 Class 200 PVC water main on Line 6. Contractor has completed the intial installation of water mains on the project. John Jackson 12/10/2018 3:54 PM
Curb - Proof Roll Passed 12/11/2018 12/11/2018
Informational
12/11/2018
Proof roll passed contractor will lay asphalt tommorrow. John Jackson 12/11/2018 4:01 PM
Sanitary Sewer - Mandrel Passed 12/11/2018 12/11/2018
Informational
12/11/2018
Mandrel test pass for the remaining proption of the sanitary sewer main and manholes. Mandrel C-8, C-7, C-6, & C-5 passed.John Jackson 12/11/2018 4:02 PM
Sanitary Sewer - Vacuum Passed 12/12/2018 12/12/2018
Misc
Informational
12/12/2018
Contractor completed vacuum test on the off-site sanitary Manholes C-5 to C-10. Vacuum complete for all MH on project.
Sanitary Sewer - Air Test Passed 12/12/2018 12/12/2018
Misc
Informational
12/12/2018
Contractor completed all air test on off-site 8” sanitary main.
Misc
Informational
12/12/2018
Contractor completed all air test on off-site 8” sanitary main.
Water Line - Thrust Restraint Passed 12/11/2018 12/12/2018
Informational
12/12/2018
Contractor poured all backing blocks and straddle blocks on water main that were required as per project plans.
Pavement-Surface Partial 12/12/2018 12/13/2018
Informational
12/13/2018
Contractor Superior Bowen Asphalt Co. completed laying the first base layer of asphalt on all street. Second base layer of asphalt is required on (Jamestown Drive). Tentative schedule to lay second base layer on (Jamestown Drive) and surface layer. John Jackson 12/13/2018 8:51 AM
Water Line - Hydrostatic Test Passed 12/13/2018 12/13/2018
Misc
Informational
12/13/2018
Hydrostatic test on water line 9, 8”PVC passed @ 11am (approximately 600’ of water main). Hydrostatic test on water line 8, 8”PVC passed @ 1:15pm (approximately 240’ of water main). Hydrostatic test on water Line 7, 8”PVC passed @ 3:45pm (approximately 150’ of water main).
Water Line - Hydrostatic Test Passed 12/19/2018 12/19/2018
Informational
12/19/2018
All water mains have been tested and passed on project. John Jackson 12/19/2018 4:25 PM
Pavement-Surface Partial 12/15/2018 02/08/2019
Misc
Informational
12/15/2018
Second asphalt base was layed on Jamestown Drive at 10:30am.
Street - Surface Course Passed 12/15/2018 02/08/2019
Misc
Informational
12/15/2018
Contractor completed laying surface asphalt on NE Saratoga Court, Unamed Stub street, Goshen Drive, & Jamestown Drive.
Street - Wedge Lift Partial 12/15/2018 02/08/2019
Misc
Informational
12/15/2018
Contractor layed wedges along NE Saratoga Court.
Misc
Informational
12/15/2018
Contractor layed wedges along NE Saratoga Court.
Street - Surface Course Partial 12/15/2018 02/08/2019
Water Line - Construction Inspection Passed 12/11/2018 02/08/2019
Misc
Informational
02/08/2019
All water lines have been installed, completely tested and passed inspection.
ADA Inspection Partial 4/3/2019 04/03/2019
Informational
04/03/2019
Met with contractor about % of ADA ramp along the collector street of Jamestown Dr. & Goshen Dr. NE corner. 5% on ramp is allowed because it is located on the collector street. Contractor was forming the other sidewalks for ADA ramps throughout the project. Contractor poured the remaining ADA ramps and sidewalks.
Site Visit Complete 4/4/2019 04/04/2019
Informational
04/04/2019
General inspection of the site. Significant progress was made on grading and laying hay mats to encourage vegetation. I will schedule inspection of ADA ramps and sidewalks. I talk with Steven Conrick and Steve Robbins about the removal of skimmer and the installation of drain piping from Water Basin to storm basin. Steve Robbins remind Hollthouse that when remove the skimmer the drain pipe is to be installed. John Jackson 04/04/2019 2:57 PM
Erosion Control Inspection Failed 4/3/2019 04/04/2019
Informational
04/04/2019
Some issues of immediate concern are on the East end (Saratoga Court) of project silt from Lots 99, 100 & 101 have caused Field Inlet 3-5 to be clogged with silt. Silt fencing along that very same street needs to be cleaned out and reinstalled. Founded during Grading Inspection of site with Steven Conrick. Pictures of affected area will be available in CityView. John Jackson 04/04/2019 3:25 PM
ESC - (Vegetation/Ground Cover) Passed 4/3/2019 04/12/2019
Informational
04/03/2019
Contractor started laying hay matting 4/2/19 Roughly 10% done at this time. Grading still required throughout the site as matting is being installed .John Jackson 04/03/2019 3:56 PM
Misc
Informational
04/12/2019
Contractor continues to lay spread seed and hay over site to promote vegetation. Approximately 90% due expected time of completion is today 4/12/19.
Street - Wedge Lift Passed 04/18/2019
Pavement-Surface Passed 04/18/2019
Street - Surface Course Passed 04/18/2019
Install Street and Stop Signs Passed 4/2/2019 04/18/2019
Misc
Informational
04/18/2019
All the street signs have been installed.
Curb - Compression Strength Passed 04/18/2019
Storm - Swales Passed 4/18/2019 04/18/2019
Misc
Informational
04/18/2019
John Jackson, Steven Concrick and myself have been out and checked the swales and as-graded and it all appears to be in good standing.
ESC - (Vegetation/Ground Cover) Partial 4/18/2019 04/18/2019
Misc
Informational
04/18/2019
The contractor has installed hay and seed throughout the site, we allowed them to install hay because of a shortage of straw.
Storm - Inlets Clean Passed 04/18/2019
Water Line - Coliform Test 1 Passed 04/18/2019
Misc
Informational
04/18/2019
The water samples have passed for 2 days.
Storm - Pipe Passed 04/18/2019
Water Line - Construction Inspection Passed 04/18/2019
Install Street and Stop Signs Passed 04/18/2019
Storm - Material Verification Passed 04/18/2019
Sanitary - Material Verification Passed 04/18/2019
Sanitary Sewer - Invert Passed 04/18/2019
Water - Material Verification Passed 04/18/2019
Water Line - Hydrostatic Test Passed 04/18/2019
Water Line - Coliform Test 1 Passed 04/18/2019
Water Line - Coliform Test 2 Passed 04/18/2019
Water Line - Valve Passed 04/18/2019
Water Line - Thrust Restraint Passed 04/18/2019
Erosion Control Inspection Passed 12/13/2018 04/18/2019
PW-Devices for Erosion and Sediment Control
Corrective Action Required
10/23/2018
There are problems with the erosion control devices on your site. On friday 10/12/18 we had an on-site meeting at the church on Lakewood Way that backs up to the Montcello Project. During the heavey rains that occured over the past weekend the temporary sediment basin overflowed and a lot of silt washed off the Monticello property onto the church property. The silt ran into the church detention basin . Troy Bellah , Chad Holthouse, Dan Harper , myself and John Jackson met on-sight and determined that the Montecello representitives have to clean out the detention basin on the church property. The church and the contractors agreed to have it done in the next few weeks. They have also installed all new erosion control devices around the entire property. Steve Robbins 10/23/2018 7:13 AM
Water Line - Construction Taps Removed Passed 04/18/2019
Sanitary Sewer - Air Test Passed 04/18/2019
Sanitary Sewer - Mandrel Passed 04/18/2019
Sanitary Sewer - Vacuum Passed 04/18/2019
Sanitary Sewer Construction Inspection Passed 04/18/2019
Storm - Rip Rap Passed 04/18/2019
Miscellaneous Correction
Corrective Action Required
11/01/2018
Contractor installed rip-rap around storm outlet as per projct plans.
Miscellaneous Correction
Corrective Action Required
11/01/2018
Contractor installed rip-rap around storm outlet as per projct plans.
Storm - Outlet Structure Passed 04/18/2019
Misc
Corrective Action Required
11/01/2018
Storm outlet structures were installed completely on 10/31/18. If further work is required on Storm outlet structures it will be done before completion of project.
Pavement-Proof Roll Passed 04/18/2019
Misc
Informational
11/05/2018
This was a proofroll for the subgrade. The fly ash did not have time to set up, it was pumping in several spots on the first street. Steve Robbins 10/26/2018 7:50 AM
Public Curb Inspection Passed 04/18/2019
Misc
Informational
11/20/2018
All storm inlet were poured and covered with blankets inaccrodance to cold weather concrete spec.
Water Line - Fire Hydrant Passed 04/18/2019
Grading/Excavation/Fill Inspection Passed 04/18/2019
Sanitary Sewer - Invert Passed 04/18/2019
Sanitary Sewer - Invert Passed 04/18/2019
ADA Inspection Passed 04/18/2019
Sanitary Sewer Construction Inspection Partial 4/17/2019 05/10/2019
Misc
Corrective Action Required
05/10/2019
The camera test that was done revealed that MH 6-029 was repaired for infiltration for the 3rd time and needs to be checks again. The sag for MH 06--70 was repaired and waiting for the 30 days for another camera test.
Sanitary Sewer Construction Inspection Partial 5/21/2019 05/21/2019
Misc
Corrective Action Required
05/10/2019
The camera test that was done revealed that MH 6-029 was repaired for infiltration for the 3rd time and needs to be checks again. The sag for MH 06--70 was repaired and waiting for the 30 days for another camera test.
Misc
Informational
05/21/2019
Sent Brent an e-mail to let him know the 30 days are up for the sag that has been repaired and to also check the infiltration on the existiing MH.Steve Robbins 05/21/2019 3:53 PM
ESC - (Vegetation/Ground Cover) Passed 5/29/2019 05/29/2019
Misc
Informational
05/29/2019
Vegetation and ground covering approximately 85% to 90% throughout 3rd plate.
Water Line - Construction Inspection Partial 7/17/2019 07/17/2019
Informational
07/17/2019
Water sample had to be retaken because of a valve was closed on Jamestown Drive and stopped the flow of water to water main on a dead end cul de sac of NE Goshen Court . The first sample was taken on 7/16/19 7:00AM and the second was taken 7/17/19 8:30 AM.
Water Line - Construction Inspection Passed 10/22/2019
Erosion Control Inspection Failed 10/21/2019 10/22/2019
PW-Misc
Corrective Action Required
10/22/2019
A complaint from 4712 Pocono Circ was received about silt running to their yard from the houses behind. I checked the complaint and it appears that silt has ran down from lot 4705, 4709, and 4713 and has filled in the swale that runs between the houses. The houses have silt fence up as of now but it appears that it has failed recently as there is a lot of silt in the swale and has come over in the yard of 4712 Pocono circ. I will reach out to the developer to see if he can work together with the builders to get this taken care of.
Sanitary Sewer Construction Inspection Passed 6/28/2019 12/04/2019
Misc
Corrective Action Required
05/21/2019
The camera test that was done revealed that MH 6-029 was repaired for infiltration for the 3rd time and needs to be checks again. The sag for MH 06--70 was repaired and waiting for the 30 days for another camera test.
Misc
Informational
05/21/2019
Sent Brent an e-mail to let him know the 30 days are up for the sag that has been repaired and to also check the infiltration on the existiing MH.Steve Robbins 05/21/2019 3:53 PM
Misc
Informational
12/04/2019
All the sanitary has passed and been accepted.
Erosion Control Inspection Passed 1/6/2020 01/06/2020
PW-Misc
Corrective Action Required
10/22/2019
A complaint from 4712 Pocono Circ was received about silt running to their yard from the houses behind. I checked the complaint and it appears that silt has ran down from lot 4705, 4709, and 4713 and has filled in the swale that runs between the houses. The houses have silt fence up as of now but it appears that it has failed recently as there is a lot of silt in the swale and has come over in the yard of 4712 Pocono circ. I will reach out to the developer to see if he can work together with the builders to get this taken care of.
Misc
Partial Correction
01/06/2020
I beleive this issue has been resolved as it was turned over to the contractors that are building the houses.
Install Street and Stop Signs Passed 01/17/2020
Storm - Material Verification Passed 01/17/2020
Sanitary - Material Verification Passed 01/17/2020
Sanitary Sewer Construction Inspection Passed 01/17/2020
Water - Material Verification Passed 01/17/2020
Water Line - Construction Inspection Passed 01/17/2020
Install Street and Stop Signs Passed 05/05/2020
Water Line - Construction Inspection Passed 05/05/2020
ESC - (Vegetation/Ground Cover) Passed 05/08/2020
Documents & Images
Date Uploaded File Type Document Name
11/03/2016 Receipt Receipt for transaction: 2016-006717
11/03/2016 Receipt Receipt for transaction: 2016-006717
07/30/2018 Receipt Receipt for transaction: 2018-005265
07/31/2018 Letter DE-Permit
08/02/2018 Letter DE-Daily Inspection Summary
08/03/2018 Letter DE-Daily Inspection Summary
08/06/2018 Letter DE-Daily Inspection Summary
08/16/2018 Letter DE-Daily Inspection Summary
08/21/2018 Letter DE-Daily Inspection Summary
08/21/2018 Letter DE-Daily Inspection Summary
08/30/2018 Letter DE-Daily Inspection Summary
08/31/2018 Letter DE-Daily Inspection Summary
09/04/2018 Letter DE-Daily Inspection Summary
09/05/2018 Letter DE-Daily Inspection Summary
09/05/2018 Receipt Receipt for transaction: 2018-006218
09/05/2018 Letter DE-Permit
09/06/2018 Letter DE-Daily Inspection Summary
09/21/2018 Letter DE-Daily Inspection Summary
09/21/2018 Letter DE-Daily Inspection Summary
09/21/2018 Letter DE-Daily Inspection Summary
09/21/2018 Letter DE-Daily Inspection Summary
09/21/2018 Letter DE-Daily Inspection Summary
09/24/2018 Letter DE-Daily Inspection Summary
09/24/2018 Letter DE-Daily Inspection Summary
09/25/2018 Letter DE-Daily Inspection Summary
09/28/2018 Letter DE-Daily Inspection Summary
09/28/2018 Letter DE-Daily Inspection Summary
10/02/2018 Letter DE-Daily Inspection Summary
10/04/2018 Letter DE-Daily Inspection Summary
10/05/2018 Letter DE-Daily Inspection Summary
10/05/2018 Letter DE-Daily Inspection Summary
10/17/2018 Letter DE-Daily Inspection Summary
10/23/2018 Letter DE-Daily Inspection Summary
10/23/2018 Letter DE-Daily Inspection Summary
10/26/2018 Letter DE-Daily Inspection Summary
10/26/2018 Letter DE-Daily Inspection Summary
10/26/2018 Letter DE-Daily Inspection Summary
10/26/2018 Letter DE-Daily Inspection Summary
11/01/2018 Letter DE-Daily Inspection Summary
11/01/2018 Letter Inspection Summary
11/01/2018 Letter Inspection Summary
11/01/2018 Letter Inspection Summary
11/01/2018 Letter Inspection Summary
11/01/2018 Letter Inspection Summary
11/01/2018 Letter DE-Daily Inspection Summary
11/01/2018 Letter Inspection Summary
11/01/2018 Letter DE-Daily Inspection Summary
11/01/2018 0485E7FB-C36E-4ABF-9B8A-8ECDF63CE67D
11/01/2018 5B996B24-250D-4CC1-B500-0027A41344E5
11/01/2018 77CD92A8-8E1B-4B14-BD22-EDF941A3239F
11/01/2018 495A6058-15BC-4B1D-8F2F-BD78F4574B16
11/01/2018 253508D6-F939-42AB-B428-C8646705801A
11/01/2018 3BB4DA50-AA36-4D71-83D0-2C2D50DA3E59
11/01/2018 73C0788F-A668-4292-9654-979597B5844D
11/01/2018 FF14ABE9-65B6-4628-88EA-CEB28A6EC0CC
11/01/2018 93776B79-593C-47BA-928F-54831BD2AC5A
11/01/2018 D34FB523-E888-4035-8955-50A86BE143F0
11/01/2018 79B6243E-4D17-4E0D-9DC7-71C5C157A103
11/01/2018 Letter Inspection Summary
11/01/2018 Letter Inspection Summary
11/05/2018 Letter DE-Daily Inspection Summary
11/16/2018 Letter Inspection Summary
11/16/2018 Letter Inspection Summary
11/20/2018 Letter DE-Daily Inspection Summary
12/05/2018 Letter DE-Daily Inspection Summary
12/05/2018 Letter DE-Daily Inspection Summary
12/07/2018 Letter DE-Daily Inspection Summary
12/10/2018 Letter DE-Daily Inspection Summary
12/11/2018 Letter DE-Daily Inspection Summary
12/11/2018 DE-Daily Inspection Summary_20181211160305
12/12/2018 Letter Inspection Summary
12/12/2018 Letter Inspection Summary
12/12/2018 Letter Inspection Summary
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter Inspection Summary
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter Inspection Summary
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter DE-Daily Inspection Summary
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter DE-Daily Inspection Summary
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter Inspection Summary
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter INSPECTION SUMMARY
12/12/2018 Letter DE-Daily Inspection Summary
12/13/2018 Letter DE-Daily Inspection Summary
12/15/2018 Letter INSPECTION SUMMARY
12/15/2018 Letter INSPECTION SUMMARY
12/15/2018 Letter INSPECTION SUMMARY
12/15/2018 Letter INSPECTION SUMMARY
12/19/2018 Letter DE-Daily Inspection Summary
02/08/2019 Letter INSPECTION SUMMARY
02/08/2019 Letter INSPECTION SUMMARY
02/08/2019 Letter INSPECTION SUMMARY
02/08/2019 Letter INSPECTION SUMMARY
02/08/2019 Letter INSPECTION SUMMARY
02/08/2019 Letter INSPECTION SUMMARY
02/08/2019 Letter INSPECTION SUMMARY
02/08/2019 Letter INSPECTION SUMMARY
02/08/2019 Letter INSPECTION SUMMARY
02/08/2019 Letter INSPECTION SUMMARY
02/08/2019 Letter INSPECTION SUMMARY
02/25/2019 Monticello 3rd Plat pic invert 06-67 (MH C-10) 1
02/25/2019 Monticello 3rd Plat pic invert 06-67 (MH C-10) 2
02/25/2019 Monticello 3rd Plat pic invert 06-67 (MH C-10) 3
02/25/2019 Letter DE-Certificate of Substantial Completion Multiple Lot
02/25/2019 Letter DE-Certificate of Substantial Completion Multiple Lot
02/25/2019 Letter DE-Certificate of Substantial Completion Multiple Lot
03/15/2019 Monticello 3rd Plat Partial Substantial
03/15/2019 Monticello 3rd Plat Partial Substantial
04/03/2019 Letter DE-Daily Inspection Summary
04/03/2019 Letter DE-Daily Inspection Summary
04/04/2019 Letter DE-Daily Inspection Summary
04/04/2019 Letter DE-Daily Inspection Summary
04/05/2019 IMG_Silt fencing 4/3/19
04/05/2019 IMG_Silting erosion 4/3/19
04/05/2019 IMG_ Field Inlet 3-5 filled with silt 4/3/19
04/05/2019 IMG_Field Inlet 3-5 filled with silt 4/3/19
04/12/2019 Letter INSPECTION SUMMARY
04/12/2019 Letter INSPECTION SUMMARY
04/12/2019 Letter INSPECTION SUMMARY
04/12/2019 Letter INSPECTION SUMMARY
04/17/2019 Letter DE-Punch List
04/17/2019 Letter DE-Certificate of Substantial Completion Multiple Lot
04/18/2019 Letter DE-Daily Inspection Summary
04/18/2019 Letter DE-Daily Inspection Summary
04/18/2019 Letter DE-Daily Inspection Summary
04/18/2019 Letter DE-Daily Inspection Summary
04/19/2019 Letter DE-Punch List
04/19/2019 Letter DE-Certificate of Substantial Completion Multiple Lot
04/19/2019 Monticello partial substantial sanitary only
05/10/2019 Letter DE-Daily Inspection Summary
05/21/2019 Letter DE-Daily Inspection Summary
07/17/2019 Letter DE-Daily Inspection Summary
10/22/2019 Letter DE-Daily Inspection Summary
12/04/2019 Letter DE-Daily Inspection Summary
01/06/2020 Letter DE-Daily Inspection Summary
05/07/2020 Letter DE-Certificate of Final Acceptance (Commercial)
05/07/2020 Monticello 3rd Plat Final Acceptance
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home