Summary


PRSITE20241812
Development - Site
Final Completion
DEVELOPMENT COMPLETE
SUMMIT ORCHARDS WEST, LOT 10C - MASS GRADING, STORM SEWER AND COMMON SPLINE DRIVE
04/12/2024
07/08/2024
06/03/2025
Locations
Contacts
PHELPS ENGINEERING, INC, Address:1270 N WINCHESTER RD, Phone:(913) 393-1155  
Fleshman Construction Inc, Address:16a Westwoods Drive, Phone:(816) 421-0052  
  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Storm Sewer Inspection Fee $957.60 $957.60 Paid 07/02/2024
Site Grading Fee $769.35 $769.35 Paid 07/02/2024
Right of Way Permit Fee $85.00 $85.00 Paid 07/02/2024
Paved Surface Inspection Fee $2,484.48 $2,484.48 Paid 07/02/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Partial 6/11/2024 6/11/2024 07/11/2024
Misc
Informational
06/11/2024
08/16/24 Friday JMJ (Fleahman Const.) sediment control silt fence appears to be working on site project.
Sidewalk Inspection Partial 7/11/2024 7/11/2024 07/11/2024
Misc
Informational
07/11/2024
07/11/24 Wednesday JMJ (Star Development) Contractor poured approximately 150' of sidewalk.
Grading/Excavation/Fill Inspection Partial 7/26/2024 7/26/2024 07/26/2024
Misc
Informational
07/26/2024
07/26/24 Friday JMJ Contractor grading the site for construction last week.
Grading/Excavation/Fill Inspection Partial 8/5/2024 8/5/2024 08/05/2024
Misc
Informational
07/26/2024
07/26/24 Friday JMJ Contractor grading the site for construction last week. 08/05/24 Monday JMJ Contractor began to excavating the existing abandon 16" water main.
Storm Sewer Construction Inspection Partial 8/7/2024 8/7/2024 08/07/2024
Misc
Informational
08/07/2024
08/07/24 Wednesday JMJ (Fleshman Construction) Contractor demolition the invert of existing storm box NE corner of project. 120' of 24" HDPE of storm pipe was installed along Ward Road head South.
Site Visit Partial 8/9/2024 8/9/2024 08/09/2024
Misc
Informational
08/09/2024
08/09/24 Friday JMJ Contractor has been removing existing gas, water, & storm lines and structures.
Storm Sewer Construction Inspection Partial 8/14/2024 8/14/2024 08/14/2024
Misc
Informational
08/14/2024
08/14/24 Wednesday JMJ (Fleshman Const) Contractor finished the installation of the storm line approximately 150' as-per project plans. inverts and collars were installed before backfill.
Sanitary Sewer Construction Inspection Partial 8/14/2024 8/14/2024 08/14/2024
Misc
Informational
08/14/2024
08/14/24 Wednesday JMJ (Fleshman Const.) Contractor began the installation of the 8" SDR-26 sanitary main starting from the exist MH that was cored in last week. Approximately 63' of sanitary main was installed today.
Sanitary Sewer Construction Inspection Partial 8/15/2024 8/15/2024 08/15/2024
Misc
Informational
08/14/2024
08/14/24 Wednesday JMJ (Fleshman Construction) Contractor began the installation of the 8" SDR-26 sanitary main starting from the exist MH that was cored in last week. Approximately 63' of sanitary main was installed today. 08/15/24 Thursday JMJ (Fleshman Construction) Contractor continued the installation of the 8" SDR-26 sanitary main stacking MH A1 and beginning. the construction MH A2.
Sanitary Sewer Construction Inspection Partial 8/16/2024 8/16/2024 08/16/2024
Misc
Informational
08/15/2024
08/14/24 Wednesday JMJ (Fleshman Construction) Contractor began the installation of the 8" SDR-26 sanitary main starting from the exist MH that was cored in last week. Approximately 63' of sanitary main was installed today. 08/15/24 Thursday JMJ (Fleshman Construction) Contractor continued the installation of the 8" SDR-26 sanitary main stacking MH A1 and beginning. the construction MH A2. 08/16/24 Friday JMJ (Fleshman Construction) Contractor continued to install approximately 375' of 8" SDR-26 sanitary main. Contractor plans to pour inverts and collars at 1:30PM today for MHs.
Sanitary Sewer Construction Inspection Partial 8/19/2024 8/19/2024 08/19/2024
Misc
Informational
08/16/2024
08/14/24 Wednesday JMJ (Fleshman Construction) Contractor began the installation of the 8" SDR-26 sanitary main starting from the exist MH that was cored in last week. Approximately 63' of sanitary main was installed today. 08/15/24 Thursday JMJ (Fleshman Construction) Contractor continued the installation of the 8" SDR-26 sanitary main stacking MH A1 and beginning. the construction MH A2. 08/16/24 Friday JMJ (Fleshman Construction) Contractor continued to install approximately 375' of 8" SDR-26 sanitary main. Contractor plans to pour inverts and collars at 1:30PM today for MHs. 08/19/24 Monday JMJ (Fleshman Construction) Contractor plans to use backflow around sanitary MHs (ground stabilization) and stack out the MHs.
Site Visit Partial 8/20/2024 8/20/2024 08/20/2024
Misc
Informational
08/09/2024
08/09/24 Friday JMJ Contractor has been removing existing gas, water, & storm lines and structures. 08/20/24 Tuesday JMJ (Fleshman Const.) Contractor has been backfilling storm and sanitary newly installed mains.
Grading/Excavation/Fill Inspection Partial 8/21/2024 8/21/2024 08/21/2024
Misc
Informational
08/05/2024
07/26/24 Friday JMJ Contractor grading the site for construction last week. 08/05/24 Monday JMJ Contractor began to excavating the existing abandon 16" water main. 08/21/24 Wednesday JMJ Contractor continued grading site to prepare subgrade for approaches & driveway construction.
Site Visit Partial 8/27/2024 8/27/2024 08/27/2024
Misc
Informational
08/20/2024
08/09/24 Friday JMJ Contractor has been removing existing gas, water, & storm lines and structures. 08/20/24 Tuesday JMJ (Fleshman Const.) Contractor has been backfilling storm and sanitary newly installed mains. 08/28/24 Tuesday JMJ (Fleshman Const.) Contractor continues to work on approaches, streets and grading. The third party testing RONE engineering for compaction testing was on site. RONE engineering passed compaction on South of proposed street/ drive-lane. Compaction FAILED on the Northside of project due to not having an adequate amount of moisture in the soil. Fleshman was advised to correct the issue. Also contractor will be ready for proof roll of approaches and road tomorrow morning .
Pavement-Proof Roll Partial 8/28/2024 8/28/2024 08/28/2024
Misc
Informational
08/28/2024
08/28/24 Wednesday JMJ (Fleshman Cont.) Proof roll past test.
Pavement-Curb Construction Partial 8/29/2024 8/29/2024 08/29/2024
Misc
Informational
08/29/2024
08/29/24 Thursday JMJ (Fleshman Const.) Forms and curbs were poured on the Southwest side of project. Formed curbs for approach were placed on the Northeast side of project.
Pavement-Curb Construction Partial 8/30/2024 8/30/2024 08/30/2024
Misc
Informational
08/29/2024
08/29/24 Thursday JMJ (Fleshman Const.) Forms and curbs were poured on the Southwest side of project. Formed curbs for approach were placed on the Northeast side of project. 08/30/24 Friday JMJ (Fleshman Const.) Forms and curbs were installed on the third Northwest side of the 3rd approach.
Driveway Inspection Partial 9/4/2024 9/4/2024 09/04/2024
Misc
Informational
09/04/2024
08/04/23 Wednesday JMJ Contractor poured Southwest approach yesterday and Northwest approach today.
Pavement-Aggregate Base Partial 9/4/2024 9/4/2024 09/04/2024
Misc
Informational
09/04/2024
09/04/24 Wednesday JMJ (Way & Son) Contractor began to lay the aggregate base for the strip of pavement running for the Southwest and the Northeast approach.
Sanitary Sewer - Mandrel Passed 9/23/2024 9/23/2024 09/23/2024
Misc
Informational
09/23/2024
09/23/24 Monday JMJ Mandrel test for all project the sewer main.
Sanitary Sewer - Air Test Passed 9/23/2024 9/23/2024 09/23/2024
Misc
Informational
09/23/2024
09/23/24 Monday JMJ (Fleshman Construction) The air system passed from SSMH A2 to A3, A2 to A1, & A1 to Existing.
Sanitary Sewer - Vacuum Passed 9/23/2024 9/23/2024 09/23/2024
Misc
Informational
09/23/2024
09/23/24 Monday JMJ ( Fleshman Construction ) Vacuum test passed for SSMH-A1, A2, & ,A3.
Grading/Excavation/Fill Inspection Partial 9/27/2024 9/27/2024 09/27/2024
Misc
Informational
08/21/2024
07/26/24 Friday JMJ Contractor grading the site for construction last week. 08/05/24 Monday JMJ Contractor began to excavating the existing abandon 16" water main. 08/21/24 Wednesday JMJ Contractor continued grading site to prepare subgrade for approaches & driveway construction. 09/27/24 Friday JMJ Contractor laid seed and hay on project site.
Driveway Inspection Passed 09/30/2024
Misc
Informational
09/04/2024
08/04/23 Wednesday JMJ Contractor poured Southwest approach yesterday and Northwest approach today.
ESC - (Vegetation/Ground Cover) Partial 09/30/2024
Misc
Informational
09/30/2024
09/30/24 Monday JMJ EC - ( Vegetation/Ground Cover) Contractor seeded and applied hay to project site.
Erosion Control Inspection Passed 09/30/2024
Misc
Informational
06/11/2024
06/11/24 Tuesday Erosion control was installed two weeks ago. Erosion control appears to be functionable. 09/30/24 Monday JMJ Erosion control appears to be functionable.
Grading/Excavation/Fill Inspection Passed 09/30/2024
Misc
Informational
09/27/2024
07/26/24 Friday JMJ Contractor grading the site for construction last week. 08/05/24 Monday JMJ Contractor began to excavating the existing abandon 16" water main. 08/21/24 Wednesday JMJ Contractor continued grading site to prepare subgrade for approaches & driveway construction. 09/27/24 Friday JMJ Contractor laid seed and hay on project site.
ESC - (Vegetation/Ground Cover) Passed 09/30/2024
Misc
Informational
09/30/2024
09/30/24 Monday JMJ EC - ( Vegetation/Ground Cover) Contractor seeded and applied hay to project site.
Pavement-Aggregate Base Passed 09/30/2024
Misc
Informational
09/04/2024
09/04/24 Wednesday JMJ (Way & Son) Contractor began to lay the aggregate base for the strip of pavement running for the Southwest and the Northeast approach.
Pavement-Proof Roll Passed 09/30/2024
Misc
Informational
08/28/2024
08/28/24 Wednesday JMJ (Fleshman Cont.) Proof roll past test.
Sanitary Sewer Construction Inspection Passed 09/30/2024
Misc
Informational
08/19/2024
08/14/24 Wednesday JMJ (Fleshman Construction) Contractor began the installation of the 8" SDR-26 sanitary main starting from the exist MH that was cored in last week. Approximately 63' of sanitary main was installed today. 08/15/24 Thursday JMJ (Fleshman Construction) Contractor continued the installation of the 8" SDR-26 sanitary main stacking MH A1 and beginning. the construction MH A2. 08/16/24 Friday JMJ (Fleshman Construction) Contractor continued to install approximately 375' of 8" SDR-26 sanitary main. Contractor plans to pour inverts and collars at 1:30PM today for MHs. 08/19/24 Monday JMJ (Fleshman Construction) Contractor plans to use backflow around sanitary MHs (ground stabilization) and stack out the MHs.
Storm Sewer Construction Inspection Passed 09/30/2024
Misc
Informational
08/07/2024
08/07/24 Wednesday JMJ (Fleshman Construction) Contractor demolition the invert of existing storm box NE corner of project. 120' of 24" HDPE of storm pipe was installed along Ward Road head South.
Site Visit Partial 10/21/2024
Misc
Informational
08/27/2024
08/09/24 Friday JMJ Contractor has been removing existing gas, water, & storm lines and structures. 08/20/24 Tuesday JMJ (Fleshman Const.) Contractor has been backfilling storm and sanitary newly installed mains. 08/28/24 Tuesday JMJ (Fleshman Const.) Contractor continues to work on approaches, streets and grading. The third party testing RONE engineering for compaction testing was on site. RONE engineering passed compaction on South of proposed street/ drive-lane. Compaction FAILED on the Northside of project due to not having an adequate amount of moisture in the soil. Fleshman was advised to correct the issue. Also contractor will be ready for proof roll of approaches and road tomorrow morning .
Misc
Informational
10/21/2024
10-21-24 Dustin A , Nobody on site this morning but a surveyor
Site Visit Partial 10/22/2024 10/22/2024 10/22/2024
Misc
Informational
10/21/2024
08/09/24 Friday JMJ Contractor has been removing existing gas, water, & storm lines and structures. 08/20/24 Tuesday JMJ (Fleshman Const.) Contractor has been backfilling storm and sanitary newly installed mains. 08/28/24 Tuesday JMJ (Fleshman Const.) Contractor continues to work on approaches, streets and grading. The third party testing RONE engineering for compaction testing was on site. RONE engineering passed compaction on South of proposed street/ drive-lane. Compaction FAILED on the Northside of project due to not having an adequate amount of moisture in the soil. Fleshman was advised to correct the issue. Also contractor will be ready for proof roll of approaches and road tomorrow morning .
Misc
Informational
10/21/2024
10-21-24 Dustin A , Nobody on site this morning but a surveyor 10-22-24 Dustin A , Pad site work
Documents & Images
Date Uploaded File Type Document Name
04/12/2024 Approved Plans APPROVED FDP_REV 0_PL2024063
06/11/2024 Letter INSPECTION SUMMARY
06/11/2024 Letter INSPECTION SUMMARY
06/12/2024 Letter INSPECTION SUMMARY
06/12/2024 Letter INSPECTION SUMMARY
07/02/2024 Receipt Receipt for transaction:2024-005440
07/08/2024 Letter DE-Permit
07/11/2024 Letter INSPECTION SUMMARY
07/11/2024 Letter INSPECTION SUMMARY
07/26/2024 Letter INSPECTION SUMMARY
07/26/2024 Letter INSPECTION SUMMARY
07/26/2024 Letter INSPECTION SUMMARY
08/05/2024 Letter INSPECTION SUMMARY
08/05/2024 Letter INSPECTION SUMMARY
08/07/2024 Letter INSPECTION SUMMARY
08/07/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/14/2024 Letter INSPECTION SUMMARY
08/14/2024 Letter INSPECTION SUMMARY
08/15/2024 Letter INSPECTION SUMMARY
08/16/2024 Letter INSPECTION SUMMARY
08/19/2024 Letter INSPECTION SUMMARY
08/20/2024 Letter INSPECTION SUMMARY
08/21/2024 Letter INSPECTION SUMMARY
08/27/2024 Letter INSPECTION SUMMARY
08/28/2024 Letter INSPECTION SUMMARY
08/28/2024 Letter INSPECTION SUMMARY
08/29/2024 Letter INSPECTION SUMMARY
08/30/2024 Letter INSPECTION SUMMARY
09/04/2024 Letter INSPECTION SUMMARY
09/04/2024 Letter INSPECTION SUMMARY
09/23/2024 Letter INSPECTION SUMMARY
09/23/2024 Letter INSPECTION SUMMARY
09/23/2024 Letter INSPECTION SUMMARY
09/23/2024 Letter INSPECTION SUMMARY
09/27/2024 Letter INSPECTION SUMMARY
09/30/2024 Letter DE-Certificate of Substantial Completion Single Lot
09/30/2024 Letter DE-Punch List
09/30/2024 Letter INSPECTION SUMMARY
09/30/2024 Letter SUBD Comment Letter
09/30/2024 Letter INSPECTION SUMMARY
09/30/2024 Letter INSPECTION SUMMARY
09/30/2024 Letter INSPECTION SUMMARY
09/30/2024 Letter INSPECTION SUMMARY
09/30/2024 Letter INSPECTION SUMMARY
09/30/2024 Letter INSPECTION SUMMARY
09/30/2024 Letter INSPECTION SUMMARY
09/30/2024 Letter INSPECTION SUMMARY
09/30/2024 Letter INSPECTION SUMMARY
09/30/2024 Letter INSPECTION SUMMARY
10/21/2024 Letter INSPECTION SUMMARY
10/22/2024 Letter INSPECTION SUMMARY
10/25/2024 Letter INSPECTION SUMMARY
05/15/2025 Approved Plans Approved Amended plans to add parking spaces_REV 0_PL2024063
05/15/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home