Permit Application Status

PRSITE20215387


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSITE20215387
Development - Site
Final Acceptance
DEVELOPMENT COMPLETE
LOT 7B STREETS OF WEST PRYOR - TOWNHOMES PHASE I- VANGUARD VILLAS - site improvements
10/14/2021
11/22/2021
02/29/2024
Locations
Contacts
EMERY SAPP AND SONS INC, Address:2301 I-70 DR NW, Phone:(573) 445-8331  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 10/14/2021 11/22/2021
Dawn Bell
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $1,267.05 $1,267.05 Paid 11/22/2021
91100C9-Water Insp Fee $608.25 $608.25 Paid 11/22/2021
9110081-Paved Surface Inspection Fee $1,314.51 $1,314.51 Paid 11/22/2021
9110071-Site Grading Fee $982.65 $982.65 Paid 11/22/2021
8331401-Water Tap Fee $9,750.00 $9,750.00 Paid 11/22/2021
8350015-Water Meter Fee $820.29 $820.29 Paid 11/22/2021
8331401-Water Tap Fee $2,435.00 $2,435.00 Paid 04/26/2022
$12,185.00
8350015-Water Meter Fee $2,325.11 $2,325.11 Paid 04/26/2022
$3,145.40
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sanitary Sewer Construction Inspection Passed 02/23/2022
Misc
Informational
02/23/2022
Sanitary line C was installed. RP 1-6-22
Sanitary - Material Verification Passed 02/23/2022
Misc
Informational
02/23/2022
Sanitary materials meets LS specs. RP 1-6-23
Sanitary Sewer - Mandrel Passed 02/23/2022
Misc
Informational
02/23/2022
The correct size mandrel passed through the lines. RP 2-23-22
Site Visit Partial 02/23/2022
Misc
Informational
02/23/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the wrong diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Site Visit Partial 2/24/2022 2/24/2022 02/24/2022
Misc
Informational
02/23/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the wrong diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
02/24/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Sanitary Sewer - Air Test Partial 02/24/2022
Misc
Corrective Action Required
02/24/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Site Visit Partial 2/25/2022 2/25/2022 02/25/2022
Misc
Informational
02/24/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the wrong diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
02/24/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Misc
Informational
02/25/2022
No work being done today that needs inspection. RP 2-25-22
Site Visit Partial 2/28/2022 2/28/2022 02/28/2022
Misc
Informational
02/25/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the wrong diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
02/25/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Misc
Informational
02/25/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
02/28/2022
No work being done on site today. RP 2-28-22
Sanitary Sewer - Air Test Passed 3/1/2022 3/1/2022 03/02/2022
Misc
Corrective Action Required
02/24/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Misc
Informational
03/02/2022
Sanitary line from A-5 to C-1 passed its air testing. RP 3-2-22
Sanitary Sewer - Vacuum Partial 03/02/2022
Misc
Informational
03/02/2022
manhole C-1 failed, but manhole C-2 passed testing. RP 3-2-22
Site Visit Partial 3/2/2022 3/2/2022 03/03/2022
Misc
Informational
02/28/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the wrong diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
02/28/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Misc
Informational
02/28/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
02/28/2022
No work being done on site today. RP 2-28-22
Misc
Informational
03/03/2022
ESS is on site grading dirt. RP 3-3-22
Grading/Excavation/Fill Inspection Partial 03/03/2022
Misc
Informational
03/03/2022
ESS is on site grading dirt. RP 3-3-22
Site Visit Partial 3/4/2022 3/4/2022 03/14/2022
Misc
Informational
03/03/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the wrong diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
03/03/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Misc
Informational
03/03/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/03/2022
No work being done on site today. RP 2-28-22
Misc
Informational
03/03/2022
ESS is on site grading dirt. RP 3-3-22
Misc
Informational
03/14/2022
No work being done on site today. RP 3-10-22
Site Visit Partial 03/14/2022
Misc
Informational
03/14/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the wrong diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
03/14/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Misc
Informational
03/14/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/14/2022
No work being done on site today. RP 2-28-22
Misc
Informational
03/14/2022
ESS is on site grading dirt. RP 3-3-22
Misc
Informational
03/14/2022
No work being done on site today. RP 3-10-22
Misc
Informational
03/14/2022
ESS is grading the site today. RP 3-14-22
Site Visit Partial 3/15/2022 3/15/2022 03/22/2022
Misc
Informational
03/14/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the wrong diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
03/14/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Misc
Informational
03/14/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/14/2022
No work being done on site today. RP 2-28-22
Misc
Informational
03/14/2022
ESS is on site grading dirt. RP 3-3-22
Misc
Informational
03/14/2022
No work being done on site today. RP 3-10-22
Misc
Informational
03/14/2022
ESS is grading the site today. RP 3-14-22
Misc
Informational
03/22/2022
Too wet to work today with last nights rain, plus more rain coming to the area. No erosion issues to report. RP 3-22-22
Erosion Control Inspection Partial 03/23/2022
Misc
Informational
03/23/2022
No erosion issues to report on the job site today. RP 3-23-22
Erosion Control Inspection Partial 03/24/2022
Misc
Informational
03/23/2022
No erosion issues to report on the job site today. RP 3-23-22
Misc
Informational
03/24/2022
Another rain day, still no erosion issues to report. RP 3-24-22
Sanitary Sewer - Vacuum Failed 3/4/2022 3/4/2022 03/25/2022
Misc
Informational
03/02/2022
manhole C-1 failed, but manhole C-2 passed testing. RP 3-2-22
Misc
Corrective Action Required
03/25/2022
Manhole C-1 failed it’s vacuum test again. RP 3-25-22
Sanitary Sewer - Vacuum Passed 3/29/2022 3/29/2022 03/29/2022
Misc
Informational
03/25/2022
manhole C-1 failed, but manhole C-2 passed testing. RP 3-2-22
Misc
Corrective Action Required
03/25/2022
Manhole C-1 failed it’s vacuum test again. RP 3-25-22
Misc
Informational
03/29/2022
Manhole C-1 passed vacuum testing. RP 3-29-22
Site Visit Partial 3/24/2022 3/24/2022 04/06/2022
Misc
Informational
03/22/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the wrong diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
03/22/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Misc
Informational
03/22/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/22/2022
No work being done on site today. RP 2-28-22
Misc
Informational
03/22/2022
ESS is on site grading dirt. RP 3-3-22
Misc
Informational
03/22/2022
No work being done on site today. RP 3-10-22
Misc
Informational
03/22/2022
ESS is grading the site today. RP 3-14-22
Misc
Informational
03/22/2022
Too wet to work today with last nights rain, plus more rain coming to the area. No erosion issues to report. RP 3-22-22
Misc
Informational
04/06/2022
No utility work or grading being done today. RP 4-6-22
Site Visit Partial 4/7/2022 4/7/2022 05/25/2022
Misc
Informational
04/06/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the wrong diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
04/06/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Misc
Informational
04/06/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
04/06/2022
No work being done on site today. RP 2-28-22
Misc
Informational
04/06/2022
ESS is on site grading dirt. RP 3-3-22
Misc
Informational
04/06/2022
No work being done on site today. RP 3-10-22
Misc
Informational
04/06/2022
ESS is grading the site today. RP 3-14-22
Misc
Informational
04/06/2022
Too wet to work today with last nights rain, plus more rain coming to the area. No erosion issues to report. RP 3-22-22
Misc
Informational
04/06/2022
No utility work or grading being done today. RP 4-6-22
Misc
Informational
05/25/2022
No work being done today with rain. 5/25/22 ES
Pavement-Aggregate Base Partial 07/20/2022
Misc
Informational
07/20/2022
Seal-O-Matic laying 3” of Type 2 base asphalt on Black Twig. 7/20/22 ES
Pavement-Surface Partial 07/20/2022
Misc
Informational
07/20/2022
Seal-O-Matic laying 3” of Type 2 R base asphalt on Black Twig. 7/20/22 ES
Pavement-Surface Partial 07/21/2022
Misc
Informational
07/20/2022
Seal-O-Matic laying 3” of Type 2 R base asphalt on Black Twig. 7/20/22 ES Seal-O-Matic laying 2” of Type 2 R base asphalt on Black Twig. 7/21/22 ES
Pavement-Proof Roll Passed 07/21/2022
Misc
Informational
07/21/2022
Performed proof roll with Cody from ESS using 20.05 ton load of rock. 6/15/22 ES Performed proof roll on remaining section of Black Twig Cir w/ 20.12 tons of rock. Passed 6/17/22 ES ESS laying and compacting aggregate. 6/20/22 ES ESS working on final grading preparing for base asphalt. 7/15/22 ES Performed proof roll with 20.24 ton load on northern parking lot and all of Black Twig Cir. Only area with issue was Far East end near connection to existing parking lot where a sprinkler had saturated the ground. 7/16/22 ES Seal-O-Matic laying 3” of Type 2 base asphalt on Black Twig. 7/20/22 ES Seal-O-Matic laying 2” of Type 2 R base asphalt on Black Twig. 7/21/22 ES
Pavement-Stabilized Subgrade Passed 07/21/2022
Misc
Informational
07/21/2022
ESS was onsite grading Black Twig preparing for grid and aggregate sub base. 6/9/22 ES ESS continued work on Black Twig Cir. 6/10/22 ES ESS laid down geogrid and started covering with rock and grading. 6/13/22 ES ESS continued work on Black Twig Cir. 6/14/22 ES Performed proof roll with Cody from ESS, had one section ~100’ from station 20+40 to 21+40 proof rolled from station 17+50 to Lowenstein Dr and all other areas passed. 6/15/22 ES Seal-o-matic was onsite performing sub base stabilization on upper part of Black Twig Cir. 6/16/22 ES Performed a proof roll on Black Twig Cir. Passed. 6/17/22 ES ESS laying and compacting aggregate on top of stabilized sub grade. 6/20/22 ES ESS grading base preparing for base asphalt this week. Looking to proof roll tomorrow. 7/11/22 ES ESS grading base rock preparing for asphalt. Will proof roll 7/15 and then look to start paving 7/16. 7/14/22 ES Seal-O-Matic laying 3” of Type 2 R base asphalt on Black Twig. 7/20/22 ES Seal-O-Matic laying 2” of Type 2 R base asphalt on Black Twig. 7/21/22 ES
Pavement-Aggregate Base Partial 07/22/2022
Misc
Informational
07/20/2022
Seal-O-Matic laying 3” of Type 2 base asphalt on Black Twig. 7/20/22 ES Seal-O-Matic laying final 2” of Type 2 R base asphalt along Black Twig Cir. 7/21/22 ES
Erosion Control Inspection Partial 08/25/2022
Misc
Informational
03/24/2022
No erosion issues to report on the job site today. RP 3-23-22
Misc
Informational
03/24/2022
Another rain day, still no erosion issues to report. RP 3-24-22
Misc
Informational
08/25/2022
Erosion control measures installed, intact and functioning. 8/25/22 ES
Erosion Control Inspection Partial 09/27/2022
Misc
Informational
08/25/2022
No erosion issues to report on the job site today. RP 3-23-22
Misc
Informational
08/25/2022
Another rain day, still no erosion issues to report. RP 3-24-22
Misc
Informational
08/25/2022
Erosion control measures installed, intact and functioning. 8/25/22 ES Erosion control measures installed, intact, and functioning. 9/26/22 ES
ESC - (Vegetation/Ground Cover) Partial 09/27/2022
Misc
Informational
09/27/2022
Vegetation behind townhomes around retention basin is established. Still no vegetation directly behind townhomes as this ares is still being utilized for construction traffic. 9/26/22 ES
Grading/Excavation/Fill Inspection Partial 3/4/2022 09/27/2022
Misc
Informational
03/03/2022
ESS is on site grading dirt. RP 3-3-22 ESS grading dirt behind first few townhomes. 9/27/22 ES
Install Street and Stop Signs Partial 09/27/2022
Misc
Informational
09/27/2022
Spoke with Codi, ESS has a contractor who will be putting up the signs along Black Twig Cir and Lowenstein Dr. 9/26/22 ES
Site Visit Partial 09/27/2022
Misc
Informational
05/25/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the wrong diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
05/25/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Misc
Informational
05/25/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
05/25/2022
No work being done on site today. RP 2-28-22
Misc
Informational
05/25/2022
ESS is on site grading dirt. RP 3-3-22
Misc
Informational
05/25/2022
No work being done on site today. RP 3-10-22
Misc
Informational
05/25/2022
ESS is grading the site today. RP 3-14-22
Misc
Informational
05/25/2022
Too wet to work today with last nights rain, plus more rain coming to the area. No erosion issues to report. RP 3-22-22
Misc
Informational
05/25/2022
No utility work or grading being done today. RP 4-6-22
Misc
Informational
05/25/2022
No work being done today with rain. 5/25/22 ES Construction continues on townhomes. 9/27/22 ES
Site Visit Partial 09/28/2022
Misc
Informational
09/27/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the wrong diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
09/27/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Misc
Informational
09/27/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
09/27/2022
No work being done on site today. RP 2-28-22
Misc
Informational
09/27/2022
ESS is on site grading dirt. RP 3-3-22
Misc
Informational
09/27/2022
No work being done on site today. RP 3-10-22
Misc
Informational
09/27/2022
ESS is grading the site today. RP 3-14-22
Misc
Informational
09/27/2022
Too wet to work today with last nights rain, plus more rain coming to the area. No erosion issues to report. RP 3-22-22
Misc
Informational
09/27/2022
No utility work or grading being done today. RP 4-6-22
Misc
Informational
09/27/2022
No work being done today with rain. 5/25/22 ES Construction continues on townhomes. 9/27/22 ES TH Construction continues. 9/28/22 ES
Site Visit Partial 09/30/2022
Misc
Informational
09/28/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the wrong diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
09/28/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Misc
Informational
09/28/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
09/28/2022
No work being done on site today. RP 2-28-22
Misc
Informational
09/28/2022
ESS is on site grading dirt. RP 3-3-22
Misc
Informational
09/28/2022
No work being done on site today. RP 3-10-22
Misc
Informational
09/28/2022
ESS is grading the site today. RP 3-14-22
Misc
Informational
09/28/2022
Too wet to work today with last nights rain, plus more rain coming to the area. No erosion issues to report. RP 3-22-22
Misc
Informational
09/28/2022
No utility work or grading being done today. RP 4-6-22
Misc
Informational
09/28/2022
No work being done today with rain. 5/25/22 ES Construction continues on townhomes. 9/27/22 ES TH Construction continues. 9/28/22 ES Framing, concrete and other crews continue working on townhomes. 9/30/22 ES
Erosion Control Inspection Partial 10/03/2022
Misc
Informational
09/27/2022
No erosion issues to report on the job site today. RP 3-23-22
Misc
Informational
09/27/2022
Another rain day, still no erosion issues to report. RP 3-24-22
Misc
Informational
09/27/2022
Erosion control measures installed, intact and functioning. 8/25/22 ES Erosion control measures installed, intact, and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. Back lots have recently regraded, but areas going down towards detention basin are vegetated. 10/3/22 ES
ESC - (Vegetation/Ground Cover) Partial 10/03/2022
Misc
Informational
09/27/2022
Vegetation behind townhomes around retention basin is established. Still no vegetation directly behind townhomes as this ares is still being utilized for construction traffic. 9/26/22 ES Vegetation behind townhomes towards basin established. Areas directly behind townhomes were just freshest graded and have no established vegetation. 10/3/22 ES
Pavement-Surface Partial 10/04/2022
Misc
Informational
07/21/2022
Seal-O-Matic laying 3” of Type 2 R base asphalt on Black Twig. 7/20/22 ES Seal-O-Matic laying 2” of Type 2 R base asphalt on Black Twig. 7/21/22 ES ESS was working on cleaning out interior courtyard of apartments and Black Twig Cir in front of first three townhomes. Seal-O-Matic is to be onsite tomorrow starting next layer of base. 10/4/22 ES
Pavement-Surface Partial 10/05/2022
Misc
Informational
10/04/2022
Seal-O-Matic laying 3” of Type 2 R base asphalt on Black Twig. 7/20/22 ES Seal-O-Matic laying 2” of Type 2 R base asphalt on Black Twig. 7/21/22 ES ESS was working on cleaning out interior courtyard of apartments and Black Twig Cir in front of first three townhomes. Seal-O-Matic is to be onsite tomorrow starting next layer of base. 10/4/22 ES Seal-O-Matic was on site laying Type 2R base asphalt on Black Twig Cir between apartments and townhomes. Mike was CFS was onsite performing compaction testing. 10/5/22 ES
Site Visit Partial 10/05/2022
Misc
Informational
09/30/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the wrong diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
09/30/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Misc
Informational
09/30/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
09/30/2022
No work being done on site today. RP 2-28-22
Misc
Informational
09/30/2022
ESS is on site grading dirt. RP 3-3-22
Misc
Informational
09/30/2022
No work being done on site today. RP 3-10-22
Misc
Informational
09/30/2022
ESS is grading the site today. RP 3-14-22
Misc
Informational
09/30/2022
Too wet to work today with last nights rain, plus more rain coming to the area. No erosion issues to report. RP 3-22-22
Misc
Informational
09/30/2022
No utility work or grading being done today. RP 4-6-22
Misc
Informational
09/30/2022
No work being done today with rain. 5/25/22 ES Construction continues on townhomes. 9/27/22 ES TH Construction continues. 9/28/22 ES Framing, concrete and other crews continue working on townhomes. 9/30/22 ES ESS continued sweeping and flushing Black Twig Cir in preps for paving. 10/5/22am ES
Pavement-Surface Partial 10/06/2022
Misc
Informational
10/05/2022
Seal-O-Matic laying 3” of Type 2 R base asphalt on Black Twig. 7/20/22 ES Seal-O-Matic laying 2” of Type 2 R base asphalt on Black Twig. 7/21/22 ES ESS was working on cleaning out interior courtyard of apartments and Black Twig Cir in front of first three townhomes. Seal-O-Matic is to be onsite tomorrow starting next layer of base. 10/4/22 ES Seal-O-Matic was on site laying Type 2R base asphalt on Black Twig Cir between apartments and townhomes. Mike was CFS was onsite performing compaction testing. 10/5/22 ES Seal-O-Matic began laying type 2R asphalt base on Black Twig Cir in front of first 3 townhome buildings. Mike from CFS was onsite performing testing. 10/6/22 ES
Pavement-Surface Partial 10/06/2022
Misc
Informational
10/06/2022
Seal-O-Matic laying 3” of Type 2 R base asphalt on Black Twig. 7/20/22 ES Seal-O-Matic laying 2” of Type 2 R base asphalt on Black Twig. 7/21/22 ES ESS was working on cleaning out interior courtyard of apartments and Black Twig Cir in front of first three townhomes. Seal-O-Matic is to be onsite tomorrow starting next layer of base. 10/4/22 ES Seal-O-Matic was on site laying Type 2R base asphalt on Black Twig Cir between apartments and townhomes. Mike was CFS was onsite performing compaction testing. 10/5/22 ES Seal-O-Matic began laying type 2R asphalt base on Black Twig Cir in front of first 3 townhome buildings. Mike from CFS was onsite performing testing. 10/6/22 ES
Pavement-Surface Partial 10/07/2022
Misc
Informational
10/06/2022
Seal-O-Matic laying 3” of Type 2 R base asphalt on Black Twig. 7/20/22 ES Seal-O-Matic laying 2” of Type 2 R base asphalt on Black Twig. 7/21/22 ES ESS was working on cleaning out interior courtyard of apartments and Black Twig Cir in front of first three townhomes. Seal-O-Matic is to be onsite tomorrow starting next layer of base. 10/4/22 ES Seal-O-Matic was on site laying Type 2R base asphalt on Black Twig Cir between apartments and townhomes. Mike was CFS was onsite performing compaction testing. 10/5/22 ES Seal-O-Matic began laying type 2R asphalt base on Black Twig Cir in front of first 3 townhome buildings. Mike from CFS was onsite performing testing. 10/6/22 ES Seal-O-Matic finished laying type 3R surface asphalt along Black Twig Cir and into courtyard and North parking lot of apartments. Mike from CFS was onsite conducting compaction testing. 10/7/22 ES
Street - Striping Partial 10/07/2022
Misc
Informational
10/07/2022
Spoke with Mike from Brinkmann, they will be striping the parking stalls in front of townhomes Monday 10/10.. 10/7/22 ES
Erosion Control Inspection Partial 10/11/2022
Misc
Informational
10/03/2022
No erosion issues to report on the job site today. RP 3-23-22
Misc
Informational
10/03/2022
Another rain day, still no erosion issues to report. RP 3-24-22
Misc
Informational
10/03/2022
Erosion control measures installed, intact and functioning. 8/25/22 ES Erosion control measures installed, intact, and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. Back lots have recently regraded, but areas going down towards detention basin are vegetated. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES
Street - Striping Partial 10/10/2022 10/10/2022 10/11/2022
Misc
Informational
10/07/2022
Spoke with Mike from Brinkmann, they will be striping the parking stalls in front of townhomes Monday 10/10.. 10/7/22 ES K&G Striping was onsite today striping North parking lot and apartment courtyard parking today. 10/10/22 ES
Site Visit Partial 10/14/2022
Misc
Informational
10/05/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the wrong diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
10/05/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Misc
Informational
10/05/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
10/05/2022
No work being done on site today. RP 2-28-22
Misc
Informational
10/05/2022
ESS is on site grading dirt. RP 3-3-22
Misc
Informational
10/05/2022
No work being done on site today. RP 3-10-22
Misc
Informational
10/05/2022
ESS is grading the site today. RP 3-14-22
Misc
Informational
10/05/2022
Too wet to work today with last nights rain, plus more rain coming to the area. No erosion issues to report. RP 3-22-22
Misc
Informational
10/05/2022
No utility work or grading being done today. RP 4-6-22
Misc
Informational
10/05/2022
No work being done today with rain. 5/25/22 ES Construction continues on townhomes. 9/27/22 ES TH Construction continues. 9/28/22 ES Framing, concrete and other crews continue working on townhomes. 9/30/22 ES ESS continued sweeping and flushing Black Twig Cir in preps for paving. 10/5/22am ES No utility work requiring inspection being completed. 10/14/22 ES
Water Service Inspection Partial 10/18/2022
Misc
Informational
10/18/2022
Steve's crew with ESS was onsite working on digging up and preparing to repair meter pits/rings/lids that have been damaged from construction equipment. 10/17/22 ES
Water Service Inspection Partial 10/18/2022
Misc
Informational
10/18/2022
Steve's crew with ESS was onsite working on digging up and preparing to repair meter pits/rings/lids that have been damaged from construction equipment. 10/17/22 ES Steve’s crew with ESS was onsite again working on meter pits. Met with Eric Wiggins from WU onsite to look at options they had for repairing meter pits. The options they had available were not sufficient and we relayed as much. Spoke with Brent and Joe from WU to get black ADS pipe approved if they were unable to source the normal white ADS pipe that is used by WU. They will be allowed as long as the black ADS pipe meets or exceeds the spec of the white pipe. 10/18/22 ES
Erosion Control Inspection Partial 10/19/2022
Misc
Informational
10/11/2022
No erosion issues to report on the job site today. RP 3-23-22
Misc
Informational
10/11/2022
Another rain day, still no erosion issues to report. RP 3-24-22
Misc
Informational
10/11/2022
Erosion control measures installed, intact and functioning. 8/25/22 ES Erosion control measures installed, intact, and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. Back lots have recently regraded, but areas going down towards detention basin are vegetated. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES
ESC - (Vegetation/Ground Cover) Partial 10/19/2022
Misc
Informational
10/03/2022
Vegetation behind townhomes around retention basin is established. Still no vegetation directly behind townhomes as this area is still being utilized for construction traffic. 9/26/22 ES Vegetation behind townhomes towards basin established. Areas directly behind townhomes were just freshest graded and have no established vegetation. 10/3/22 ES Next to Nature still working on getting trees planted coming up Lowenstein along the backside of these townhomes. 10/18/22 ES
Water Service Inspection Partial 10/19/2022
Misc
Informational
10/18/2022
Steve's crew with ESS was onsite working on digging up and preparing to repair meter pits/rings/lids that have been damaged from construction equipment. 10/17/22 ES Steve’s crew with ESS was onsite again working on meter pits. Met with Eric Wiggins from WU onsite to look at options they had for repairing meter pits. The options they had available were not sufficient and we relayed as much. Spoke with Brent and Joe from WU to get black ADS pipe approved if they were unable to source the normal white ADS pipe that is used by WU. They will be allowed as long as the black ADS pipe meets or exceeds the spec of the white pipe. 10/18/22 ES Steve and Jeremiah crew working on meter pits, using black ADS pipe. The first pit they were replacing had the meter too high in the pit. Reminded them that the top of the meters need to be within 14-18” from the lid. 10/19/22am ES
Erosion Control Inspection Partial 11/08/2022
Misc
Informational
10/19/2022
No erosion issues to report on the job site today. RP 3-23-22
Misc
Informational
10/19/2022
Another rain day, still no erosion issues to report. RP 3-24-22
Misc
Informational
10/19/2022
Erosion control measures installed, intact and functioning. 8/25/22 ES Erosion control measures installed, intact, and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. Back lots have recently regraded, but areas going down towards detention basin are vegetated. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Erosion control measures installed, intact, and functioning. 11/7/22 ES
Water Service Inspection Passed 12/08/2022
Misc
Informational
10/19/2022
Steve's crew with ESS was onsite working on digging up and preparing to repair meter pits/rings/lids that have been damaged from construction equipment. 10/17/22 ES Steve’s crew with ESS was onsite again working on meter pits. Met with Eric Wiggins from WU onsite to look at options they had for repairing meter pits. The options they had available were not sufficient and we relayed as much. Spoke with Brent and Joe from WU to get black ADS pipe approved if they were unable to source the normal white ADS pipe that is used by WU. They will be allowed as long as the black ADS pipe meets or exceeds the spec of the white pipe. 10/18/22 ES Steve and Jeremiah crew working on meter pits, using black ADS pipe. The first pit they were replacing had the meter too high in the pit. Reminded them that the top of the meters need to be within 14-18” from the lid. 10/19/22am ES
Grading/Excavation/Fill Inspection Passed 12/08/2022
Misc
Informational
09/27/2022
ESS is on site grading dirt. RP 3-3-22 ESS grading dirt behind first few townhomes. 9/27/22 ES
Pavement-Aggregate Base Passed 12/08/2022
Misc
Informational
07/22/2022
Seal-O-Matic laying 3” of Type 2 base asphalt on Black Twig. 7/20/22 ES Seal-O-Matic laying final 2” of Type 2 R base asphalt along Black Twig Cir. 7/21/22 ES
Pavement-Surface Passed 12/08/2022
Misc
Informational
10/07/2022
Seal-O-Matic laying 3” of Type 2 R base asphalt on Black Twig. 7/20/22 ES Seal-O-Matic laying 2” of Type 2 R base asphalt on Black Twig. 7/21/22 ES ESS was working on cleaning out interior courtyard of apartments and Black Twig Cir in front of first three townhomes. Seal-O-Matic is to be onsite tomorrow starting next layer of base. 10/4/22 ES Seal-O-Matic was on site laying Type 2R base asphalt on Black Twig Cir between apartments and townhomes. Mike was CFS was onsite performing compaction testing. 10/5/22 ES Seal-O-Matic began laying type 2R asphalt base on Black Twig Cir in front of first 3 townhome buildings. Mike from CFS was onsite performing testing. 10/6/22 ES Seal-O-Matic finished laying type 3R surface asphalt along Black Twig Cir and into courtyard and North parking lot of apartments. Mike from CFS was onsite conducting compaction testing. 10/7/22 ES
Site Visit Complete 12/08/2022
Misc
Informational
10/14/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the wrong diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
10/14/2022
Did air test from manhole C-1 to C-2, but couldn’t air test C-1 to A-5 because clean outs weren’t sealed. RP 2-24-22
Misc
Informational
10/14/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
10/14/2022
No work being done on site today. RP 2-28-22
Misc
Informational
10/14/2022
ESS is on site grading dirt. RP 3-3-22
Misc
Informational
10/14/2022
No work being done on site today. RP 3-10-22
Misc
Informational
10/14/2022
ESS is grading the site today. RP 3-14-22
Misc
Informational
10/14/2022
Too wet to work today with last nights rain, plus more rain coming to the area. No erosion issues to report. RP 3-22-22
Misc
Informational
10/14/2022
No utility work or grading being done today. RP 4-6-22
Misc
Informational
10/14/2022
No work being done today with rain. 5/25/22 ES Construction continues on townhomes. 9/27/22 ES TH Construction continues. 9/28/22 ES Framing, concrete and other crews continue working on townhomes. 9/30/22 ES ESS continued sweeping and flushing Black Twig Cir in preps for paving. 10/5/22am ES No utility work requiring inspection being completed. 10/14/22 ES
Street - Striping Passed 12/08/2022
Misc
Informational
10/11/2022
Spoke with Mike from Brinkmann, they will be striping the parking stalls in front of townhomes Monday 10/10.. 10/7/22 ES K&G Striping was onsite today striping North parking lot and apartment courtyard parking today. 10/10/22 ES
Documents & Images
Date Uploaded File Type Document Name
11/22/2021 Receipt Receipt for transaction:2021-008894
11/22/2021 Letter DE-Permit
02/23/2022 Letter INSPECTION SUMMARY
02/23/2022 Letter INSPECTION SUMMARY
02/23/2022 Letter INSPECTION SUMMARY
02/23/2022 Letter INSPECTION SUMMARY
02/24/2022 Letter INSPECTION SUMMARY
02/24/2022 Letter INSPECTION SUMMARY
02/25/2022 Letter INSPECTION SUMMARY
02/28/2022 Letter INSPECTION SUMMARY
03/02/2022 Letter INSPECTION SUMMARY
03/02/2022 Letter INSPECTION SUMMARY
03/03/2022 Letter INSPECTION SUMMARY
03/03/2022 Letter INSPECTION SUMMARY
03/14/2022 Letter INSPECTION SUMMARY
03/14/2022 Letter INSPECTION SUMMARY
03/22/2022 Letter INSPECTION SUMMARY
03/23/2022 Letter INSPECTION SUMMARY
03/24/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/29/2022 Letter INSPECTION SUMMARY
04/06/2022 Letter INSPECTION SUMMARY
04/26/2022 Receipt Receipt for transaction:2022-002421
05/25/2022 Letter INSPECTION SUMMARY
07/20/2022 Letter INSPECTION SUMMARY
07/20/2022 Letter INSPECTION SUMMARY
07/20/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/22/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
09/27/2022 Letter INSPECTION SUMMARY
09/27/2022 Letter INSPECTION SUMMARY
09/27/2022 Letter INSPECTION SUMMARY
09/27/2022 Letter INSPECTION SUMMARY
09/27/2022 Letter INSPECTION SUMMARY
09/28/2022 Letter INSPECTION SUMMARY
09/30/2022 Letter INSPECTION SUMMARY
10/03/2022 Letter INSPECTION SUMMARY
10/03/2022 Letter INSPECTION SUMMARY
10/04/2022 Letter INSPECTION SUMMARY
10/05/2022 Letter INSPECTION SUMMARY
10/05/2022 Letter INSPECTION SUMMARY
10/06/2022 Letter INSPECTION SUMMARY
10/06/2022 Letter INSPECTION SUMMARY
10/07/2022 Letter INSPECTION SUMMARY
10/07/2022 Letter INSPECTION SUMMARY
10/11/2022 Letter INSPECTION SUMMARY
10/11/2022 Letter INSPECTION SUMMARY
10/14/2022 Letter INSPECTION SUMMARY
10/18/2022 Letter INSPECTION SUMMARY
10/18/2022 Letter INSPECTION SUMMARY
10/19/2022 Letter INSPECTION SUMMARY
10/19/2022 Letter INSPECTION SUMMARY
10/19/2022 Letter INSPECTION SUMMARY
11/08/2022 Letter INSPECTION SUMMARY
11/21/2022 SWP 2021 5387 Irrigation Tap
11/22/2021 Approved Plans APPROVED - SWP Lot 7B PHASE 1 FDP 11.22.21
12/08/2022 Letter INSPECTION SUMMARY
12/08/2022 Letter INSPECTION SUMMARY
12/08/2022 Letter INSPECTION SUMMARY
12/08/2022 Letter INSPECTION SUMMARY
12/08/2022 Letter INSPECTION SUMMARY
12/08/2022 Lot 7B Streets of West Pryor-Townhome Phase I-Vanguard Villas-Site Substantial Completion
12/08/2022 Lot 7B Streets of West Pryor-Townhomes Phase I-Vangurard Villias Site Punch List
02/29/2024 Letter DE-Certificate of Final Acceptance (Commercial)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home