PRSGN20235200
Sign Permit
Final Completion
SWITCH ELECTRIC LLC
SIGN
Install 2 signs for Priority Auto Repair
10/10/2023
10/26/2023
12/04/2023
Locations
Contacts
DIGITAL NICHE, Address:952 SE 7TH TER, Phone:(816) 373-5049  
SWITCH ELECTRIC LLC, Address:713 NE TUDOR RD UNIT 10  
Christian Stewart, Address:952 SE 7th Terrace, Phone:(816) 896-4846  
Reviews
Review Type Outcome Est. Completion Date Completed
Sign Permit Review Approved 10/27/2023 10/25/2023
Hector Soto Jr.
Sign Permit Review Rejected 10/12/2023 10/10/2023
Hector Soto Jr.
Resolved
10/25/2023

SIGNAGE. The two (2) proposed wall signs comply with the sign regulations for the PI (Planned Industrial) zoning district. However, the proposed auto repair business requires going through a 3-month public hearing process in order to gain approval of a special use permit in order to allow the business to operate at this location. Staff cannot issue approval of the sign permits until such time as the special use permit process is completed to determine if a special use permit is granted to allow the operation of the auto repair business. Until such time as final action is taken on the special use permit application, the status of the sign permit application will be "Rejected". If and when the special use permit application is approved, the status will be changed to "Approved", at which time the $200 permit fee can be paid and the permit issued.
Fees
Paid Fees Amount Paid Owing Date Paid
9110062-Sign Permit-Permanent Fee $200.00 $200.00 Paid 10/26/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Final Electrical Inspection Failed 11/9/2023 11/13/2023 11/13/2023
Misc
Informational
11/13/2023
-Signs are in place. Waiting on floodlights to be installed,
Sign Confirmation Inspection Passed 11/16/2023 11/16/2023
Final Electrical Inspection Passed 12/4/2023 12/04/2023
Misc
Informational
11/13/2023
-Signs are in place. Waiting on floodlights to be installed,
Documents & Images
Date Uploaded File Type Document Name
10/10/2023 PriorityAutoRepairPermitBinder
10/10/2023 Sign Permit Authorization
10/10/2023 Permit DS P/R Corrections Document
10/25/2023 Permit DS P/R Corrections Document
10/26/2023 Permit DS Building Permit
10/26/2023 Receipt Receipt for transaction:2023-008072
11/13/2023 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home