Summary
PRRES20254263
Building Permit - Residential
Temporary Occupancy
NEW SINGLE FAMILY
NEW HOUSE - ROOF TRUSSES - UNFINISHED BASEMENT - STOP WORK ORDER generated on 10/30/2025 12:00 AM by username 'Mitchell Schwarz'. STOP WORK ORDER removed on 11/06/2025 12:00 AM by username 'Mitchell Schwarz'. STOP WORK ORDER generated on 02/09/2026 12:00 AM by username 'Dustin Agcopra'.
10/03/2025
10/10/2025
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:10450 Holmes Rd Suite 100, Phone:(816) 246-6700  
Summit Homes, Address:120 SE 30th St, Phone:(816) 434-5074 Ext:320  
COULTER@SUMMITHOMESKC.COM  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
BILL'S PLUMBING SERVICE LLC, Address:308 E PARK STREET, Phone:(913) 829-8213  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Development Fee $2,398.00 $2,398.00 Paid 10/10/2025
Right of Way Permit Fee $85.00 $85.00 Paid 10/10/2025
Residential Excise Tax Fee $1,022.72 $1,022.72 Paid 10/10/2025
Water Tap Fee $4,080.00 $4,080.00 Paid 10/10/2025
Water Meter Fee $791.53 $791.53 Paid 10/10/2025
Valuation Fee New Single Family $1,903.59 $1,903.59 Paid 10/10/2025
Parks Impact Fee Residential Zone 2 $1,000.00 $1,000.00 Paid 10/10/2025
Not Ready Inspection Fee $75.00 $75.00 Paid 02/25/2026
Not Ready Inspection Fee $75.00 $75.00 Paid 02/25/2026
Temporary Occupancy Fee $50.00 $50.00 Paid 02/25/2026
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sidewalk Inspection Pending
Misc
Informational
02/05/2026
1-13-26 Dustin A, sw is formed and compacted to city specs. Slopes are in compliance Approved to pour 2-5-26 Dustin A, Cannot due a full inspection due to dirt on sidewalk . What can be seen is no expansion joint around water valve which would result in a fail. Call back in for another inspection once sidewalk is cleared
Erosion Control Inspection Residential Pending
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
02/09/2026
2-5-26 Dustin A, Erosion control needs to be repaired and restroom needs to be moved to a green space. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 2-9-26 Dustin A, Restroom was moved to the driveway instead of a green space. ARestrooms cannot be placed on roads, sidewalks or or drives per city code. Fail. Stop work is issued.
Occupancy Inspection - Codes Residential Pending
Footing Inspection - Residential Failed 10/28/2025 10/28/2025
Miscellaneous Correction
Corrective Action Required
10/28/2025
No gravel entrance, 3rd party inspection denied. Erosion control not in compliance
Erosion Control Inspection Residential Failed 10/28/2025 10/28/2025 10/28/2025
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
10/28/2025
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. MISSING GRAVEL ENTRANCE
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
10/28/2025
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Erosion Control Inspection Residential Failed - Stop Work 10/30/2025 10/30/2025 10/30/2025
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
10/28/2025
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. MISSING GRAVEL ENTRANCE
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
10/28/2025
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Erosion Control Inspection Residential Partial 11/6/2025 11/6/2025 11/06/2025
DCM2 ESC DEFICIENT INSTALLATION
Resolved
11/06/2025
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. MISSING GRAVEL ENTRANCE
DCM3 ESC REQUIRED 2 DAY
Resolved
11/06/2025
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Misc
Corrective Action Required
11/06/2025
Silt fence to be repaired at entrance
Footing Inspection - Residential Passed 11/7/2025 11/07/2025
Miscellaneous Correction
Resolved
11/07/2025
No gravel entrance, 3rd party inspection denied. Erosion control not in compliance
Underslab Plumbing Inspection - Residential Passed 11/7/2025 11/7/2025 11/07/2025
All Rough Inspection - Residential Partial 11/20/2025 11/20/2025 11/20/2025
Misc
Informational
11/20/2025
Garage portal frame exterior nailing okay to cover
Sewer Service Inspection - R Passed 12/5/2025 12/5/2025 12/05/2025
Water Service Inspection - R Passed 12/8/2025 12/8/2025 12/08/2025
All Rough Inspection - Residential Not Ready 12/17/2025 12/17/2025 12/17/2025
Misc
Informational
11/20/2025
Garage portal frame exterior nailing okay to cover
Misc
Corrective Action Required
12/17/2025
Plans on site are not the correct set
Gas Service Inspection - Residential Failed 12/17/2025 12/17/2025 12/17/2025
Electrical Service Inspection Failed 12/17/2025 12/17/2025 12/17/2025
All Rough Inspection - Residential Failed 12/18/2025 12/18/2025 12/18/2025
Misc
Informational
12/17/2025
Garage portal frame exterior nailing okay to cover
Misc
Resolved
12/18/2025
Plans on site are not the correct set
Misc
Corrective Action Required
12/18/2025
Repair downed silt fence before calling for inspection Provide complete set of plans for inspection -missing truss plans
Gas Service Inspection - Residential Failed 12/18/2025 12/18/2025 12/18/2025
Misc
Corrective Action Required
12/18/2025
Provide proper erosion control, and full set of plans on site
Electrical Service Inspection Failed 12/18/2025 12/18/2025 12/18/2025
Erosion Control Inspection Residential Failed 12/18/2025 12/18/2025 12/18/2025
Misc
Corrective Action Required
11/06/2025
Silt fence to be repaired at entrance
Electrical Service Inspection Failed 12/19/2025 12/19/2025 12/19/2025
Misc
Corrective Action Required
12/19/2025
Inspection denied Repair downed silt fence
All Rough Inspection - Residential Not Ready 12/19/2025 12/19/2025 12/19/2025
Misc
Informational
12/18/2025
Garage portal frame exterior nailing okay to cover
Misc
Corrective Action Required
12/18/2025
Repair downed silt fence before calling for inspection (NOT DONE) Provide complete set of plans for inspection -missing truss plans
Gas Service Inspection - Residential Failed 12/19/2025 12/19/2025 12/19/2025
Misc
Corrective Action Required
12/18/2025
Provide proper erosion control, and full set of plans on site
Erosion Control Inspection Residential Failed 12/19/2025 12/19/2025
Misc
Corrective Action Required
12/18/2025
Silt fence to be repaired at entrance
Erosion Control Inspection Residential Partial 12/22/2025 12/22/2025 12/22/2025
Misc
Resolved
12/22/2025
Silt fence to be repaired at entrance
DCM3 ESC REQUIRED 2 DAY
Resolved
12/22/2025
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Electrical Service Inspection Passed 12/22/2025 12/22/2025 12/22/2025
Misc
Resolved
12/22/2025
Inspection denied Repair downed silt fence
All Rough Inspection - Residential Failed 12/22/2025 12/22/2025 12/22/2025
Misc
Resolved
12/22/2025
Garage portal frame exterior nailing okay to cover
Misc
Resolved
12/22/2025
Repair downed silt fence before calling for inspection (NOT DONE) Provide complete set of plans for inspection -missing truss plans
Misc
Corrective Action Required
12/22/2025
-uncover covered front porch -seal top plate penetration right of steel column in garage -seal top of steel column in garage exterior wall -strap top plate foyer door wall top plate not interconnected to other walls -plans call for (2) 2x12 above foyer entry -move electrical outlet in flex room to furr out wall -nail all double trusses together to plans -missing truss bracing throughout -support and complete bath vents throughout
Gas Service Inspection - Residential Passed 12/22/2025 12/22/2025 12/22/2025
Misc
Resolved
12/22/2025
Provide proper erosion control, and full set of plans on site
All Rough Inspection - Residential Failed 12/30/2025 12/30/2025 12/30/2025
Misc
Corrective Action Required
12/22/2025
-uncover covered front porch (can not verify truss hold downs) -plans call for (2) 2x12 above foyer entry -move electrical outlet in flex room to furr out wall -support and complete bath vents throughout
All Rough Inspection - Residential Failed 1/6/2026 1/6/2026 01/06/2026
Misc
Corrective Action Required
12/30/2025
-support and complete bath vents throughout
All Rough Inspection - Residential Passed 1/7/2026 1/7/2026 01/07/2026
Misc
Resolved
01/07/2026
-support and complete bath vents throughout
Driveway Inspection Partial 1/13/2026 1/13/2026 01/13/2026
Misc
Corrective Action Required
01/13/2026
1-13-26 Dustin A, dw is formed and compacted to city specs. Approved to pour
Sidewalk Inspection Partial 1/13/2026 1/13/2026 01/13/2026
Misc
Informational
01/13/2026
1-13-26 Dustin A, sw is formed and compacted to city specs. Slopes are in compliance Approved to pour
Driveway Inspection Passed 2/5/2026 2/5/2026 02/05/2026
Misc
Corrective Action Required
01/13/2026
1-13-26 Dustin A, dw is formed and compacted to city specs. Approved to pour 2-5-26 Dustin A, Dw is poured to city specs.
Sidewalk Inspection Failed 2/5/2026 2/5/2026 02/05/2026
Misc
Informational
01/13/2026
1-13-26 Dustin A, sw is formed and compacted to city specs. Slopes are in compliance Approved to pour 2-5-26 Dustin A, Cannot due a full inspection due to dirt on sidewalk . What can be seen is no expansion joint around water valve which would result in a fail. Call back in for another inspection once sidewalk is cleared
Erosion Control Inspection Residential Failed 2/5/2026 2/5/2026 02/05/2026
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
02/05/2026
2-5-26 Dustin A, Erosion control needs to be repaired and restroom needs to be moved to a green space. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Plot Plan Inspection Passed 2/5/2026 02/05/2026
Erosion Control Inspection Residential Failed - Stop Work 2/9/2026 2/9/2026 02/09/2026
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
02/05/2026
2-5-26 Dustin A, Erosion control needs to be repaired and restroom needs to be moved to a green space. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 2-9-26 Dustin A, Restroom was moved to the driveway instead of a green space. ARestrooms cannot be placed on roads, sidewalks or or drives per city code. Fail. Stop work is issued.
Occupancy Inspection - Codes Residential Failed 2/19/2026 2/19/2026 02/19/2026
Miscellaneous Correction
Corrective Action Required
02/19/2026
- Outlet cover missing in upstairs hallway - Non gfci outlet in basement not labeled - Missing security screws at front door
Occupancy Inspection - Codes Residential Temporary C of O 2/23/2026 2/23/2026 02/23/2026
Miscellaneous Correction
Resolved
02/23/2026
- Outlet cover missing in upstairs hallway - Non gfci outlet in basement not labeled - Missing security screws at front door
Misc
Informational
02/24/2026
-Plot plan inspection needed -no sod in place at this time
Occupancy Inspection - Codes Residential Ready for Temp CO 2/24/2026 02/24/2026
Misc
Informational
02/24/2026
-plot plan inspection needed -sod not in place at this time
Documents & Images
Date Uploaded File Type Document Name
10/03/2025 Application Form BY #0380 - PERMIT APP
10/10/2025 Approved Plans APPROVED PLANS
10/10/2025 Plot Plan APPROVED PLOT PLAN
10/10/2025 Approved Plans APPROVED TRUSS LAYOUT
10/10/2025 Approved Plans APPROVED TRUSS PACKET
10/10/2025 Permit Codes Residential Plan Review
10/10/2025 Permit DS Building Permit
10/10/2025 Receipt Receipt for transaction:2025-007677
10/27/2025 3RD Party Insp Report 380 Bailey Farms- FTNG - Stamped
10/28/2025 Letter INSPECTION SUMMARY
10/28/2025 Letter INSPECTION SUMMARY
10/30/2025 Letter Stop Work Order
11/06/2025 Letter INSPECTION SUMMARY
11/07/2025 Letter INSPECTION SUMMARY
11/07/2025 Letter INSPECTION SUMMARY
11/20/2025 Letter INSPECTION SUMMARY
12/05/2025 Letter INSPECTION SUMMARY
12/08/2025 Letter INSPECTION SUMMARY
12/17/2025 Letter INSPECTION SUMMARY
12/17/2025 Letter INSPECTION SUMMARY
12/17/2025 Letter INSPECTION SUMMARY
12/18/2025 Letter INSPECTION SUMMARY
12/18/2025 Letter INSPECTION SUMMARY
12/18/2025 Letter INSPECTION SUMMARY
12/18/2025 Letter INSPECTION SUMMARY
12/19/2025 Letter INSPECTION SUMMARY
12/19/2025 Letter INSPECTION SUMMARY
12/19/2025 Letter INSPECTION SUMMARY
12/19/2025 Letter INSPECTION SUMMARY
12/22/2025 Letter INSPECTION SUMMARY
12/22/2025 Letter INSPECTION SUMMARY
12/22/2025 Letter INSPECTION SUMMARY
12/22/2025 Letter INSPECTION SUMMARY
12/30/2025 Letter INSPECTION SUMMARY
01/05/2026 Engineer Report/Study BY 0380 - FRONT DOOR HDR
01/06/2026 Letter INSPECTION SUMMARY
01/07/2026 Letter INSPECTION SUMMARY
01/13/2026 Letter INSPECTION SUMMARY
01/13/2026 Letter INSPECTION SUMMARY
02/04/2026 BY 380
02/04/2026 Plot Plan approved as graded plot plan
02/05/2026 Letter INSPECTION SUMMARY
02/05/2026 Letter INSPECTION SUMMARY
02/05/2026 Letter INSPECTION SUMMARY
02/05/2026 Letter INSPECTION SUMMARY
02/05/2026 Letter INSPECTION SUMMARY
02/09/2026 Letter Stop Work Order
02/09/2026 Letter Stop Work Order
02/19/2026 Letter INSPECTION SUMMARY
02/23/2026 Certificate/License Codes Temporary Certificate of Occupancy
02/25/2026 Certificate/License Codes Temporary Certificate of Occupancy
02/25/2026 Receipt Receipt for transaction:2026-001151
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home