PRRES20250844
Building Permit - Residential
Issued
NEW SINGLE FAMILY
NEW HOUSE - UNFINISHED BASEMENT - COVERED PATIO STOP WORK ORDER generated on 07/29/2025 12:00 AM by username 'Jamie Simerly'. STOP WORK ORDER removed on 08/06/2025 12:00 AM by username 'Dustin Agcopra'.
03/13/2025
03/18/2025
09/14/2025
Locations
Contacts
SAB CONSTRUCTION INC, Address:PO BOX 942, Phone:(816) 524-3855  
Joseph Matthew Schartz, Address:PO Box 942, Phone:(816) 524-3855  
JOE@SABHOMES.COM  
MIKE BRYANT HEATING & COOLING , Address:1711 E 123RD , Phone:(913) 441-7807  
TEAGUE ELECTRIC CONSTRUCTION LLC, Address:12425 W 92ND ST, Phone:(913) 529-4600  
GARRISON PLUMBING, Address:15430 S MAHAFFIE ST STE 102, Phone:(913) 768-1311  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Development Fee $2,285.00 $2,285.00 Paid 03/18/2025
Right of Way Permit Fee $85.00 $85.00 Paid 03/18/2025
Residential Excise Tax Fee $1,022.72 $1,022.72 Paid 03/18/2025
Water Tap Fee $3,973.00 $3,973.00 Paid 03/18/2025
Water Meter Fee $748.03 $748.03 Paid 03/18/2025
Valuation Fee New Single Family $1,549.19 $1,549.19 Paid 03/18/2025
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sidewalk Inspection Pending
Misc
Corrective Action Required
08/13/2025
8/6/25 Tyler S. SW is formed and compacted. Slopes are in compliance. Approved to pour. 8/13/25 Tyler S. SW appear to meet city code and ADA is in compliance. Cant pass at this time due to the forms not being pulled.
Driveway Inspection Pending
Misc
Informational
08/13/2025
8/6/25 Tyler S. DW is formed and compacted to city spec. Approved to pour. 8/13/25 Tyler S. DW is not in compliance with ADA standards. Cross slope is more the 2.1% in multiple area. Inspection failed. Will need to tear out and replace. Please call in for another pre-inspection when ready.
Erosion Control Inspection Residential Pending
Miscellaneous Correction
Corrective Action Required
09/11/2025
- Erosion contol in place
Occupancy Inspection - Codes Residential Pending
Misc
Corrective Action Required
09/16/2025
-outlet cover in garage needed -lockout needed for cook top and oven at electrical panel -uncover all smoke co2 detectors
Erosion Control Inspection Residential Partial 4/16/2025 4/16/2025 04/16/2025
Underslab Plumbing Inspection - Residential Passed 4/16/2025 4/16/2025 04/16/2025
Sewer Service Inspection - R Passed 4/17/2025 4/17/2025 04/17/2025
Water Service Inspection - R Partial 4/17/2025 4/17/2025 04/17/2025
Water Service Inspection - R Passed 4/18/2025 4/18/2025 04/18/2025
Footing Inspection - Residential Passed 5/27/2025 05/27/2025
All Rough Inspection - Residential Partial 5/27/2025 5/27/2025 05/27/2025
Misc
Informational
05/27/2025
garage portal frame ok back porch ok to cover
Electrical Service Inspection Passed 6/13/2025 6/13/2025 06/13/2025
Gas Service Inspection - Residential Passed 6/13/2025 6/13/2025 06/13/2025
All Rough Inspection - Residential Failed 6/13/2025 6/13/2025 06/13/2025
Misc
Informational
05/27/2025
garage portal frame ok back porch ok to cover
Misc
Corrective Action Required
06/13/2025
2611 SW Firefly ln - Fire blocking at left end of fireplace bump out - Fire blocking in bedroom 2 closet, where wires go to attic by the screen porch door - 2 king studs required at each end of window unit at back wall of great room -
All Rough Inspection - Residential Passed 6/18/2025 06/18/2025
Misc
Informational
06/13/2025
garage portal frame ok back porch ok to cover
Misc
Resolved
06/18/2025
2611 SW Firefly ln - Fire blocking at left end of fireplace bump out - Fire blocking in bedroom 2 closet, where wires go to attic by the screen porch door - 2 king studs required at each end of window unit at back wall of great room -
Erosion Control Inspection Residential Failed 7/25/2025 7/25/2025 07/25/2025
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
07/25/2025
07/25/25 Jamie S, Erosion control needs to be reestablished. Silt needs to be cleaned off sidewalk and storm drain. Strom drain needs to be cleaned and properly protected. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Erosion Control Inspection Residential Failed - Stop Work 7/29/2025 7/29/2025 07/29/2025
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
07/25/2025
07/25/25 Jamie S, Erosion control needs to be reestablished. Silt needs to be cleaned off sidewalk and storm drain. Strom drain needs to be cleaned and properly protected. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 07/29/25 Jamie S, Erosion control needs to be reestablished. Silt needs to be cleaned off sidewalk and storm drain. Strom drain needs to be cleaned and properly protected.
Erosion Control Inspection Residential Partial 8/6/2025 8/6/2025 08/06/2025
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
07/29/2025
07/25/25 Jamie S, Erosion control needs to be reestablished. Silt needs to be cleaned off sidewalk and storm drain. Strom drain needs to be cleaned and properly protected. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 07/29/25 Jamie S, Erosion control needs to be reestablished. Silt needs to be cleaned off sidewalk and storm drain. Strom drain needs to be cleaned and properly protected. 8/6/25 Tyler S straw waddle is replaced. Streets and curb are being cleaned. Erosion control must be maintained through out project.
Driveway Inspection Partial 08/06/2025
Misc
Informational
08/06/2025
8/6/25 Tyler S. DW is formed and compacted to city spec. Approved to pour.
Sidewalk Inspection Partial 8/6/2025 8/6/2025 08/06/2025
Misc
Informational
08/06/2025
8/6/25 Tyler S. SW is formed and compacted. Slopes are in compliance. Approved to pour.
Sidewalk Inspection Failed 8/13/2025 8/13/2025 08/13/2025
Misc
Corrective Action Required
08/13/2025
8/6/25 Tyler S. SW is formed and compacted. Slopes are in compliance. Approved to pour. 8/13/25 Tyler S. SW appear to meet city code and ADA is in compliance. Cant pass at this time due to the forms not being pulled.
Driveway Inspection Failed 8/13/2025 8/13/2025 08/13/2025
Misc
Informational
08/06/2025
8/6/25 Tyler S. DW is formed and compacted to city spec. Approved to pour. 8/13/25 Tyler S. DW is not in compliance with ADA standards. Cross slope is more the 2.1% in multiple area. Inspection failed. Will need to tear out and replace. Please call in for another pre-inspection when ready.
Erosion Control Inspection Residential Partial 9/11/2025 09/11/2025
DCM3 ESC REQUIRED 2 DAY
Resolved
09/11/2025
07/25/25 Jamie S, Erosion control needs to be reestablished. Silt needs to be cleaned off sidewalk and storm drain. Strom drain needs to be cleaned and properly protected. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 07/29/25 Jamie S, Erosion control needs to be reestablished. Silt needs to be cleaned off sidewalk and storm drain. Strom drain needs to be cleaned and properly protected. 8/6/25 Tyler S straw waddle is replaced. Streets and curb are being cleaned. Erosion control must be maintained through out project.
Miscellaneous Correction
Corrective Action Required
09/11/2025
- Erosion contol in place
Plot Plan Inspection Passed 9/11/2025 09/11/2025
Occupancy Inspection - Codes Residential Failed 9/16/2025 9/16/2025 09/16/2025
Misc
Corrective Action Required
09/16/2025
-outlet cover in garage needed -lockout needed for cook top and oven at electrical panel -uncover all smoke co2 detectors
Documents & Images
Date Uploaded File Type Document Name
03/13/2025 HF165 - Air Combustion Calcs
03/13/2025 HF165 - Excise Tax Application
03/13/2025 HF165 - Permit Application
03/18/2025 Permit Codes Residential Plan Review
03/18/2025 Approved Plans APPROVED PLANS
03/18/2025 Permit Codes Residential Plan Review
03/18/2025 Permit DS Building Permit
03/18/2025 Receipt Receipt for transaction:2025-001632
03/24/2025 Plot Plan APPROVED PLOT PLAN
03/25/2025 3RD Party Insp Report 2611 SW Firefly Ln LSMO Footing Inspection Pg 1
03/25/2025 3RD Party Insp Report 2611 SW Firefly Ln LSMO Footing Inspection Pg 2
04/16/2025 Letter INSPECTION SUMMARY
04/16/2025 Letter INSPECTION SUMMARY
04/17/2025 Letter INSPECTION SUMMARY
04/17/2025 Letter INSPECTION SUMMARY
04/17/2025 HF165 - Transmittal Letter
04/18/2025 Approved Plans 4-18-25 APPROVED PLANS
04/18/2025 Letter INSPECTION SUMMARY
05/21/2025 2025_04_22_2611 SW Firefly Ln_LSMO_Report_Sealed
05/27/2025 Letter INSPECTION SUMMARY
05/27/2025 Letter INSPECTION SUMMARY
06/13/2025 Letter INSPECTION SUMMARY
06/13/2025 Letter INSPECTION SUMMARY
06/13/2025 Letter INSPECTION SUMMARY
06/18/2025 Letter INSPECTION SUMMARY
07/25/2025 Letter INSPECTION SUMMARY
07/29/2025 Letter Stop Work Order
08/06/2025 Letter INSPECTION SUMMARY
08/06/2025 Letter INSPECTION SUMMARY
08/06/2025 Letter INSPECTION SUMMARY
08/13/2025 Letter INSPECTION SUMMARY
08/13/2025 Letter INSPECTION SUMMARY
09/10/2025 LOT 165 ASBUILT
09/10/2025 Plot Plan APPROVED AS GRADED PLOT PLAN
09/11/2025 Letter INSPECTION SUMMARY
09/11/2025 Letter INSPECTION SUMMARY
09/16/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home