Permit Application Status

PRRES20220388


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20220388
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - UNFINISHED BASEMENT - COVERED PATIO
01/31/2022
02/11/2022
07/31/2022
08/05/2024
Locations
Contacts
ASPEN HOME BUILDERS LLC, Address:6618 ROYAL ST #B, Phone:(816) 507-0123  
Steve Gilliland, Address:6618 Royal Street  
MCDANIEL FURNACE & SHEET METAL, Address:2905 S M 291 FRONTAGE RD, Phone:(816) 373-6370  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
trevor@aspenhomeskc.com  
N & E Plumbing LLC, Address:17301 Jennifer St.  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,469.88 $1,469.88 Paid 02/11/2022
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 02/11/2022
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 02/11/2022
8331507-Sewer Connection Fee $600.00 $600.00 Paid 02/11/2022
8331401-Water Tap Fee $3,655.00 $3,655.00 Paid 02/11/2022
8350015-Water Meter Fee $479.24 $479.24 Paid 02/11/2022
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 04/05/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Not Ready 4/5/2022 (8:00) 4/5/2022 04/05/2022
Misc
Corrective Action Required
04/05/2022
-no city stamped plans on site -pier pads and mulitlple areas of footing not to depth
Footing Inspection - Residential Passed 4/5/2022 (8:30) 4/5/2022 04/05/2022
Misc
Resolved
04/05/2022
-no city stamped plans on site -pier pads and mulitlple areas of footing not to depth
Water Service Inspection - R Passed 6/8/2022 (2:30) 6/8/2022 06/08/2022
Sewer Service Inspection - R Passed 6/8/2022 6/8/2022 06/08/2022
Erosion Control Inspection Residential Failed 10/18/2022 10/18/2022
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
10/18/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. maintain silt fence maintain overgrown vegetation
Underslab Plumbing Inspection - Residential Failed 10/18/2022 10/18/2022 10/18/2022
Misc
Corrective Action Required
10/18/2022
-use rated/listed materal for underslab conduit
Underslab Plumbing Inspection - Residential Passed 10/20/2022 10/20/2022 10/20/2022
Misc
Corrective Action Required
10/18/2022
-use rated/listed materal for underslab conduit
Miscellaneous Inspection Passed 6/7/2023 06/07/2023
Misc
Informational
06/07/2023
permit extension request granted framing to start in July 2023.
Erosion Control Inspection Residential Failed 7/20/2023 07/20/2023
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
10/18/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. maintain silt fence maintain overgrown vegetation
Erosion Control Inspection Residential Failed 8/11/2023 08/11/2023
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
07/20/2023
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS maintain overgrown vegetation
Erosion Control Inspection Residential Failed 8/16/2023 8/17/2023 08/17/2023
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
08/11/2023
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS maintain overgrown vegetation some has been fixed but still needs addressed at rear of lot.
Piers/Caissons Inspection - Residential Passed 8/21/2023 (9:45) 8/21/2023 08/21/2023
All Rough Inspection - Residential Partial 9/5/2023 9/5/2023 09/05/2023
Misc
Informational
09/05/2023
Garage portal frame exterior okay to cover
Gas Service Inspection - Residential Failed 10/25/2023 10/25/2023 10/25/2023
Misc
Corrective Action Required
10/25/2023
Provide minimum 10psi for 10 min at pressure gauge for inspection
All Rough Inspection - Residential Failed 10/25/2023 10/25/2023 10/25/2023
Misc
Corrective Action Required
10/25/2023
-anchor bolts to be in the middle 1/3 of sill plate -return air stud cavity shall not convey air from more than one floor(see dining room) -seal return air space at master bed entry and in master bedroom -fireblock wall space to ceiling space at master bed E wall -nail exterior wall studs together to code and plans -lib on wall that has been headered off -h2.5 missing on header at bed 4 -osb used as blocking for rafters
All Rough Inspection - Residential Failed 10/25/2023 10/25/2023 10/25/2023
Misc
Corrective Action Required
10/25/2023
-anchor bolts to be in the middle 1/3 of sill plate -return air stud cavity shall not convey air from more than one floor(see dining room) -seal return air space at master bed entry and in master bedroom -fireblock wall space to ceiling space at master bed E wall -nail exterior wall studs together to code and plans -h2.5 missing on header at bed 4
Electrical Service Inspection Passed 10/30/2023 10/30/2023 10/30/2023
Gas Service Inspection - Residential Passed 10/30/2023 10/30/2023 10/30/2023
Misc
Resolved
10/30/2023
Provide minimum 10psi for 10 min at pressure gauge for inspection
All Rough Inspection - Residential Passed 10/30/2023 10/30/2023 10/30/2023
Misc
Resolved
10/30/2023
-anchor bolts to be in the middle 1/3 of sill plate -return air stud cavity shall not convey air from more than one floor(see dining room) -seal return air space at master bed entry and in master bedroom -fireblock wall space to ceiling space at master bed E wall -nail exterior wall studs together to code and plans -h2.5 missing on header at bed 4
Sidewalk Inspection Partial 12/18/2023 12/18/2023 12/18/2023
Misc
Informational
12/18/2023
12-18-23 Dustin A, Sw is formed and is compacted. Slopes are in compliance , Approved to pour
Driveway Inspection Partial 12/18/2023 12/18/2023 12/18/2023
Misc
Informational
12/18/2023
12-18-23 Dustin A, Dw is formed and aggregate is compacted, Will need to maintain slopes through approach. Approved to pour
Driveway Inspection Passed 12/27/2023 12/27/2023 12/27/2023
Misc
Informational
12/18/2023
12-18-23 Dustin A, Dw is formed and aggregate is compacted, Will need to maintain slopes through approach. Approved to pour 12-27-23 Dustin A, dw is poured, slopes are in compliance. Passed
Sidewalk Inspection Partial 12/27/2023 12/27/2023 12/27/2023
Misc
Corrective Action Required
12/27/2023
12-27-23 Dustin A, sw is poured and slopes are in compliance. white cure needs to be added
Sidewalk Inspection Partial 1/5/2024 1/5/2024 01/05/2024
Misc
Corrective Action Required
12/27/2023
12-27-23 Dustin A, sw is poured and slopes are in compliance. white cure needs to be added 1-5-24 Dustin A, conditions have not changed
Sidewalk Inspection Passed 1/30/2024 1/30/2024 01/25/2024
Misc
Corrective Action Required
01/05/2024
12-27-23 Dustin A, sw is poured and slopes are in compliance. white cure needs to be added 1-5-24 Dustin A, conditions have not changed 1-25-24 Dustin A, white cure is added.
Erosion Control Inspection Residential Failed 2/6/2024 02/06/2024
DCM3 ESC REQUIRED 2 DAY
Resolved
02/06/2024
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS maintain overgrown vegetation some has been fixed but still needs addressed at rear of lot.
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
02/06/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. No erosion control installed
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
02/06/2024
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Erosion Control Inspection Residential Partial 2/13/2024 02/13/2024
DCM2 ESC DEFICIENT INSTALLATION
Resolved
02/13/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. No erosion control installed
DCM3 ESC REQUIRED 2 DAY
Resolved
02/13/2024
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Misc
Informational
02/13/2024
Erosion control back in compliance at time of inspection.
Plot Plan Inspection Passed 07/10/2024
Occupancy Inspection - Codes Residential Failed 7/10/2024 7/10/2024 07/10/2024
Misc
Corrective Action Required
07/10/2024
-All outlets in laundry to be GFCI protected -security screws at rear door -stairs from entry way to basement door greater that 3/8” difference in rise -tamper caps missing at A/c unit -seal all exterior penetrations -sump pump discharge to extend 36” from foundation
Erosion Control Inspection Residential Passed 08/05/2024
Misc
Resolved
08/05/2024
Erosion control back in compliance at time of inspection.
Occupancy Inspection - Codes Residential Full C of O 8/5/2024 8/5/2024 08/05/2024
Misc
Resolved
08/05/2024
-All outlets in laundry to be GFCI protected -security screws at rear door -stairs from entry way to basement door greater that 3/8” difference in rise -tamper caps missing at A/c unit -seal all exterior penetrations -sump pump discharge to extend 36” from foundation
Documents & Images
Date Uploaded File Type Document Name
01/31/2022 Lot 88 HF Tax app
01/31/2022 Lot 88 HF permit app
02/01/2022 Permit Codes Residential Plan Review
02/07/2022 Approved Plans Approved Drawings
02/07/2022 Plot Plan Approved Plot Plan
02/07/2022 Permit Codes Residential Plan Review
02/11/2022 Permit DS Building Permit
02/11/2022 Receipt Receipt for transaction:2022-000782
04/05/2022 Letter INSPECTION SUMMARY
04/05/2022 Receipt Receipt for transaction:2022-001863
04/05/2022 Letter INSPECTION SUMMARY
06/08/2022 Letter INSPECTION SUMMARY
10/18/2022 Letter INSPECTION SUMMARY
10/18/2022 Letter INSPECTION SUMMARY
10/20/2022 Letter INSPECTION SUMMARY
03/09/2023 Letter Codes 140 Day Letter
04/18/2023 Letter Codes 180 Day Letter
06/06/2023 Extension Request 2
06/06/2023 Extension Request
06/07/2023 Letter INSPECTION SUMMARY
07/20/2023 Letter INSPECTION SUMMARY
08/11/2023 Letter INSPECTION SUMMARY
08/17/2023 Letter INSPECTION SUMMARY
08/21/2023 Letter INSPECTION SUMMARY
09/05/2023 Letter INSPECTION SUMMARY
10/25/2023 Letter INSPECTION SUMMARY
10/25/2023 Letter INSPECTION SUMMARY
10/25/2023 Letter INSPECTION SUMMARY
10/30/2023 Letter INSPECTION SUMMARY
10/30/2023 Letter INSPECTION SUMMARY
10/30/2023 Letter INSPECTION SUMMARY
12/18/2023 Letter INSPECTION SUMMARY
12/18/2023 Letter INSPECTION SUMMARY
12/27/2023 Letter INSPECTION SUMMARY
12/27/2023 Letter INSPECTION SUMMARY
12/27/2023 Letter INSPECTION SUMMARY
01/05/2024 Letter INSPECTION SUMMARY
01/25/2024 Letter INSPECTION SUMMARY
02/06/2024 Letter INSPECTION SUMMARY
02/13/2024 Letter INSPECTION SUMMARY
07/02/2024 Letter Codes Residential Plan Review
07/02/2024 Letter Codes 140 Day Letter
07/02/2024 Letter Codes 140 Day Letter
07/02/2024 Letter Codes 140 Day Letter
07/10/2024 Letter Codes 140 Day Letter
07/10/2024 Letter Codes 140 Day Letter
07/10/2024 Letter INSPECTION SUMMARY
07/10/2024 Letter Codes 140 Day Letter
07/10/2024 Letter Codes 140 Day Letter
07/10/2024 Letter INSPECTION SUMMARY
08/05/2024 Letter Codes 140 Day Letter
08/05/2024 Letter INSPECTION SUMMARY
08/05/2024 Letter Codes Final Certificate of Occupancy
08/05/2024 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home