Summary
PRRES20216203
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - UNFINISHED BASEMENT - UNCOVERED PATIO STOP WORK ORDER generated on 04/27/2022 12:00 AM by username 'Mitchell Schwarz'. STOP WORK ORDER removed on 05/24/2022 12:00 AM by username 'Mitchell Schwarz'.
12/02/2021
12/20/2021
05/31/2022
12/13/2022
Locations
Contacts
ELEVATE DESIGN & BUILD LLC, Address:350 SW LONGVIEW BLVD, Phone:(816) 622-8826  
Elevate Design + Build , Address:350 Longview Blvd.   
R-MECH HEATING COOLING PLUMBING/RHODES HEATING COOLING PLUMBING AND ROOTER, Address:1425 AGNES AVE, Phone:(816) 920-5955  
ELECTRICAL CONNECTIONS, Address:20112 HOPS CREEK DR, Phone:(816) 838-6946  
CENTURY PLUMBING, Address:14001 CENTURY LN, Phone:(816) 765-6066  
GLEN@elevatedesignbuildkc.com  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,124.79 $1,124.79 Paid 12/20/2021
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 12/20/2021
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 12/20/2021
8331507-Sewer Connection Fee $450.00 $450.00 Paid 12/20/2021
8331401-Water Tap Fee $3,655.00 $3,655.00 Paid 12/20/2021
8350015-Water Meter Fee $479.24 $479.24 Paid 12/20/2021
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 02/07/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Residential Failed 1/12/2022 01/12/2022
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
01/12/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. REPAIR DOWNED SILT FENCE
Water Service Inspection - R Partial 1/18/2022 (8:30) 1/18/2022 01/18/2022
Misc
Informational
01/18/2022
pex ran with open trench for sewer
Sewer Service Inspection - R Passed 1/18/2022 (8:30) 1/18/2022 01/18/2022
Water Service Inspection - R Passed 1/19/2022 (11:15) 1/19/2022 01/19/2022
Misc
Resolved
01/19/2022
pex ran with open trench for sewer
Underslab Plumbing Inspection - Residential Not Ready 2/1/2022 2/1/2022 02/01/2022
Misc
Corrective Action Required
02/01/2022
*INSPECTION DENIED* -NO PREMISES IDENTIFICATION -EROSION CONTROL NOT IN COMPLIANCE
Erosion Control Inspection Residential Failed 2/1/2022 02/01/2022
DCM3 ESC REQUIRED 2 DAY
Resolved
02/01/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. REPAIR DOWNED SILT FENCE
DCM5 ESC INSP DENIED
Corrective Action Required
02/01/2022
REQUESTED INSPECTION(S) DENIED DUE TO DEFICIENT EROSION CONTROL INSTALLATION.
Underslab Plumbing Inspection - Residential Passed 2/8/2022 02/08/2022
Misc
Resolved
02/08/2022
*INSPECTION DENIED* -NO PREMISES IDENTIFICATION -EROSION CONTROL NOT IN COMPLIANCE
Erosion Control Inspection Residential Failed 3/29/2022 03/29/2022
DCM5 ESC INSP DENIED
Resolved
03/29/2022
REQUESTED INSPECTION(S) DENIED DUE TO DEFICIENT EROSION CONTROL INSTALLATION.
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
03/29/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. Mitchell Schwarz 03/29/2022 11:21 AM
Erosion Control Inspection Residential Failed - Stop Work 4/27/2022 04/27/2022
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
03/29/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. Mitchell Schwarz 03/29/2022 11:21 AM
Misc
Corrective Action Required
04/27/2022
erosion control still not in compliance, stop work issued Mitchell Schwarz 04/27/2022 9:47 AM
Erosion Control Inspection Residential Partial 5/24/2022 5/24/2022 05/24/2022
DCM3 ESC REQUIRED 2 DAY
Resolved
05/24/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. Mitchell Schwarz 03/29/2022 11:21 AM
Misc
Resolved
05/24/2022
erosion control still not in compliance, stop work issued Mitchell Schwarz 04/27/2022 9:47 AM
Misc
Informational
05/24/2022
Erosion control back in compliance at time of inspection 5/24/22
Electrical Service Inspection Failed 5/23/2022 5/24/2022 05/24/2022
Misc
Corrective Action Required
05/24/2022
Use approved clamp at ufer
Gas Service Inspection - Residential Passed 5/23/2022 5/24/2022 05/24/2022
All Rough Inspection - Residential Failed 5/23/2022 5/24/2022 05/24/2022
Misc
Corrective Action Required
05/24/2022
-provide proper nailing for PFH at garage -column in garage to be of correct size -address rafters landing on blocks -anchor bolts to be in the middle 1/3 of sill plate -anchor bolts to be within 12” of plate breaks but not close than 7x the diameter of the bolt -minimum 1 20 amp outlet per vehicle bay in garage -fireblock top of furr out walls in garage -protect all NM with in 6’ of attic access -seal penetrations in RA space garage entry see floor and joist space -fire block hvac chase -missing nails in hangers in garage entry furr down -fire block garage entry bath dwv into furr down -add boca plate to top at dwv states above -fire block kitchen wall into furr down in garage entry -provide proper bearing for joist above kitchen/hvac chase -provide proper support for dwv above kitchen and bath -missing joist hanger above kitchen where headered off -address hole in floor in kitchen -boca plate for pex at fridge -boca plate protection for pex at great room windows. -fireblock furr out wall at great room windows -provide support for dwv above kitchen/great room (traps not considered support) -outlet spacing to code at rear great room windows -strap top plate where lapped less than 24” flex room W wall -missing nail in hanger above great room/flex room -fireblock walls to ceiling space in master bedroom -fireblock hvac chase 2nd floor -plans call for 3 2x12 above master bath -missing nails in multiple hangers at ceiling joists to lvl above 2nd floor hallway -provide proper clamp at ufer ground rod -fix RA panning at ufer ground
All Rough Inspection - Residential Passed 6/8/2022 6/8/2022 06/08/2022
Misc
Resolved
06/08/2022
-address rafters landing on blocks -anchor bolts to be in the middle 1/3 of sill plate -anchor bolts to be within 12” of plate breaks but not close than 7x the diameter of the bolt -minimum 1 20 amp outlet per vehicle bay in garage -fireblock top of furr out walls in garage -protect all NM with in 6’ of attic access -seal penetrations in RA space garage entry see floor and joist space -fire block hvac chase -missing nails in hangers in garage entry furr down -fire block garage entry bath dwv into furr down -add boca plate to top at dwv states above -fire block kitchen wall into furr down in garage entry -provide proper bearing for joist above kitchen/hvac chase -provide proper support for dwv above kitchen and bath -missing joist hanger above kitchen where headered off -address hole in floor in kitchen -boca plate for pex at fridge -boca plate protection for pex at great room windows. -fireblock furr out wall at great room windows -provide support for dwv above kitchen/great room (traps not considered support) -outlet spacing to code at rear great room windows -strap top plate where lapped less than 24” flex room W wall -missing nail in hanger above great room/flex room -fireblock walls to ceiling space in master bedroom -fireblock hvac chase 2nd floor -plans call for 3 2x12 above master bath -missing nails in multiple hangers at ceiling joists to lvl above 2nd floor hallway -provide proper clamp at ufer ground rod -fix RA panning at ufer ground
Electrical Service Inspection Passed 6/8/2022 6/8/2022 06/08/2022
Misc
Resolved
06/08/2022
Use approved clamp at ufer
Driveway Inspection Partial 7/12/2022 7/12/2022 07/12/2022
Misc
Informational
07/12/2022
On 7.12.2022 I conducted a driveway inspection and pass the subgrade to pour concrete.
Driveway Inspection Passed 8/31/2022 8/31/2022 07/14/2022
Misc
Informational
07/12/2022
On 7.12.2022 I conducted a driveway inspection and pass the subgrade to pour concrete. 7.14.2022 Driveway appears to be compliant
Sidewalk Inspection Partial 7/14/2022 07/14/2022
Misc
Informational
07/14/2022
On 7.14.2022 I conducted a sidewalk inspection and pass the sub-grade to pour concrete.
Sidewalk Inspection Passed 7/14/2022 7/14/2022 07/19/2022
Misc
Informational
07/19/2022
7.19.2022 Sidewalk appears to be in compliance
Occupancy Inspection - Codes Residential Failed 9/15/2022 9/15/2022 09/15/2022
Misc
Corrective Action Required
09/15/2022
inspection denied -no address posted -no erosion control -footing poured without inspection upload 3rd party footing inspection -piers poured without inspetion
Erosion Control Inspection Residential Failed 9/15/2022 09/15/2022
Misc
Resolved
09/15/2022
Erosion control back in compliance at time of inspection 5/24/22
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
09/15/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Occupancy Inspection - Codes Residential Failed 10/3/2022 10/3/2022 10/03/2022
Misc
Corrective Action Required
09/15/2022
inspection denied -footing poured without inspection upload 3rd party footing inspection -piers poured without inspetion
Footing Inspection - Residential Passed 10/12/2022 10/12/2022
Erosion Control Inspection Residential Passed 10/13/2022 10/13/2022
DCM3 ESC REQUIRED 2 DAY
Resolved
10/13/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Occupancy Inspection - Codes Residential Failed 10/13/2022 10/13/2022 10/13/2022
Misc
Resolved
10/13/2022
inspection denied -footing poured without inspection upload 3rd party footing inspection -piers poured without inspetion
Misc
Corrective Action Required
10/13/2022
-provide as graded plot plan -splash block and sump pump discharge to extend 36” from foundation -rear patio steps greater than 7 3/4” -spark rings at kitchen outlets where required by code -garage door to be self closing and latching -label all non GFCI outlets in unfinished spaces -garage stairs greater than 3/8” in risers -address nosing at stairwell to 2nd floor not to code see code section R311.7.5.3 of the irc -top step to basement greater than 7 3/4” -dishwasher to be GFCI -GFCI protection for outlet under sink -secure SE cable at service panel -address siding from grade at rear of home Must be 6” from ground 2” from concrete patio
Miscellaneous Inspection Passed 10/31/2022 10/31/2022
Misc
Informational
10/31/2022
met with Forest on site about inspection item questions he had.
Occupancy Inspection - Codes Residential Failed 12/9/2022 12/9/2022 12/09/2022
Misc
Corrective Action Required
10/13/2022
-provide as graded plot plan -address siding clearance from grade at rear of home must be 6” from grade (this includes sod, rocks, mulch, etc landscaping) and 2” clearance from concrete patio
Plot Plan Inspection Passed 12/12/2022 12/12/2022
Occupancy Inspection - Codes Residential Full C of O 12/13/2022 12/13/2022 12/13/2022
Misc
Resolved
12/13/2022
-provide as graded plot plan -address siding clearance from grade at rear of home must be 6” from grade (this includes sod, rocks, mulch, etc landscaping) and 2” clearance from concrete patio
Documents & Images
Date Uploaded File Type Document Name
12/02/2021 License_Tax_Application
12/02/2021 Residental Permit Application_1
12/02/2021 Approved Plans Approved Drawings
12/02/2021 Permit Codes Residential Plan Review
12/03/2021 Review Comment Response
12/15/2021 Plot Plan Approved Plot Plan
12/15/2021 Permit Codes Residential Plan Review
12/20/2021 Permit DS Building Permit
12/20/2021 Receipt Receipt for transaction:2021-009382
01/12/2022 Letter INSPECTION SUMMARY
01/18/2022 Letter INSPECTION SUMMARY
01/18/2022 Letter INSPECTION SUMMARY
01/19/2022 Letter INSPECTION SUMMARY
02/01/2022 Letter INSPECTION SUMMARY
02/01/2022 Letter INSPECTION SUMMARY
02/07/2022 Receipt Receipt for transaction:2022-000666
02/08/2022 Letter INSPECTION SUMMARY
03/29/2022 Letter INSPECTION SUMMARY
05/03/2022 Letter Stop Work Order
05/24/2022 Letter INSPECTION SUMMARY
05/24/2022 Letter INSPECTION SUMMARY
05/24/2022 Letter INSPECTION SUMMARY
05/24/2022 Letter INSPECTION SUMMARY
06/07/2022 2046 SW Hook Farm Dr Letter - signed
06/08/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
09/15/2022 Letter INSPECTION SUMMARY
09/15/2022 Letter INSPECTION SUMMARY
10/03/2022 Letter INSPECTION SUMMARY
10/12/2022 Letter INSPECTION SUMMARY
10/13/2022 Letter INSPECTION SUMMARY
10/13/2022 Letter INSPECTION SUMMARY
10/13/2022 Letter INSPECTION SUMMARY
12/09/2022 Letter INSPECTION SUMMARY
12/09/2022 Plot Plan Approved As-Graded Plot Plan
12/12/2022 Letter INSPECTION SUMMARY
12/13/2022 Letter INSPECTION SUMMARY
12/13/2022 Letter Field Certificate of Occupancy
12/13/2022 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home