Summary
PRRES20213494
Building Permit - Residential
Certificate of Occupancy
CMH PARKS INC
NEW SINGLE FAMILY
NEW HOUSE - UNFINISHED BASEMENT - COVERED PATIO
07/07/2021
07/08/2021
01/04/2022
06/29/2022
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:10450 Holmes Rd Suite 100, Phone:(816) 246-6700  
CMH PARKS INC, Address:5000 CLAYTON RD  
Summit Homes, Address:120 SE 30th St, Phone:(816) 434-5074 Ext:320  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
LOREN@SUMMITHOMESKC.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee New Single Family $1,000.56 $1,000.56 Paid 07/08/2021
Right of Way Permit Fee $80.00 $80.00 Paid 07/08/2021
Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 07/08/2021
8331507-Sewer Connection Fee $360.00 $360.00 Paid 07/08/2021
Water Tap Fee $3,655.00 $3,655.00 Paid 07/08/2021
Water Meter Fee $479.24 $479.24 Paid 07/08/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 8/18/2021 (10:00) 8/18/2021 08/18/2021
Underslab Plumbing Inspection - Residential Passed 9/29/2021 9/29/2021 09/29/2021
Sewer Service Inspection - R Passed 11/3/2021 (1:30) 11/3/2021 11/03/2021
Water Service Inspection - R Passed 11/9/2021 (1:00) 11/9/2021 11/09/2021
Erosion Control Inspection Residential Failed 11/9/2021 11/09/2021
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
11/09/2021
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE.
Gas Service Inspection - Residential Passed 3/22/2022 3/22/2022 03/22/2022
Electrical Service Inspection Failed 3/22/2022 3/22/2022 03/22/2022
Misc
Corrective Action Required
03/22/2022
ground ufer to middle grounded bus bar
All Rough Inspection - Residential Failed 3/22/2022 3/22/2022 03/22/2022
Misc
Corrective Action Required
03/22/2022
-Complete PFH at garage -protect NM within 6’ of attic access -All anchor bolts to be tight -furr out and fireblock wall for dryer vent garage wall -strap both top plates where lapped less than 24” left of garage owners entry -seal top plate penetration W garage wall -add h 2.5 for gt truss bearing N garage wall -cspf nailing per plans -fireblock above fireplace -strap top plate lapped less than 24” above fireplace -address all studs over bored/notched at and left of fireplace -GT bearing required 4 2x4 per plans (bed 1,) -h2.5 at gt above bed one entry both sides -seal top plate penetrations bath 1 closet -uncover covered patio to inspect for hip/jack connector per plans -truss lateral bracing per plans though out -solid blocking per plans under kitchen island -could not inspect front covered patio -ground ufer to middle grounded bus bar
Electrical Service Inspection Passed 3/28/2022 3/28/2022 03/28/2022
Misc
Corrective Action Required
03/22/2022
ground ufer to middle grounded bus bar
All Rough Inspection - Residential Failed 3/28/2022 3/28/2022 03/28/2022
Misc
Corrective Action Required
03/22/2022
-Complete PFH at garage (nail off anchor straps completely -protect NM within 6’ of attic access -furr out and fireblock wall for dryer vent garage wall ufer to remain accessible at finish -fireblock above fireplace(seal gaps) -h2.5 at gt above bed one entry both sides -truss lateral bracing per plans though out -solid blocking per plans under kitchen island -could not inspect front covered patio -ground ufer to middle grounded bus bar -nail exterior sheathing per plans -support ridge beam at front covered patio -support rafters at front cover patio
All Rough Inspection - Residential Passed 3/30/2022 3/30/2022 03/30/2022
Misc
Resolved
03/30/2022
-Complete PFH at garage (nail off anchor straps -protect NM within 6’ of attic access -furr out and fireblock wall for dryer vent garage wall ufer to remain accessible at finish -fireblock above fireplace(seal gaps)
Driveway Inspection Passed 4/22/2022 04/22/2022
Misc
Informational
04/22/2022
On Friday, 4-22-2022 I performed and passed driveway for placement of concrete.
Sidewalk Inspection Passed 4/22/2022 04/22/2022
Misc
Informational
04/22/2022
On Friday, 4-22-2022, I performed and passed sidewalk inspection for concrete placement.
Occupancy Inspection - Codes Residential Failed 6/16/2022 6/16/2022 06/16/2022
Misc
Corrective Action Required
06/16/2022
-address piers poured without inspection -final grade and sod -splash blocks and sump pump discharge to extend 36” from foundation -seal top of meter can, A/c disconnect and all other exterior penetrations -check water meter at time of final grade and sod -guard rail at front stoop where required by code -hardware at sliding back patio door -self closing device at garage owners entry
Erosion Control Inspection Residential Passed 6/29/2022 06/29/2022
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
11/09/2021
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE.
Piers/Caissons Inspection - Residential Passed 6/29/2022 06/29/2022
Plot Plan Inspection Passed 6/29/2022 06/29/2022
Occupancy Inspection - Codes Residential Full C of O 6/29/2022 6/29/2022 06/29/2022
Misc
Resolved
06/29/2022
-address piers poured without inspection -final grade and sod -splash blocks and sump pump discharge to extend 36” from foundation -seal top of meter can, A/c disconnect and all other exterior penetrations -check water meter at time of final grade and sod -guard rail at front stoop where required by code -hardware at sliding back patio door -self closing device at garage owners entry
Documents & Images
Date Uploaded File Type Document Name
07/07/2021 H3 #72 - PERMIT APPLICATION
07/08/2021 Approved Plans Approved Drawings
07/08/2021 Approved Plans Approved Truss Layout
07/08/2021 Approved Plans Approved Truss Package
07/08/2021 Permit Codes Residential Plan Review
07/08/2021 Plot Plan Approved Plot Plan
07/08/2021 Permit Codes Residential Plan Review
07/08/2021 Permit DS Building Permit
07/08/2021 Receipt Receipt for transaction:2021-005491
08/18/2021 Letter INSPECTION SUMMARY
09/29/2021 Letter INSPECTION SUMMARY
11/03/2021 Letter INSPECTION SUMMARY
11/09/2021 Letter INSPECTION SUMMARY
11/09/2021 Letter INSPECTION SUMMARY
03/22/2022 Letter INSPECTION SUMMARY
03/22/2022 Letter INSPECTION SUMMARY
03/22/2022 Letter INSPECTION SUMMARY
03/22/2022 Letter INSPECTION SUMMARY
03/27/2022 72 Hawthorne Ridge Letter
03/28/2022 Letter INSPECTION SUMMARY
03/28/2022 Letter INSPECTION SUMMARY
03/30/2022 Letter INSPECTION SUMMARY
04/22/2022 Letter INSPECTION SUMMARY
04/22/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/16/2022 7821-6
06/16/2022 72 inspection 1
06/16/2022 7821-7
06/29/2022 Letter Codes Final Certificate of Occupancy
06/29/2022 Letter Field Certificate of Occupancy
06/29/2022 Letter INSPECTION SUMMARY
06/29/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents