Summary
PRRES20212553
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - UNFINISHED BASEMENT - COVERED PATIO STOP WORK ORDER generated on 07/29/2021 12:00 AM by username 'Patrick Schonfeldt'. STOP WORK ORDER removed on 07/30/2021 12:00 AM by username 'Patrick Schonfeldt'.
05/18/2021
05/21/2021
11/15/2021
07/21/2022
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
Summit Homes, Address:120 SE 30th St, Phone:(816) 434-5074 Ext:320  
LOREN@SUMMITHOMESKC.COM  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 05/21/2021
7232302-Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 05/21/2021
8331507-Sewer Connection Fee $600.00 $600.00 Paid 05/21/2021
8331401-Water Tap Fee $3,581.00 $3,581.00 Paid 05/21/2021
8350015-Water Meter Fee $455.54 $455.54 Paid 05/21/2021
9110078-Valuation Fee New Single Family $1,364.77 $1,364.77 Paid 05/21/2021
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 03/07/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underslab Plumbing Inspection - Residential Failed 7/29/2021 7/29/2021 07/29/2021
Misc
Corrective Action Required
07/29/2021
INSPECTION DENIED FOOTING POURED WITHOUT INSPECTION
Footing Inspection - Residential Failed - Stop Work 7/29/2021 7/29/2021 07/29/2021
Misc
Corrective Action Required
07/29/2021
FOOTING POURED WITHOUT INSPECTION, ENGINEER REPORT IS REQUIRED TO BE SUBMITTED WITHIN 48 HOURS OF INSPECTION STOP WORK ORDER ISSUED
Footing Inspection - Residential Passed 7/30/2021 07/30/2021
Misc
Informational
07/30/2021
APPROVED PER BRADLEY HUXOL 6/24/21
Underslab Plumbing Inspection - Residential Passed 8/2/2021 8/2/2021 08/02/2021
Misc
Resolved
08/02/2021
Water Service Inspection - R Passed 8/27/2021 (10:00) 8/27/2021 08/27/2021
Sewer Service Inspection - R Passed 8/27/2021 (9:45) 8/27/2021 08/27/2021
Erosion Control Inspection Residential Failed 8/27/2021 8/27/2021 08/27/2021
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
08/27/2021
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE.
Electrical Service Inspection Not Ready 2/23/2022 2/23/2022 02/23/2022
Gas Service Inspection - Residential Passed 2/23/2022 2/23/2022 02/23/2022
All Rough Inspection - Residential Failed 2/23/2022 2/23/2022 02/23/2022
Misc
Corrective Action Required
02/23/2022
-uncover PFH nail pattern for inspection at garage -complete electrical in garage -complete lib in garage and bed 5 -snow blocking in pantry -seal upward penetration at front door -fire block vertical to lateral furr downs -protect NM within 6’ of attic access -fire block hvac chase -seal and secure around gas line at fireplace -connect bath exhaust fan to exterior vent in 1st floor bath -bed 5 windows to be installed -egress window in basement to be installed -anchor all steel columns -complete exhaust for bath 1 -jacuzzi tub motor and outlet to be accessible for service at time of finish per code -(2) h2.5 at each bearing end of GT trusses -h2.5 at truss bed 2 closet -mid way strap dwv 2” or less -support dwv every 4’ -fire block bath one ceiling line -hanger for header at stairwell -B vent must terminate 2ft. Higher than any portion of building within 10ft
All Rough Inspection - Residential Failed 3/1/2022 3/1/2022 03/02/2022
Misc
Corrective Action Required
03/01/2022
-protect NM within 6’ of attic access -fire block hvac chase -bed 5 windows to be installed -egress window in basement to be installed -jacuzzi tub motor and outlet to be accessible for service at time of finish per code
Electrical Service Inspection Passed 3/1/2022 3/1/2022 03/02/2022
All Rough Inspection - Residential Failed 3/7/2022 3/7/2022 03/07/2022
Misc
Corrective Action Required
03/01/2022
-protect NM within 6’ of attic access -bed 5 windows to be installed OKAY TO INSULATE DONT COVER ITEMS STILL NEEDING INSPECTION
All Rough Inspection - Residential Passed 3/8/2022 3/8/2022 03/08/2022
Misc
Corrective Action Required
03/07/2022
-bed 5 windows to be installed
Driveway Inspection Passed 4/27/2022 04/27/2022
Misc
Informational
04/27/2022
On Wednesday, 4-27-2022, I performed and passed a driveway inspection for placement of concrete.
Sidewalk Inspection Passed 4/27/2022 04/27/2022
Misc
Informational
04/27/2022
On Wednesday, 4-27-2022. I performed and passed a sidewalk Inspection for concrete installation.
Plot Plan Inspection Passed 6/23/2022 06/23/2022
Occupancy Inspection - Codes Residential Failed 6/23/2022 6/23/2022 06/23/2022
Misc
Corrective Action Required
06/23/2022
-sod -splash blocks and sump pump discharge to extend 36” from foundation -check water meter at time of sod -spark ring above fireplace -spark rings at kitchen outlets as required by code -complete stove top hood -garage stairs to comply with code -lock out for kitchen stove hood breaker -provide code compliant access to jacuzzi tub motor in master bath -GFCI protection for all outdoor outlets -secure A/c disconnect whip within 12” of disconnect
Occupancy Inspection - Codes Residential Failed 7/7/2022 7/7/2022 07/07/2022
Misc
Corrective Action Required
06/23/2022
-check water meter at time of sod locate water meter.. -complete stove top hood -garage stairs to comply with code, over 1/2" difference.
Occupancy Inspection - Codes Residential Failed 7/19/2022 7/19/2022 07/19/2022
Misc
Corrective Action Required
07/07/2022
-garage stairs to comply with code, over 1/2" difference.
Erosion Control Inspection Residential Passed 7/21/2022 07/21/2022
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
08/27/2021
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE.
Occupancy Inspection - Codes Residential Full C of O 7/21/2022 7/21/2022 07/21/2022
Misc
Resolved
07/21/2022
-garage stairs to comply with code, over 1/2" difference.
Documents & Images
Date Uploaded File Type Document Name
05/18/2021 HT #137 - PERMIT APP
05/18/2021 Approved Plans Approved Drawings
05/18/2021 Approved Plans Approved Truss Layout
05/18/2021 Approved Plans Approved Truss Package
05/19/2021 Permit Codes Residential Plan Review
05/21/2021 Plot Plan Approved Plot Plan
05/21/2021 Permit Codes Residential Plan Review
05/21/2021 Permit DS Building Permit
05/21/2021 Receipt Receipt for transaction:2021-003351
06/29/2021 2766770 RF SEAL 06292021
07/28/2021 Lot 137 Hawthorne Ridge Foundation Inspection
07/29/2021 Letter INSPECTION SUMMARY
07/29/2021 Letter Stop Work Order
07/29/2021 Lot 137 Hawthorne Ridge Footing Inspection
07/30/2021 Letter INSPECTION SUMMARY
08/02/2021 Letter INSPECTION SUMMARY
08/27/2021 Letter INSPECTION SUMMARY
08/27/2021 Letter INSPECTION SUMMARY
08/27/2021 Letter INSPECTION SUMMARY
02/23/2022 Letter INSPECTION SUMMARY
02/23/2022 Letter INSPECTION SUMMARY
02/23/2022 Letter INSPECTION SUMMARY
03/01/2022 Letter INSPECTION SUMMARY
03/01/2022 Letter INSPECTION SUMMARY
03/02/2022 Letter INSPECTION SUMMARY
03/02/2022 Letter INSPECTION SUMMARY
03/07/2022 Letter INSPECTION SUMMARY
03/07/2022 Receipt Receipt for transaction:2022-001190
03/08/2022 Letter INSPECTION SUMMARY
04/27/2022 Letter INSPECTION SUMMARY
04/27/2022 Letter INSPECTION SUMMARY
06/23/2022 Letter INSPECTION SUMMARY
06/23/2022 Letter INSPECTION SUMMARY
07/07/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter Codes Final Certificate of Occupancy
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter Field Certificate of Occupancy
07/21/2022 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide: