Summary
PRRES20212322
Building Permit - Residential
Certificate of Occupancy
CMH PARKS INC
NEW SINGLE FAMILY
NEW HOUSE - FINISHED BASEMENT - COVERED DECK
05/07/2021
05/12/2021
03/04/2022
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:10450 Holmes Rd Suite 100, Phone:(816) 246-6700  
CMH PARKS INC, Address:5000 CLAYTON RD  
Summit Homes, Address:120 SE 30th St, Phone:(816) 434-5074 Ext:320  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Right of Way Permit Fee $80.00 $80.00 Paid 05/12/2021
Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 05/12/2021
8331507-Sewer Connection Fee $360.00 $360.00 Paid 05/12/2021
Water Tap Fee $3,581.00 $3,581.00 Paid 05/12/2021
Water Meter Fee $455.54 $455.54 Paid 05/12/2021
Valuation Fee New Single Family $832.75 $832.75 Paid 05/12/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 5/26/2021 05/26/2021
Underslab Plumbing Inspection - Residential Failed 6/29/2021 6/29/2021 06/29/2021
Misc
Corrective Action Required
06/29/2021
UNABLE TO INSPECT DWV DUE TO WATER AND MUD COVER. PUMP OUT WATER OR WAIT UNTIL CONDITIONS CLEAR BEFORE RESCHEDULING
Sewer Service Inspection - R Passed 7/7/2021 (9:45) 7/7/2021 07/07/2021
Underslab Plumbing Inspection - Residential Passed 7/8/2021 7/8/2021 07/07/2021
Misc
Resolved
07/07/2021
Water Service Inspection - R Passed 7/9/2021 (11:15) 7/9/2021 07/09/2021
Erosion Control Inspection Residential Failed 7/9/2021 7/9/2021 07/09/2021
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
07/09/2021
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
All Rough Inspection - Residential Partial 8/19/2021 8/19/2021 08/19/2021
Misc
Informational
08/19/2021
GARAGE PORTAL EXTERIOR OK TO COVER
Piers/Caissons Inspection - Residential Failed 10/4/2021 (8:00) 10/4/2021 10/04/2021
Misc
Corrective Action Required
10/04/2021
REMOVE ALL LOOSE SOIL FROM PIERS
Piers/Caissons Inspection - Residential Passed 10/4/2021 (11:30) 10/4/2021 10/04/2021
Misc
Resolved
10/04/2021
REMOVE ALL LOOSE SOIL FROM PIERS
Electrical Service Inspection Failed 11/3/2021 11/3/2021 11/03/2021
Misc
Corrective Action Required
11/03/2021
-Identify GEC at termination -use UFER ground clamp as designed for separation of conductor and UFER
Gas Service Inspection - Residential Failed 11/3/2021 11/3/2021 11/03/2021
Misc
Corrective Action Required
11/03/2021
-Gas pressure at 0 psi, must maintain 10 psi for test
All Rough Inspection - Residential Failed 11/3/2021 11/3/2021 11/03/2021
Misc
Informational
08/19/2021
GARAGE PORTAL EXTERIOR OK TO COVER
Misc
Corrective Action Required
11/03/2021
-H2.5 clip at truss bearing end, north garage wall -Attic access garage needs to be accessible to all attic space -intersecting corner at SW garage wall over bored and notched for electrical -receptacle required at stair wall 1st floor great room -secure gas flex line at fireplace -Fireblock between top plates at dbl wall kitchen/fridge -Nail sheathing at master bed west wall exterior wall, nails missed studs -fireblock deadspace master water closet/shower/hall wall -(4) 2x4 stud packs required at girder truss bearing ends per plans -Nail all truss hangers front bedroom hall at dbl girder truss -fireblock vertical every 10’ between studs and foundation wall/framing at finished basement -fireblock between top plates at finished basement -protection plate DWV top plate basement bath -Address floor joist that has been bored for sump pump discharge less than 2” from bottom of joist -(4) 2x6 stud pack at steel beam bearing per plans at bed#3 basement -Identify white conductors used as current carrying conductors at both points of termination
All Rough Inspection - Residential Failed 11/9/2021 11/9/2021 11/09/2021
Misc
Informational
11/03/2021
GARAGE PORTAL EXTERIOR OK TO COVER
Misc
Corrective Action Required
11/03/2021
-fireblock vertical every 10’ between studs and foundation wall/framing at finished basement, seal any penetrations and gaps in fireblock material -fireblock between top plates at finished basement
Electrical Service Inspection Passed 11/9/2021 11/9/2021 11/09/2021
Misc
Resolved
11/09/2021
Gas Service Inspection - Residential Passed 11/9/2021 11/9/2021 11/09/2021
Misc
Resolved
11/09/2021
-Gas pressure at 0 psi, must maintain 10 psi for test
All Rough Inspection - Residential Passed 11/11/2021 11/11/2021 11/11/2021
Misc
Resolved
11/11/2021
GARAGE PORTAL EXTERIOR OK TO COVER
Misc
Resolved
11/11/2021
-fireblock vertical every 10’ between studs and foundation wall/framing at finished basement, seal any penetrations and gaps in fireblock material -fireblock between top plates at finished basement
Driveway Inspection Passed 11/12/2021 11/12/2021 11/12/2021
Misc
Informational
11/12/2021
On Friday, 11-12-2021, I performed a driveway inspection that passed forming and sub-grade inspection.
Sidewalk Inspection Passed 11/12/2021 11/12/2021 11/12/2021
Misc
Informational
11/12/2021
On Friday, 11-12-2021. I performed a sidewalk inspection and passed sub-grade and forming for placement of concrete.
Occupancy Inspection - Codes Residential Failed 1/21/2022 1/21/2022 01/21/2022
Misc
Corrective Action Required
01/21/2022
-complete final grade and sod -Install gutters and downspouts -splash blocks at all downspouts and sump pump discharge -seal all penetrations in siding, seal along top of AC disconnect and meter can -address studs removed at stair wall behind furnace in mechanical room and proper header per code at HVAC duct through stair wall. That Stair wall is a load bearing wall. -(2) 1/2” through bolts at each post/beam connection at deck -full height continuous 6x6 cedar posts at covered deck per plans
Erosion Control Inspection Residential Partial 1/21/2022 1/21/2022 01/21/2022
DCM2 ESC DEFICIENT INSTALLATION
Resolved
01/21/2022
Misc
Corrective Action Required
01/21/2022
EROSION CONTROL ACCEPTABLE AT TIME OF INSPECTION
Occupancy Inspection - Codes Residential Temporary C of O 2/4/2022 2/4/2022 02/04/2022
Misc
Corrective Action Required
01/21/2022
TCO UNTIL 4/4/22 -complete final grade and sod -splash blocks at all downspouts and sump pump discharge -seal all penetrations in siding, seal along top of AC disconnect and meter can
Erosion Control Inspection Residential Passed 3/4/2022 03/04/2022
Misc
Resolved
03/04/2022
EROSION CONTROL ACCEPTABLE AT TIME OF INSPECTION
Plot Plan Inspection Passed 3/4/2022 03/04/2022
Occupancy Inspection - Codes Residential Full C of O 3/4/2022 3/4/2022 03/04/2022
Misc
Resolved
03/04/2022
TCO UNTIL 4/4/22 -complete final grade and sod -splash blocks at all downspouts and sump pump discharge -seal all penetrations in siding, seal along top of AC disconnect and meter can
Documents & Images
Date Uploaded File Type Document Name
05/07/2021 H3 #1 - PERMIT APP
05/07/2021 Approved Plans Approved Drawings
05/07/2021 Approved Plans Approved Truss Layout
05/07/2021 Approved Plans Approved Truss Package
05/07/2021 Plot Plan Approved Plot Plan
05/07/2021 Permit Codes Residential Plan Review
05/12/2021 Permit DS Building Permit
05/12/2021 Receipt Receipt for transaction:2021-002950
05/26/2021 Letter INSPECTION SUMMARY
06/29/2021 Letter INSPECTION SUMMARY
07/07/2021 Letter INSPECTION SUMMARY
07/07/2021 Letter INSPECTION SUMMARY
07/09/2021 Letter INSPECTION SUMMARY
07/09/2021 Letter INSPECTION SUMMARY
08/19/2021 Letter INSPECTION SUMMARY
10/04/2021 Letter INSPECTION SUMMARY
10/04/2021 Letter INSPECTION SUMMARY
11/03/2021 Letter INSPECTION SUMMARY
11/03/2021 Letter INSPECTION SUMMARY
11/03/2021 Letter INSPECTION SUMMARY
11/05/2021 1 Hawthorne Ridge notched stud and over bored floor joist letter
11/09/2021 Letter INSPECTION SUMMARY
11/09/2021 Letter INSPECTION SUMMARY
11/09/2021 Letter INSPECTION SUMMARY
11/11/2021 Letter INSPECTION SUMMARY
11/12/2021 Letter INSPECTION SUMMARY
11/12/2021 Letter INSPECTION SUMMARY
01/21/2022 Letter INSPECTION SUMMARY
01/21/2022 Letter INSPECTION SUMMARY
02/02/2022 1 hawthorne ridge deck post and load bearing wall letter
02/04/2022 Letter Codes Temporary Certificate of Occupancy
03/04/2022 Letter Codes Final Certificate of Occupancy
03/04/2022 Letter Field Certificate of Occupancy
03/04/2022 Letter INSPECTION SUMMARY
03/04/2022 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home