Summary
PRRES20211914
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - PARTIAL FINISHED BASEMENT - COVERED PATIO SUSPENDED STOOP
04/20/2021
04/27/2021
10/23/2021
04/06/2022
Locations
Contacts
SAB CONSTRUCTION INC, Address:PO BOX 942, Phone:(816) 524-3855  
MIKE BRYANT HEATING & COOLING , Address:1711 E 123RD , Phone:(913) 441-7807  
C-R ELECTRICAL LLC, Address:4539 RIDGEWAY, Phone:(816) 803-3500  
GARRISON PLUMBING, Address:15430 S MAHAFFIE ST STE 102, Phone:(913) 768-1311  
ROBERT@SABHOMES.COM  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 04/29/2021 04/27/2021
Kim Brennan
Property boundary
Corrective Action Required
04/27/2021

Property boundary distances and bearings, as shown on the recorded plat, must be provided on the plot plan. Missing the 26.04 dimension aloing north west side of the lot.
Right-of-way
Corrective Action Required
04/27/2021

The right-of-way with dimensions must be provided on the plot plan. Please show this dimension along Freehold Court as well as Jamestown Drive.
Sidewalks
Corrective Action Required
04/27/2021

Sidewalks with dimensions must be provided on the plot plan. Please show sidewalk along NE Janestown Drive
Residential Plan Review Approved 04/29/2021 04/27/2021
Kim Brennan
Plot Plan Review Rejected 04/27/2021 04/26/2021
Kim Brennan
Property boundary
Corrective Action Required
04/26/2021

Property boundary distances and bearings, as shown on the recorded plat, must be provided on the plot plan. Missing the 26.04 dimension aloing north west side of the lot.
Right-of-way
Corrective Action Required
04/26/2021

The right-of-way with dimensions must be provided on the plot plan. Please show this dimension along Freehold Court as well as Jamestown Drive.
Sidewalks
Corrective Action Required
04/26/2021

Sidewalks with dimensions must be provided on the plot plan. Please show sidewalk along NE Janestown Drive
Residential Plan Review Approved 04/27/2021 04/23/2021
Kim Brennan
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,109.05 $1,109.05 Paid 04/27/2021
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 04/27/2021
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 04/27/2021
8331507-Sewer Connection Fee $420.00 $420.00 Paid 04/27/2021
8331401-Water Tap Fee $3,581.00 $3,581.00 Paid 04/27/2021
8350015-Water Meter Fee $455.54 $455.54 Paid 04/27/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Water Service Inspection - R Passed 5/21/2021 (10:45) 5/21/2021 05/21/2021
Footing Inspection - Residential Passed 06/08/2021
Informational
06/08/2021
FOOTING APPROVED BY ENGINEER
Underslab Plumbing Inspection - Residential Failed 6/8/2021 6/8/2021 06/08/2021
Misc
Corrective Action Required
06/08/2021
INSPECTION DENIED DUE TO EROSION CONTROL DEFICIENCY
Erosion Control Inspection Residential Failed 6/8/2021 06/08/2021
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
06/08/2021
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Piers/Caissons Inspection - Residential Failed 6/10/2021 (9:30) 6/10/2021 06/10/2021
Misc
Corrective Action Required
06/10/2021
Remove loose dirt from pier hole; one of the two piers closer to the house is misplaced about a ft.
Underslab Plumbing Inspection - Residential Passed 6/10/2021 06/10/2021
Misc
Resolved
06/10/2021
INSPECTION DENIED DUE TO EROSION CONTROL DEFICIENCY
Sewer Service Inspection - R Passed 6/21/2021 (1:00) 6/21/2021 06/21/2021
Piers/Caissons Inspection - Residential Passed 7/14/2021 (9:45) 7/14/2021 07/14/2021
Misc
Resolved
07/14/2021
Remove loose dirt from pier hole; one of the two piers closer to the house is misplaced about a ft.
Suspended Slab Inspection Passed 8/4/2021 8/4/2021 08/04/2021
Rough Framing Inspection - Residential Failed 8/5/2021 8/5/2021 08/05/2021
Misc
Corrective Action Required
08/05/2021
-Nail garage PFH wall sheathing to sill plates @ 3" oc
All Rough Inspection - Residential Failed 10/5/2021 10/5/2021 10/05/2021
Misc
Corrective Action Required
10/05/2021
-Nail exterior wall sheathing per code -Nail corner studs per code -Protect wiring running across joists and studding where within 6 ft of attic access -Anchor garage plate at front entry garage -Protect plumbing at master closet Install a floor receptacle at dining rail -Unblock return air at rear basement bedroom wall and pan off return air space from ceiling space **OK TO INSULATE
Electrical Service Inspection Failed 10/5/2021 10/5/2021 10/05/2021
Misc
Corrective Action Required
10/05/2021
-Connect the GEC to the middle grounded bus bar or install #4 jumper
Gas Service Inspection - Residential Passed 10/5/2021 10/5/2021 10/05/2021
All Rough Inspection - Residential Failed 10/11/2021 10/11/2021 10/11/2021
Misc
Corrective Action Required
10/05/2021
-At rear basement bed-pan off return air space from ceiling space
Electrical Service Inspection Passed 10/11/2021 10/11/2021 10/11/2021
Misc
Resolved
10/11/2021
-Connect the GEC to the middle grounded bus bar or install #4 jumper
Rough Framing Inspection - Residential Passed 10/11/2021 10/11/2021 10/11/2021
Misc
Resolved
10/11/2021
-Nail garage PFH wall sheathing to sill plates @ 3" oc
All Rough Inspection - Residential Passed 10/12/2021 10/12/2021
Misc
Resolved
10/12/2021
-At rear basement bed-pan off return air space from ceiling space
Driveway Inspection Partial 12/9/2021 12/09/2021
Misc
Informational
12/09/2021
12-9-21 AN Forms are in place and aggregate is present and compacted
Sidewalk Inspection Partial 12/9/2021 12/09/2021
Misc
Informational
12/09/2021
12-9-21 AN Forms are in place and aggregate is present and compacted
Sidewalk Inspection Passed 12/17/2021 12/17/2021 12/20/2021
Misc
Informational
12/09/2021
12-9-21 AN Forms are in place and aggregate is present and compacted
Misc
Informational
12/20/2021
Sidewalk meets LS and Ada spec. 12/20/21 ES
Driveway Inspection Passed 12/17/2021 12/17/2021 12/20/2021
Misc
Informational
12/09/2021
12-9-21 AN Forms are in place and aggregate is present and compacted
Misc
Informational
12/20/2021
Driveway meets LS and Ada spec. 12/20/21 ES
Occupancy Inspection - Codes Residential Failed 1/18/2022 1/18/2022 01/18/2022
Misc
Corrective Action Required
01/18/2022
**Exterior not inspected at this time -Address must be located so that it can be illuminated at night -Final grade, sod, downspout and sump pump extension -Seal exterior wall penetrations; seal above meter, AC disconnect, seal exterior lights, etc -Provide sewer tracer wire port at grade -Front bedroom smoke alarm not sounding -Provide gfci protection for dishwasher outlet. Not tripping -What type of protection is the microwave breaker? Provide afci breaker -Locate and make accessible the sewer clean out
Occupancy Inspection - Codes Residential Temporary C of O 1/20/2022 1/20/2022 01/20/2022
Misc
Corrective Action Required
01/18/2022
-Final grade, sod, downspout and sump pump extension -Seal exterior wall penetrations; seal above meter, AC disconnect, seal exterior lights, etc -Provide gfci protection for dishwasher outlet. Not tripping
Occupancy Inspection - Codes Residential Temporary C of O 1/21/2022 01/21/2022
Misc
Corrective Action Required
01/20/2022
-Final grade, sod, downspout and sump pump extension -Seal exterior wall penetrations; seal above meter, AC disconnect, seal exterior lights, etc
Erosion Control Inspection Residential Passed 04/06/2022
DCM2 ESC DEFICIENT INSTALLATION
Resolved
04/06/2022
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Occupancy Inspection - Codes Residential Full C of O 4/6/2022 4/6/2022 04/06/2022
Misc
Resolved
04/06/2022
-Final grade, sod, downspout and sump pump extension -Seal exterior wall penetrations; seal above meter, AC disconnect, seal exterior lights, etc
Documents & Images
Date Uploaded File Type Document Name
04/20/2021 Application Form Permit Application
04/20/2021 Application Form License Tax Form
04/23/2021 MO127 - Air Combustion 4_23_21
04/26/2021 Approved Plans Approved Drawings
04/26/2021 Letter Codes Residential Plan Review
04/27/2021 Plot Plan Approved Plot Plan
04/27/2021 Receipt Receipt for transaction:2021-002269
04/27/2021 Letter DS Building Permit
05/07/2021 M L Crose 4801 NE Freehold Ct LSMO Monticello Lot 125 3rd Party Footing Inspection Report 5-6-21
05/21/2021 Letter INSPECTION SUMMARY
06/08/2021 Letter INSPECTION SUMMARY
06/08/2021 Letter INSPECTION SUMMARY
06/08/2021 Letter INSPECTION SUMMARY
06/10/2021 Letter INSPECTION SUMMARY
06/10/2021 Letter INSPECTION SUMMARY
06/21/2021 Letter INSPECTION SUMMARY
07/14/2021 Letter INSPECTION SUMMARY
08/04/2021 Letter INSPECTION SUMMARY
08/05/2021 Letter INSPECTION SUMMARY
08/18/2021 Approved Plans Approved Revision to deck Drawings
10/05/2021 Letter INSPECTION SUMMARY
10/05/2021 Letter INSPECTION SUMMARY
10/05/2021 Letter INSPECTION SUMMARY
10/11/2021 Letter INSPECTION SUMMARY
10/11/2021 Letter INSPECTION SUMMARY
10/11/2021 Letter INSPECTION SUMMARY
10/12/2021 Letter INSPECTION SUMMARY
12/09/2021 Letter INSPECTION SUMMARY
12/09/2021 Letter INSPECTION SUMMARY
12/20/2021 Letter INSPECTION SUMMARY
12/20/2021 Letter INSPECTION SUMMARY
01/18/2022 Letter INSPECTION SUMMARY
01/20/2022 Letter Codes Temporary Certificate of Occupancy
01/21/2022 Letter Codes Temporary Certificate of Occupancy
04/06/2022 Letter Codes Final Certificate of Occupancy
04/06/2022 Letter Field Certificate of Occupancy
04/06/2022 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home