Review Type |
Outcome |
Est. Completion Date |
Completed |
Plot Plan Review
|
Approved
|
05/14/2021
|
05/12/2021
|
|
Kim Brennan
|
|
Front building line
Corrective Action Required
Front building line and dimension to front of building must be provided on the plot plan.
|
|
Deck location
Corrective Action Required
Deck location, with dimensions to property lines must be provided on the plot plan.
|
|
Right-of-way
Corrective Action Required
The right-of-way with dimensions must be provided on the plot plan.
|
|
Building elevations
Corrective Action Required
Existing and finished elevations at building footprint corners must be provided on the plot plan.
|
|
Lot elevations
Corrective Action Required
Existing and finish elevations at all property corners must be provided on the plot plan.
|
|
Curb elevation
Corrective Action Required
The elevation at top of curb at end of driveway and at lot corners adjacent to street must be provided on the plot plan.
|
|
Spot elevations
Corrective Action Required
Spot elevations and drainage flow arrows shall be provided throughout the lot.
|
|
City infrustructure
Corrective Action Required
Show all manholes, water valve boxes, fire hydrants, and stormwater structures.
|
|
|
Residential Plan Review
|
Approved
|
05/14/2021
|
05/12/2021
|
|
Kim Brennan
|
|
02 One (1) complete license tax application
Corrective Action Required
One (1) complete license tax application
|
|
Misc
Corrective Action Required
All subs and on-site contact information needs to be completed
|
|
05 Provide square footage of living area, garage area, unfinished basement
Corrective Action Required
Provide square footage of living area, garage area, unfinished basement area, etc (IRC Section R304)
These need to reflect both sides of the structure.
|
|
Miscellaneous Correction
Corrective Action Required
Drawings need to show both sides of the duplex, not just one side. The drawings only show both sides on the elevations.
|
|
07 Identify emergency escape openings from bedrooms
Corrective Action Required
Identify emergency escape openings from bedrooms and basement(s). (IRC Section R310 as amended per Ordinance)
|
|
10 Combustion air
Corrective Action Required
Provide combustion air calculations and specify transfer air grilles for fuel burning appliances located in confined space(s). (IRC Chapter 17 and Section G2407)
|
|
12 Detail required separation between garage and living area including door
Corrective Action Required
Detail required separation between garage and living area including door, door closer and gypsum board. (IRC R302.5)
Does not specify self-closing
|
|
33 Identify braced wall locations and length of braced wall panel(s).
Corrective Action Required
Identify braced wall locations and length of braced wall panel(s). (IRC Section R602.10)
|
|
|
Plot Plan Review
|
Rejected
|
04/27/2021
|
04/23/2021
|
|
Kim Brennan
|
|
Front building line
Corrective Action Required
Front building line and dimension to front of building must be provided on the plot plan.
|
|
Deck location
Corrective Action Required
Deck location, with dimensions to property lines must be provided on the plot plan.
|
|
Right-of-way
Corrective Action Required
The right-of-way with dimensions must be provided on the plot plan.
|
|
Building elevations
Corrective Action Required
Existing and finished elevations at building footprint corners must be provided on the plot plan.
|
|
Lot elevations
Corrective Action Required
Existing and finish elevations at all property corners must be provided on the plot plan.
|
|
Curb elevation
Corrective Action Required
The elevation at top of curb at end of driveway and at lot corners adjacent to street must be provided on the plot plan.
|
|
Spot elevations
Corrective Action Required
Spot elevations and drainage flow arrows shall be provided throughout the lot.
|
|
City infrustructure
Corrective Action Required
Show all manholes, water valve boxes, fire hydrants, and stormwater structures.
|
|
|
Residential Plan Review
|
Rejected
|
04/27/2021
|
04/23/2021
|
|
Kim Brennan
|
|
02 One (1) complete license tax application
Corrective Action Required
One (1) complete license tax application
|
|
Misc
Corrective Action Required
All subs and on-site contact information needs to be completed
|
|
05 Provide square footage of living area, garage area, unfinished basement
Corrective Action Required
Provide square footage of living area, garage area, unfinished basement area, etc (IRC Section R304)
These need to reflect both sides of the structure.
|
|
Miscellaneous Correction
Corrective Action Required
Drawings need to show both sides of the duplex, not just one side. The drawings only show both sides on the elevations.
|
|
07 Identify emergency escape openings from bedrooms
Corrective Action Required
Identify emergency escape openings from bedrooms and basement(s). (IRC Section R310 as amended per Ordinance)
|
|
10 Combustion air
Corrective Action Required
Provide combustion air calculations and specify transfer air grilles for fuel burning appliances located in confined space(s). (IRC Chapter 17 and Section G2407)
|
|
12 Detail required separation between garage and living area including door
Corrective Action Required
Detail required separation between garage and living area including door, door closer and gypsum board. (IRC R302.5)
Does not specify self-closing
|
|
33 Identify braced wall locations and length of braced wall panel(s).
Corrective Action Required
Identify braced wall locations and length of braced wall panel(s). (IRC Section R602.10)
|
|
|
Plot Plan Review
|
Rejected
|
03/23/2021
|
03/19/2021
|
|
Kim Brennan
|
|
Front building line
Corrective Action Required
Front building line and dimension to front of building must be provided on the plot plan.
|
|
Deck location
Corrective Action Required
Deck location, with dimensions to property lines must be provided on the plot plan.
|
|
Right-of-way
Corrective Action Required
The right-of-way with dimensions must be provided on the plot plan.
|
|
Building elevations
Corrective Action Required
Existing and finished elevations at building footprint corners must be provided on the plot plan.
|
|
Lot elevations
Corrective Action Required
Existing and finish elevations at all property corners must be provided on the plot plan.
|
|
Curb elevation
Corrective Action Required
The elevation at top of curb at end of driveway and at lot corners adjacent to street must be provided on the plot plan.
|
|
Spot elevations
Corrective Action Required
Spot elevations and drainage flow arrows shall be provided throughout the lot.
|
|
City infrustructure
Corrective Action Required
Show all manholes, water valve boxes, fire hydrants, and stormwater structures.
|
|
|
Residential Plan Review
|
Rejected
|
03/23/2021
|
03/19/2021
|
|
Kim Brennan
|
|
02 One (1) complete license tax application
Corrective Action Required
One (1) complete license tax application
|
|
Misc
Corrective Action Required
All subs and on-site contact information needs to be completed
|
|
05 Provide square footage of living area, garage area, unfinished basement
Corrective Action Required
Provide square footage of living area, garage area, unfinished basement area, etc (IRC Section R304)
These need to reflect both sides of the structure.
|
|
Miscellaneous Correction
Corrective Action Required
Drawings need to show both sides of the duplex, not just one side. The drawings only show both sides on the elevations.
|
|
07 Identify emergency escape openings from bedrooms
Corrective Action Required
Identify emergency escape openings from bedrooms and basement(s). (IRC Section R310 as amended per Ordinance)
|
|
10 Combustion air
Corrective Action Required
Provide combustion air calculations and specify transfer air grilles for fuel burning appliances located in confined space(s). (IRC Chapter 17 and Section G2407)
|
|
12 Detail required separation between garage and living area including door
Corrective Action Required
Detail required separation between garage and living area including door, door closer and gypsum board. (IRC R302.5)
Does not specify self-closing
|
|
33 Identify braced wall locations and length of braced wall panel(s).
Corrective Action Required
Identify braced wall locations and length of braced wall panel(s). (IRC Section R602.10)
|
|
|