Summary
PRRES20210281
Building Permit - Residential
Certificate of Occupancy
CMH PARKS INC
NEW SINGLE FAMILY
NEW HOUSE - UNFINISHED BASEMENT - COVERED DECK STOP WORK ORDER generated on 03/31/2021 12:00 AM by username 'Patrick Schonfeldt'. STOP WORK ORDER removed on 04/01/2021 12:00 AM by username 'Patrick Schonfeldt'.
01/20/2021
01/21/2021
07/19/2021
12/17/2021
Locations
Contacts
CMH PARKS INC, Address:5000 CLAYTON RD  
CLAYTON PROPERTIES GROUP, INC, Address:10450 Holmes Rd Suite 100, Phone:(816) 246-6700  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
RYAN@SUMMITHOMESKC.COM  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 01/25/2021 01/21/2021
Kim Brennan
Lot elevations
Corrective Action Required
01/21/2021

Existing and finish elevations at all property corners must be provided on the plot plan. Not provided for the south east corner
As-graded plot plan
Corrective Action Required
01/21/2021

A as-graded plot plan per Section 7-160, Code of Ordinances, is required prior to occupancy.
Residential Plan Review Approved 01/25/2021 01/21/2021
Kim Brennan
Plot Plan Review Rejected 01/22/2021 01/20/2021
Kim Brennan
Lot elevations
Corrective Action Required
01/20/2021

Existing and finish elevations at all property corners must be provided on the plot plan. Not provided for the south east corner
As-graded plot plan
Corrective Action Required
01/20/2021

A as-graded plot plan per Section 7-160, Code of Ordinances, is required prior to occupancy.
Residential Plan Review Approved 01/22/2021 01/20/2021
Kim Brennan
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee New Single Family $1,279.51 $1,279.51 Paid 01/21/2021
Right of Way Permit Fee $80.00 $80.00 Paid 01/21/2021
Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 01/21/2021
8331507-Sewer Connection Fee $570.00 $570.00 Paid 01/21/2021
Water Tap Fee $3,581.00 $3,581.00 Paid 01/21/2021
Water Meter Fee $455.54 $455.54 Paid 01/21/2021
Not Ready Inspection Fee $50.00 $50.00 Paid 11/09/2021
Not Ready Inspection Fee $50.00 $50.00 Paid 11/09/2021
3rd and Subsequent Inspection Fee (Per Hour) $50.00 $50.00 Paid 11/09/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Failed - Stop Work 3/31/2021 3/31/2021 03/31/2021
Misc
Corrective Action Required
03/31/2021
-FOOTING POURED WITHOUT INSPECTION, SUBMIT ENGINEER REPORT. THIRD PARTY INSPECTION REPORT REQUIRED TO BE SUBMITTED TO PERMIT WITHIN (2) DAYS OF INSPECTION
Footing Inspection - Residential Passed 4/1/2021 4/1/2021 04/01/2021
Misc
Resolved
04/01/2021
-FOOTING POURED WITHOUT INSPECTION, SUBMIT ENGINEER REPORT. THIRD PARTY INSPECTION REPORT REQUIRED TO BE SUBMITTED TO PERMIT WITHIN (2) DAYS OF INSPECTION
Underslab Plumbing Inspection - Residential Passed 4/22/2021 4/22/2021 04/21/2021
Erosion Control Inspection Residential Failed 6/25/2021 6/25/2021 06/25/2021
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
06/25/2021
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. CLEAN MUD AND GRAVEL FROM STREET
Sewer Service Inspection - R Passed 6/30/2021 (10:30) 6/30/2021 06/30/2021
Water Service Inspection - R Passed 7/1/2021 (9:00) 7/1/2021 07/01/2021
All Rough Inspection - Residential Not Ready 7/29/2021 7/29/2021 07/29/2021
Misc
Corrective Action Required
07/29/2021
INSPECTION DENIED, NOT READY FOR INSPECTION, NO FIREBLOCKING ATTEMPTED THROUGHOUT HOUSE AT TIME OF INSPECTION
All Rough Inspection - Residential Failed 7/30/2021 7/30/2021 07/30/2021
Misc
Corrective Action Required
07/29/2021
-Fireblock DWV/HVAC chase garage, seal all gaps, seal vertical to horizontal at the furred down -seal all top plate penetrations-see garage, master bed, front bed 1st floor, 2nd floor bath#2, 2nd floor bed#2 -attic access at garage requires 30” vertical clearance -Ensure access to jacuzzi tub motor at finish, master bath 1st floor -complete all bath exhaust fan duct discharge -Fireblock fireplace master bed wall space above above solid blocking between studs -complete gas line to fireplace -Remove insulation from great room walls at windows to allow inspection, ensure wall construction per plans,15/33” osb 8D at 6” edge 12” field, blocking at base and top of window with wood structural panel over osb nailed 3” oc at top and bottom of band/rim joist -add protection plate bottom plate pex refrigerator at kitchen -properly support beam at front bedroom corner for covered porch -LIB bracing all locations per plans -nail pattern per plans at dining room windows CS-PF design per plans -wood stud overbored for DWV vanity master bath bearing wall left side, add stud shoes to other (3) bites for DWV at vanity -Fireblock deadspace at 2nd floor bed#4 closet, seal all gaps at fireblock material -Fireblock HVAC/b vent chase at 2nd floor hall -Fireblock all tub traps -Anchor bolts required within 12” of plate break in basement -Complete all gas lines, no gas lines present in house -pier locations “A” at basement stair wall (3) 2x4 stud packs per plans -Add joist hangers to all joist 48” or more at back of stair wall at header near furnace -Nail exterior sheathing per plans -exterior sheathing damaged at SW rear corner of house
All Rough Inspection - Residential Failed 8/6/2021 8/6/2021 08/06/2021
Misc
Corrective Action Required
07/30/2021
-Fireblock around DWV at chase garage, vertical to horizontal at the furred down -seal all top plate penetrations-see master bed south wall, 2nd floor bath#2, 2nd floor bed#2 -protect flex gas line at fireplace entrance -OK to insulate only at dining room and great windows that required osb installed on interior wall. Reinspection of installed osb required before rock - see engineer letter
All Rough Inspection - Residential Passed 8/10/2021 8/10/2021 08/10/2021
Misc
Resolved
08/10/2021
Electrical Service Inspection Passed 8/26/2021 8/26/2021 08/26/2021
Gas Service Inspection - Residential Passed 8/26/2021 8/26/2021 08/26/2021
Driveway Inspection Passed 9/16/2021 9/16/2021 09/17/2021
Misc
Informational
09/17/2021
On Thursday, 9-16-2021. I performed a driveway inspection and passed driveway for concrete installation.
Occupancy Inspection - Codes Residential Failed 11/4/2021 11/4/2021 11/04/2021
Misc
Corrective Action Required
11/04/2021
-resolve outstanding inspection fee(s) before final c of o -sod -Guardrail at front porch, more than 30” from grade -splash blocks at all downspout and sump pump discharge locations, min 36" discharge from foundation -seal all penetrations in siding, seal along top of meter can and AC disconnect -smoke/co detector required outside front bed 1st floor -non combustible attic access cover required at garage access -repair damaged rock at garage ceiling receptacle near attic access -no access to electrical receptacle at master bath jacuzzi tub -all smokes to be operational and interconnected -no setback of box allowed at combustible material - see electrical receptacle at great room fireplace -Install sliding glass door locking hardware -secondary toe lock required at sliding glass door -(2) 1/2” through bolts required at each post/beam connection at deck -flashing at rear great room window exterior trim
Piers/Caissons Inspection - Residential Passed 11/30/2021 11/30/2021
Misc
Informational
11/30/2021
third party footing inspection indicated inspection of deck piers
Plot Plan Inspection Passed 11/30/2021 11/30/2021
Occupancy Inspection - Codes Residential Failed 11/30/2021 11/30/2021 11/30/2021
Misc
Corrective Action Required
11/04/2021
-seal along top of meter can -master bath jacuzzi tub motor needs GFCI protection -all smokes to be operational and interconnected -flashing at rear great room window exterior trim
Misc
Corrective Action Required
11/29/2021
-Remove debris from water meter well- provide 12" of clearance below water meter assembly.
Occupancy Inspection - Codes Residential Failed 12/10/2021 12/10/2021 12/10/2021
Misc
Corrective Action Required
11/30/2021
-ALL smokes to be operational and interconnected(see front entry and great room)
Misc
Resolved
12/10/2021
-Remove debris from water meter well- provide 12" of clearance below water meter assembly.
Erosion Control Inspection Residential Passed 12/17/2021 12/17/2021
DCM3 ESC REQUIRED 2 DAY
Resolved
12/17/2021
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. CLEAN MUD AND GRAVEL FROM STREET
Occupancy Inspection - Codes Residential Full C of O 12/17/2021 12/17/2021 12/17/2021
Misc
Resolved
12/17/2021
-ALL smokes to be operational and interconnected(see front entry and great room)
Documents & Images
Date Uploaded File Type Document Name
01/20/2021 Application Form Permit Application and License Tax Form
01/20/2021 Letter Codes Residential Plan Review
01/20/2021 Approved Plans Approved Drawings
01/21/2021 Approved Plans Approved Truss Layout
01/21/2021 Approved Plans Approved Truss Package
01/21/2021 Plot Plan Approved Plot Plan
01/21/2021 Receipt Receipt for transaction:2021-000337
01/21/2021 Letter DS Building Permit
03/31/2021 Lot 25 Hawthorn Ridge Wall Inspection
03/31/2021 Lot 25 Hawthorn Ridge Footing Inspection
03/31/2021 Letter Stop Work Order
04/01/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
06/25/2021 Letter INSPECTION SUMMARY
06/30/2021 Letter INSPECTION SUMMARY
07/01/2021 Letter INSPECTION SUMMARY
07/14/2021 25 Hawthorne Ridge Braced wall panels letter
07/29/2021 Letter INSPECTION SUMMARY
07/30/2021 Letter INSPECTION SUMMARY
08/05/2021 25 Hawthorne Ridge Braced wall panels letter
08/05/2021 25 Hawthorne Ridge Stud Shoe Letter
08/06/2021 Letter INSPECTION SUMMARY
08/10/2021 Letter INSPECTION SUMMARY
08/26/2021 Letter INSPECTION SUMMARY
08/26/2021 Letter INSPECTION SUMMARY
09/17/2021 Letter INSPECTION SUMMARY
10/19/2021 Plot Plan APPROVED AS BUILT PLOT PLAN
11/04/2021 Letter INSPECTION SUMMARY
11/09/2021 Receipt Receipt for transaction:2021-008615
11/30/2021 Letter INSPECTION SUMMARY
11/30/2021 Letter INSPECTION SUMMARY
11/30/2021 Letter INSPECTION SUMMARY
12/10/2021 Letter INSPECTION SUMMARY
12/10/2021 Letter INSPECTION SUMMARY
12/17/2021 Letter Codes Final Certificate of Occupancy
12/17/2021 Letter Field Certificate of Occupancy
12/17/2021 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home