Permit Application Status

PRRES20203873


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20203873
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - FINISHED BASEMENT - COVERED DECK
10/21/2020
10/26/2020
04/21/2021
04/12/2022
Locations
Contacts
NEW MARK HOMES - KC LLC, Address:5207 NW CROOKED ROAD, Phone:(816) 969-9010  
ASHLEY@NEWMARKHOMESKC.COM  
HARRINGTON BROTHERS HEATING & COOLING, Address:15630 S KEELER ST, Phone:(913) 422-5444  
CLASS ONE ELECTRIC INC, Address:PO BOX 24343, Phone:(913) 915-1767  
R & R PLUMBING INC, Address:2001 GASLIGHT DR, Phone:(816) 772-5431  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 10/28/2020 10/26/2020
Dylan Eppert
Residential Plan Review Approved 10/28/2020 10/26/2020
Dylan Eppert
Plot Plan Review Approved 10/23/2020 10/26/2020
Dylan Eppert
Basement egress
Corrective Action Required
10/23/2020

Basement egress location(s) and elevation of the lowest adjacent grade must be provided on the plot plan. NEED LAG FOR WALKOUT, I SAW THE LAG FOR EGRESS WELL LABELED (31) BUT NOTHING FOR THE WALKOUT DOOR.
Residential Plan Review Approved 10/23/2020 10/26/2020
Dylan Eppert
05 Provide square footage of living area, garage area, unfinished basement
Corrective Action Required
10/22/2020

Provide square footage of living area, garage area, unfinished basement area, etc (IRC Section R304) MISSING: GARAGE SQ FOOTAGE COVERED DECK SQ FOOTAGE UNFINISHED BASEMENT SQ FOOTAGE
Miscellaneous Correction
Corrective Action Required
10/22/2020

MISSING HOUSE ADDRESS ON PLANS AS THEY SHOULD BE ON ALL SHEETS.
11 Designate R-value(s) for floors, walls, ceilings, roof/ceilings.
Corrective Action Required
10/22/2020

Designate R-value(s) for floors, walls, ceilings, roof/ceilings. (LSCO 7-802)
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,056.89 $1,056.89 Paid 10/26/2020
8331507-Sewer Connection Fee $420.00 $420.00 Paid 10/26/2020
8331401-Water Tap Fee $3,581.00 $3,581.00 Paid 10/26/2020
8350015-Water Meter Fee $455.54 $455.54 Paid 10/26/2020
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 10/26/2020
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 10/26/2020
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 12/17/2020 (2:30) 12/17/2020 12/17/2020
Erosion Control Inspection Residential Failed 01/07/2021
Misc
Informational
01/07/2021
1-7-21 3:38pm There is no silt fence on the back side of the lot. There is a creek on the back side and this needs addressed ASAP.
Underslab Plumbing Inspection - Residential Failed 1/29/2021 1/29/2021 01/29/2021
Misc
Corrective Action Required
01/29/2021
Complete installation of interior underslab drain tile with positive or neutral slope throughout and connect to sump pit
Erosion Control Inspection Residential Failed 01/29/2021
Misc
Resolved
01/29/2021
1-7-21 3:38pm There is no silt fence on the back side of the lot. There is a creek on the back side and this needs addressed ASAP.
Misc
Corrective Action Required
01/29/2021
Immediate Street clean up required
Underslab Plumbing Inspection - Residential Passed 2/3/2021 2/3/2021 02/03/2021
Misc
Resolved
02/03/2021
Complete installation of interior underslab drain tile with positive or neutral slope throughout and connect to sump pit
Erosion Control Inspection Residential Passed 02/03/2021
Misc
Resolved
02/03/2021
Immediate Street clean up required
Erosion Control Inspection Residential Failed 03/10/2021
Misc
Corrective Action Required
03/10/2021
-Erosion control requires continuous maintenance. Repair damaged sections within 48 hours -immediate street cleanup required -no further inspections until issues are resolved
Rough Framing Inspection - Residential Failed 3/10/2021 3/10/2021 03/10/2021
Misc
Corrective Action Required
03/10/2021
-two bottom plates per plan 1/S4.0 -two rows of 16D sinker nails 3" OC at braced wall panel top plates per plan, see section view of detail 1/S4.0
Erosion Control Inspection Residential Failed 03/17/2021
Misc
Corrective Action Required
03/10/2021
-Erosion control requires continuous maintenance. Repair damaged sections within 48 hours -immediate street cleanup required -no further inspections until issues are resolved
Rough Framing Inspection - Residential Partial 4/5/2021 4/5/2021 04/05/2021
Misc
Resolved
04/05/2021
-two bottom plates per plan 1/S4.0 -two rows of 16D sinker nails 3" OC at braced wall panel top plates per plan, see section view of detail 1/S4.0
Piers/Caissons Inspection - Residential Passed 4/5/2021 (8:00) 4/5/2021 04/05/2021
Gas Service Inspection - Residential Failed 4/6/2021 4/6/2021 04/06/2021
Misc
Corrective Action Required
04/06/2021
4/6/21 **SPOKE WITH CRAIG ON GAS SERVICE INSPECTION PROCESS, WILL CALL BACK IN WHEN READY**
Sewer Service Inspection - R Passed 5/11/2021 (10:00) 5/11/2021 05/11/2021
Water Service Inspection - R Passed 5/12/2021 (10:00) 5/12/2021 05/12/2021
All Rough Inspection - Residential Failed 6/28/2021 6/28/2021 06/28/2021
Misc
Corrective Action Required
06/28/2021
-Deck not ready for inspection -Minimum 12” field 6” edge exterior sheathing fastening -Tighten anchor bolts throughout -Provide collar ties at ridges throughout -Double top plate spices to offset minimum 24 inches, locations marked -12” oc fastening, stud to stud and abutting studs at intersecting braced walls, Locations marked -Fireblock Plate Penetrations, Locations marked -Provide minimum 16g galvanized metal ties 1.5” wide at over bored exterior top plates. Fasten ties across and to the plate with minimum 4-10dx1.5” at each side of straps. The metal tie must extend a minimum of 6” past the opening. See figure R602.6.1, Mudroom bath -Complete framing, main level at stairs -Fasten king studs to headers per code -Fireblock and Vertical to Horizontal at drop ceiling to wall connection, master closet -Provide nail plate protection of DWV minimum 2 inches below top Plate Penetration, master bath -Address Conductor cut at bottom plate in master bath -Complete underslab electrical installation, Conductor must be rated for wet location -Provide king stud at header, exterior wall gym -Fasten floor joists to top plates/sills per code throughout -Seal Penetrations in Floor Joists throughout where cavities are used as return air Plenum -Seal all joints in ductwork, unfinished area -Penetrations in floor joists shall not be closer than 2 inches to the top or bottom of the member, above bed 5 -Provide nail plate protection at DWV top plate Penetration, Basement bar -Address over bored floor joist above bedroom four -Provide nail plate protection at DWV top Plate Penetration bedroom four bath -Water shut off valve required to remain accessible, Bedroom four closet -Repair/replace full depth solid blocking between floor joists over beams where damaged/removed by other trades -Support 2x4’s laid flat in basement soffit to floor joists above where soffit width exceeds 4 feet -Nonconventional rafter bearing per plan options see page S3.2
Gas Service Inspection - Residential Passed 6/28/2021 6/28/2021 06/28/2021
Misc
Resolved
06/28/2021
4/6/21 **SPOKE WITH CRAIG ON GAS SERVICE INSPECTION PROCESS, WILL CALL BACK IN WHEN READY**
Electrical Service Inspection Passed 6/28/2021 06/28/2021
All Rough Inspection - Residential Passed 7/8/2021 7/8/2021 07/08/2021
Misc
Resolved
07/08/2021
-Deck not ready for inspection -Minimum 12” field 6” edge exterior sheathing fastening -Provide collar ties at ridges throughout -Double top plate spices to offset minimum 24 inches, locations marked -12” oc fastening, stud to stud and abutting studs at intersecting braced walls, Locations marked -Fireblock Plate Penetrations, Locations marked -Provide minimum 16g galvanized metal ties 1.5” wide at over bored exterior top plates. Fasten ties across and to the plate with minimum 4-10dx1.5” at each side of straps. The metal tie must extend a minimum of 6” past the opening. See figure R602.6.1, Mudroom bath -Complete framing, main level at stairs -Fasten king studs to headers per code -Fireblock and Vertical to Horizontal at drop ceiling to wall connection, master closet -Provide nail plate protection of DWV minimum 2 inches below top Plate Penetration, master bath -Address Conductor cut at bottom plate in master bath -Complete underslab electrical installation, Conductor must be rated for wet location -Provide king stud at header, exterior wall gym -Fasten floor joists to top plates/sills per code throughout -Seal Penetrations in Floor Joists throughout where cavities are used as return air Plenum -Seal all joints in ductwork, unfinished area -Penetrations in floor joists shall not be closer than 2 inches to the top or bottom of the member, above bed 5 -Provide nail plate protection at DWV top plate Penetration, Basement bar -Address over bored floor joist above bedroom four -Provide nail plate protection at DWV top Plate Penetration bedroom four bath -Water shut off valve required to remain accessible, Bedroom four closet -Repair/replace full depth solid blocking between floor joists over beams where damaged/removed by other trades -Support 2x4’s laid flat in basement soffit to floor joists above where soffit width exceeds 4 feet -Nonconventional rafter bearing per plan options see page S3.2
Driveway Inspection Partial 7/27/2021 7/27/2021 07/27/2021
Misc
Informational
07/27/2021
7/27/21 14:25 - Crew is carrying the correct % throughout the drive for the sidewalk. Drive is the correct depth and has the correct depth of rock. Curb is also being poured and is correct.
Sidewalk Inspection Partial 7/27/2021 7/27/2021 07/27/2021
Misc
Informational
07/27/2021
7/27/21 14:45 - Crew has the correct depth of rock and forms are the correct depth. 5ft off the back of the curb and is carrying the correct % throughout.
Driveway Inspection Passed 8/4/2021 8/4/2021 08/04/2021
Misc
Informational
07/27/2021
7/27/21 14:25 - Crew is carrying the correct % throughout the drive for the sidewalk. Drive is the correct depth and has the correct depth of rock. Curb is also being poured and is correct.
Misc
Informational
08/04/2021
8/4/21 13:50 - Drive is installed correct with expansion joints on the easement and curb line, correct % throughout the sidewalk is placed.
Sidewalk Inspection Passed 8/4/2021 8/4/2021 08/04/2021
Misc
Informational
07/27/2021
7/27/21 14:45 - Crew has the correct depth of rock and forms are the correct depth. 5ft off the back of the curb and is carrying the correct % throughout.
Misc
Informational
08/04/2021
8/4/21 13:55 - Sidewalk is installed correct with the correct % throughout.
Occupancy Inspection - Codes Residential Temporary C of O 10/26/2021 10/26/2021 10/26/2021
Misc
Corrective Action Required
10/26/2021
-obtain an sprinkler permit and submit back flow certificate - final grade and sod -1/2” through bolts on deck 3 post -attach a/c whip - complete stucco on front on house
Erosion Control Inspection Residential Passed 01/10/2022
Misc
Corrective Action Required
03/17/2021
-Erosion control requires continuous maintenance. Repair damaged sections within 48 hours -immediate street cleanup required -no further inspections until issues are resolved
Plot Plan Inspection Passed 3/1/2022 03/01/2022
Occupancy Inspection - Codes Residential Failed 4/8/2022 4/8/2022 04/08/2022
Misc
Corrective Action Required
10/26/2021
-obtain an sprinkler permit and submit back flow certificate
Occupancy Inspection - Codes Residential Full C of O 4/12/2022 04/12/2022
Misc
Resolved
04/12/2022
-obtain an sprinkler permit and submit back flow certificate
Documents & Images
Date Uploaded File Type Document Name
10/21/2020 2020.10.16_20-081 Lot 4 Whispering Woods (Timberland Reverse) S&S
10/21/2020 signed pp lot 4
10/21/2020 WW04 - PERMIT APPLICATION
10/23/2020 Letter Codes Residential Plan Review
10/26/2020 Plot Plan APPROVED PLOT PLAN
10/26/2020 Plans APPROVED HOUSE PLAN
10/26/2020 Receipt Receipt for transaction:2020-007171
10/26/2020 Letter DS Building Permit
12/17/2020 Letter INSPECTION SUMMARY
12/17/2020 Letter Codes Residential Plan Review
01/07/2021 Letter INSPECTION SUMMARY
01/29/2021 Letter INSPECTION SUMMARY
01/29/2021 Letter INSPECTION SUMMARY
02/03/2021 Letter INSPECTION SUMMARY
02/03/2021 Letter INSPECTION SUMMARY
03/10/2021 Letter INSPECTION SUMMARY
03/10/2021 Letter INSPECTION SUMMARY
03/17/2021 Letter INSPECTION SUMMARY
04/05/2021 Letter INSPECTION SUMMARY
04/05/2021 Letter INSPECTION SUMMARY
04/06/2021 Letter INSPECTION SUMMARY
05/11/2021 Letter INSPECTION SUMMARY
05/12/2021 Letter INSPECTION SUMMARY
06/28/2021 Letter INSPECTION SUMMARY
06/28/2021 Letter INSPECTION SUMMARY
06/28/2021 Letter INSPECTION SUMMARY
07/02/2021 Final_2021_06_28_Struct_LSMO_New Mark Homes-REVISED
07/08/2021 Letter INSPECTION SUMMARY
07/21/2021 20-081 Lot 4 Whispering Woods 2
07/22/2021 revised application_001
07/22/2021 20-081 Lot 4 Whispering Woods
07/22/2021 Approved Plans approved updated basment finish plan Page #2
07/22/2021 Application Form APPLICATION
07/27/2021 Letter INSPECTION SUMMARY
07/27/2021 Letter INSPECTION SUMMARY
08/04/2021 Letter INSPECTION SUMMARY
08/04/2021 Letter INSPECTION SUMMARY
10/26/2021 Letter Codes Temporary Certificate of Occupancy
01/10/2022 Letter INSPECTION SUMMARY
02/28/2022 Plot Plan Approved As Graded Plot Plan
03/01/2022 Letter INSPECTION SUMMARY
04/08/2022 Letter INSPECTION SUMMARY
04/12/2022 Letter Codes Final Certificate of Occupancy
04/27/2022 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home