Summary
PRRES20192660
Building Permit - Residential
Certificate of Occupancy
CMH PARKS INC
NEW SINGLE FAMILY
NEW HOUSE - COVERED PATIO - UNFINISHED BASEMENT
09/17/2019
09/30/2019
07/08/2020
Locations
Contacts
CMH PARKS INC, Address:5000 CLAYTON RD  
CLAYTON PROPERTIES GROUP, INC, Address:10450 Holmes Rd Suite 100, Phone:(816) 246-6700  
PERMITTING@SUMMITHOMESKC.COM  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
KIMBEL MECHANICAL SYSTEMS, INC, Address:1936 N SHILOH DR, Phone:(479) 756-1099  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 09/19/2019 09/30/2019
Dylan Eppert
As-graded plot plan
Corrective Action Required
09/17/2019

A as-graded plot plan per Section 7-160, Code of Ordinances, is required prior to occupancy. ***ADD "AS-GRADED PLOT PLAN PRIOR TO SODDING" TO PLOT PLAN.***
Basement opening elevations
Corrective Action Required
09/17/2019

Minimum Building Opening Elevation (MBOE) and location on structure must be provided on the plot plan. ***ON THE REAR SOUTHWEST CORNER OF THE LOT THE MBOE IS NOT MATCHING UP PLEASE VERIFY. ***
Planning Review (RES) Approved 09/19/2019 09/17/2019
Victoria Nelson
Residential Plan Review Approved 09/19/2019 09/17/2019
Dylan Eppert
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee New Single Family $1,405.20 $1,405.20 Paid 09/30/2019
8331507-Sewer Connection Fee $600.00 $600.00 Paid 09/30/2019
Water Tap Fee $3,477.00 $3,477.00 Paid 09/30/2019
Water Meter Fee $425.02 $425.02 Paid 09/30/2019
Right of Way Permit Fee $80.00 $80.00 Paid 09/30/2019
Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 09/30/2019
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Failed 10/23/2019 10/23/2019
Misc
Corrective Action Required
10/23/2019
-No address posted -no rebar in place as plan shows Do not pour Call back in when ready
Footing Inspection - Residential Passed 10/23/2019 10/23/2019 10/23/2019
Misc
Informational
10/23/2019
-No address posted Ok to pour
Underslab Plumbing Inspection - Residential Passed 11/21/2019 11/21/2019 11/21/2019
Erosion Control Inspection Residential Failed 11/21/2019
Misc
Corrective Action Required
11/21/2019
Install erosion control at rear of lot asap
Piers/Caissons Inspection - Residential Passed 2/18/2020 (8:15) 2/18/2020 02/18/2020
Misc
Informational
02/18/2020
(1) 24 x 36 (1) 24 x 48
Sewer Service Inspection - R Passed 2/20/2020 (1:00) 2/20/2020 02/20/2020
Water Service Inspection - R Passed 2/21/2020 2/21/2020 02/21/2020
All Rough Inspection - Residential Failed 3/27/2020 3/27/2020 03/27/2020
Misc
Corrective Action Required
03/27/2020
-PROVIDE ANCHOR BOLTS WITHIN 12" OF PLATE BREAK GARAGE - - PROVIDE BLOCKING AT SHEATHING BREAKS GARAGE PORTAL FRAMING - - PROVIDE PFH PORTAL FRAMING PER PLAN GARAGE DOOR - - PROVIDE MINIMUM 2 ANCHOR BOLT SCH 40 COLUMN GARAGE - - FIRE BLOCK TOP FURR OUT GARAGE - - FIRE BLOCK TOP FUR OUT GREAT ROOM - - PROVIDE H 2.5 TRUSS REAR WALL BEDROOM #5 - - PROVIDE 3 STUDS UNDER LVL BREAKFAST NOOK - - PROVIDE JOIST HANGERS @ LVL & CANTILEVER BASEMENT BETWEEN SERVICE PANEL & STAIRS - - NAIL OFF SHEATHING & FIREBLOCK AT LANDING TO 2ND FLOOR - - PROVIDE HANGER PER TRUSS PLANS MASTER TRUSS CJ13 - - PLANS SHOW (3) 9 1/4 LVLs NEAR STAIRS AT GREAT ROOM/DINING FRAMED WITH ONLY (2) - - PLANS SHOWS DOUBLED 2 X 10 JOIST THROUGH GREAT ROOM & KITCHEN FRAMED DBL EVERY OTHER -
Gas Piping Inspection - Residential Passed 3/27/2020 3/27/2020 03/27/2020
Gas Service Inspection - Residential Passed 3/27/2020 03/27/2020
Electrical Service Inspection Passed 3/27/2020 3/27/2020 03/27/2020
All Rough Inspection - Residential Failed 4/3/2020 4/3/2020 04/03/2020
Misc
Corrective Action Required
03/27/2020
- FIRE BLOCK TOP FUR OUT GREAT ROOM - - NAIL OFF SHEATHING AT LANDING TO 2ND FLOOR
All Rough Inspection - Residential Failed 4/6/2020 4/6/2020 04/06/2020
Misc
Corrective Action Required
04/03/2020
- NAIL OFF SHEATHING AT LANDING TO 2ND FLOOR -
All Rough Inspection - Residential Passed 4/7/2020 4/7/2020 04/07/2020
Misc
Resolved
04/07/2020
Occupancy Inspection - Codes Residential Failed 6/3/2020 6/3/2020 06/03/2020
Misc
Corrective Action Required
06/03/2020
- Submit as graded plot plan for review - Complete final grade and sod - Complete siding/stone at front - Place splashblocks at all downspout and sump pump discharge locations for minimum distance from foundation 36” - Security screws at back door, provide (2) 3” screws each exterior hinge and strike plate - Remove all paint covers from smokes - Complete light fixture in master bath above tub - Provide access for jacuzzi tub motor, when access cover is removed access to motor is blocked by drywall - Basement GFCI outlet at sub panel testing at hot/neut reverse - Dishwasher requires GFCI protection - AFCI protection at laundry circuit
Plot Plan Inspection Passed 6/5/2020 06/05/2020
Occupancy Inspection - Codes Residential Failed 7/6/2020 7/6/2020 07/06/2020
Misc
Corrective Action Required
06/03/2020
- Security screws at back door, provide (2) 3” screws each exterior hinge and strike plate - Remove all paint covers from smokes - Final driveway inspection
Driveway Inspection Passed 7/6/2020 07/06/2020
Misc
Informational
07/06/2020
On Thursday, 5-14-2020. I performed a driveway inspection. Sub-grade and forming meet city standard and pass inspection.
Misc
Informational
07/06/2020
The driveway has been poured and has now passed.
Driveway Inspection Passed 5/14/2020 5/14/2020 07/07/2020
Misc
Informational
05/14/2020
On Thursday, 5-14-2020. I performed a driveway inspection. Sub-grade and forming meet city standard and pass inspection.
Occupancy Inspection - Codes Residential Full C of O 7/8/2020 7/8/2020 07/08/2020
Misc
Resolved
07/08/2020
Documents & Images
Date Uploaded File Type Document Name
09/20/2019 Letter Codes Residential Plan Review
09/30/2019 Receipt Receipt for transaction: 2019-006508
09/30/2019 Letter DS Building Permit
10/03/2019 Engineer Report/Study DOC100319-10032019102153
10/03/2019 Plot Plan DOC100319-10032019102203
10/23/2019 Letter INSPECTION SUMMARY
10/23/2019 Letter INSPECTION SUMMARY
10/23/2019 DBFF2963-32E3-48EE-97C1-F1E9322FDA83
10/23/2019 2CEBA9EB-B568-47CF-943E-B5E361C6E240
11/21/2019 Letter INSPECTION SUMMARY
11/21/2019 Letter INSPECTION SUMMARY
02/18/2020 Letter INSPECTION SUMMARY
02/20/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
03/27/2020 Letter INSPECTION SUMMARY
03/27/2020 Letter INSPECTION SUMMARY
03/27/2020 Letter INSPECTION SUMMARY
03/27/2020 Letter INSPECTION SUMMARY
04/03/2020 Letter INSPECTION SUMMARY
04/06/2020 Letter INSPECTION SUMMARY
04/06/2020 Letter INSPECTION SUMMARY
04/07/2020 Letter INSPECTION SUMMARY
06/03/2020 Letter INSPECTION SUMMARY
06/04/2020 Plot Plan APPROVED AS-GRADED PLOT PLANS
06/05/2020 Letter INSPECTION SUMMARY
07/06/2020 Letter INSPECTION SUMMARY
07/06/2020 Letter DE-Daily Inspection Summary
07/06/2020 Letter DE-Daily Inspection Summary
07/07/2020 Letter INSPECTION SUMMARY
07/08/2020 Letter Field Certificate of Occupancy
07/08/2020 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide: