Summary


PRPWFR20171953
Public Works Infrastructure Permit - Residential
Final Acceptance
CLAYTON PROPERTIES GROUP, INC
DEVELOPMENT COMPLETE
Manor at Stoney Creek 2nd plat - County Line Rd improvements
06/13/2017
11/29/2017
02/17/2023
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
RANDY SPALDING EXCAVATING INC, Address:PO BOX 1421, Phone:(816) 318-9500  
REDFORD CONSTRUCTION INC, Address:PO BOX 1065, Phone:(816) 540-2030  
CMH PARKS INC, Address:5000 CLAYTON RD  
HEARTLAND TRAFFIC SERVICES INC, Address:626 N 47TH ST, Phone:(913) 428-2575  
STONEY CREEK ESTATES HOMEOWNERS ASSOCIATION INC, Address:120 SE 30TH ST  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 06/13/2017 08/28/2017
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
9110081-Paved Surface Inspection Fee $49.10 $49.10 Paid 06/13/2017
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Street - Striping Passed 2/21/2018 at 1:00 PM 02/21/2018
Informational
02/21/2018
Brice Lawson 02/21/2018 2:38 PM It appears that the existing double yellow lines and diagonal striping that was proposed to be removed has been removed. Jeremy with K & G Striping let me know that high build paint was used for the new white and yellow striping. The two new arrows have been installed in the turn lane. A 12' lane width was not achieved as shown on the plans. I spoke to Kent about the lane widths not being 12' as shown on plans and he thought it would be fine. I explained that the new lane widths are close the the existing lane widths that are east of Alabaster. The plans show a proposed taper length of 150'. The taper has been installed approx. 210' in length.
Verify Final Inspection Status (PW) Complete 9/6/2018 02/17/2023
Documents & Images
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home