Summary


PRPWFC20173845
Public Works Infrastructure Permit - Commercial
Closed
RAINTREE INVESTORS LLC
DEVELOPMENT COMPLETE
Scooters coffee - site development
11/27/2017
03/05/2018
Locations
Contacts
RAINTREE INVESTORS LLC, Address:7387 W 162ND ST  
BOUWENS CONTRACTING SERVICES, LLC, Address:11669 S CHESTNUT ST, Phone:(913) 369-5828  
BRANDON NARRON, Phone:(816) 935-5715  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 11/27/2017 11/27/2017
Development Center
Fees
Paid Fees Amount Paid Owing Date Paid
91100C9-Water Insp Fee $152.73 $152.73 Paid 11/27/2017
9110072-Water Test Fee $200.00 $200.00 Paid 11/27/2017
9110068-Storm Sewer Inspection Fee $280.80 $280.80 Paid 11/27/2017
9110071-Site Grading Fee $3,036.99 $3,036.99 Paid 11/27/2017
91100C8-Sanitary Sewer Insp Fees $109.50 $109.50 Paid 11/27/2017
9110069-After Hours Inspections (Public Works)(Per Hour) $236.10 $236.10 Paid 03/16/2018
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Partial 11/30/2017 at 1:45 PM 11/30/2017
PW-Misc
Informational
11/30/2017
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Devices for Erosion and Sediment Control
Informational
03/02/2018
There are problems with the erosion control devices on your site.
Site Visit Partial 12/1/2017 at 3:10 PM 12/01/2017
PW-Misc
Informational
12/01/2017
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
Erosion Control Inspection Partial 12/4/2017 at 10:02 AM 12/04/2017
PW-Misc
Informational
11/30/2017
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
12/04/2017
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
Erosion Control Inspection Partial 12/5/2017 at 9:21 AM 12/05/2017
PW-Misc
Informational
12/04/2017
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
12/04/2017
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
PW-Misc
Informational
12/05/2017
Matt Munger 12/05/2017 9:21 AM I observed an ESC Device in place with two cinder blocks between the device and inlet on the CI that I had asked Sheldon to take care of. I spoke with Sheldon while he was on site and he stated the Utilities Contractor will possibly start next week.
Site Visit Partial 12/6/2017 at 10:56 AM 12/06/2017
PW-Misc
Informational
12/01/2017
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
12/06/2017
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
Site Visit Partial 12/7/2017 at 10:16 AM 12/07/2017
PW-Misc
Informational
12/06/2017
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
12/06/2017
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
12/07/2017
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
Site Visit Partial 12/7/2017 at 1:40 PM 12/07/2017
PW-Misc
Informational
12/07/2017
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
12/07/2017
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
12/07/2017
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
12/07/2017
Matt Munger 12/07/2017 1:40 PM No workers were present.
Site Visit Partial 12/8/2017 at 9:46 AM 12/08/2017
PW-Misc
Informational
12/07/2017
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
12/07/2017
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
12/07/2017
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
12/07/2017
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
12/08/2017
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
Site Visit Partial 12/8/2017 at 1:55 PM 12/08/2017
PW-Misc
Informational
12/08/2017
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
12/08/2017
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
12/08/2017
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
12/08/2017
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
12/08/2017
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
12/08/2017
Matt Munger 12/08/2017 1:55 PM No workers were present.
Erosion Control Inspection Partial 12/14/2017 at 10:00 AM 12/11/2017
PW-Misc
Informational
12/05/2017
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
12/05/2017
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
PW-Misc
Informational
12/05/2017
Matt Munger 12/05/2017 9:21 AM I observed an ESC Device in place with two cinder blocks between the device and inlet on the CI that I had asked Sheldon to take care of. I spoke with Sheldon while he was on site and he stated the Utilities Contractor will possibly start next week.
PW-Misc
Informational
12/11/2017
Matt Munger 12/11/2017 10:00 AM No workers were present, ESC devices and silt fence were in place. Emailed Sheldon about the project and if there was anything that he needed from me since I had not seen anyone out at the site.
Site Visit Partial 12/12/2017 at 2:41 PM 12/12/2017
PW-Misc
Informational
12/08/2017
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
12/08/2017
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
12/08/2017
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
12/08/2017
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
12/08/2017
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
12/08/2017
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
12/12/2017
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
Site Visit Partial 12/13/2017 at 10:50 AM 12/13/2017
PW-Misc
Informational
12/12/2017
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
12/12/2017
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
12/12/2017
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
12/12/2017
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
12/12/2017
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
12/12/2017
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
12/12/2017
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
12/13/2017
Matt Munger 12/13/2017 10:50 AM No workers were present.
Site Visit Partial 12/14/2017 at 8:10 AM 12/14/2017
PW-Misc
Informational
12/13/2017
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
12/13/2017
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
12/13/2017
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
12/13/2017
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
12/13/2017
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
12/13/2017
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
12/13/2017
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
12/13/2017
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
12/14/2017
Matt Munger 12/14/2017 8:15 AM No workers were present.
Site Visit Partial 12/15/2017 at 2:15 PM 12/15/2017
PW-Misc
Informational
12/14/2017
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
12/14/2017
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
12/14/2017
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
12/14/2017
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
12/14/2017
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
12/14/2017
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
12/14/2017
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
12/14/2017
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
12/14/2017
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
12/15/2017
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
Site Visit Partial 12/18/2017 at 11:15 AM 12/18/2017
PW-Misc
Informational
12/15/2017
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
12/15/2017
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
12/15/2017
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
12/15/2017
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
12/15/2017
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
12/15/2017
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
12/15/2017
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
12/15/2017
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
12/15/2017
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
12/15/2017
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
12/18/2017
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
Erosion Control Inspection Partial 12/19/2017 at 10:10 AM 12/19/2017
PW-Misc
Informational
12/11/2017
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
12/11/2017
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
PW-Misc
Informational
12/11/2017
Matt Munger 12/05/2017 9:21 AM I observed an ESC Device in place with two cinder blocks between the device and inlet on the CI that I had asked Sheldon to take care of. I spoke with Sheldon while he was on site and he stated the Utilities Contractor will possibly start next week.
PW-Misc
Informational
12/11/2017
Matt Munger 12/11/2017 10:00 AM No workers were present, ESC devices and silt fence were in place. Emailed Sheldon about the project and if there was anything that he needed from me since I had not seen anyone out at the site.
PW-Misc
Informational
12/19/2017
Matt Munger 12/19/2017 10:10 AM Construction Entrance was in place, large Rip Rap was used. Workers were removing dirt from property.
Erosion Control Inspection Failed 12/20/2017 at 10:05 AM 12/20/2017
PW-Misc
Informational
12/19/2017
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
12/19/2017
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
PW-Misc
Informational
12/19/2017
Matt Munger 12/05/2017 9:21 AM I observed an ESC Device in place with two cinder blocks between the device and inlet on the CI that I had asked Sheldon to take care of. I spoke with Sheldon while he was on site and he stated the Utilities Contractor will possibly start next week.
PW-Misc
Informational
12/19/2017
Matt Munger 12/11/2017 10:00 AM No workers were present, ESC devices and silt fence were in place. Emailed Sheldon about the project and if there was anything that he needed from me since I had not seen anyone out at the site.
PW-Misc
Informational
12/19/2017
Matt Munger 12/19/2017 10:10 AM Construction Entrance was in place, large Rip Rap was used. Workers were removing dirt from property.
PW-Devices for Erosion and Sediment Control
Informational
12/20/2017
Matt Munger 12/20/2017 10:21 AM There are problems with the erosion control devices on your site. The silt fence on the south west side of the property has a section that is not secure due to the excavation work being done and in no longer trenched in properly. I spoke with the worker and just asked that he be mindful of the fence to ensure that it remains in place.
Site Visit Partial 12/21/2017 at 2:42 PM 12/21/2017
PW-Misc
Informational
12/18/2017
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
12/18/2017
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
12/18/2017
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
12/18/2017
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
12/18/2017
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
12/18/2017
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
12/18/2017
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
12/18/2017
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
12/18/2017
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
12/18/2017
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
12/18/2017
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
12/21/2017
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
Erosion Control Inspection Partial 12/21/2017 at 2:51 PM 12/21/2017
PW-Misc
Informational
12/20/2017
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
12/20/2017
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
PW-Misc
Informational
12/20/2017
Matt Munger 12/05/2017 9:21 AM I observed an ESC Device in place with two cinder blocks between the device and inlet on the CI that I had asked Sheldon to take care of. I spoke with Sheldon while he was on site and he stated the Utilities Contractor will possibly start next week.
PW-Misc
Informational
12/20/2017
Matt Munger 12/11/2017 10:00 AM No workers were present, ESC devices and silt fence were in place. Emailed Sheldon about the project and if there was anything that he needed from me since I had not seen anyone out at the site.
PW-Misc
Informational
12/20/2017
Matt Munger 12/19/2017 10:10 AM Construction Entrance was in place, large Rip Rap was used. Workers were removing dirt from property.
PW-Devices for Erosion and Sediment Control
Informational
12/20/2017
Matt Munger 12/20/2017 10:21 AM There are problems with the erosion control devices on your site. The silt fence on the south west side of the property has a section that is not secure due to the excavation work being done and in no longer trenched in properly. I spoke with the worker and just asked that he be mindful of the fence to ensure that it remains in place.
PW-Erosion and Sediment Control
Corrective Action Required
12/21/2017
Matt Munger 12/21/2017 2:52 PM Your project is in violation of the Erosion and Sediment control policy. There needs to be a silt fence along section of property that is adjacent to MO-150. After discussing schedules earlier in the day Sheldon stated he would get the silt fence up along the section of property adjacent to MO-150.
Site Visit Partial 12/28/2017 at 9:51 AM 12/28/2017
PW-Misc
Informational
12/21/2017
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
12/21/2017
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
12/21/2017
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
12/21/2017
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
12/21/2017
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
12/21/2017
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
12/21/2017
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
12/21/2017
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
12/21/2017
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
12/21/2017
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
12/21/2017
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
12/21/2017
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
12/28/2017
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
Site Visit Partial 12/29/2017 at 11:16 AM 12/29/2017
PW-Misc
Informational
12/28/2017
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
12/28/2017
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
12/28/2017
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
12/28/2017
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
12/28/2017
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
12/28/2017
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
12/28/2017
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
12/28/2017
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
12/28/2017
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
12/28/2017
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
12/28/2017
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
12/28/2017
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
12/28/2017
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
12/29/2017
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
Erosion Control Inspection Partial 1/4/2018 at 10:48 AM 01/02/2018
PW-Misc
Informational
12/21/2017
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
12/21/2017
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
PW-Misc
Informational
12/21/2017
Matt Munger 12/05/2017 9:21 AM I observed an ESC Device in place with two cinder blocks between the device and inlet on the CI that I had asked Sheldon to take care of. I spoke with Sheldon while he was on site and he stated the Utilities Contractor will possibly start next week.
PW-Misc
Informational
12/21/2017
Matt Munger 12/11/2017 10:00 AM No workers were present, ESC devices and silt fence were in place. Emailed Sheldon about the project and if there was anything that he needed from me since I had not seen anyone out at the site.
PW-Misc
Informational
12/21/2017
Matt Munger 12/19/2017 10:10 AM Construction Entrance was in place, large Rip Rap was used. Workers were removing dirt from property.
PW-Devices for Erosion and Sediment Control
Informational
12/21/2017
Matt Munger 12/20/2017 10:21 AM There are problems with the erosion control devices on your site. The silt fence on the south west side of the property has a section that is not secure due to the excavation work being done and in no longer trenched in properly. I spoke with the worker and just asked that he be mindful of the fence to ensure that it remains in place.
PW-Erosion and Sediment Control
Corrective Action Required
12/21/2017
Matt Munger 12/21/2017 2:52 PM Your project is in violation of the Erosion and Sediment control policy. There needs to be a silt fence along section of property that is adjacent to MO-150. After discussing schedules earlier in the day Sheldon stated he would get the silt fence up along the section of property adjacent to MO-150.
PW-Misc
Informational
01/02/2018
Matt Munger 01/02/2018 10:57 AM I walked along the silt fence and observed the silt fence was staked and in place. Will need to keep an eye on the staples that are securing the fence to the stakes to ensure the fence does not pull away and sag.
Site Visit Partial 1/4/2018 at 9:16 AM 01/04/2018
PW-Misc
Informational
12/29/2017
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
12/29/2017
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
12/29/2017
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
12/29/2017
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
12/29/2017
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
12/29/2017
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
12/29/2017
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
12/29/2017
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
12/29/2017
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
12/29/2017
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
12/29/2017
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
12/29/2017
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
12/29/2017
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
12/29/2017
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
01/04/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
Sanitary Sewer Construction Inspection Passed 1/5/2018 at 9:45 AM 01/05/2018
PW-Main inspection
Informational
01/05/2018
Matt Munger 01/05/2018 9:45 AM Me and Bob B. checked on the sewer line that was installed. I observed adequate amount of gravel below the pipe and SDR26 was installed. I did observe two cleanouts that they had installed. The Contractor stated he was going to put 8" of gravel above the sewer line.
Water Line - Construction Inspection Partial 1/5/2018 at 9:45 AM 01/05/2018
PW-Main inspection
Informational
01/05/2018
Matt Munger 01/05/2018 9:45 AM Me and Bob B. came out to inspect the water line that had been installed. The Water Department had came out and installed the tap to the C900 water main. I observed copper pipe from the main to where the meter will be set as well as at least 10ft of copper past the meter. They had the poly water line ran to the building as well. I will return to check the meter once it is installed.
Water Line - Construction Inspection Passed 1/5/2018 at 2:31 PM 01/05/2018
PW-Main inspection
Informational
01/05/2018
Matt Munger 01/05/2018 9:45 AM Me and Bob B. came out to inspect the water line that had been installed. The Water Department had came out and installed the tap to the C900 water main. I observed copper pipe from the main to where the meter will be set as well as at least 10ft of copper past the meter. They had the poly water line ran to the building as well. I will return to check the meter once it is installed.
PW-Main inspection
Informational
01/05/2018
Matt Munger 01/05/2018 3:45 PM The water line had been backfilled prior to my arrival. I observed the meter will in place with a lid and ring. I measured the space between the meter and lid and it was at 16.5" between the allowed 14"-18" in the LS Detail. There was clean gravel at the bottom of the meter as well.
Sanitary - Material Verification Passed 1/5/2018 at 9:45 AM 01/05/2018
Informational
01/05/2018
Matt Munger 01/05/2018 9:45 AM When Bob B. and I were on site I observed 4" SDR26.
Site Visit Partial 1/8/2018 at 9:47 AM 01/08/2018
PW-Misc
Informational
01/04/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
01/04/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
01/04/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
01/04/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
01/04/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
01/04/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
01/04/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
01/04/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
01/04/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
01/04/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
01/04/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
01/04/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
01/04/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
01/04/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
01/04/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
01/08/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
Erosion Control Inspection Failed 1/9/2018 at 11:25 AM 01/09/2018
PW-Misc
Informational
01/02/2018
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
01/02/2018
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
PW-Misc
Informational
01/02/2018
Matt Munger 12/05/2017 9:21 AM I observed an ESC Device in place with two cinder blocks between the device and inlet on the CI that I had asked Sheldon to take care of. I spoke with Sheldon while he was on site and he stated the Utilities Contractor will possibly start next week.
PW-Misc
Informational
01/02/2018
Matt Munger 12/11/2017 10:00 AM No workers were present, ESC devices and silt fence were in place. Emailed Sheldon about the project and if there was anything that he needed from me since I had not seen anyone out at the site.
PW-Misc
Informational
01/02/2018
Matt Munger 12/19/2017 10:10 AM Construction Entrance was in place, large Rip Rap was used. Workers were removing dirt from property.
PW-Devices for Erosion and Sediment Control
Informational
01/02/2018
Matt Munger 12/20/2017 10:21 AM There are problems with the erosion control devices on your site. The silt fence on the south west side of the property has a section that is not secure due to the excavation work being done and in no longer trenched in properly. I spoke with the worker and just asked that he be mindful of the fence to ensure that it remains in place.
PW-Erosion and Sediment Control
Corrective Action Required
01/02/2018
Matt Munger 12/21/2017 2:52 PM Your project is in violation of the Erosion and Sediment control policy. There needs to be a silt fence along section of property that is adjacent to MO-150. After discussing schedules earlier in the day Sheldon stated he would get the silt fence up along the section of property adjacent to MO-150.
PW-Misc
Informational
01/02/2018
Matt Munger 01/02/2018 10:57 AM I walked along the silt fence and observed the silt fence was staked and in place. Will need to keep an eye on the staples that are securing the fence to the stakes to ensure the fence does not pull away and sag.
PW-Erosion and Sediment Control
Corrective Action Required
01/09/2018
Matt Munger 01/09/2018 11:28 AM I observed gravel and mud on the roadway from the construction entrance. The construction entrance has small gravel that has been poured over the top of the Rip Rap that was put in initially and will need to be replaced with larger Rip Rap to not track onto the street as construction vehicles leave the site.
Erosion Control Inspection Partial 1/9/2018 at 2:15 PM 01/09/2018
PW-Misc
Informational
01/09/2018
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
01/09/2018
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
PW-Misc
Informational
01/09/2018
Matt Munger 12/05/2017 9:21 AM I observed an ESC Device in place with two cinder blocks between the device and inlet on the CI that I had asked Sheldon to take care of. I spoke with Sheldon while he was on site and he stated the Utilities Contractor will possibly start next week.
PW-Misc
Informational
01/09/2018
Matt Munger 12/11/2017 10:00 AM No workers were present, ESC devices and silt fence were in place. Emailed Sheldon about the project and if there was anything that he needed from me since I had not seen anyone out at the site.
PW-Misc
Informational
01/09/2018
Matt Munger 12/19/2017 10:10 AM Construction Entrance was in place, large Rip Rap was used. Workers were removing dirt from property.
PW-Devices for Erosion and Sediment Control
Informational
01/09/2018
Matt Munger 12/20/2017 10:21 AM There are problems with the erosion control devices on your site. The silt fence on the south west side of the property has a section that is not secure due to the excavation work being done and in no longer trenched in properly. I spoke with the worker and just asked that he be mindful of the fence to ensure that it remains in place.
PW-Erosion and Sediment Control
Corrective Action Required
01/09/2018
Matt Munger 12/21/2017 2:52 PM Your project is in violation of the Erosion and Sediment control policy. There needs to be a silt fence along section of property that is adjacent to MO-150. After discussing schedules earlier in the day Sheldon stated he would get the silt fence up along the section of property adjacent to MO-150.
PW-Misc
Informational
01/09/2018
Matt Munger 01/02/2018 10:57 AM I walked along the silt fence and observed the silt fence was staked and in place. Will need to keep an eye on the staples that are securing the fence to the stakes to ensure the fence does not pull away and sag.
PW-Erosion and Sediment Control
Corrective Action Required
01/09/2018
Matt Munger 01/09/2018 11:28 AM I observed gravel and mud on the roadway from the construction entrance. The construction entrance has small gravel that has been poured over the top of the Rip Rap that was put in initially and will need to be replaced with larger Rip Rap to not track onto the street as construction vehicles leave the site.
PW-Erosion and Sediment Control
Corrective Action Required
01/09/2018
Matt Munger 01/09/2018 2:15 PM I had emailed Sheldon an inspection report and left a message earlier in the day informing him about the condition of the road and construction entrance. I had received a text message from Sheldon at 12:46 pm stating they would get the entrance taken care of. As I had arrived on site at 2:15 pm I observed gravel in the roadway. They had cleaned some of the gravel off the street but there was still gravel scattered up and down the road. The construction will also need to have the 3/4" gravel that was put on top of the Rip Rap removed to prevent this issue. I had spoke with Sheldon and his father in regards to the issue and informed them that they need to keep the roadway clean. If the roadway is not kept clean a Stop Work Order can be issued. I emailed Sheldon after our conversation on site in regards to the situation and let him know that the Inspector that was with me had also pointed out the construction entrance needs to be extended (total length should be 50ft). In my email I informed Sheldon that I would like to see the entrance in compliance by the end of day tomorrow (1/10/18).
Storm - Material Verification Passed 1/10/2018 at 8:30 AM 01/10/2018
Informational
01/10/2018
Matt Munger 01/10/2018 8:30 AM Looked over the storm pipe that was on site and observed that it was 18" HDPE with bell and spigot ends with AASHTO M294 2306 stamped on the side of the pipe. I also observed the storm box that was delivered was precast.
Storm Sewer Construction Inspection Partial 1/10/2018 at 9:00 AM 01/10/2018
PW-Storm Sewer Inspection
Informational
01/10/2018
Matt Munger 01/10/2018 8:30 AM I spoke with Sue (Engineer) in regards to the clearance issues with the existing water line and the storm sewer that was going to be installed. Sue had stated if they could not get 12" of clearance then it would be ok to encase the pipe in concrete. When I arrived on site and Aaron was still working on getting the area potholed to find out the depth of the pipe. I told them to call me when they had the pipe exposed. Contractor was also working on the construction entrance.
Storm Sewer Construction Inspection Partial 1/10/2018 at 10:36 AM 01/10/2018
PW-Storm Sewer Inspection
Informational
01/10/2018
Matt Munger 01/10/2018 8:30 AM I spoke with Sue (Engineer) in regards to the clearance issues with the existing water line and the storm sewer that was going to be installed. Sue had stated if they could not get 12" of clearance then it would be ok to encase the pipe in concrete. When I arrived on site and Aaron was still working on getting the area potholed to find out the depth of the pipe. I told them to call me when they had the pipe exposed. Contractor was also working on the construction entrance.
PW-Storm Sewer Inspection
Informational
01/10/2018
Matt Munger 01/10/2018 10:36 AM Aaron from Cohurst had dug down the water main and after measuring we discovered there was going to be an issue with getting 18" of clearance. I had informed them that Sue had stated if they could get 12" of clearance they wouldn't need to encase the pipe. After further inspection we saw that was not going to be the case. I called John Haily to come out and check out the situtation. We had Aaron measure from the top of pipe to where the bottom of the pipe would be see if concrete encasement would be an option (if there was 6" of clearance between concrete encasement). John had thought it would be ok to encase the pipe. I told them they will need to have 5ft on each side of center of the where the storm pipe was going. As well as having 6" of concrete above and below the water main. They also were going to use rebar to build a cage around the water line.
Storm Sewer Construction Inspection Partial 1/10/2018 at 3:05 PM 01/10/2018
PW-Storm Sewer Inspection
Informational
01/10/2018
Matt Munger 01/10/2018 8:30 AM I spoke with Sue (Engineer) in regards to the clearance issues with the existing water line and the storm sewer that was going to be installed. Sue had stated if they could not get 12" of clearance then it would be ok to encase the pipe in concrete. When I arrived on site and Aaron was still working on getting the area potholed to find out the depth of the pipe. I told them to call me when they had the pipe exposed. Contractor was also working on the construction entrance.
PW-Storm Sewer Inspection
Informational
01/10/2018
Matt Munger 01/10/2018 10:36 AM Aaron from Cohurst had dug down the water main and after measuring we discovered there was going to be an issue with getting 18" of clearance. I had informed them that Sue had stated if they could get 12" of clearance they wouldn't need to encase the pipe. After further inspection we saw that was not going to be the case. I called John Haily to come out and check out the situtation. We had Aaron measure from the top of pipe to where the bottom of the pipe would be see if concrete encasement would be an option (if there was 6" of clearance between concrete encasement). John had thought it would be ok to encase the pipe. I told them they will need to have 5ft on each side of center of the where the storm pipe was going. As well as having 6" of concrete above and below the water main. They also were going to use rebar to build a cage around the water line.
PW-Storm Sewer Inspection
Informational
01/10/2018
Matt Munger 01/10/2018 3:05 PM I observed the rebar cage around the water main and had watched them pour the concrete. I observed them using a spade shovel to chock in the concrete mix under the water pipe.
Erosion Control Inspection Partial 1/10/2018 at 2:00 PM 01/10/2018
PW-Misc
Informational
01/09/2018
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
01/09/2018
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
PW-Misc
Informational
01/09/2018
Matt Munger 12/05/2017 9:21 AM I observed an ESC Device in place with two cinder blocks between the device and inlet on the CI that I had asked Sheldon to take care of. I spoke with Sheldon while he was on site and he stated the Utilities Contractor will possibly start next week.
PW-Misc
Informational
01/09/2018
Matt Munger 12/11/2017 10:00 AM No workers were present, ESC devices and silt fence were in place. Emailed Sheldon about the project and if there was anything that he needed from me since I had not seen anyone out at the site.
PW-Misc
Informational
01/09/2018
Matt Munger 12/19/2017 10:10 AM Construction Entrance was in place, large Rip Rap was used. Workers were removing dirt from property.
PW-Devices for Erosion and Sediment Control
Informational
01/09/2018
Matt Munger 12/20/2017 10:21 AM There are problems with the erosion control devices on your site. The silt fence on the south west side of the property has a section that is not secure due to the excavation work being done and in no longer trenched in properly. I spoke with the worker and just asked that he be mindful of the fence to ensure that it remains in place.
PW-Erosion and Sediment Control
Corrective Action Required
01/09/2018
Matt Munger 12/21/2017 2:52 PM Your project is in violation of the Erosion and Sediment control policy. There needs to be a silt fence along section of property that is adjacent to MO-150. After discussing schedules earlier in the day Sheldon stated he would get the silt fence up along the section of property adjacent to MO-150.
PW-Misc
Informational
01/09/2018
Matt Munger 01/02/2018 10:57 AM I walked along the silt fence and observed the silt fence was staked and in place. Will need to keep an eye on the staples that are securing the fence to the stakes to ensure the fence does not pull away and sag.
PW-Erosion and Sediment Control
Corrective Action Required
01/09/2018
Matt Munger 01/09/2018 11:28 AM I observed gravel and mud on the roadway from the construction entrance. The construction entrance has small gravel that has been poured over the top of the Rip Rap that was put in initially and will need to be replaced with larger Rip Rap to not track onto the street as construction vehicles leave the site.
PW-Erosion and Sediment Control
Corrective Action Required
01/09/2018
Matt Munger 01/09/2018 2:15 PM I had emailed Sheldon an inspection report and left a message earlier in the day informing him about the condition of the road and construction entrance. I had received a text message from Sheldon at 12:46 pm stating they would get the entrance taken care of. As I had arrived on site at 2:15 pm I observed gravel in the roadway. They had cleaned some of the gravel off the street but there was still gravel scattered up and down the road. The construction will also need to have the 3/4" gravel that was put on top of the Rip Rap removed to prevent this issue. I had spoke with Sheldon and his father in regards to the issue and informed them that they need to keep the roadway clean. If the roadway is not kept clean a Stop Work Order can be issued. I emailed Sheldon after our conversation on site in regards to the situation and let him know that the Inspector that was with me had also pointed out the construction entrance needs to be extended (total length should be 50ft). In my email I informed Sheldon that I would like to see the entrance in compliance by the end of day tomorrow (1/10/18).
PW-Misc
Informational
01/10/2018
Matt Munger 01/10/2018 2:00 PM The construction entrance had been lengthened and large riprap was in place. The gravel in the roadway from the day prior was cleaned up.
Site Visit Partial 1/11/2018 at 10:30 AM 01/11/2018
PW-Misc
Informational
01/08/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
01/08/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
01/08/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
01/08/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
01/08/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
01/08/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
01/08/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
01/08/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
01/08/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
01/08/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
01/08/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
01/08/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
01/08/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
01/08/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
01/08/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
01/08/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
01/11/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
Site Visit Partial 1/12/2018 at 1:57 PM 01/12/2018
PW-Misc
Informational
01/11/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
01/11/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
01/11/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
01/11/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
01/11/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
01/11/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
01/11/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
01/11/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
01/11/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
01/11/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
01/11/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
01/11/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
01/11/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
01/11/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
01/11/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
01/11/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
01/11/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
PW-Misc
Informational
01/12/2018
Matt Munger 01/12/2018 1:57 PM No utility work was being done due to the weather. Street was clean and the erosion control was in place. Sheldon had emailed earlier in the day informing me that they would be digging the storm sewer on Tuesday. I informed Sheldon when they backfill frozen material is not allowed back in the trench. Just wanted to remind him since the temps have dropped (below freezing) and will stay that way into Tuesday of next week.
Site Visit Partial 1/16/2018 at 10:55 AM 01/16/2018
PW-Misc
Informational
01/12/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
01/12/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
01/12/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
01/12/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
01/12/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
01/12/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
01/12/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
01/12/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
01/12/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
01/12/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
01/12/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
01/12/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
01/12/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
01/12/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
01/12/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
01/12/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
01/12/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
PW-Misc
Informational
01/12/2018
Matt Munger 01/12/2018 1:57 PM No utility work was being done due to the weather. Street was clean and the erosion control was in place. Sheldon had emailed earlier in the day informing me that they would be digging the storm sewer on Tuesday. I informed Sheldon when they backfill frozen material is not allowed back in the trench. Just wanted to remind him since the temps have dropped (below freezing) and will stay that way into Tuesday of next week.
PW-Misc
Informational
01/16/2018
Matt Munger 01/16/2018 10:55 AM No workers were present due to the weather. Sheldon had emailed me on Friday stating they would be working today on the storm sewer and I had informed him that since the weather has been so cold frozen backfill material would not be acceptable.
Site Visit Partial 1/17/2018 at 11:00 AM 01/17/2018
PW-Misc
Informational
01/16/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
01/16/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
01/16/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
01/16/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
01/16/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
01/16/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
01/16/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
01/16/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
01/16/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
01/16/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
01/16/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
01/16/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
01/16/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
01/16/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
01/16/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
01/16/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
01/16/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
PW-Misc
Informational
01/16/2018
Matt Munger 01/12/2018 1:57 PM No utility work was being done due to the weather. Street was clean and the erosion control was in place. Sheldon had emailed earlier in the day informing me that they would be digging the storm sewer on Tuesday. I informed Sheldon when they backfill frozen material is not allowed back in the trench. Just wanted to remind him since the temps have dropped (below freezing) and will stay that way into Tuesday of next week.
PW-Misc
Informational
01/16/2018
Matt Munger 01/16/2018 10:55 AM No workers were present due to the weather. Sheldon had emailed me on Friday stating they would be working today on the storm sewer and I had informed him that since the weather has been so cold frozen backfill material would not be acceptable.
PW-Misc
Informational
01/17/2018
Matt Munger 01/17/2018 11:00 AM No utility work was being done due to the weather.
Storm Sewer Construction Inspection Partial 1/18/2018 at 10:52 AM 01/18/2018
PW-Storm Sewer Inspection
Informational
01/10/2018
Matt Munger 01/10/2018 8:30 AM I spoke with Sue (Engineer) in regards to the clearance issues with the existing water line and the storm sewer that was going to be installed. Sue had stated if they could not get 12" of clearance then it would be ok to encase the pipe in concrete. When I arrived on site and Aaron was still working on getting the area potholed to find out the depth of the pipe. I told them to call me when they had the pipe exposed. Contractor was also working on the construction entrance.
PW-Storm Sewer Inspection
Informational
01/10/2018
Matt Munger 01/10/2018 10:36 AM Aaron from Cohurst had dug down the water main and after measuring we discovered there was going to be an issue with getting 18" of clearance. I had informed them that Sue had stated if they could get 12" of clearance they wouldn't need to encase the pipe. After further inspection we saw that was not going to be the case. I called John Haily to come out and check out the situtation. We had Aaron measure from the top of pipe to where the bottom of the pipe would be see if concrete encasement would be an option (if there was 6" of clearance between concrete encasement). John had thought it would be ok to encase the pipe. I told them they will need to have 5ft on each side of center of the where the storm pipe was going. As well as having 6" of concrete above and below the water main. They also were going to use rebar to build a cage around the water line.
PW-Storm Sewer Inspection
Informational
01/10/2018
Matt Munger 01/10/2018 3:05 PM I observed the rebar cage around the water main and had watched them pour the concrete. I observed them using a spade shovel to chock in the concrete mix under the water pipe.
PW-Storm Sewer Inspection
Informational
01/18/2018
Matt Munger 01/18/2018 10:52 AM I had observed the workers digging the trench where the storm pipe is going to be put in. I had spoke with Aaron from Cohurst on the phone earlier in the morning and on site and informed him that putting frozen backfill material does not meet our standard and that I would have to fail the inspection. I explained to Aaron the concern would be that the soil would not be compacted properly and could cause a sink hole and issues down the road, especially where they are putting pavement in. I observed the curb inlet at Sta. 0+80.29 was set in place with gravel base underneath that was set in prior to my arrival. I informed Aaron to contact me prior to backfilling the trench.
Storm Sewer Construction Inspection Partial 1/18/2018 at 2:25 PM 01/18/2018
PW-Storm Sewer Inspection
Informational
01/18/2018
Matt Munger 01/10/2018 8:30 AM I spoke with Sue (Engineer) in regards to the clearance issues with the existing water line and the storm sewer that was going to be installed. Sue had stated if they could not get 12" of clearance then it would be ok to encase the pipe in concrete. When I arrived on site and Aaron was still working on getting the area potholed to find out the depth of the pipe. I told them to call me when they had the pipe exposed. Contractor was also working on the construction entrance.
PW-Storm Sewer Inspection
Informational
01/18/2018
Matt Munger 01/10/2018 10:36 AM Aaron from Cohurst had dug down the water main and after measuring we discovered there was going to be an issue with getting 18" of clearance. I had informed them that Sue had stated if they could get 12" of clearance they wouldn't need to encase the pipe. After further inspection we saw that was not going to be the case. I called John Haily to come out and check out the situtation. We had Aaron measure from the top of pipe to where the bottom of the pipe would be see if concrete encasement would be an option (if there was 6" of clearance between concrete encasement). John had thought it would be ok to encase the pipe. I told them they will need to have 5ft on each side of center of the where the storm pipe was going. As well as having 6" of concrete above and below the water main. They also were going to use rebar to build a cage around the water line.
PW-Storm Sewer Inspection
Informational
01/18/2018
Matt Munger 01/10/2018 3:05 PM I observed the rebar cage around the water main and had watched them pour the concrete. I observed them using a spade shovel to chock in the concrete mix under the water pipe.
PW-Storm Sewer Inspection
Informational
01/18/2018
Matt Munger 01/18/2018 10:52 AM I had observed the workers digging the trench where the storm pipe is going to be put in. I had spoke with Aaron from Cohurst on the phone earlier in the morning and on site and informed him that putting frozen backfill material does not meet our standard and that I would have to fail the inspection. I explained to Aaron the concern would be that the soil would not be compacted properly and could cause a sink hole and issues down the road, especially where they are putting pavement in. I observed the curb inlet at Sta. 0+80.29 was set in place with gravel base underneath that was set in prior to my arrival. I informed Aaron to contact me prior to backfilling the trench.
PW-Storm Sewer Inspection
Informational
01/18/2018
Matt Munger 01/18/2018 2:25 PM Tom C. and I went out to check on the storm sewer that had been installed. I observed adequate amount of gravel above and below the storm pipe. The backfill material that was on site good and didn't have alot of chunks. They had separated frozen material to ensure good material was going getting backfilled. I had also received the concrete ticket for the collars.
Erosion Control Inspection Partial 1/22/2018 at 11:21 AM 01/22/2018
PW-Misc
Informational
01/10/2018
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
01/10/2018
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
PW-Misc
Informational
01/10/2018
Matt Munger 12/05/2017 9:21 AM I observed an ESC Device in place with two cinder blocks between the device and inlet on the CI that I had asked Sheldon to take care of. I spoke with Sheldon while he was on site and he stated the Utilities Contractor will possibly start next week.
PW-Misc
Informational
01/10/2018
Matt Munger 12/11/2017 10:00 AM No workers were present, ESC devices and silt fence were in place. Emailed Sheldon about the project and if there was anything that he needed from me since I had not seen anyone out at the site.
PW-Misc
Informational
01/10/2018
Matt Munger 12/19/2017 10:10 AM Construction Entrance was in place, large Rip Rap was used. Workers were removing dirt from property.
PW-Devices for Erosion and Sediment Control
Informational
01/10/2018
Matt Munger 12/20/2017 10:21 AM There are problems with the erosion control devices on your site. The silt fence on the south west side of the property has a section that is not secure due to the excavation work being done and in no longer trenched in properly. I spoke with the worker and just asked that he be mindful of the fence to ensure that it remains in place.
PW-Erosion and Sediment Control
Corrective Action Required
01/10/2018
Matt Munger 12/21/2017 2:52 PM Your project is in violation of the Erosion and Sediment control policy. There needs to be a silt fence along section of property that is adjacent to MO-150. After discussing schedules earlier in the day Sheldon stated he would get the silt fence up along the section of property adjacent to MO-150.
PW-Misc
Informational
01/10/2018
Matt Munger 01/02/2018 10:57 AM I walked along the silt fence and observed the silt fence was staked and in place. Will need to keep an eye on the staples that are securing the fence to the stakes to ensure the fence does not pull away and sag.
PW-Erosion and Sediment Control
Corrective Action Required
01/10/2018
Matt Munger 01/09/2018 11:28 AM I observed gravel and mud on the roadway from the construction entrance. The construction entrance has small gravel that has been poured over the top of the Rip Rap that was put in initially and will need to be replaced with larger Rip Rap to not track onto the street as construction vehicles leave the site.
PW-Erosion and Sediment Control
Corrective Action Required
01/10/2018
Matt Munger 01/09/2018 2:15 PM I had emailed Sheldon an inspection report and left a message earlier in the day informing him about the condition of the road and construction entrance. I had received a text message from Sheldon at 12:46 pm stating they would get the entrance taken care of. As I had arrived on site at 2:15 pm I observed gravel in the roadway. They had cleaned some of the gravel off the street but there was still gravel scattered up and down the road. The construction will also need to have the 3/4" gravel that was put on top of the Rip Rap removed to prevent this issue. I had spoke with Sheldon and his father in regards to the issue and informed them that they need to keep the roadway clean. If the roadway is not kept clean a Stop Work Order can be issued. I emailed Sheldon after our conversation on site in regards to the situation and let him know that the Inspector that was with me had also pointed out the construction entrance needs to be extended (total length should be 50ft). In my email I informed Sheldon that I would like to see the entrance in compliance by the end of day tomorrow (1/10/18).
PW-Misc
Informational
01/10/2018
Matt Munger 01/10/2018 2:00 PM The construction entrance had been lengthened and large riprap was in place. The gravel in the roadway from the day prior was cleaned up.
PW-Misc
Informational
01/22/2018
Matt Munger 01/22/2018 11:25 AM Silt fence and ESC devices were in place.
Site Visit Partial 1/23/2018 at 2:57 PM 01/23/2018
PW-Misc
Informational
01/17/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
01/17/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
01/17/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
01/17/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
01/17/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
01/17/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
01/17/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
01/17/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
01/17/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
01/17/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
01/17/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
01/17/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
01/17/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
01/17/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
01/17/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
01/17/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
01/17/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
PW-Misc
Informational
01/17/2018
Matt Munger 01/12/2018 1:57 PM No utility work was being done due to the weather. Street was clean and the erosion control was in place. Sheldon had emailed earlier in the day informing me that they would be digging the storm sewer on Tuesday. I informed Sheldon when they backfill frozen material is not allowed back in the trench. Just wanted to remind him since the temps have dropped (below freezing) and will stay that way into Tuesday of next week.
PW-Misc
Informational
01/17/2018
Matt Munger 01/16/2018 10:55 AM No workers were present due to the weather. Sheldon had emailed me on Friday stating they would be working today on the storm sewer and I had informed him that since the weather has been so cold frozen backfill material would not be acceptable.
PW-Misc
Informational
01/17/2018
Matt Munger 01/17/2018 11:00 AM No utility work was being done due to the weather.
PW-Misc
Informational
01/23/2018
Matt Munger 01/23/2018 2:57 PM Workers were working on the building. No other infrastructure work was being done.
Storm Sewer Construction Inspection Passed 1/24/2018 at 10:35 AM 01/29/2018
PW-Storm Sewer Inspection
Informational
01/18/2018
Matt Munger 01/10/2018 8:30 AM I spoke with Sue (Engineer) in regards to the clearance issues with the existing water line and the storm sewer that was going to be installed. Sue had stated if they could not get 12" of clearance then it would be ok to encase the pipe in concrete. When I arrived on site and Aaron was still working on getting the area potholed to find out the depth of the pipe. I told them to call me when they had the pipe exposed. Contractor was also working on the construction entrance.
PW-Storm Sewer Inspection
Informational
01/18/2018
Matt Munger 01/10/2018 10:36 AM Aaron from Cohurst had dug down the water main and after measuring we discovered there was going to be an issue with getting 18" of clearance. I had informed them that Sue had stated if they could get 12" of clearance they wouldn't need to encase the pipe. After further inspection we saw that was not going to be the case. I called John Haily to come out and check out the situtation. We had Aaron measure from the top of pipe to where the bottom of the pipe would be see if concrete encasement would be an option (if there was 6" of clearance between concrete encasement). John had thought it would be ok to encase the pipe. I told them they will need to have 5ft on each side of center of the where the storm pipe was going. As well as having 6" of concrete above and below the water main. They also were going to use rebar to build a cage around the water line.
PW-Storm Sewer Inspection
Informational
01/18/2018
Matt Munger 01/10/2018 3:05 PM I observed the rebar cage around the water main and had watched them pour the concrete. I observed them using a spade shovel to chock in the concrete mix under the water pipe.
PW-Storm Sewer Inspection
Informational
01/18/2018
Matt Munger 01/18/2018 10:52 AM I had observed the workers digging the trench where the storm pipe is going to be put in. I had spoke with Aaron from Cohurst on the phone earlier in the morning and on site and informed him that putting frozen backfill material does not meet our standard and that I would have to fail the inspection. I explained to Aaron the concern would be that the soil would not be compacted properly and could cause a sink hole and issues down the road, especially where they are putting pavement in. I observed the curb inlet at Sta. 0+80.29 was set in place with gravel base underneath that was set in prior to my arrival. I informed Aaron to contact me prior to backfilling the trench.
PW-Storm Sewer Inspection
Informational
01/18/2018
Matt Munger 01/18/2018 2:25 PM Tom C. and I went out to check on the storm sewer that had been installed. I observed adequate amount of gravel above and below the storm pipe. The backfill material that was on site good and didn't have alot of chunks. They had separated frozen material to ensure good material was going getting backfilled. I had also received the concrete ticket for the collars.
PW-Storm Sewer Inspection
Informational
01/24/2018
Matt Munger 01/24/2018 10:35 AM Opened up the Public CI (Sta. 0+00.00) to make sure the concrete collar hadn't pulled away from the existing concrete after it had cured for a few days.
Site Visit Partial 1/29/2018 at 9:42 AM 01/29/2018
PW-Misc
Informational
01/23/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
01/23/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
01/23/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
01/23/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
01/23/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
01/23/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
01/23/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
01/23/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
01/23/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
01/23/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
01/23/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
01/23/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
01/23/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
01/23/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
01/23/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
01/23/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
01/23/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
PW-Misc
Informational
01/23/2018
Matt Munger 01/12/2018 1:57 PM No utility work was being done due to the weather. Street was clean and the erosion control was in place. Sheldon had emailed earlier in the day informing me that they would be digging the storm sewer on Tuesday. I informed Sheldon when they backfill frozen material is not allowed back in the trench. Just wanted to remind him since the temps have dropped (below freezing) and will stay that way into Tuesday of next week.
PW-Misc
Informational
01/23/2018
Matt Munger 01/16/2018 10:55 AM No workers were present due to the weather. Sheldon had emailed me on Friday stating they would be working today on the storm sewer and I had informed him that since the weather has been so cold frozen backfill material would not be acceptable.
PW-Misc
Informational
01/23/2018
Matt Munger 01/17/2018 11:00 AM No utility work was being done due to the weather.
PW-Misc
Informational
01/23/2018
Matt Munger 01/23/2018 2:57 PM Workers were working on the building. No other infrastructure work was being done.
PW-Misc
Informational
01/29/2018
Matt Munger 01/29/2018 9:53 AM Spoke with Mr. Bouwens as he was cleaning loose dirt off the street. Workers were grading out the pavement areas and that they were going to be putting down geogrid instead of fly ash. He said they would start working on the curb Wednesday. I discussed putting the geogrid a foot past the curb as well.
Erosion Control Inspection Partial 1/30/2018 at 10:54 AM 01/30/2018
PW-Misc
Informational
01/22/2018
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
01/22/2018
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
PW-Misc
Informational
01/22/2018
Matt Munger 12/05/2017 9:21 AM I observed an ESC Device in place with two cinder blocks between the device and inlet on the CI that I had asked Sheldon to take care of. I spoke with Sheldon while he was on site and he stated the Utilities Contractor will possibly start next week.
PW-Misc
Informational
01/22/2018
Matt Munger 12/11/2017 10:00 AM No workers were present, ESC devices and silt fence were in place. Emailed Sheldon about the project and if there was anything that he needed from me since I had not seen anyone out at the site.
PW-Misc
Informational
01/22/2018
Matt Munger 12/19/2017 10:10 AM Construction Entrance was in place, large Rip Rap was used. Workers were removing dirt from property.
PW-Devices for Erosion and Sediment Control
Informational
01/22/2018
Matt Munger 12/20/2017 10:21 AM There are problems with the erosion control devices on your site. The silt fence on the south west side of the property has a section that is not secure due to the excavation work being done and in no longer trenched in properly. I spoke with the worker and just asked that he be mindful of the fence to ensure that it remains in place.
PW-Erosion and Sediment Control
Corrective Action Required
01/22/2018
Matt Munger 12/21/2017 2:52 PM Your project is in violation of the Erosion and Sediment control policy. There needs to be a silt fence along section of property that is adjacent to MO-150. After discussing schedules earlier in the day Sheldon stated he would get the silt fence up along the section of property adjacent to MO-150.
PW-Misc
Informational
01/22/2018
Matt Munger 01/02/2018 10:57 AM I walked along the silt fence and observed the silt fence was staked and in place. Will need to keep an eye on the staples that are securing the fence to the stakes to ensure the fence does not pull away and sag.
PW-Erosion and Sediment Control
Corrective Action Required
01/22/2018
Matt Munger 01/09/2018 11:28 AM I observed gravel and mud on the roadway from the construction entrance. The construction entrance has small gravel that has been poured over the top of the Rip Rap that was put in initially and will need to be replaced with larger Rip Rap to not track onto the street as construction vehicles leave the site.
PW-Erosion and Sediment Control
Corrective Action Required
01/22/2018
Matt Munger 01/09/2018 2:15 PM I had emailed Sheldon an inspection report and left a message earlier in the day informing him about the condition of the road and construction entrance. I had received a text message from Sheldon at 12:46 pm stating they would get the entrance taken care of. As I had arrived on site at 2:15 pm I observed gravel in the roadway. They had cleaned some of the gravel off the street but there was still gravel scattered up and down the road. The construction will also need to have the 3/4" gravel that was put on top of the Rip Rap removed to prevent this issue. I had spoke with Sheldon and his father in regards to the issue and informed them that they need to keep the roadway clean. If the roadway is not kept clean a Stop Work Order can be issued. I emailed Sheldon after our conversation on site in regards to the situation and let him know that the Inspector that was with me had also pointed out the construction entrance needs to be extended (total length should be 50ft). In my email I informed Sheldon that I would like to see the entrance in compliance by the end of day tomorrow (1/10/18).
PW-Misc
Informational
01/22/2018
Matt Munger 01/10/2018 2:00 PM The construction entrance had been lengthened and large riprap was in place. The gravel in the roadway from the day prior was cleaned up.
PW-Misc
Informational
01/22/2018
Matt Munger 01/22/2018 11:25 AM Silt fence and ESC devices were in place.
PW-Devices for Erosion and Sediment Control
Informational
01/30/2018
Matt Munger 01/30/2018 10:57 AM Street was clean, ESC devices were in place. The silt fence on the south side will need some minor adjustments to keep the fence from sagging.
Site Visit Partial 1/30/2018 at 10:54 AM 01/30/2018
PW-Misc
Informational
01/29/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
01/29/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
01/29/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
01/29/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
01/29/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
01/29/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
01/29/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
01/29/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
01/29/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
01/29/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
01/29/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
01/29/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
01/29/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
01/29/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
01/29/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
01/29/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
01/29/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
PW-Misc
Informational
01/29/2018
Matt Munger 01/12/2018 1:57 PM No utility work was being done due to the weather. Street was clean and the erosion control was in place. Sheldon had emailed earlier in the day informing me that they would be digging the storm sewer on Tuesday. I informed Sheldon when they backfill frozen material is not allowed back in the trench. Just wanted to remind him since the temps have dropped (below freezing) and will stay that way into Tuesday of next week.
PW-Misc
Informational
01/29/2018
Matt Munger 01/16/2018 10:55 AM No workers were present due to the weather. Sheldon had emailed me on Friday stating they would be working today on the storm sewer and I had informed him that since the weather has been so cold frozen backfill material would not be acceptable.
PW-Misc
Informational
01/29/2018
Matt Munger 01/17/2018 11:00 AM No utility work was being done due to the weather.
PW-Misc
Informational
01/29/2018
Matt Munger 01/23/2018 2:57 PM Workers were working on the building. No other infrastructure work was being done.
PW-Misc
Informational
01/29/2018
Matt Munger 01/29/2018 9:53 AM Spoke with Mr. Bouwens as he was cleaning loose dirt off the street. Workers were grading out the pavement areas and that they were going to be putting down geogrid instead of fly ash. He said they would start working on the curb Wednesday. I discussed putting the geogrid a foot past the curb as well.
PW-Misc
Informational
01/30/2018
Matt Munger 01/30/2018 11:00 AM Workers had cut out the area where pavement and curb is going to be put it. I had emailed Sheldon on 1/29/18 informing to get with me when they were ready for the proof roll for the curbs. They decided to use geogrid instead of fly ash.
Pavement-Stabilized Subgrade Partial 1/30/2018 at 2:30 PM 01/30/2018
PW-Misc
Informational
01/30/2018
Matt Munger 01/30/2018 2:41 PM I observed geogrid in place over compacted subgrade with AB3 material on top of the geogrid. It appears the workers were not done spreading and compacting the AB3 material. This work was done prior to my arrival. The area that had geogrid and AB3 material in place was on the east side of the building where the parking spaces were going in, and from where the construction entrance ends.
Erosion Control Inspection Partial 1/31/2018 at 10:31 AM 01/31/2018
PW-Misc
Informational
01/30/2018
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
01/30/2018
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
PW-Misc
Informational
01/30/2018
Matt Munger 12/05/2017 9:21 AM I observed an ESC Device in place with two cinder blocks between the device and inlet on the CI that I had asked Sheldon to take care of. I spoke with Sheldon while he was on site and he stated the Utilities Contractor will possibly start next week.
PW-Misc
Informational
01/30/2018
Matt Munger 12/11/2017 10:00 AM No workers were present, ESC devices and silt fence were in place. Emailed Sheldon about the project and if there was anything that he needed from me since I had not seen anyone out at the site.
PW-Misc
Informational
01/30/2018
Matt Munger 12/19/2017 10:10 AM Construction Entrance was in place, large Rip Rap was used. Workers were removing dirt from property.
PW-Devices for Erosion and Sediment Control
Informational
01/30/2018
Matt Munger 12/20/2017 10:21 AM There are problems with the erosion control devices on your site. The silt fence on the south west side of the property has a section that is not secure due to the excavation work being done and in no longer trenched in properly. I spoke with the worker and just asked that he be mindful of the fence to ensure that it remains in place.
PW-Erosion and Sediment Control
Corrective Action Required
01/30/2018
Matt Munger 12/21/2017 2:52 PM Your project is in violation of the Erosion and Sediment control policy. There needs to be a silt fence along section of property that is adjacent to MO-150. After discussing schedules earlier in the day Sheldon stated he would get the silt fence up along the section of property adjacent to MO-150.
PW-Misc
Informational
01/30/2018
Matt Munger 01/02/2018 10:57 AM I walked along the silt fence and observed the silt fence was staked and in place. Will need to keep an eye on the staples that are securing the fence to the stakes to ensure the fence does not pull away and sag.
PW-Erosion and Sediment Control
Corrective Action Required
01/30/2018
Matt Munger 01/09/2018 11:28 AM I observed gravel and mud on the roadway from the construction entrance. The construction entrance has small gravel that has been poured over the top of the Rip Rap that was put in initially and will need to be replaced with larger Rip Rap to not track onto the street as construction vehicles leave the site.
PW-Erosion and Sediment Control
Corrective Action Required
01/30/2018
Matt Munger 01/09/2018 2:15 PM I had emailed Sheldon an inspection report and left a message earlier in the day informing him about the condition of the road and construction entrance. I had received a text message from Sheldon at 12:46 pm stating they would get the entrance taken care of. As I had arrived on site at 2:15 pm I observed gravel in the roadway. They had cleaned some of the gravel off the street but there was still gravel scattered up and down the road. The construction will also need to have the 3/4" gravel that was put on top of the Rip Rap removed to prevent this issue. I had spoke with Sheldon and his father in regards to the issue and informed them that they need to keep the roadway clean. If the roadway is not kept clean a Stop Work Order can be issued. I emailed Sheldon after our conversation on site in regards to the situation and let him know that the Inspector that was with me had also pointed out the construction entrance needs to be extended (total length should be 50ft). In my email I informed Sheldon that I would like to see the entrance in compliance by the end of day tomorrow (1/10/18).
PW-Misc
Informational
01/30/2018
Matt Munger 01/10/2018 2:00 PM The construction entrance had been lengthened and large riprap was in place. The gravel in the roadway from the day prior was cleaned up.
PW-Misc
Informational
01/30/2018
Matt Munger 01/22/2018 11:25 AM Silt fence and ESC devices were in place.
PW-Devices for Erosion and Sediment Control
Informational
01/30/2018
Matt Munger 01/30/2018 10:57 AM Street was clean, ESC devices were in place. The silt fence on the south side will need some minor adjustments to keep the fence from sagging.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
01/31/2018
Matt Munger 01/31/2018 11:00 AM The silt fence on along SW Lemans Rd. has started to fall down and will need to be pulled up.
Pavement-Stabilized Subgrade Partial 1/31/2018 at 10:31 AM 01/31/2018
PW-Misc
Informational
01/30/2018
Matt Munger 01/30/2018 2:41 PM I observed geogrid in place over compacted subgrade with AB3 material on top of the geogrid. It appears the workers were not done spreading and compacting the AB3 material. This work was done prior to my arrival. The area that had geogrid and AB3 material in place was on the east side of the building where the parking spaces were going in, and from where the construction entrance ends.
PW-Misc
Informational
01/31/2018
Matt Munger 01/31/2018 10:53 AM Spoke with Mr. Bouwens on site and informed him that we will need to do a curb proof roll. He stated they were using their rolling machine over the entire area and that should be good. I informed him that I need to be present to pass the proof roll for the curbs. We also had talked about he geogrid and materials being a foot past the curb. The workers had cut out the driveway area for the west entrance. Geogrid was not in place for that area at this time.
Curb - Proof Roll Partial 1/31/2018 at 2:48 PM 01/31/2018
PW-Misc
Partial Correction
01/31/2018
Matt Munger 01/31/2018 2:48 PM I observed the proof roll for the curbs. There were a couple corners that were a little bit soft (due to the material being a little wet), I had the equipment operator go back and roll over it a few times to compact the areas that I had a concern with. Majority of the material did not flex as they were driving over the curb line.
Curb - Proof Roll Passed 2/1/2018 at 8:49 AM 02/01/2018
PW-Misc
Partial Correction
01/31/2018
Matt Munger 01/31/2018 2:48 PM I observed the proof roll for the curbs. There were a couple corners that were a little bit soft (due to the material being a little wet), I had the equipment operator go back and roll over it a few times to compact the areas that I had a concern with. Majority of the material did not flex as they were driving over the curb line.
PW-Misc
Informational
02/01/2018
Matt Munger 02/01/2018 8:57 AM The workers had went over the couple areas that I was concerned about and made sure they were compacted. They started setting up the forms on the north side of the site.
Commercial Curb Inspection Partial 2/2/2018 at 11:29 AM 02/02/2018
Informational
02/02/2018
Matt Munger 02/02/2018 11:29 AM When I arrived on site I observed the curbs on the north side and in the parking stalls had been poured and there were blankets out. I spoke with the worker on site and asked to him to make sure they kept the curbs covered. Due to the temperatures being low at the time (24 degrees) I sent Sheldon a message informing him that I didn't think it would be best to pour the curbs due to the drop in temps, Sheldon replied that the temps were going to go up 11 degrees and he would make sure they were covered. He also stated they would be pouring later in the day.
Commercial Curb Inspection Partial 2/2/2018 at 2:07 PM 02/02/2018
Informational
02/02/2018
Matt Munger 02/02/2018 2:07 PM I had stopped by to see what work had gotten done. I spoke with Dan (Cohurst) and had asked him to make sure that they cover the curbs and saw that they spray the curbs with a cure. I also pointed out to Dan that the back of the curbs needs a non shrink grout applied to the areas that have honeycomb spots. Dan had said he would have to talk with his boss about that and I explained to Dan that in the even moisture gets behind the curb and gets in the crevices that would cause the concrete to pop from freezing. I told Dan to make sure to not backfill behind the curbs until I could verify the areas were grouted. I also contacted Sheldon and informed him that the curbs needed to be grouted, he stated he would take care of it.
Site Visit Partial 2/5/2018 at 9:15 AM 02/05/2018
PW-Misc
Informational
01/30/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
01/30/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
01/30/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
01/30/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
01/30/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
01/30/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
01/30/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
01/30/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
01/30/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
01/30/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
01/30/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
01/30/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
01/30/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
01/30/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
01/30/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
01/30/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
01/30/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
PW-Misc
Informational
01/30/2018
Matt Munger 01/12/2018 1:57 PM No utility work was being done due to the weather. Street was clean and the erosion control was in place. Sheldon had emailed earlier in the day informing me that they would be digging the storm sewer on Tuesday. I informed Sheldon when they backfill frozen material is not allowed back in the trench. Just wanted to remind him since the temps have dropped (below freezing) and will stay that way into Tuesday of next week.
PW-Misc
Informational
01/30/2018
Matt Munger 01/16/2018 10:55 AM No workers were present due to the weather. Sheldon had emailed me on Friday stating they would be working today on the storm sewer and I had informed him that since the weather has been so cold frozen backfill material would not be acceptable.
PW-Misc
Informational
01/30/2018
Matt Munger 01/17/2018 11:00 AM No utility work was being done due to the weather.
PW-Misc
Informational
01/30/2018
Matt Munger 01/23/2018 2:57 PM Workers were working on the building. No other infrastructure work was being done.
PW-Misc
Informational
01/30/2018
Matt Munger 01/29/2018 9:53 AM Spoke with Mr. Bouwens as he was cleaning loose dirt off the street. Workers were grading out the pavement areas and that they were going to be putting down geogrid instead of fly ash. He said they would start working on the curb Wednesday. I discussed putting the geogrid a foot past the curb as well.
PW-Misc
Informational
01/30/2018
Matt Munger 01/30/2018 11:00 AM Workers had cut out the area where pavement and curb is going to be put it. I had emailed Sheldon on 1/29/18 informing to get with me when they were ready for the proof roll for the curbs. They decided to use geogrid instead of fly ash.
PW-Misc
Informational
02/05/2018
Matt Munger 02/05/2018 9:15 AM No work was being done on site.
Commercial Curb Inspection Partial 2/6/2018 at 10:38 AM 02/06/2018
Informational
02/06/2018
Matt Munger 02/06/2018 10:43 Am Blankets were over the curbs that have been pour prior to the weather change. No more work was being done due to the weather.
Site Visit Partial 2/7/2018 at 9:22 AM 02/07/2018
PW-Misc
Informational
02/05/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
02/05/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
02/05/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
02/05/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
02/05/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
02/05/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
02/05/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
02/05/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
02/05/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
02/05/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
02/05/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
02/05/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
02/05/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
02/05/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
02/05/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
02/05/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
02/05/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
PW-Misc
Informational
02/05/2018
Matt Munger 01/12/2018 1:57 PM No utility work was being done due to the weather. Street was clean and the erosion control was in place. Sheldon had emailed earlier in the day informing me that they would be digging the storm sewer on Tuesday. I informed Sheldon when they backfill frozen material is not allowed back in the trench. Just wanted to remind him since the temps have dropped (below freezing) and will stay that way into Tuesday of next week.
PW-Misc
Informational
02/05/2018
Matt Munger 01/16/2018 10:55 AM No workers were present due to the weather. Sheldon had emailed me on Friday stating they would be working today on the storm sewer and I had informed him that since the weather has been so cold frozen backfill material would not be acceptable.
PW-Misc
Informational
02/05/2018
Matt Munger 01/17/2018 11:00 AM No utility work was being done due to the weather.
PW-Misc
Informational
02/05/2018
Matt Munger 01/23/2018 2:57 PM Workers were working on the building. No other infrastructure work was being done.
PW-Misc
Informational
02/05/2018
Matt Munger 01/29/2018 9:53 AM Spoke with Mr. Bouwens as he was cleaning loose dirt off the street. Workers were grading out the pavement areas and that they were going to be putting down geogrid instead of fly ash. He said they would start working on the curb Wednesday. I discussed putting the geogrid a foot past the curb as well.
PW-Misc
Informational
02/05/2018
Matt Munger 01/30/2018 11:00 AM Workers had cut out the area where pavement and curb is going to be put it. I had emailed Sheldon on 1/29/18 informing to get with me when they were ready for the proof roll for the curbs. They decided to use geogrid instead of fly ash.
PW-Misc
Informational
02/05/2018
Matt Munger 02/05/2018 9:15 AM No work was being done on site.
PW-Misc
Informational
02/07/2018
Matt Munger 02/07/2018 9:22 AM No work was being done onsite.
Commercial Curb Inspection Partial 2/8/2018 at 10:40 AM 02/08/2018
Informational
02/08/2018
Matt Munger 02/08/2018 10:48 AM Spoke with Sheldon about making sure the back of the curbs were grouted. He stated they have never heard of that. I explained to him due to moisture getting in the crevices when it freezes it can cause issues. I explained to him we are looking out for his best interest of the owner to prevent issues down the road. He stated they would get it taken care of.
Erosion Control Inspection Partial 2/8/2018 at 10:40 AM 02/08/2018
PW-Misc
Informational
01/31/2018
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
01/31/2018
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
PW-Misc
Informational
01/31/2018
Matt Munger 12/05/2017 9:21 AM I observed an ESC Device in place with two cinder blocks between the device and inlet on the CI that I had asked Sheldon to take care of. I spoke with Sheldon while he was on site and he stated the Utilities Contractor will possibly start next week.
PW-Misc
Informational
01/31/2018
Matt Munger 12/11/2017 10:00 AM No workers were present, ESC devices and silt fence were in place. Emailed Sheldon about the project and if there was anything that he needed from me since I had not seen anyone out at the site.
PW-Misc
Informational
01/31/2018
Matt Munger 12/19/2017 10:10 AM Construction Entrance was in place, large Rip Rap was used. Workers were removing dirt from property.
PW-Devices for Erosion and Sediment Control
Informational
01/31/2018
Matt Munger 12/20/2017 10:21 AM There are problems with the erosion control devices on your site. The silt fence on the south west side of the property has a section that is not secure due to the excavation work being done and in no longer trenched in properly. I spoke with the worker and just asked that he be mindful of the fence to ensure that it remains in place.
PW-Erosion and Sediment Control
Corrective Action Required
01/31/2018
Matt Munger 12/21/2017 2:52 PM Your project is in violation of the Erosion and Sediment control policy. There needs to be a silt fence along section of property that is adjacent to MO-150. After discussing schedules earlier in the day Sheldon stated he would get the silt fence up along the section of property adjacent to MO-150.
PW-Misc
Informational
01/31/2018
Matt Munger 01/02/2018 10:57 AM I walked along the silt fence and observed the silt fence was staked and in place. Will need to keep an eye on the staples that are securing the fence to the stakes to ensure the fence does not pull away and sag.
PW-Erosion and Sediment Control
Corrective Action Required
01/31/2018
Matt Munger 01/09/2018 11:28 AM I observed gravel and mud on the roadway from the construction entrance. The construction entrance has small gravel that has been poured over the top of the Rip Rap that was put in initially and will need to be replaced with larger Rip Rap to not track onto the street as construction vehicles leave the site.
PW-Erosion and Sediment Control
Corrective Action Required
01/31/2018
Matt Munger 01/09/2018 2:15 PM I had emailed Sheldon an inspection report and left a message earlier in the day informing him about the condition of the road and construction entrance. I had received a text message from Sheldon at 12:46 pm stating they would get the entrance taken care of. As I had arrived on site at 2:15 pm I observed gravel in the roadway. They had cleaned some of the gravel off the street but there was still gravel scattered up and down the road. The construction will also need to have the 3/4" gravel that was put on top of the Rip Rap removed to prevent this issue. I had spoke with Sheldon and his father in regards to the issue and informed them that they need to keep the roadway clean. If the roadway is not kept clean a Stop Work Order can be issued. I emailed Sheldon after our conversation on site in regards to the situation and let him know that the Inspector that was with me had also pointed out the construction entrance needs to be extended (total length should be 50ft). In my email I informed Sheldon that I would like to see the entrance in compliance by the end of day tomorrow (1/10/18).
PW-Misc
Informational
01/31/2018
Matt Munger 01/10/2018 2:00 PM The construction entrance had been lengthened and large riprap was in place. The gravel in the roadway from the day prior was cleaned up.
PW-Misc
Informational
01/31/2018
Matt Munger 01/22/2018 11:25 AM Silt fence and ESC devices were in place.
PW-Devices for Erosion and Sediment Control
Informational
01/31/2018
Matt Munger 01/30/2018 10:57 AM Street was clean, ESC devices were in place. The silt fence on the south side will need some minor adjustments to keep the fence from sagging.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
01/31/2018
Matt Munger 01/31/2018 11:00 AM The silt fence on along SW Lemans Rd. has started to fall down and will need to be pulled up.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/08/2018
Matt Munger 02/08/2018 10:46 AM Silt fence on the south side needs to be pulled back up and secured to the stakes. I spoke with Sheldong in regards to the concern and he stated he would get it taken care of.
Miscellaneous PWORKS Inspection Passed 2/9/2018 at 11:00 AM 02/09/2018
PW-Misc
Informational
02/09/2018
I drove to the site and the curb crew was out forming some curbs and doing some saw cuts around the sidewalk for the building.Steve Robbins 02/09/2018 3:50 PM
Commercial Curb Inspection Partial 2/12/2018 at 9:41 AM 02/12/2018
Informational
02/12/2018
Matt Munger 02/12/2018 9:41 AM The curbs had contraction joints cut in at approximately every 10ft. I did observed honeycomb areas on the back of the curb that I spoke with Sheldon about grouting. He said once all of the curb is in they will grout the backs of the curbs. * I also informed Sheldon when they go to put in the sidewalk/driveway approach in the ROW to call me to do pre-pour inspection.
Commercial Curb Inspection Partial 2/13/2018 at 10:50 AM 02/13/2018
Corrective Action Required
02/13/2018
Matt Munger 02/13/2018 11:20 AM John H. and I spoke with the contractor about making sure to use KCMMB 4k with white cure, smooth #5 dowels instead of what they had put in already. They only had 2 dowels in place, we advised to not use wings for the sidewalk. I had emailed Sheldon our detail for sidewalks, curbs and driveways on 2/12/18. I also called Sheldon and informed him of the concerns I had with what I saw.
Commercial Curb Inspection Partial 2/13/2018 at 1:52 PM 02/13/2018
Corrective Action Required
02/13/2018
Matt Munger 02/13/2018 1:59 PM Came back out to check on the curbs that they had formed up. No further work had been done on the curbs. I did not see any gravel under where the curbs will go in the ROW. I had spoke with Dan about making sure when they get ready for the approach they have it dug out enough to have 4" of compacted gravel and enough room for 8" of concrete. I also spoke with John from the concrete company on the phone earlier about the concerns that I had with what I saw on site earlier in the morning.
Driveway Inspection Partial 2/14/2018 at 10:54 AM 02/14/2018
PW-Misc
Corrective Action Required
02/14/2018
Matt Munger 02/14/2018 11:08 AM I observed loose material and advised Sheldon to have the workers compact the material. I also informed him to make sure they use KCMMB 4k mix and use the white cure after the concrete approach is poured. I measured the stakes that they had in place to ensure there would be a minimum of 8" of concrete in place. I also advised them to remove any chunks of dirt.
Erosion Control Inspection Failed 2/14/2018 at 11:10 AM 02/14/2018
PW-Misc
Informational
02/08/2018
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
02/08/2018
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
PW-Misc
Informational
02/08/2018
Matt Munger 12/05/2017 9:21 AM I observed an ESC Device in place with two cinder blocks between the device and inlet on the CI that I had asked Sheldon to take care of. I spoke with Sheldon while he was on site and he stated the Utilities Contractor will possibly start next week.
PW-Misc
Informational
02/08/2018
Matt Munger 12/11/2017 10:00 AM No workers were present, ESC devices and silt fence were in place. Emailed Sheldon about the project and if there was anything that he needed from me since I had not seen anyone out at the site.
PW-Misc
Informational
02/08/2018
Matt Munger 12/19/2017 10:10 AM Construction Entrance was in place, large Rip Rap was used. Workers were removing dirt from property.
PW-Devices for Erosion and Sediment Control
Informational
02/08/2018
Matt Munger 12/20/2017 10:21 AM There are problems with the erosion control devices on your site. The silt fence on the south west side of the property has a section that is not secure due to the excavation work being done and in no longer trenched in properly. I spoke with the worker and just asked that he be mindful of the fence to ensure that it remains in place.
PW-Erosion and Sediment Control
Corrective Action Required
02/08/2018
Matt Munger 12/21/2017 2:52 PM Your project is in violation of the Erosion and Sediment control policy. There needs to be a silt fence along section of property that is adjacent to MO-150. After discussing schedules earlier in the day Sheldon stated he would get the silt fence up along the section of property adjacent to MO-150.
PW-Misc
Informational
02/08/2018
Matt Munger 01/02/2018 10:57 AM I walked along the silt fence and observed the silt fence was staked and in place. Will need to keep an eye on the staples that are securing the fence to the stakes to ensure the fence does not pull away and sag.
PW-Erosion and Sediment Control
Corrective Action Required
02/08/2018
Matt Munger 01/09/2018 11:28 AM I observed gravel and mud on the roadway from the construction entrance. The construction entrance has small gravel that has been poured over the top of the Rip Rap that was put in initially and will need to be replaced with larger Rip Rap to not track onto the street as construction vehicles leave the site.
PW-Erosion and Sediment Control
Corrective Action Required
02/08/2018
Matt Munger 01/09/2018 2:15 PM I had emailed Sheldon an inspection report and left a message earlier in the day informing him about the condition of the road and construction entrance. I had received a text message from Sheldon at 12:46 pm stating they would get the entrance taken care of. As I had arrived on site at 2:15 pm I observed gravel in the roadway. They had cleaned some of the gravel off the street but there was still gravel scattered up and down the road. The construction will also need to have the 3/4" gravel that was put on top of the Rip Rap removed to prevent this issue. I had spoke with Sheldon and his father in regards to the issue and informed them that they need to keep the roadway clean. If the roadway is not kept clean a Stop Work Order can be issued. I emailed Sheldon after our conversation on site in regards to the situation and let him know that the Inspector that was with me had also pointed out the construction entrance needs to be extended (total length should be 50ft). In my email I informed Sheldon that I would like to see the entrance in compliance by the end of day tomorrow (1/10/18).
PW-Misc
Informational
02/08/2018
Matt Munger 01/10/2018 2:00 PM The construction entrance had been lengthened and large riprap was in place. The gravel in the roadway from the day prior was cleaned up.
PW-Misc
Informational
02/08/2018
Matt Munger 01/22/2018 11:25 AM Silt fence and ESC devices were in place.
PW-Devices for Erosion and Sediment Control
Informational
02/08/2018
Matt Munger 01/30/2018 10:57 AM Street was clean, ESC devices were in place. The silt fence on the south side will need some minor adjustments to keep the fence from sagging.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/08/2018
Matt Munger 01/31/2018 11:00 AM The silt fence on along SW Lemans Rd. has started to fall down and will need to be pulled up.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/08/2018
Matt Munger 02/08/2018 10:46 AM Silt fence on the south side needs to be pulled back up and secured to the stakes. I spoke with Sheldong in regards to the concern and he stated he would get it taken care of.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/14/2018
Matt Munger 02/14/2018 11:14 AM Silt fence is down on the SW corner of the property. I informed Sheldon of the correction needed.
Commercial Curb Inspection Partial 2/14/2018 at 10:54 AM 02/14/2018
Informational
02/14/2018
Matt Munger 02/14/2018 11:06 AM I observed workers grouting the back of the curbs.
Driveway Inspection Partial 2/14/2018 at 3:05 PM 02/14/2018
PW-Misc
Corrective Action Required
02/14/2018
Matt Munger 02/14/2018 11:08 AM I observed loose material and advised Sheldon to have the workers compact the material. I also informed him to make sure they use KCMMB 4k mix and use the white cure after the concrete approach is poured. I measured the stakes that they had in place to ensure there would be a minimum of 8" of concrete in place. I also advised them to remove any chunks of dirt.
PW-Misc
Informational
02/14/2018
Matt Munger 02/14/2018 3:19 PM Took a snap of the concrete ticket (KCMMB 4K). Asked Dan to make sure they put blankets over the existing approach that they had poured today. I did observe them spray white cure on the newly poured driveway approach. The approach area that they cut out to put in the ADA had enough material but needed to be compacted. I also asked that they cut the curb straight. They stated they would be pouring in the morning.
Driveway Inspection Partial 2/15/2018 at 8:30 AM 02/15/2018
PW-Misc
Corrective Action Required
02/14/2018
Matt Munger 02/14/2018 11:08 AM I observed loose material and advised Sheldon to have the workers compact the material. I also informed him to make sure they use KCMMB 4k mix and use the white cure after the concrete approach is poured. I measured the stakes that they had in place to ensure there would be a minimum of 8" of concrete in place. I also advised them to remove any chunks of dirt.
PW-Misc
Informational
02/14/2018
Matt Munger 02/14/2018 3:19 PM Took a snap of the concrete ticket (KCMMB 4K). Asked Dan to make sure they put blankets over the existing approach that they had poured today. I did observe them spray white cure on the newly poured driveway approach. The approach area that they cut out to put in the ADA had enough material but needed to be compacted. I also asked that they cut the curb straight. They stated they would be pouring in the morning.
PW-Misc
Informational
02/15/2018
Matt Munger 02/15/2018 8:30 AM I observed smooth dowels in place in the curbs for the SW driveway approach that was cut out to allo ADA compliance with the sidewalk. The material they had in place was loose and I had asked that they compact the material.
Sidewalk Inspection Partial 2/15/2018 at 11:15 AM 02/15/2018
PW-Misc
Informational
02/15/2018
Matt Munger 02/15/2018 11:15 AM Bob B. and I went out to do a pre-pour inspection. I observed adequate amount of aggregate base that was compacted. Forms were set to acheive 2% or less.
Sidewalk Inspection Partial 2/16/2018 at 8:56 AM 02/16/2018
PW-Misc
Informational
02/15/2018
Matt Munger 02/15/2018 11:15 AM Bob B. and I went out to do a pre-pour inspection. I observed adequate amount of aggregate base that was compacted. Forms were set to acheive 2% or less.
PW-Misc
Informational
02/16/2018
Matt Munger 02/16/2018 9:03 AM Sidewalk and driveway approaches were covered with blankets.
Miscellaneous PWORKS Inspection Partial 2/19/2018 at 7:50 AM 02/19/2018
Informational
02/19/2018
Matt Munger 02/19/2018 9:23 AM Prior to the proof roll I did advise Sheldon (GC) about the rain that is expected possibly mid morning. I explained to him my concerns about the temps of the asphalt if the rain does come through. I observed APWA Type 1 base asphalt being installed for the parking lot. I took temperatures of the asphalt as it was being loaded in the machine and when they were rolling the asphalt out. I observed the crew using a roller machine with the vibratory steel wheel on each pass and I did observe them checking the depth (under 4"). The curb faces were tack coated prior to the base asphalt being installed. Weather was cloudy and 61º F with a few sprinkles that started around 11:04 AM but stopped shorlty after, then again 11:50 AM but stopped shortly after. - Base asphalt roll temps ranged from 194º F to 271º F - Load #1 308º F - Load #11 298º F - Load #2 300º F - Load #12 271º F - Load #3 300º F - Load #13 258º F - Load #4 274º F - Load #14 240º F - Load #5 304º F - Load #15 264º F - Load #6 300º F - Load #16 286º F - Load #7 272º F - Load #8 281º F - Load #9 267º F - Load #10 280º F
Proof roll parking lot Passed 2/19/2018 at 7:50 AM 02/19/2018
Informational
02/19/2018
Matt Munger 02/19/2018 9:14 AM The Contractors used a tandem axle dump truck full of material to do the proof roll. There was minimal deflection in the AB3 base material, it was compacted very well. After the proof roll was performed they went over the AB3 base material again with a roller. There was a little bit of moisture in the AB3 material and I informed Sheldon of my concerns with the material but the proof roll proved the material was compacted very well.
Erosion Control Inspection Failed 2/19/2018 at 11:15 AM 02/19/2018
PW-Misc
Informational
02/14/2018
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
02/14/2018
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
PW-Misc
Informational
02/14/2018
Matt Munger 12/05/2017 9:21 AM I observed an ESC Device in place with two cinder blocks between the device and inlet on the CI that I had asked Sheldon to take care of. I spoke with Sheldon while he was on site and he stated the Utilities Contractor will possibly start next week.
PW-Misc
Informational
02/14/2018
Matt Munger 12/11/2017 10:00 AM No workers were present, ESC devices and silt fence were in place. Emailed Sheldon about the project and if there was anything that he needed from me since I had not seen anyone out at the site.
PW-Misc
Informational
02/14/2018
Matt Munger 12/19/2017 10:10 AM Construction Entrance was in place, large Rip Rap was used. Workers were removing dirt from property.
PW-Devices for Erosion and Sediment Control
Informational
02/14/2018
Matt Munger 12/20/2017 10:21 AM There are problems with the erosion control devices on your site. The silt fence on the south west side of the property has a section that is not secure due to the excavation work being done and in no longer trenched in properly. I spoke with the worker and just asked that he be mindful of the fence to ensure that it remains in place.
PW-Erosion and Sediment Control
Corrective Action Required
02/14/2018
Matt Munger 12/21/2017 2:52 PM Your project is in violation of the Erosion and Sediment control policy. There needs to be a silt fence along section of property that is adjacent to MO-150. After discussing schedules earlier in the day Sheldon stated he would get the silt fence up along the section of property adjacent to MO-150.
PW-Misc
Informational
02/14/2018
Matt Munger 01/02/2018 10:57 AM I walked along the silt fence and observed the silt fence was staked and in place. Will need to keep an eye on the staples that are securing the fence to the stakes to ensure the fence does not pull away and sag.
PW-Erosion and Sediment Control
Corrective Action Required
02/14/2018
Matt Munger 01/09/2018 11:28 AM I observed gravel and mud on the roadway from the construction entrance. The construction entrance has small gravel that has been poured over the top of the Rip Rap that was put in initially and will need to be replaced with larger Rip Rap to not track onto the street as construction vehicles leave the site.
PW-Erosion and Sediment Control
Corrective Action Required
02/14/2018
Matt Munger 01/09/2018 2:15 PM I had emailed Sheldon an inspection report and left a message earlier in the day informing him about the condition of the road and construction entrance. I had received a text message from Sheldon at 12:46 pm stating they would get the entrance taken care of. As I had arrived on site at 2:15 pm I observed gravel in the roadway. They had cleaned some of the gravel off the street but there was still gravel scattered up and down the road. The construction will also need to have the 3/4" gravel that was put on top of the Rip Rap removed to prevent this issue. I had spoke with Sheldon and his father in regards to the issue and informed them that they need to keep the roadway clean. If the roadway is not kept clean a Stop Work Order can be issued. I emailed Sheldon after our conversation on site in regards to the situation and let him know that the Inspector that was with me had also pointed out the construction entrance needs to be extended (total length should be 50ft). In my email I informed Sheldon that I would like to see the entrance in compliance by the end of day tomorrow (1/10/18).
PW-Misc
Informational
02/14/2018
Matt Munger 01/10/2018 2:00 PM The construction entrance had been lengthened and large riprap was in place. The gravel in the roadway from the day prior was cleaned up.
PW-Misc
Informational
02/14/2018
Matt Munger 01/22/2018 11:25 AM Silt fence and ESC devices were in place.
PW-Devices for Erosion and Sediment Control
Informational
02/14/2018
Matt Munger 01/30/2018 10:57 AM Street was clean, ESC devices were in place. The silt fence on the south side will need some minor adjustments to keep the fence from sagging.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/14/2018
Matt Munger 01/31/2018 11:00 AM The silt fence on along SW Lemans Rd. has started to fall down and will need to be pulled up.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/14/2018
Matt Munger 02/08/2018 10:46 AM Silt fence on the south side needs to be pulled back up and secured to the stakes. I spoke with Sheldong in regards to the concern and he stated he would get it taken care of.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/14/2018
Matt Munger 02/14/2018 11:14 AM Silt fence is down on the SW corner of the property. I informed Sheldon of the correction needed.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/19/2018
Matt Munger 02/19/2018 11:16 AM I had talked with Sheldon on site about making sure the silt fence that is down on the SW corner gets put back up before the end of the day; since rain is expected.
Erosion Control Inspection Failed 2/20/2018 at 11:20 AM 02/20/2018
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/20/2018
Matt Munger 02/20/2018 11:20 AM The silt fence is down on the SW corner of the site. ESC is not in compliance will need to be in place at the end of day on 2/21/18 or a Stop Work Order can be issued.
Water - Material Verification Passed 02/21/2018
Erosion Control Inspection Partial 2/21/2018 at 11:16 AM 02/21/2018
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/20/2018
Matt Munger 02/20/2018 11:20 AM The silt fence is down on the SW corner of the site. ESC is not in compliance will need to be in place at the end of day on 2/21/18 or a Stop Work Order can be issued.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/21/2018
Matt Munger 02/21/2018 11:16 AM Silt fence was placed along the roadway on the south side of the site, but was not trenched in due to the ground being frozen. Silt has not left the site yet but ESC does need to be in place to prevent that from happening. I had pointed out to Sheldon my concerns with the SW corner and the north side of the west entrance (Commerce Bank side) that I pointed out to Sheldon and recommended using straw waddles in the areas of concern. Sheldon stated he would monitor the ESC and get it taken care of.
Sidewalk Inspection Partial 2/22/2018 at 2:05 PM 02/22/2018
PW-Misc
Informational
02/16/2018
Matt Munger 02/15/2018 11:15 AM Bob B. and I went out to do a pre-pour inspection. I observed adequate amount of aggregate base that was compacted. Forms were set to acheive 2% or less.
PW-Misc
Informational
02/16/2018
Matt Munger 02/16/2018 9:03 AM Sidewalk and driveway approaches were covered with blankets.
Sidewalk Inspection Failed 2/23/2018 at 8:40 AM 02/23/2018
PW-Misc
Informational
02/22/2018
Matt Munger 02/15/2018 11:15 AM Bob B. and I went out to do a pre-pour inspection. I observed adequate amount of aggregate base that was compacted. Forms were set to acheive 2% or less.
PW-Misc
Informational
02/22/2018
Matt Munger 02/16/2018 9:03 AM Sidewalk and driveway approaches were covered with blankets.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
02/23/2018
Matt Munger 02/23/2018 9:46 AM The sidewalk does not meet ADA guidelines. There is a panel that exceeds 8.33% ramp slope and (street slope is lower as well) and the sidewalk within the transition area is under 5 ft. The City requires sidewalks to be 5ft wide.
Sidewalk Inspection Partial 2/23/2018 at 10:10 AM 02/23/2018
PW-Misc
Informational
02/23/2018
Matt Munger 02/15/2018 11:15 AM Bob B. and I went out to do a pre-pour inspection. I observed adequate amount of aggregate base that was compacted. Forms were set to acheive 2% or less.
PW-Misc
Informational
02/23/2018
Matt Munger 02/16/2018 9:03 AM Sidewalk and driveway approaches were covered with blankets.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
02/23/2018
Matt Munger 02/23/2018 9:46 AM The sidewalk does not meet ADA guidelines. There is a panel that exceeds 8.33% ramp slope and (street slope is lower as well) and the sidewalk within the transition area is under 5 ft. The City requires sidewalks to be 5ft wide.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
02/23/2018
Matt Munger 02/23/2018 10:10 AM The sidewalk does not meet ADA guidelines. I spoke with Mr. Bouwens and pointed out the issues with the slope % and area that was not 5ft in width. He said he would get it taken care of.
Erosion Control Inspection Failed 2/23/2018 at 10:10 AM 02/23/2018
PW-Misc
Informational
02/19/2018
Matt Munger 11/30/2017 2:19 PM Silt fence was put in place along the south and west sides of the site. I spoke with Sheldon about the notes for the PVC pipe in the plans and advised that any materials that are going to be ordered will need to be compliant with what is required in the LS D&C. I told Sheldon I would speak with his Utilities Sub-Contractor when that time comes and go over any details.
PW-Misc
Informational
02/19/2018
Matt Munger 12/04/2017 12:58 PM No workers were present, silt fence was in place. There needs to be an ESC Device in place for the curb inlet on SW Lemans Lane before the Commmerce Bank entrance. I spoke with Sheldon about getting one in place and he stated he would have someone take care of it.
PW-Misc
Informational
02/19/2018
Matt Munger 12/19/2017 10:10 AM Construction Entrance was in place, large Rip Rap was used. Workers were removing dirt from property.
PW-Devices for Erosion and Sediment Control
Informational
02/19/2018
Matt Munger 12/20/2017 10:21 AM There are problems with the erosion control devices on your site. The silt fence on the south west side of the property has a section that is not secure due to the excavation work being done and in no longer trenched in properly. I spoke with the worker and just asked that he be mindful of the fence to ensure that it remains in place.
PW-Erosion and Sediment Control
Corrective Action Required
02/19/2018
Matt Munger 12/21/2017 2:52 PM Your project is in violation of the Erosion and Sediment control policy. There needs to be a silt fence along section of property that is adjacent to MO-150. After discussing schedules earlier in the day Sheldon stated he would get the silt fence up along the section of property adjacent to MO-150.
PW-Misc
Informational
02/19/2018
Matt Munger 01/02/2018 10:57 AM I walked along the silt fence and observed the silt fence was staked and in place. Will need to keep an eye on the staples that are securing the fence to the stakes to ensure the fence does not pull away and sag.
PW-Erosion and Sediment Control
Corrective Action Required
02/19/2018
Matt Munger 01/09/2018 11:28 AM I observed gravel and mud on the roadway from the construction entrance. The construction entrance has small gravel that has been poured over the top of the Rip Rap that was put in initially and will need to be replaced with larger Rip Rap to not track onto the street as construction vehicles leave the site.
PW-Erosion and Sediment Control
Corrective Action Required
02/19/2018
Matt Munger 01/09/2018 2:15 PM I had emailed Sheldon an inspection report and left a message earlier in the day informing him about the condition of the road and construction entrance. I had received a text message from Sheldon at 12:46 pm stating they would get the entrance taken care of. As I had arrived on site at 2:15 pm I observed gravel in the roadway. They had cleaned some of the gravel off the street but there was still gravel scattered up and down the road. The construction will also need to have the 3/4" gravel that was put on top of the Rip Rap removed to prevent this issue. I had spoke with Sheldon and his father in regards to the issue and informed them that they need to keep the roadway clean. If the roadway is not kept clean a Stop Work Order can be issued. I emailed Sheldon after our conversation on site in regards to the situation and let him know that the Inspector that was with me had also pointed out the construction entrance needs to be extended (total length should be 50ft). In my email I informed Sheldon that I would like to see the entrance in compliance by the end of day tomorrow (1/10/18).
PW-Misc
Informational
02/19/2018
Matt Munger 01/10/2018 2:00 PM The construction entrance had been lengthened and large riprap was in place. The gravel in the roadway from the day prior was cleaned up.
PW-Misc
Informational
02/19/2018
Matt Munger 01/22/2018 11:25 AM Silt fence and ESC devices were in place.
PW-Devices for Erosion and Sediment Control
Informational
02/19/2018
Matt Munger 01/30/2018 10:57 AM Street was clean, ESC devices were in place. The silt fence on the south side will need some minor adjustments to keep the fence from sagging.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/19/2018
Matt Munger 01/31/2018 11:00 AM The silt fence on along SW Lemans Rd. has started to fall down and will need to be pulled up.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/19/2018
Matt Munger 02/08/2018 10:46 AM Silt fence on the south side needs to be pulled back up and secured to the stakes. I spoke with Sheldong in regards to the concern and he stated he would get it taken care of.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/19/2018
Matt Munger 02/14/2018 11:14 AM Silt fence is down on the SW corner of the property. I informed Sheldon of the correction needed.
PW-Misc
Informational
02/19/2018
Matt Munger 12/05/2017 9:21 AM I observed an ESC Device in place with two cinder blocks between the device and inlet on the CI that I had asked Sheldon to take care of. I spoke with Sheldon while he was on site and he stated the Utilities Contractor will possibly start next week.
PW-Misc
Informational
02/19/2018
Matt Munger 12/11/2017 10:00 AM No workers were present, ESC devices and silt fence were in place. Emailed Sheldon about the project and if there was anything that he needed from me since I had not seen anyone out at the site.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/19/2018
Matt Munger 02/19/2018 11:16 AM I had talked with Sheldon on site about making sure the silt fence that is down on the SW corner gets put back up before the end of the day; since rain is expected.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/23/2018
Matt Munger 02/23/2018 10:10 AM Spoke with Mr. Bowen's on site about the issues that I had explained to Sheldon and informed that he could use straw waddles in lieu of silt fence. The silt fence had fallen down again on the SW side of the property. Mr. Bowen stated they were working on the landscaping next week and would need to move the silt fence anyway.
Site Visit Partial 2/26/2018 at 9:10 AM 02/26/2018
PW-Misc
Informational
02/07/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
02/07/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
02/07/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
02/07/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
02/07/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
02/07/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
02/07/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
02/07/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
02/07/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
02/07/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
02/07/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
02/07/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
02/07/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
02/07/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
02/07/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
02/07/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
02/07/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
PW-Misc
Informational
02/07/2018
Matt Munger 01/12/2018 1:57 PM No utility work was being done due to the weather. Street was clean and the erosion control was in place. Sheldon had emailed earlier in the day informing me that they would be digging the storm sewer on Tuesday. I informed Sheldon when they backfill frozen material is not allowed back in the trench. Just wanted to remind him since the temps have dropped (below freezing) and will stay that way into Tuesday of next week.
PW-Misc
Informational
02/07/2018
Matt Munger 01/16/2018 10:55 AM No workers were present due to the weather. Sheldon had emailed me on Friday stating they would be working today on the storm sewer and I had informed him that since the weather has been so cold frozen backfill material would not be acceptable.
PW-Misc
Informational
02/07/2018
Matt Munger 01/17/2018 11:00 AM No utility work was being done due to the weather.
PW-Misc
Informational
02/07/2018
Matt Munger 01/23/2018 2:57 PM Workers were working on the building. No other infrastructure work was being done.
PW-Misc
Informational
02/07/2018
Matt Munger 01/29/2018 9:53 AM Spoke with Mr. Bouwens as he was cleaning loose dirt off the street. Workers were grading out the pavement areas and that they were going to be putting down geogrid instead of fly ash. He said they would start working on the curb Wednesday. I discussed putting the geogrid a foot past the curb as well.
PW-Misc
Informational
02/07/2018
Matt Munger 01/30/2018 11:00 AM Workers had cut out the area where pavement and curb is going to be put it. I had emailed Sheldon on 1/29/18 informing to get with me when they were ready for the proof roll for the curbs. They decided to use geogrid instead of fly ash.
PW-Misc
Informational
02/07/2018
Matt Munger 02/05/2018 9:15 AM No work was being done on site.
PW-Misc
Informational
02/07/2018
Matt Munger 02/07/2018 9:38 AM No workers were present.
Erosion Control Inspection Failed 2/28/2018 at 1:40 PM 02/28/2018
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/28/2018
Matt Munger 02/28/2018 3:36 PM ESC was not in place due to the grading that was being done. I asked Sheldon to put up straw waddles since we are expecting rain overnight into the moring.I also advised him to place a gutter device in the curb inlet on the private side. He said he would take care of the ESC issues.
Erosion Control Inspection Partial 3/1/2018 at 9:50 AM 03/01/2018
PW-Devices for Erosion and Sediment Control
Informational
03/01/2018
Matt Munger 02/28/2018 3:36 PM ESC was not in place due to the grading that was being done. I asked Sheldon to put up straw waddles since we are expecting rain overnight into the moring.I also advised him to place a gutter device in the curb inlet on the private side. He said he would take care of the ESC issues.
PW-Devices for Erosion and Sediment Control
Informational
03/01/2018
Matt Munger 03/01/2018 9:59 AM Straw wattles were set in place at the down side of the hill. Irrigation was going to be going in.
Sidewalk Inspection Partial 3/1/2018 at 10:00 AM 03/01/2018
PW-Misc
Informational
02/23/2018
Matt Munger 02/15/2018 11:15 AM Bob B. and I went out to do a pre-pour inspection. I observed adequate amount of aggregate base that was compacted. Forms were set to acheive 2% or less.
PW-Misc
Informational
02/23/2018
Matt Munger 02/16/2018 9:03 AM Sidewalk and driveway approaches were covered with blankets.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
02/23/2018
Matt Munger 02/23/2018 9:46 AM The sidewalk does not meet ADA guidelines. There is a panel that exceeds 8.33% ramp slope and (street slope is lower as well) and the sidewalk within the transition area is under 5 ft. The City requires sidewalks to be 5ft wide.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
02/23/2018
Matt Munger 02/23/2018 10:10 AM The sidewalk does not meet ADA guidelines. I spoke with Mr. Bouwens and pointed out the issues with the slope % and area that was not 5ft in width. He said he would get it taken care of.
PW-Misc
Informational
03/01/2018
Matt Munger 03/01/2018 10:16 AM I put my level on the forms on the sections of sidewalk that I had the contractor tear out. The continuous slope was less than 8.33% and the cross slope was within ADA specs. I told them to mindful when they finish to make sure they are under 2% cross slope.
Water - Material Verification Passed 03/01/2018
Storm - Pipe Passed 03/01/2018
Sidewalk Inspection Partial 3/1/2018 at 11:40 AM 03/01/2018
PW-Misc
Informational
03/01/2018
Matt Munger 02/15/2018 11:15 AM Bob B. and I went out to do a pre-pour inspection. I observed adequate amount of aggregate base that was compacted. Forms were set to acheive 2% or less.
PW-Misc
Informational
03/01/2018
Matt Munger 02/16/2018 9:03 AM Sidewalk and driveway approaches were covered with blankets.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
03/01/2018
Matt Munger 02/23/2018 9:46 AM The sidewalk does not meet ADA guidelines. There is a panel that exceeds 8.33% ramp slope and (street slope is lower as well) and the sidewalk within the transition area is under 5 ft. The City requires sidewalks to be 5ft wide.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
03/01/2018
Matt Munger 02/23/2018 10:10 AM The sidewalk does not meet ADA guidelines. I spoke with Mr. Bouwens and pointed out the issues with the slope % and area that was not 5ft in width. He said he would get it taken care of.
PW-Misc
Informational
03/01/2018
Matt Munger 03/01/2018 10:16 AM I put my level on the forms on the sections of sidewalk that I had the contractor tear out. The continuous slope was less than 8.33% and the cross slope was within ADA specs. I told them to mindful when they finish to make sure they are under 2% cross slope.
PW-Misc
Corrective Action Required
03/01/2018
Matt Munger 03/01/2018 11:52 AM I had a concern with how curb area was cut out so I spoke with Bob (ROW Inspector) to seek additional clarification in regards to the small section of curb that was cut out to widen the entry to ensure the sidewalk was 5ft rather then the 4ft that was in place prior to the tear out. I contacted Sheldon to let him know the concern and that they need to tear out more of the curb and not just that small section. They are going to tear out the portion of the curb to ensure the sidewalk is 5ft.
Site Visit Partial 3/1/2018 at 1:28 PM 03/01/2018
PW-Misc
Informational
02/26/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
02/26/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
02/26/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
02/26/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
02/26/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
02/26/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
02/26/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
02/26/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
02/26/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
02/26/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
02/26/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
02/26/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
02/26/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
02/26/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
02/26/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
02/26/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
02/26/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
PW-Misc
Informational
02/26/2018
Matt Munger 01/12/2018 1:57 PM No utility work was being done due to the weather. Street was clean and the erosion control was in place. Sheldon had emailed earlier in the day informing me that they would be digging the storm sewer on Tuesday. I informed Sheldon when they backfill frozen material is not allowed back in the trench. Just wanted to remind him since the temps have dropped (below freezing) and will stay that way into Tuesday of next week.
PW-Misc
Informational
02/26/2018
Matt Munger 01/16/2018 10:55 AM No workers were present due to the weather. Sheldon had emailed me on Friday stating they would be working today on the storm sewer and I had informed him that since the weather has been so cold frozen backfill material would not be acceptable.
PW-Misc
Informational
02/26/2018
Matt Munger 01/17/2018 11:00 AM No utility work was being done due to the weather.
PW-Misc
Informational
02/26/2018
Matt Munger 01/23/2018 2:57 PM Workers were working on the building. No other infrastructure work was being done.
PW-Misc
Informational
02/26/2018
Matt Munger 01/29/2018 9:53 AM Spoke with Mr. Bouwens as he was cleaning loose dirt off the street. Workers were grading out the pavement areas and that they were going to be putting down geogrid instead of fly ash. He said they would start working on the curb Wednesday. I discussed putting the geogrid a foot past the curb as well.
PW-Misc
Informational
02/26/2018
Matt Munger 01/30/2018 11:00 AM Workers had cut out the area where pavement and curb is going to be put it. I had emailed Sheldon on 1/29/18 informing to get with me when they were ready for the proof roll for the curbs. They decided to use geogrid instead of fly ash.
PW-Misc
Informational
02/26/2018
Matt Munger 02/05/2018 9:15 AM No work was being done on site.
PW-Misc
Informational
02/26/2018
Matt Munger 02/07/2018 9:38 AM No workers were present.
PW-Misc
Informational
03/01/2018
Matt Munger 03/01/2018 2:09 PM Looked over the site with Jon H. and put together a list of items that will need to be done before substantial can be given.
Miscellaneous PWORKS Inspection Partial 3/2/2018 at 7:55 AM 03/02/2018
PW-Misc
Informational
03/02/2018
Matt Munger 03/02/2018 7:55 AM When I arrived the asphalt crew was cleaning the debris off the base layer and had started to put on the tack coat.
Miscellaneous PWORKS Inspection Partial 3/2/2018 at 9:27 AM 03/02/2018
PW-Misc
Informational
03/02/2018
Matt Munger 03/02/2018 7:55 AM When I arrived the asphalt crew was cleaning the debris off the base layer and had started to put on the tack coat.
PW-Misc
Informational
03/02/2018
Matt Munger 03/02/2018 11:05 AM I observed the temps of the asphalt going into the machine and the roll temps. The temps for the material going into the machine ranged from 252 degrees to 283 degrees. The roll temps ranged from 179 degrees to 248 degrees. The base layer was tac coated prior to the aspahlt getting put in. They did use the vibratory roller machine over the surface layer.
Sidewalk Inspection Failed 3/2/2018 at 11:20 AM 03/02/2018
PW-Misc
Informational
03/01/2018
Matt Munger 02/15/2018 11:15 AM Bob B. and I went out to do a pre-pour inspection. I observed adequate amount of aggregate base that was compacted. Forms were set to acheive 2% or less.
PW-Misc
Informational
03/01/2018
Matt Munger 02/16/2018 9:03 AM Sidewalk and driveway approaches were covered with blankets.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
03/01/2018
Matt Munger 02/23/2018 9:46 AM The sidewalk does not meet ADA guidelines. There is a panel that exceeds 8.33% ramp slope and (street slope is lower as well) and the sidewalk within the transition area is under 5 ft. The City requires sidewalks to be 5ft wide.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
03/01/2018
Matt Munger 02/23/2018 10:10 AM The sidewalk does not meet ADA guidelines. I spoke with Mr. Bouwens and pointed out the issues with the slope % and area that was not 5ft in width. He said he would get it taken care of.
PW-Misc
Informational
03/01/2018
Matt Munger 03/01/2018 10:16 AM I put my level on the forms on the sections of sidewalk that I had the contractor tear out. The continuous slope was less than 8.33% and the cross slope was within ADA specs. I told them to mindful when they finish to make sure they are under 2% cross slope.
PW-Misc
Corrective Action Required
03/01/2018
Matt Munger 03/01/2018 11:52 AM I had a concern with how curb area was cut out so I spoke with Bob (ROW Inspector) to seek additional clarification in regards to the small section of curb that was cut out to widen the entry to ensure the sidewalk was 5ft rather then the 4ft that was in place prior to the tear out. I contacted Sheldon to let him know the concern and that they need to tear out more of the curb and not just that small section. They are going to tear out the portion of the curb to ensure the sidewalk is 5ft.
PW-Curb ramp is out of compliance
Corrective Action Required
03/02/2018
Matt Munger 03/02/2018 11:42 AM The curb ramp does not meet specs. I spoke with Sheldon on site to show him the issue. There another area on the sidewalk that had been gouged with equipment and will need to be replaced.
Miscellaneous PWORKS Inspection Partial 3/2/2018 at 2:05 PM 03/02/2018
PW-Misc
Informational
03/02/2018
Matt Munger 03/02/2018 7:55 AM When I arrived the asphalt crew was cleaning the debris off the base layer and had started to put on the tack coat.
PW-Misc
Informational
03/02/2018
Matt Munger 03/02/2018 11:05 AM I observed the temps of the asphalt going into the machine and the roll temps. The temps for the material going into the machine ranged from 252 degrees to 283 degrees. The roll temps ranged from 179 degrees to 248 degrees. The base layer was tac coated prior to the aspahlt getting put in. They did use the vibratory roller machine over the surface layer.
PW-Misc
Informational
03/02/2018
Matt Munger 03/02/2018 2:17 PM The asphalt crew was working on the striping the parking stalls, etc. They didn't install the temporary asphalt curb on the east side of the site but will put it in next week.
Site Visit Partial 3/5/2018 at 2:45 PM 03/05/2018
PW-Misc
Informational
03/01/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
03/01/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
03/01/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
03/01/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
03/01/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
03/01/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
03/01/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
03/01/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
03/01/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
03/01/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
03/01/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
03/01/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
03/01/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
03/01/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
03/01/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
03/01/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
03/01/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
PW-Misc
Informational
03/01/2018
Matt Munger 01/12/2018 1:57 PM No utility work was being done due to the weather. Street was clean and the erosion control was in place. Sheldon had emailed earlier in the day informing me that they would be digging the storm sewer on Tuesday. I informed Sheldon when they backfill frozen material is not allowed back in the trench. Just wanted to remind him since the temps have dropped (below freezing) and will stay that way into Tuesday of next week.
PW-Misc
Informational
03/01/2018
Matt Munger 01/16/2018 10:55 AM No workers were present due to the weather. Sheldon had emailed me on Friday stating they would be working today on the storm sewer and I had informed him that since the weather has been so cold frozen backfill material would not be acceptable.
PW-Misc
Informational
03/01/2018
Matt Munger 01/17/2018 11:00 AM No utility work was being done due to the weather.
PW-Misc
Informational
03/01/2018
Matt Munger 01/23/2018 2:57 PM Workers were working on the building. No other infrastructure work was being done.
PW-Misc
Informational
03/01/2018
Matt Munger 01/29/2018 9:53 AM Spoke with Mr. Bouwens as he was cleaning loose dirt off the street. Workers were grading out the pavement areas and that they were going to be putting down geogrid instead of fly ash. He said they would start working on the curb Wednesday. I discussed putting the geogrid a foot past the curb as well.
PW-Misc
Informational
03/01/2018
Matt Munger 01/30/2018 11:00 AM Workers had cut out the area where pavement and curb is going to be put it. I had emailed Sheldon on 1/29/18 informing to get with me when they were ready for the proof roll for the curbs. They decided to use geogrid instead of fly ash.
PW-Misc
Informational
03/01/2018
Matt Munger 02/05/2018 9:15 AM No work was being done on site.
PW-Misc
Informational
03/01/2018
Matt Munger 02/07/2018 9:38 AM No workers were present.
PW-Misc
Informational
03/01/2018
Matt Munger 03/01/2018 2:09 PM Looked over the site with Jon H. and put together a list of items that will need to be done before substantial can be given.
PW-Misc
Informational
03/05/2018
Matt Munger 03/05/2018 2:47 PM The landscape company was working on the irrigation system. The spoil piles have not been hauled off site.
Miscellaneous PWORKS Inspection Failed 3/6/2018 at 10:10 AM 03/06/2018
PW-Misc
Informational
03/02/2018
Matt Munger 03/02/2018 7:55 AM When I arrived the asphalt crew was cleaning the debris off the base layer and had started to put on the tack coat.
PW-Misc
Informational
03/02/2018
Matt Munger 03/02/2018 11:05 AM I observed the temps of the asphalt going into the machine and the roll temps. The temps for the material going into the machine ranged from 252 degrees to 283 degrees. The roll temps ranged from 179 degrees to 248 degrees. The base layer was tac coated prior to the aspahlt getting put in. They did use the vibratory roller machine over the surface layer.
PW-Misc
Informational
03/02/2018
Matt Munger 03/02/2018 2:17 PM The asphalt crew was working on the striping the parking stalls, etc. They didn't install the temporary asphalt curb on the east side of the site but will put it in next week.
Corrective Action Required
03/06/2018
Matt Munger 03/06/2018 10:17 AM As I arrived the O'donnell Way Aasphalt Company all but 2-3ft of the asphalt curb formed on the SE corner closest to the SE driveway approach. I took temperatures of the asphalt and the curb was 88 degrees and the asphalt material in the skid steer bucket prior to pouring into their form machine was at 112 degrees. After I had spoke with the workers about the concern they took a propane torch to try and heat up the material before they put it into the curb form machine. After they heated up the material for the remainder of the 2-3 ft of curb closest to the SE driveway approach, I took a temp and it was 174 degrees. After they had put the asphalt through the machine the asphalt did not form smoothly. I do not feel the work that was performed is satisfactory. I told the workers they may need to redo the work.
Site Visit Partial 3/6/2018 at 1:05 PM 03/06/2018
PW-Misc
Informational
03/05/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
03/05/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
03/05/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
03/05/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
03/05/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
03/05/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
03/05/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
03/05/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
03/05/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
03/05/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
03/05/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
03/05/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
03/05/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
03/05/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
03/05/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
03/05/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
03/05/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
PW-Misc
Informational
03/05/2018
Matt Munger 01/12/2018 1:57 PM No utility work was being done due to the weather. Street was clean and the erosion control was in place. Sheldon had emailed earlier in the day informing me that they would be digging the storm sewer on Tuesday. I informed Sheldon when they backfill frozen material is not allowed back in the trench. Just wanted to remind him since the temps have dropped (below freezing) and will stay that way into Tuesday of next week.
PW-Misc
Informational
03/05/2018
Matt Munger 01/16/2018 10:55 AM No workers were present due to the weather. Sheldon had emailed me on Friday stating they would be working today on the storm sewer and I had informed him that since the weather has been so cold frozen backfill material would not be acceptable.
PW-Misc
Informational
03/05/2018
Matt Munger 01/17/2018 11:00 AM No utility work was being done due to the weather.
PW-Misc
Informational
03/05/2018
Matt Munger 01/23/2018 2:57 PM Workers were working on the building. No other infrastructure work was being done.
PW-Misc
Informational
03/05/2018
Matt Munger 01/29/2018 9:53 AM Spoke with Mr. Bouwens as he was cleaning loose dirt off the street. Workers were grading out the pavement areas and that they were going to be putting down geogrid instead of fly ash. He said they would start working on the curb Wednesday. I discussed putting the geogrid a foot past the curb as well.
PW-Misc
Informational
03/05/2018
Matt Munger 01/30/2018 11:00 AM Workers had cut out the area where pavement and curb is going to be put it. I had emailed Sheldon on 1/29/18 informing to get with me when they were ready for the proof roll for the curbs. They decided to use geogrid instead of fly ash.
PW-Misc
Informational
03/05/2018
Matt Munger 02/05/2018 9:15 AM No work was being done on site.
PW-Misc
Informational
03/05/2018
Matt Munger 02/07/2018 9:38 AM No workers were present.
PW-Misc
Informational
03/05/2018
Matt Munger 03/01/2018 2:09 PM Looked over the site with Jon H. and put together a list of items that will need to be done before substantial can be given.
PW-Misc
Informational
03/05/2018
Matt Munger 03/05/2018 2:47 PM The landscape company was working on the irrigation system. The spoil piles have not been hauled off site.
PW-Misc
Informational
03/06/2018
Matt Munger 03/06/2018 1:10 PM Grading work was being done on the north, north east side of the site. KC Test Lab was on site.
Sidewalk Inspection Partial 3/7/2018 at 9:00 AM 03/07/2018
PW-Misc
Informational
03/02/2018
Matt Munger 02/15/2018 11:15 AM Bob B. and I went out to do a pre-pour inspection. I observed adequate amount of aggregate base that was compacted. Forms were set to acheive 2% or less.
PW-Misc
Informational
03/02/2018
Matt Munger 02/16/2018 9:03 AM Sidewalk and driveway approaches were covered with blankets.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
03/02/2018
Matt Munger 02/23/2018 9:46 AM The sidewalk does not meet ADA guidelines. There is a panel that exceeds 8.33% ramp slope and (street slope is lower as well) and the sidewalk within the transition area is under 5 ft. The City requires sidewalks to be 5ft wide.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
03/02/2018
Matt Munger 02/23/2018 10:10 AM The sidewalk does not meet ADA guidelines. I spoke with Mr. Bouwens and pointed out the issues with the slope % and area that was not 5ft in width. He said he would get it taken care of.
PW-Misc
Informational
03/02/2018
Matt Munger 03/01/2018 10:16 AM I put my level on the forms on the sections of sidewalk that I had the contractor tear out. The continuous slope was less than 8.33% and the cross slope was within ADA specs. I told them to mindful when they finish to make sure they are under 2% cross slope.
PW-Misc
Corrective Action Required
03/02/2018
Matt Munger 03/01/2018 11:52 AM I had a concern with how curb area was cut out so I spoke with Bob (ROW Inspector) to seek additional clarification in regards to the small section of curb that was cut out to widen the entry to ensure the sidewalk was 5ft rather then the 4ft that was in place prior to the tear out. I contacted Sheldon to let him know the concern and that they need to tear out more of the curb and not just that small section. They are going to tear out the portion of the curb to ensure the sidewalk is 5ft.
PW-Curb ramp is out of compliance
Corrective Action Required
03/02/2018
Matt Munger 03/02/2018 11:42 AM The curb ramp does not meet specs. I spoke with Sheldon on site to show him the issue. There another area on the sidewalk that had been gouged with equipment and will need to be replaced.
PW-Curb ramp is out of compliance
Informational
03/07/2018
Matt Munger 03/07/2018 9:20 AM Spoke with Sheldon about my concern with the curb ramp and explained to him that I would be having another inspector come out and look at it sometime today.
Sidewalk Inspection Failed 3/7/2018 at 10:15 AM 03/07/2018
PW-Misc
Informational
03/07/2018
Matt Munger 02/15/2018 11:15 AM Bob B. and I went out to do a pre-pour inspection. I observed adequate amount of aggregate base that was compacted. Forms were set to acheive 2% or less.
PW-Misc
Informational
03/07/2018
Matt Munger 02/16/2018 9:03 AM Sidewalk and driveway approaches were covered with blankets.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
03/07/2018
Matt Munger 02/23/2018 9:46 AM The sidewalk does not meet ADA guidelines. There is a panel that exceeds 8.33% ramp slope and (street slope is lower as well) and the sidewalk within the transition area is under 5 ft. The City requires sidewalks to be 5ft wide.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
03/07/2018
Matt Munger 02/23/2018 10:10 AM The sidewalk does not meet ADA guidelines. I spoke with Mr. Bouwens and pointed out the issues with the slope % and area that was not 5ft in width. He said he would get it taken care of.
PW-Misc
Informational
03/07/2018
Matt Munger 03/01/2018 10:16 AM I put my level on the forms on the sections of sidewalk that I had the contractor tear out. The continuous slope was less than 8.33% and the cross slope was within ADA specs. I told them to mindful when they finish to make sure they are under 2% cross slope.
PW-Misc
Corrective Action Required
03/07/2018
Matt Munger 03/01/2018 11:52 AM I had a concern with how curb area was cut out so I spoke with Bob (ROW Inspector) to seek additional clarification in regards to the small section of curb that was cut out to widen the entry to ensure the sidewalk was 5ft rather then the 4ft that was in place prior to the tear out. I contacted Sheldon to let him know the concern and that they need to tear out more of the curb and not just that small section. They are going to tear out the portion of the curb to ensure the sidewalk is 5ft.
PW-Curb ramp is out of compliance
Corrective Action Required
03/07/2018
Matt Munger 03/02/2018 11:42 AM The curb ramp does not meet specs. I spoke with Sheldon on site to show him the issue. There another area on the sidewalk that had been gouged with equipment and will need to be replaced.
PW-Curb ramp is out of compliance
Informational
03/07/2018
Matt Munger 03/07/2018 9:20 AM Spoke with Sheldon about my concern with the curb ramp and explained to him that I would be having another inspector come out and look at it sometime today.
PW-Misc
Corrective Action Required
03/07/2018
Matt Munger 03/07/2018 10:45 AM Tom C. and I went out to look over the ADA ramp on the SE side of the site and there ramp is not in compliance. The driveway approach may need to be taken out to achieve compliance. I will be bringing Dan H. (Assitant Director) to look over the issues.
Sidewalk Inspection Failed 3/7/2018 at 1:00 PM 03/07/2018
PW-Misc
Informational
03/07/2018
Matt Munger 02/15/2018 11:15 AM Bob B. and I went out to do a pre-pour inspection. I observed adequate amount of aggregate base that was compacted. Forms were set to acheive 2% or less.
PW-Misc
Informational
03/07/2018
Matt Munger 02/16/2018 9:03 AM Sidewalk and driveway approaches were covered with blankets.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
03/07/2018
Matt Munger 02/23/2018 9:46 AM The sidewalk does not meet ADA guidelines. There is a panel that exceeds 8.33% ramp slope and (street slope is lower as well) and the sidewalk within the transition area is under 5 ft. The City requires sidewalks to be 5ft wide.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
03/07/2018
Matt Munger 02/23/2018 10:10 AM The sidewalk does not meet ADA guidelines. I spoke with Mr. Bouwens and pointed out the issues with the slope % and area that was not 5ft in width. He said he would get it taken care of.
PW-Misc
Informational
03/07/2018
Matt Munger 03/01/2018 10:16 AM I put my level on the forms on the sections of sidewalk that I had the contractor tear out. The continuous slope was less than 8.33% and the cross slope was within ADA specs. I told them to mindful when they finish to make sure they are under 2% cross slope.
PW-Misc
Corrective Action Required
03/07/2018
Matt Munger 03/01/2018 11:52 AM I had a concern with how curb area was cut out so I spoke with Bob (ROW Inspector) to seek additional clarification in regards to the small section of curb that was cut out to widen the entry to ensure the sidewalk was 5ft rather then the 4ft that was in place prior to the tear out. I contacted Sheldon to let him know the concern and that they need to tear out more of the curb and not just that small section. They are going to tear out the portion of the curb to ensure the sidewalk is 5ft.
PW-Curb ramp is out of compliance
Corrective Action Required
03/07/2018
Matt Munger 03/02/2018 11:42 AM The curb ramp does not meet specs. I spoke with Sheldon on site to show him the issue. There another area on the sidewalk that had been gouged with equipment and will need to be replaced.
PW-Curb ramp is out of compliance
Informational
03/07/2018
Matt Munger 03/07/2018 9:20 AM Spoke with Sheldon about my concern with the curb ramp and explained to him that I would be having another inspector come out and look at it sometime today.
PW-Misc
Corrective Action Required
03/07/2018
Matt Munger 03/07/2018 10:45 AM Tom C. and I went out to look over the ADA ramp on the SE side of the site and there ramp is not in compliance. The driveway approach may need to be taken out to achieve compliance. I will be bringing Dan H. (Assitant Director) to look over the issues.
PW-Curb ramp is out of compliance
Corrective Action Required
03/07/2018
Matt Munger 03/07/2018 1:36 PM Dan Harper and I met with Sheldon to discuss the issues with the transitional area between the driveway approach and ramp. Temp occupancy would be granted in contingency that they get the ADA issue fixed within 10 days. Dan stated he would be ok if they block off to keep people from using it until they correct the issue.
Driveway Inspection Partial 3/7/2018 at 1:00 PM 03/07/2018
PW-Misc
Corrective Action Required
02/15/2018
Matt Munger 02/14/2018 11:08 AM I observed loose material and advised Sheldon to have the workers compact the material. I also informed him to make sure they use KCMMB 4k mix and use the white cure after the concrete approach is poured. I measured the stakes that they had in place to ensure there would be a minimum of 8" of concrete in place. I also advised them to remove any chunks of dirt.
PW-Misc
Informational
02/15/2018
Matt Munger 02/14/2018 3:19 PM Took a snap of the concrete ticket (KCMMB 4K). Asked Dan to make sure they put blankets over the existing approach that they had poured today. I did observe them spray white cure on the newly poured driveway approach. The approach area that they cut out to put in the ADA had enough material but needed to be compacted. I also asked that they cut the curb straight. They stated they would be pouring in the morning.
PW-Misc
Informational
02/15/2018
Matt Munger 02/15/2018 8:30 AM I observed smooth dowels in place in the curbs for the SW driveway approach that was cut out to allo ADA compliance with the sidewalk. The material they had in place was loose and I had asked that they compact the material.
PW-Misc
Corrective Action Required
03/07/2018
Matt Munger 03/07/2018 1:45 PM Dan Harper and I met with Sheldon to discuss the issues with the transitional area between the driveway approach and ramp. A portion of the driveway approach will need to be taken out. Temp occupancy would be granted in contingency that they get the ADA issue fixed within 10 days. Dan stated he would be ok if they block off to keep people from using it until they correct the issue
Sidewalk Inspection Partial 3/9/2018 at 10:00 AM 03/09/2018
PW-Misc
Informational
03/07/2018
Matt Munger 02/15/2018 11:15 AM Bob B. and I went out to do a pre-pour inspection. I observed adequate amount of aggregate base that was compacted. Forms were set to acheive 2% or less.
PW-Misc
Informational
03/07/2018
Matt Munger 02/16/2018 9:03 AM Sidewalk and driveway approaches were covered with blankets.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
03/07/2018
Matt Munger 02/23/2018 9:46 AM The sidewalk does not meet ADA guidelines. There is a panel that exceeds 8.33% ramp slope and (street slope is lower as well) and the sidewalk within the transition area is under 5 ft. The City requires sidewalks to be 5ft wide.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
03/07/2018
Matt Munger 02/23/2018 10:10 AM The sidewalk does not meet ADA guidelines. I spoke with Mr. Bouwens and pointed out the issues with the slope % and area that was not 5ft in width. He said he would get it taken care of.
PW-Misc
Informational
03/07/2018
Matt Munger 03/01/2018 10:16 AM I put my level on the forms on the sections of sidewalk that I had the contractor tear out. The continuous slope was less than 8.33% and the cross slope was within ADA specs. I told them to mindful when they finish to make sure they are under 2% cross slope.
PW-Misc
Corrective Action Required
03/07/2018
Matt Munger 03/01/2018 11:52 AM I had a concern with how curb area was cut out so I spoke with Bob (ROW Inspector) to seek additional clarification in regards to the small section of curb that was cut out to widen the entry to ensure the sidewalk was 5ft rather then the 4ft that was in place prior to the tear out. I contacted Sheldon to let him know the concern and that they need to tear out more of the curb and not just that small section. They are going to tear out the portion of the curb to ensure the sidewalk is 5ft.
PW-Curb ramp is out of compliance
Corrective Action Required
03/07/2018
Matt Munger 03/02/2018 11:42 AM The curb ramp does not meet specs. I spoke with Sheldon on site to show him the issue. There another area on the sidewalk that had been gouged with equipment and will need to be replaced.
PW-Curb ramp is out of compliance
Informational
03/07/2018
Matt Munger 03/07/2018 9:20 AM Spoke with Sheldon about my concern with the curb ramp and explained to him that I would be having another inspector come out and look at it sometime today.
PW-Misc
Corrective Action Required
03/07/2018
Matt Munger 03/07/2018 10:45 AM Tom C. and I went out to look over the ADA ramp on the SE side of the site and there ramp is not in compliance. The driveway approach may need to be taken out to achieve compliance. I will be bringing Dan H. (Assitant Director) to look over the issues.
PW-Curb ramp is out of compliance
Corrective Action Required
03/07/2018
Matt Munger 03/07/2018 1:36 PM Dan Harper and I met with Sheldon to discuss the issues with the transitional area between the driveway approach and ramp. Temp occupancy would be granted in contingency that they get the ADA issue fixed within 10 days. Dan stated he would be ok if they block off to keep people from using it until they correct the issue.
PW-Misc
Informational
03/09/2018
Matt Munger 03/09/2018 10:30 AM Tom C. and I came out and gave the detail sheet for the ADA requirements (second time giving Dan the sheets) and put the level on what they had formed up. Dan stated he understood the requirements and was making sure his guys knew what to do. I reminded Dan to make sure to carry less than 2% cross slope in the area where they took out some of the approach.
Driveway Inspection Passed 3/12/2018 at 8:05 AM 03/12/2018
PW-Misc
Corrective Action Required
03/07/2018
Matt Munger 02/14/2018 11:08 AM I observed loose material and advised Sheldon to have the workers compact the material. I also informed him to make sure they use KCMMB 4k mix and use the white cure after the concrete approach is poured. I measured the stakes that they had in place to ensure there would be a minimum of 8" of concrete in place. I also advised them to remove any chunks of dirt.
PW-Misc
Informational
03/07/2018
Matt Munger 02/14/2018 3:19 PM Took a snap of the concrete ticket (KCMMB 4K). Asked Dan to make sure they put blankets over the existing approach that they had poured today. I did observe them spray white cure on the newly poured driveway approach. The approach area that they cut out to put in the ADA had enough material but needed to be compacted. I also asked that they cut the curb straight. They stated they would be pouring in the morning.
PW-Misc
Informational
03/07/2018
Matt Munger 02/15/2018 8:30 AM I observed smooth dowels in place in the curbs for the SW driveway approach that was cut out to allo ADA compliance with the sidewalk. The material they had in place was loose and I had asked that they compact the material.
PW-Misc
Corrective Action Required
03/07/2018
Matt Munger 03/07/2018 1:45 PM Dan Harper and I met with Sheldon to discuss the issues with the transitional area between the driveway approach and ramp. A portion of the driveway approach will need to be taken out. Temp occupancy would be granted in contingency that they get the ADA issue fixed within 10 days. Dan stated he would be ok if they block off to keep people from using it until they correct the issue
PW-Misc
Informational
03/12/2018
Matt Munger 03/12/2018 8:14 AM Driveway met ADA standards.
Sidewalk Inspection Passed 3/12/2018 at 8:05 AM 03/12/2018
PW-Misc
Informational
03/09/2018
Matt Munger 02/15/2018 11:15 AM Bob B. and I went out to do a pre-pour inspection. I observed adequate amount of aggregate base that was compacted. Forms were set to acheive 2% or less.
PW-Misc
Informational
03/09/2018
Matt Munger 02/16/2018 9:03 AM Sidewalk and driveway approaches were covered with blankets.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
03/09/2018
Matt Munger 02/23/2018 9:46 AM The sidewalk does not meet ADA guidelines. There is a panel that exceeds 8.33% ramp slope and (street slope is lower as well) and the sidewalk within the transition area is under 5 ft. The City requires sidewalks to be 5ft wide.
PW-Sidewalk does not meet ADA requirements
Corrective Action Required
03/09/2018
Matt Munger 02/23/2018 10:10 AM The sidewalk does not meet ADA guidelines. I spoke with Mr. Bouwens and pointed out the issues with the slope % and area that was not 5ft in width. He said he would get it taken care of.
PW-Misc
Informational
03/09/2018
Matt Munger 03/01/2018 10:16 AM I put my level on the forms on the sections of sidewalk that I had the contractor tear out. The continuous slope was less than 8.33% and the cross slope was within ADA specs. I told them to mindful when they finish to make sure they are under 2% cross slope.
PW-Misc
Corrective Action Required
03/09/2018
Matt Munger 03/01/2018 11:52 AM I had a concern with how curb area was cut out so I spoke with Bob (ROW Inspector) to seek additional clarification in regards to the small section of curb that was cut out to widen the entry to ensure the sidewalk was 5ft rather then the 4ft that was in place prior to the tear out. I contacted Sheldon to let him know the concern and that they need to tear out more of the curb and not just that small section. They are going to tear out the portion of the curb to ensure the sidewalk is 5ft.
PW-Curb ramp is out of compliance
Corrective Action Required
03/09/2018
Matt Munger 03/02/2018 11:42 AM The curb ramp does not meet specs. I spoke with Sheldon on site to show him the issue. There another area on the sidewalk that had been gouged with equipment and will need to be replaced.
PW-Curb ramp is out of compliance
Informational
03/09/2018
Matt Munger 03/07/2018 9:20 AM Spoke with Sheldon about my concern with the curb ramp and explained to him that I would be having another inspector come out and look at it sometime today.
PW-Misc
Corrective Action Required
03/09/2018
Matt Munger 03/07/2018 10:45 AM Tom C. and I went out to look over the ADA ramp on the SE side of the site and there ramp is not in compliance. The driveway approach may need to be taken out to achieve compliance. I will be bringing Dan H. (Assitant Director) to look over the issues.
PW-Curb ramp is out of compliance
Corrective Action Required
03/09/2018
Matt Munger 03/07/2018 1:36 PM Dan Harper and I met with Sheldon to discuss the issues with the transitional area between the driveway approach and ramp. Temp occupancy would be granted in contingency that they get the ADA issue fixed within 10 days. Dan stated he would be ok if they block off to keep people from using it until they correct the issue.
PW-Misc
Informational
03/09/2018
Matt Munger 03/09/2018 10:30 AM Tom C. and I came out and gave the detail sheet for the ADA requirements (second time giving Dan the sheets) and put the level on what they had formed up. Dan stated he understood the requirements and was making sure his guys knew what to do. I reminded Dan to make sure to carry less than 2% cross slope in the area where they took out some of the approach.
PW-Misc
Informational
03/12/2018
Matt Munger 03/12/2018 8:15 AM Sidewalk met ADA requirements.
ESC - (Vegetation/Ground Cover) Partial 3/12/2018 at 8:15 AM 03/12/2018
PW-Misc
Corrective Action Required
03/12/2018
Matt Munger 03/12/2018 8:17 AM East side of the property will need to have vegetation established. Sod has been installed througout the rest of the site.
Miscellaneous PWORKS Inspection Passed 03/12/2018
PW-Misc
Informational
03/06/2018
Matt Munger 03/02/2018 7:55 AM When I arrived the asphalt crew was cleaning the debris off the base layer and had started to put on the tack coat.
PW-Misc
Informational
03/06/2018
Matt Munger 03/02/2018 11:05 AM I observed the temps of the asphalt going into the machine and the roll temps. The temps for the material going into the machine ranged from 252 degrees to 283 degrees. The roll temps ranged from 179 degrees to 248 degrees. The base layer was tac coated prior to the aspahlt getting put in. They did use the vibratory roller machine over the surface layer.
Commercial Curb Inspection Passed 03/12/2018
Pavement-Stabilized Subgrade Passed 03/12/2018
PW-Misc
Informational
01/31/2018
Matt Munger 01/30/2018 2:41 PM I observed geogrid in place over compacted subgrade with AB3 material on top of the geogrid. It appears the workers were not done spreading and compacting the AB3 material. This work was done prior to my arrival. The area that had geogrid and AB3 material in place was on the east side of the building where the parking spaces were going in, and from where the construction entrance ends.
PW-Misc
Informational
01/31/2018
Matt Munger 01/31/2018 10:53 AM Spoke with Mr. Bouwens on site and informed him that we will need to do a curb proof roll. He stated they were using their rolling machine over the entire area and that should be good. I informed him that I need to be present to pass the proof roll for the curbs. We also had talked about he geogrid and materials being a foot past the curb. The workers had cut out the driveway area for the west entrance. Geogrid was not in place for that area at this time.
Storm Sewer Construction Inspection Passed 03/12/2018
PW-Storm Sewer Inspection
Informational
01/24/2018
Matt Munger 01/10/2018 8:30 AM I spoke with Sue (Engineer) in regards to the clearance issues with the existing water line and the storm sewer that was going to be installed. Sue had stated if they could not get 12" of clearance then it would be ok to encase the pipe in concrete. When I arrived on site and Aaron was still working on getting the area potholed to find out the depth of the pipe. I told them to call me when they had the pipe exposed. Contractor was also working on the construction entrance.
PW-Storm Sewer Inspection
Informational
01/24/2018
Matt Munger 01/10/2018 10:36 AM Aaron from Cohurst had dug down the water main and after measuring we discovered there was going to be an issue with getting 18" of clearance. I had informed them that Sue had stated if they could get 12" of clearance they wouldn't need to encase the pipe. After further inspection we saw that was not going to be the case. I called John Haily to come out and check out the situtation. We had Aaron measure from the top of pipe to where the bottom of the pipe would be see if concrete encasement would be an option (if there was 6" of clearance between concrete encasement). John had thought it would be ok to encase the pipe. I told them they will need to have 5ft on each side of center of the where the storm pipe was going. As well as having 6" of concrete above and below the water main. They also were going to use rebar to build a cage around the water line.
PW-Storm Sewer Inspection
Informational
01/24/2018
Matt Munger 01/10/2018 3:05 PM I observed the rebar cage around the water main and had watched them pour the concrete. I observed them using a spade shovel to chock in the concrete mix under the water pipe.
PW-Storm Sewer Inspection
Informational
01/24/2018
Matt Munger 01/18/2018 10:52 AM I had observed the workers digging the trench where the storm pipe is going to be put in. I had spoke with Aaron from Cohurst on the phone earlier in the morning and on site and informed him that putting frozen backfill material does not meet our standard and that I would have to fail the inspection. I explained to Aaron the concern would be that the soil would not be compacted properly and could cause a sink hole and issues down the road, especially where they are putting pavement in. I observed the curb inlet at Sta. 0+80.29 was set in place with gravel base underneath that was set in prior to my arrival. I informed Aaron to contact me prior to backfilling the trench.
PW-Storm Sewer Inspection
Informational
01/24/2018
Matt Munger 01/18/2018 2:25 PM Tom C. and I went out to check on the storm sewer that had been installed. I observed adequate amount of gravel above and below the storm pipe. The backfill material that was on site good and didn't have alot of chunks. They had separated frozen material to ensure good material was going getting backfilled. I had also received the concrete ticket for the collars.
PW-Storm Sewer Inspection
Informational
01/24/2018
Matt Munger 01/24/2018 10:35 AM Opened up the Public CI (Sta. 0+00.00) to make sure the concrete collar hadn't pulled away from the existing concrete after it had cured for a few days.
Site Visit Partial 3/12/2018 at 11:22 AM 03/12/2018
PW-Misc
Informational
03/06/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
03/06/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
03/06/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
03/06/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
03/06/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
03/06/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
03/06/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
03/06/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
03/06/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
03/06/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
03/06/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
03/06/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
03/06/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
03/06/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
03/06/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
03/06/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
03/06/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
PW-Misc
Informational
03/06/2018
Matt Munger 01/12/2018 1:57 PM No utility work was being done due to the weather. Street was clean and the erosion control was in place. Sheldon had emailed earlier in the day informing me that they would be digging the storm sewer on Tuesday. I informed Sheldon when they backfill frozen material is not allowed back in the trench. Just wanted to remind him since the temps have dropped (below freezing) and will stay that way into Tuesday of next week.
PW-Misc
Informational
03/06/2018
Matt Munger 01/16/2018 10:55 AM No workers were present due to the weather. Sheldon had emailed me on Friday stating they would be working today on the storm sewer and I had informed him that since the weather has been so cold frozen backfill material would not be acceptable.
PW-Misc
Informational
03/06/2018
Matt Munger 01/17/2018 11:00 AM No utility work was being done due to the weather.
PW-Misc
Informational
03/06/2018
Matt Munger 01/23/2018 2:57 PM Workers were working on the building. No other infrastructure work was being done.
PW-Misc
Informational
03/06/2018
Matt Munger 01/29/2018 9:53 AM Spoke with Mr. Bouwens as he was cleaning loose dirt off the street. Workers were grading out the pavement areas and that they were going to be putting down geogrid instead of fly ash. He said they would start working on the curb Wednesday. I discussed putting the geogrid a foot past the curb as well.
PW-Misc
Informational
03/06/2018
Matt Munger 01/30/2018 11:00 AM Workers had cut out the area where pavement and curb is going to be put it. I had emailed Sheldon on 1/29/18 informing to get with me when they were ready for the proof roll for the curbs. They decided to use geogrid instead of fly ash.
PW-Misc
Informational
03/06/2018
Matt Munger 02/05/2018 9:15 AM No work was being done on site.
PW-Misc
Informational
03/06/2018
Matt Munger 02/07/2018 9:38 AM No workers were present.
PW-Misc
Informational
03/06/2018
Matt Munger 03/01/2018 2:09 PM Looked over the site with Jon H. and put together a list of items that will need to be done before substantial can be given.
PW-Misc
Informational
03/06/2018
Matt Munger 03/05/2018 2:47 PM The landscape company was working on the irrigation system. The spoil piles have not been hauled off site.
PW-Misc
Informational
03/06/2018
Matt Munger 03/06/2018 1:10 PM Grading work was being done on the north, north east side of the site. KC Test Lab was on site.
Informational
03/12/2018
Matt Munger 03/12/2018 12:05 PM Spoke with Sheldon on site over the punch list items that will need to be taken care of. Pointed out the sanitary sewer cleanout needing to be cut down. The area to the east that was disturbed will need to be vegetated and the rock and debris will need to be removed. I also informed Sheldon I would like to see the area around the NW concrete flume maintain positive drainage to the ditch along M-150 HWY.
Commercial Curb Inspection Failed 3/16/2018 at 9:12 AM 03/16/2018
Corrective Action Required
03/16/2018
Matt Munger 03/16/2018 9:12 AM The temporary asphalt curb is chipping in a few areas. I had informed Sheldon of my concerns with the asphalt curb during installation.
Site Visit Partial 3/16/2018 at 9:12 AM 03/16/2018
PW-Misc
Informational
03/12/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
03/12/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
03/12/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
03/12/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
03/12/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
03/12/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
03/12/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
03/12/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
03/12/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
03/12/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
03/12/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
03/12/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
03/12/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
03/12/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
03/12/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
03/12/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
03/12/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
PW-Misc
Informational
03/12/2018
Matt Munger 01/12/2018 1:57 PM No utility work was being done due to the weather. Street was clean and the erosion control was in place. Sheldon had emailed earlier in the day informing me that they would be digging the storm sewer on Tuesday. I informed Sheldon when they backfill frozen material is not allowed back in the trench. Just wanted to remind him since the temps have dropped (below freezing) and will stay that way into Tuesday of next week.
PW-Misc
Informational
03/12/2018
Matt Munger 01/16/2018 10:55 AM No workers were present due to the weather. Sheldon had emailed me on Friday stating they would be working today on the storm sewer and I had informed him that since the weather has been so cold frozen backfill material would not be acceptable.
PW-Misc
Informational
03/12/2018
Matt Munger 01/17/2018 11:00 AM No utility work was being done due to the weather.
PW-Misc
Informational
03/12/2018
Matt Munger 01/23/2018 2:57 PM Workers were working on the building. No other infrastructure work was being done.
PW-Misc
Informational
03/12/2018
Matt Munger 01/29/2018 9:53 AM Spoke with Mr. Bouwens as he was cleaning loose dirt off the street. Workers were grading out the pavement areas and that they were going to be putting down geogrid instead of fly ash. He said they would start working on the curb Wednesday. I discussed putting the geogrid a foot past the curb as well.
PW-Misc
Informational
03/12/2018
Matt Munger 01/30/2018 11:00 AM Workers had cut out the area where pavement and curb is going to be put it. I had emailed Sheldon on 1/29/18 informing to get with me when they were ready for the proof roll for the curbs. They decided to use geogrid instead of fly ash.
PW-Misc
Informational
03/12/2018
Matt Munger 02/05/2018 9:15 AM No work was being done on site.
PW-Misc
Informational
03/12/2018
Matt Munger 02/07/2018 9:38 AM No workers were present.
PW-Misc
Informational
03/12/2018
Matt Munger 03/01/2018 2:09 PM Looked over the site with Jon H. and put together a list of items that will need to be done before substantial can be given.
PW-Misc
Informational
03/12/2018
Matt Munger 03/05/2018 2:47 PM The landscape company was working on the irrigation system. The spoil piles have not been hauled off site.
PW-Misc
Informational
03/16/2018
Matt Munger 03/16/2018 9:12 AM I checked on the drainage flume on the NW corner to see if the flume was draining properly. It did appear to be holding a small amount of water. I will return to check on this when we get more rain.
Storm - Outlet Structure Failed 3/19/2018 at 10:53 AM 03/19/2018
PW-Misc
Corrective Action Required
03/19/2018
Matt Munger 03/19/2018 3:26 PM The flume that was installed to drain the rain run off from the parking lot into the ditch off M150 appears to be holding water.
Storm - Outlet Structure Passed 3/20/2018 at 10:50 AM 03/20/2018
PW-Misc
Corrective Action Required
03/19/2018
Matt Munger 03/19/2018 3:26 PM The flume that was installed to drain the rain run off from the parking lot into the ditch off M150 appears to be holding water.
PW-Misc
Informational
03/20/2018
Matt Munger 03/20/2018 10:54 AM I had taken a picture of the drainage from the flume to the swale on 3/19/18 since we had rain in excess of an inch that day. I spoke with Dan Harper in regards to my concern with the NW flume/swale and he stated it was a little bit of concern but it was draining and would be ok.
Storm - Swales Passed 3/20/2018 at 10:00 AM 03/20/2018
PW-Misc
Informational
03/20/2018
Matt Munger 03/20/2018 10:54 AM I had taken a picture of the drainage from the flume to the swale on 3/19/18 since we had rain in excess of an inch that day. I spoke with Dan Harper in regards to my concern with the NW flume/swale and he stated it was a little bit of concern but it was draining and would be ok.
Storm - Inlets Clean Passed 3/20/2018 at 12:15 PM 03/20/2018
PW-Misc
Informational
03/20/2018
Matt Munger 03/20/2018 12:33 PM I opened up the manholes for the private and publice curb inlets and there was not any major debris inside of them. I did pull out a plastic bottle that was in the inlet off the road.
ESC - (Vegetation/Ground Cover) Partial 3/20/2018 at 12:33 PM 03/20/2018
PW-Misc
Corrective Action Required
03/12/2018
Matt Munger 03/12/2018 8:17 AM East side of the property will need to have vegetation established. Sod has been installed througout the rest of the site.
PW-Misc
Informational
03/20/2018
Matt Munger 03/20/2018 12:38 PM Erosion control devices have been removed and sod was installed. Sheldon is going to hydra seed the disturbed area on the east.
Commercial Curb Inspection Passed 03/21/2018
ESC - (Vegetation/Ground Cover) Partial 3/21/2018 at 3:35 PM 03/21/2018
PW-Misc
Corrective Action Required
03/20/2018
Matt Munger 03/12/2018 8:17 AM East side of the property will need to have vegetation established. Sod has been installed througout the rest of the site.
PW-Misc
Informational
03/20/2018
Matt Munger 03/20/2018 12:38 PM Erosion control devices have been removed and sod was installed. Sheldon is going to hydra seed the disturbed area on the east.
PW-Misc
Informational
03/21/2018
Matt Munger 03/21/2018 3:45 PM The disturbed soil on the east side on the vacant lot has been hydro seeded.
Site Visit Partial 3/30/2018 at 8:56 AM 03/30/2018
PW-Misc
Informational
03/16/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
03/16/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
03/16/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
03/16/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
03/16/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
03/16/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
03/16/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
03/16/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
03/16/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
03/16/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
03/16/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
03/16/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
03/16/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
03/16/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
03/16/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
03/16/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
03/16/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
PW-Misc
Informational
03/16/2018
Matt Munger 01/12/2018 1:57 PM No utility work was being done due to the weather. Street was clean and the erosion control was in place. Sheldon had emailed earlier in the day informing me that they would be digging the storm sewer on Tuesday. I informed Sheldon when they backfill frozen material is not allowed back in the trench. Just wanted to remind him since the temps have dropped (below freezing) and will stay that way into Tuesday of next week.
PW-Misc
Informational
03/16/2018
Matt Munger 01/16/2018 10:55 AM No workers were present due to the weather. Sheldon had emailed me on Friday stating they would be working today on the storm sewer and I had informed him that since the weather has been so cold frozen backfill material would not be acceptable.
PW-Misc
Informational
03/16/2018
Matt Munger 01/17/2018 11:00 AM No utility work was being done due to the weather.
PW-Misc
Informational
03/16/2018
Matt Munger 01/23/2018 2:57 PM Workers were working on the building. No other infrastructure work was being done.
PW-Misc
Informational
03/16/2018
Matt Munger 01/29/2018 9:53 AM Spoke with Mr. Bouwens as he was cleaning loose dirt off the street. Workers were grading out the pavement areas and that they were going to be putting down geogrid instead of fly ash. He said they would start working on the curb Wednesday. I discussed putting the geogrid a foot past the curb as well.
PW-Misc
Informational
03/16/2018
Matt Munger 01/30/2018 11:00 AM Workers had cut out the area where pavement and curb is going to be put it. I had emailed Sheldon on 1/29/18 informing to get with me when they were ready for the proof roll for the curbs. They decided to use geogrid instead of fly ash.
PW-Misc
Informational
03/16/2018
Matt Munger 02/05/2018 9:15 AM No work was being done on site.
PW-Misc
Informational
03/16/2018
Matt Munger 02/07/2018 9:38 AM No workers were present.
PW-Misc
Informational
03/16/2018
Matt Munger 03/01/2018 2:09 PM Looked over the site with Jon H. and put together a list of items that will need to be done before substantial can be given.
PW-Misc
Informational
03/16/2018
Matt Munger 03/05/2018 2:47 PM The landscape company was working on the irrigation system. The spoil piles have not been hauled off site.
PW-Misc
Informational
03/16/2018
Matt Munger 03/16/2018 9:12 AM I checked on the drainage flume on the NW corner to see if the flume was draining properly. It did appear to be holding a small amount of water. I will return to check on this when we get more rain.
PW-Misc
Informational
03/30/2018
Matt Munger 03/30/2018 9:05 AM The forms were removed off the ADA ramp, some of the hydro seed that was applied looks to have washed down the hill.
Grading/Excavation/Fill Inspection Passed 04/03/2018
ESC - (Vegetation/Ground Cover) Partial 4/3/2018 at 2:39 PM 04/03/2018
PW-Misc
Corrective Action Required
03/21/2018
Matt Munger 03/12/2018 8:17 AM East side of the property will need to have vegetation established. Sod has been installed througout the rest of the site.
PW-Misc
Informational
03/21/2018
Matt Munger 03/20/2018 12:38 PM Erosion control devices have been removed and sod was installed. Sheldon is going to hydra seed the disturbed area on the east.
PW-Misc
Informational
03/21/2018
Matt Munger 03/21/2018 3:45 PM The disturbed soil on the east side on the vacant lot has been hydro seeded.
PW-Misc
Informational
04/03/2018
Matt Munger 04/03/2018 2:42 PM It appears the hydro seed that was applied to the vacant lot to the east has washed off in a few spots.
ESC - (Vegetation/Ground Cover) Partial 4/13/2018 at 9:49 AM 04/13/2018
PW-Misc
Corrective Action Required
04/03/2018
Matt Munger 03/12/2018 8:17 AM East side of the property will need to have vegetation established. Sod has been installed througout the rest of the site.
PW-Misc
Informational
04/03/2018
Matt Munger 03/20/2018 12:38 PM Erosion control devices have been removed and sod was installed. Sheldon is going to hydra seed the disturbed area on the east.
PW-Misc
Informational
04/03/2018
Matt Munger 03/21/2018 3:45 PM The disturbed soil on the east side on the vacant lot has been hydro seeded.
PW-Misc
Informational
04/03/2018
Matt Munger 04/03/2018 2:42 PM It appears the hydro seed that was applied to the vacant lot to the east has washed off in a few spots.
PW-Misc
Informational
04/13/2018
Matt Munger 04/13/2018 10:00 AM Grass has started to grow on the vacant lot.
ESC - (Vegetation/Ground Cover) Partial 4/18/2018 at 1:40 PM 04/18/2018
PW-Misc
Corrective Action Required
04/13/2018
Matt Munger 03/12/2018 8:17 AM East side of the property will need to have vegetation established. Sod has been installed througout the rest of the site.
PW-Misc
Informational
04/13/2018
Matt Munger 03/20/2018 12:38 PM Erosion control devices have been removed and sod was installed. Sheldon is going to hydra seed the disturbed area on the east.
PW-Misc
Informational
04/13/2018
Matt Munger 03/21/2018 3:45 PM The disturbed soil on the east side on the vacant lot has been hydro seeded.
PW-Misc
Informational
04/13/2018
Matt Munger 04/03/2018 2:42 PM It appears the hydro seed that was applied to the vacant lot to the east has washed off in a few spots.
PW-Misc
Informational
04/13/2018
Matt Munger 04/13/2018 10:00 AM Grass has started to grow on the vacant lot.
PW-Misc
Informational
04/18/2018
Matt Munger 04/18/2018 1:40 PM Grass has started to grow on the vacant lot, but there is not enough vegetation established at this time.
ESC - (Vegetation/Ground Cover) Partial 4/23/2018 at 9:56 AM 04/23/2018
PW-Misc
Corrective Action Required
04/18/2018
Matt Munger 03/12/2018 8:17 AM East side of the property will need to have vegetation established. Sod has been installed througout the rest of the site.
PW-Misc
Informational
04/18/2018
Matt Munger 03/20/2018 12:38 PM Erosion control devices have been removed and sod was installed. Sheldon is going to hydra seed the disturbed area on the east.
PW-Misc
Informational
04/18/2018
Matt Munger 03/21/2018 3:45 PM The disturbed soil on the east side on the vacant lot has been hydro seeded.
PW-Misc
Informational
04/18/2018
Matt Munger 04/03/2018 2:42 PM It appears the hydro seed that was applied to the vacant lot to the east has washed off in a few spots.
PW-Misc
Informational
04/18/2018
Matt Munger 04/13/2018 10:00 AM Grass has started to grow on the vacant lot.
PW-Misc
Informational
04/18/2018
Matt Munger 04/18/2018 1:40 PM Grass has started to grow on the vacant lot, but there is not enough vegetation established at this time.
PW-Misc
Informational
04/23/2018
Matt Munger 04/23/2018 10:03 AM Some grass has started to grow but there is still a larger area of bare soil that will need to be vegetated on the vacant lot.
ESC - (Vegetation/Ground Cover) Partial 5/2/2018 at 10:34 AM 05/02/2018
PW-Misc
Corrective Action Required
04/23/2018
Matt Munger 03/12/2018 8:17 AM East side of the property will need to have vegetation established. Sod has been installed througout the rest of the site.
PW-Misc
Informational
04/23/2018
Matt Munger 03/20/2018 12:38 PM Erosion control devices have been removed and sod was installed. Sheldon is going to hydra seed the disturbed area on the east.
PW-Misc
Informational
04/23/2018
Matt Munger 03/21/2018 3:45 PM The disturbed soil on the east side on the vacant lot has been hydro seeded.
PW-Misc
Informational
04/23/2018
Matt Munger 04/03/2018 2:42 PM It appears the hydro seed that was applied to the vacant lot to the east has washed off in a few spots.
PW-Misc
Informational
04/23/2018
Matt Munger 04/13/2018 10:00 AM Grass has started to grow on the vacant lot.
PW-Misc
Informational
04/23/2018
Matt Munger 04/18/2018 1:40 PM Grass has started to grow on the vacant lot, but there is not enough vegetation established at this time.
PW-Misc
Informational
04/23/2018
Matt Munger 04/23/2018 10:03 AM Some grass has started to grow but there is still a larger area of bare soil that will need to be vegetated on the vacant lot.
PW-Misc
Informational
05/02/2018
Matt Munger 05/02/2018 10:43 AM Grass has started to grow on the vacant lot but there are some bare areas that have not started to show signs of growth.
ESC - (Vegetation/Ground Cover) Partial 5/10/2018 at 8:10 AM 05/10/2018
PW-Misc
Corrective Action Required
05/02/2018
Matt Munger 03/12/2018 8:17 AM East side of the property will need to have vegetation established. Sod has been installed througout the rest of the site.
PW-Misc
Informational
05/02/2018
Matt Munger 03/20/2018 12:38 PM Erosion control devices have been removed and sod was installed. Sheldon is going to hydra seed the disturbed area on the east.
PW-Misc
Informational
05/02/2018
Matt Munger 03/21/2018 3:45 PM The disturbed soil on the east side on the vacant lot has been hydro seeded.
PW-Misc
Informational
05/02/2018
Matt Munger 04/03/2018 2:42 PM It appears the hydro seed that was applied to the vacant lot to the east has washed off in a few spots.
PW-Misc
Informational
05/02/2018
Matt Munger 04/13/2018 10:00 AM Grass has started to grow on the vacant lot.
PW-Misc
Informational
05/02/2018
Matt Munger 04/18/2018 1:40 PM Grass has started to grow on the vacant lot, but there is not enough vegetation established at this time.
PW-Misc
Informational
05/02/2018
Matt Munger 04/23/2018 10:03 AM Some grass has started to grow but there is still a larger area of bare soil that will need to be vegetated on the vacant lot.
PW-Misc
Informational
05/02/2018
Matt Munger 05/02/2018 10:43 AM Grass has started to grow on the vacant lot but there are some bare areas that have not started to show signs of growth.
PW-Misc
Informational
05/10/2018
Matt Munger 05/10/2018 8:26 AM The lot on the east side has some grass growing but there are some bare spots. I moved some rocks into a pile so the mowers dont hit them.
ESC - (Vegetation/Ground Cover) Partial 5/17/2018 at 10:01 AM 05/17/2018
PW-Misc
Corrective Action Required
05/10/2018
Matt Munger 03/12/2018 8:17 AM East side of the property will need to have vegetation established. Sod has been installed througout the rest of the site.
PW-Misc
Informational
05/10/2018
Matt Munger 03/20/2018 12:38 PM Erosion control devices have been removed and sod was installed. Sheldon is going to hydra seed the disturbed area on the east.
PW-Misc
Informational
05/10/2018
Matt Munger 03/21/2018 3:45 PM The disturbed soil on the east side on the vacant lot has been hydro seeded.
PW-Misc
Informational
05/10/2018
Matt Munger 04/03/2018 2:42 PM It appears the hydro seed that was applied to the vacant lot to the east has washed off in a few spots.
PW-Misc
Informational
05/10/2018
Matt Munger 04/13/2018 10:00 AM Grass has started to grow on the vacant lot.
PW-Misc
Informational
05/10/2018
Matt Munger 04/18/2018 1:40 PM Grass has started to grow on the vacant lot, but there is not enough vegetation established at this time.
PW-Misc
Informational
05/10/2018
Matt Munger 04/23/2018 10:03 AM Some grass has started to grow but there is still a larger area of bare soil that will need to be vegetated on the vacant lot.
PW-Misc
Informational
05/10/2018
Matt Munger 05/02/2018 10:43 AM Grass has started to grow on the vacant lot but there are some bare areas that have not started to show signs of growth.
PW-Misc
Informational
05/10/2018
Matt Munger 05/10/2018 8:26 AM The lot on the east side has some grass growing but there are some bare spots. I moved some rocks into a pile so the mowers dont hit them.
PW-Misc
Informational
05/17/2018
Matt Munger 05/17/2018 10:06 AM Grass is growing on the vacant lot where the soil has ben disturbed. There is not enough vegetation to finallize the project.
Commercial Curb Inspection Passed 05/17/2018
ESC - (Vegetation/Ground Cover) Partial 5/23/2018 at 9:51 AM 05/21/2018
PW-Misc
Corrective Action Required
05/17/2018
Matt Munger 03/12/2018 8:17 AM East side of the property will need to have vegetation established. Sod has been installed througout the rest of the site.
PW-Misc
Informational
05/17/2018
Matt Munger 03/20/2018 12:38 PM Erosion control devices have been removed and sod was installed. Sheldon is going to hydra seed the disturbed area on the east.
PW-Misc
Informational
05/17/2018
Matt Munger 03/21/2018 3:45 PM The disturbed soil on the east side on the vacant lot has been hydro seeded.
PW-Misc
Informational
05/17/2018
Matt Munger 04/03/2018 2:42 PM It appears the hydro seed that was applied to the vacant lot to the east has washed off in a few spots.
PW-Misc
Informational
05/17/2018
Matt Munger 04/13/2018 10:00 AM Grass has started to grow on the vacant lot.
PW-Misc
Informational
05/17/2018
Matt Munger 04/18/2018 1:40 PM Grass has started to grow on the vacant lot, but there is not enough vegetation established at this time.
PW-Misc
Informational
05/17/2018
Matt Munger 04/23/2018 10:03 AM Some grass has started to grow but there is still a larger area of bare soil that will need to be vegetated on the vacant lot.
PW-Misc
Informational
05/17/2018
Matt Munger 05/02/2018 10:43 AM Grass has started to grow on the vacant lot but there are some bare areas that have not started to show signs of growth.
PW-Misc
Informational
05/17/2018
Matt Munger 05/10/2018 8:26 AM The lot on the east side has some grass growing but there are some bare spots. I moved some rocks into a pile so the mowers dont hit them.
PW-Misc
Informational
05/17/2018
Matt Munger 05/17/2018 10:06 AM Grass is growing on the vacant lot where the soil has ben disturbed. There is not enough vegetation to finallize the project.
PW-Misc
Informational
05/21/2018
Matt Munger 05/21/2018 9:59 AM Grass has been growing on the areas that were disturbed. Will continue to monitor the vegetation.
ESC - (Vegetation/Ground Cover) Passed 6/4/2018 at 10:00 AM 06/06/2018
PW-Misc
Corrective Action Required
05/21/2018
Matt Munger 03/12/2018 8:17 AM East side of the property will need to have vegetation established. Sod has been installed througout the rest of the site.
PW-Misc
Informational
05/21/2018
Matt Munger 03/20/2018 12:38 PM Erosion control devices have been removed and sod was installed. Sheldon is going to hydra seed the disturbed area on the east.
PW-Misc
Informational
05/21/2018
Matt Munger 03/21/2018 3:45 PM The disturbed soil on the east side on the vacant lot has been hydro seeded.
PW-Misc
Informational
05/21/2018
Matt Munger 04/03/2018 2:42 PM It appears the hydro seed that was applied to the vacant lot to the east has washed off in a few spots.
PW-Misc
Informational
05/21/2018
Matt Munger 04/13/2018 10:00 AM Grass has started to grow on the vacant lot.
PW-Misc
Informational
05/21/2018
Matt Munger 04/18/2018 1:40 PM Grass has started to grow on the vacant lot, but there is not enough vegetation established at this time.
PW-Misc
Informational
05/21/2018
Matt Munger 04/23/2018 10:03 AM Some grass has started to grow but there is still a larger area of bare soil that will need to be vegetated on the vacant lot.
PW-Misc
Informational
05/21/2018
Matt Munger 05/02/2018 10:43 AM Grass has started to grow on the vacant lot but there are some bare areas that have not started to show signs of growth.
PW-Misc
Informational
05/21/2018
Matt Munger 05/10/2018 8:26 AM The lot on the east side has some grass growing but there are some bare spots. I moved some rocks into a pile so the mowers dont hit them.
PW-Misc
Informational
05/21/2018
Matt Munger 05/17/2018 10:06 AM Grass is growing on the vacant lot where the soil has ben disturbed. There is not enough vegetation to finallize the project.
PW-Misc
Informational
05/21/2018
Matt Munger 05/21/2018 9:59 AM Grass has been growing on the areas that were disturbed. Will continue to monitor the vegetation.
PW-Misc
Informational
06/04/2018
Matt Munger 06/04/2018 10:10 AM Vegetation has started to grow very well on the vacant lot that was disturbed.
Erosion Control Inspection Passed 06/06/2018
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/21/2018
Matt Munger 02/20/2018 11:20 AM The silt fence is down on the SW corner of the site. ESC is not in compliance will need to be in place at the end of day on 2/21/18 or a Stop Work Order can be issued.
PW-Devices for Erosion and Sediment Control
Corrective Action Required
02/21/2018
Matt Munger 02/21/2018 11:16 AM Silt fence was placed along the roadway on the south side of the site, but was not trenched in due to the ground being frozen. Silt has not left the site yet but ESC does need to be in place to prevent that from happening. I had pointed out to Sheldon my concerns with the SW corner and the north side of the west entrance (Commerce Bank side) that I pointed out to Sheldon and recommended using straw waddles in the areas of concern. Sheldon stated he would monitor the ESC and get it taken care of.
Erosion Control Inspection Passed 06/06/2018
PW-Devices for Erosion and Sediment Control
Informational
03/01/2018
Matt Munger 02/28/2018 3:36 PM ESC was not in place due to the grading that was being done. I asked Sheldon to put up straw waddles since we are expecting rain overnight into the moring.I also advised him to place a gutter device in the curb inlet on the private side. He said he would take care of the ESC issues.
PW-Devices for Erosion and Sediment Control
Informational
03/01/2018
Matt Munger 03/01/2018 9:59 AM Straw wattles were set in place at the down side of the hill. Irrigation was going to be going in.
Site Visit Complete 06/06/2018
PW-Misc
Informational
03/30/2018
Matt Munger 12/01/2017 4:53 PM No workers were present, spoke with Sheldon on the phone to see how everyting was going and if had any questions and had asked if he could email me the sub-contractors info to me.
PW-Misc
Informational
03/30/2018
Matt Munger 12/06/2017 10:56 AM Silt fence was intact and ESC Device in curb inlet was in place.
PW-Misc
Informational
03/30/2018
Matt Munger 12/07/2017 10:16 No workers were present, ESC devices and silt fence was in place.
PW-Misc
Informational
03/30/2018
Matt Munger 12/07/2017 1:40 PM No workers were present.
PW-Misc
Informational
03/30/2018
Matt Munger 12/08/2017 9:46 AM No workers were present, ESC was in place.
PW-Misc
Informational
03/30/2018
Matt Munger 12/08/2017 1:55 PM No workers were present.
PW-Misc
Informational
03/30/2018
Matt Munger 12/12/2017 2:41 PM No workers were present, silt fence and ESC devices were in place.
PW-Misc
Informational
03/30/2018
Matt Munger 12/13/2017 10:50 AM No workers were present.
PW-Misc
Informational
03/30/2018
Matt Munger 12/14/2017 8:15 AM No workers were present.
PW-Misc
Informational
03/30/2018
Matt Munger 12/15/2017 2:15 PM Site was clean, ESC in place. No Utility work was being done.
PW-Misc
Informational
03/30/2018
Matt Munger 12/18/2017 11:45 AM Silt fence was in place and gutter device was in CI. I spoke with Travis on site and he was working on removing dirt from the driveway area. I had informed Travis that Rip Rap needs to be put in place to prevent mud and gravel from getting onto the roadway. Water Utilities workers were on site performing the test shutdown in case the water main needs to be relocated. The shutdown should only affect Commerce Bank.
PW-Misc
Informational
03/30/2018
Matt Munger 12/21/2017 2:44 PM No Utility work was being performed while I was on site. Workers were framing in the building. Contacted Sheldon in regards to the Holiday schedule and that Tom C. and Steve R. would be covering me on the 22nd and 27th while I was off. Sheldon stated he would get the silt fence up on the section of property closest to 150 HWY. We also discussed setting up a meeting before any Utility work starts.
PW-Misc
Informational
03/30/2018
Matt Munger 12/28/2017 9:51 AM No utility workers were present. Silt Fence in place.
PW-Misc
Informational
03/30/2018
Matt Munger 12/29/2017 11:16AM No workers were present due to the weather.
PW-Misc
Informational
03/30/2018
Matt Munger 01/04/2018 9:16 AM No utility work was being done on site. Spoke with Sheldon and he stated they would be there in the afternoon but no inspections were going to be needed.
PW-Misc
Informational
03/30/2018
Matt Munger 01/08/2018 9:58 AM No utility work was being done. * Sheldon stated that the storm sewer work will start on Wednesday the 10th.
PW-Misc
Informational
03/30/2018
Matt Munger 01/11/2018 10:30 AM No workers were present due to the weather.
PW-Misc
Informational
03/30/2018
Matt Munger 01/12/2018 1:57 PM No utility work was being done due to the weather. Street was clean and the erosion control was in place. Sheldon had emailed earlier in the day informing me that they would be digging the storm sewer on Tuesday. I informed Sheldon when they backfill frozen material is not allowed back in the trench. Just wanted to remind him since the temps have dropped (below freezing) and will stay that way into Tuesday of next week.
PW-Misc
Informational
03/30/2018
Matt Munger 01/16/2018 10:55 AM No workers were present due to the weather. Sheldon had emailed me on Friday stating they would be working today on the storm sewer and I had informed him that since the weather has been so cold frozen backfill material would not be acceptable.
PW-Misc
Informational
03/30/2018
Matt Munger 01/17/2018 11:00 AM No utility work was being done due to the weather.
PW-Misc
Informational
03/30/2018
Matt Munger 01/23/2018 2:57 PM Workers were working on the building. No other infrastructure work was being done.
PW-Misc
Informational
03/30/2018
Matt Munger 01/29/2018 9:53 AM Spoke with Mr. Bouwens as he was cleaning loose dirt off the street. Workers were grading out the pavement areas and that they were going to be putting down geogrid instead of fly ash. He said they would start working on the curb Wednesday. I discussed putting the geogrid a foot past the curb as well.
PW-Misc
Informational
03/30/2018
Matt Munger 01/30/2018 11:00 AM Workers had cut out the area where pavement and curb is going to be put it. I had emailed Sheldon on 1/29/18 informing to get with me when they were ready for the proof roll for the curbs. They decided to use geogrid instead of fly ash.
PW-Misc
Informational
03/30/2018
Matt Munger 02/05/2018 9:15 AM No work was being done on site.
PW-Misc
Informational
03/30/2018
Matt Munger 02/07/2018 9:38 AM No workers were present.
PW-Misc
Informational
03/30/2018
Matt Munger 03/01/2018 2:09 PM Looked over the site with Jon H. and put together a list of items that will need to be done before substantial can be given.
PW-Misc
Informational
03/30/2018
Matt Munger 03/05/2018 2:47 PM The landscape company was working on the irrigation system. The spoil piles have not been hauled off site.
PW-Misc
Informational
03/30/2018
Matt Munger 03/16/2018 9:12 AM I checked on the drainage flume on the NW corner to see if the flume was draining properly. It did appear to be holding a small amount of water. I will return to check on this when we get more rain.
PW-Misc
Informational
03/30/2018
Matt Munger 03/30/2018 9:05 AM The forms were removed off the ADA ramp, some of the hydro seed that was applied looks to have washed down the hill.
ESC - (Vegetation/Ground Cover) Passed 06/06/2018
PW-Misc
Corrective Action Required
06/04/2018
Matt Munger 03/12/2018 8:17 AM East side of the property will need to have vegetation established. Sod has been installed througout the rest of the site.
PW-Misc
Informational
06/04/2018
Matt Munger 03/20/2018 12:38 PM Erosion control devices have been removed and sod was installed. Sheldon is going to hydra seed the disturbed area on the east.
PW-Misc
Informational
06/04/2018
Matt Munger 03/21/2018 3:45 PM The disturbed soil on the east side on the vacant lot has been hydro seeded.
PW-Misc
Informational
06/04/2018
Matt Munger 04/03/2018 2:42 PM It appears the hydro seed that was applied to the vacant lot to the east has washed off in a few spots.
PW-Misc
Informational
06/04/2018
Matt Munger 04/13/2018 10:00 AM Grass has started to grow on the vacant lot.
PW-Misc
Informational
06/04/2018
Matt Munger 04/18/2018 1:40 PM Grass has started to grow on the vacant lot, but there is not enough vegetation established at this time.
PW-Misc
Informational
06/04/2018
Matt Munger 04/23/2018 10:03 AM Some grass has started to grow but there is still a larger area of bare soil that will need to be vegetated on the vacant lot.
PW-Misc
Informational
06/04/2018
Matt Munger 05/02/2018 10:43 AM Grass has started to grow on the vacant lot but there are some bare areas that have not started to show signs of growth.
PW-Misc
Informational
06/04/2018
Matt Munger 05/10/2018 8:26 AM The lot on the east side has some grass growing but there are some bare spots. I moved some rocks into a pile so the mowers dont hit them.
PW-Misc
Informational
06/04/2018
Matt Munger 05/17/2018 10:06 AM Grass is growing on the vacant lot where the soil has ben disturbed. There is not enough vegetation to finallize the project.
PW-Misc
Informational
06/04/2018
Matt Munger 05/21/2018 9:59 AM Grass has been growing on the areas that were disturbed. Will continue to monitor the vegetation.
PW-Misc
Informational
06/04/2018
Matt Munger 06/04/2018 10:10 AM Vegetation has started to grow very well on the vacant lot that was disturbed.
Documents & Images
Date Uploaded File Type Document Name
11/27/2017 Receipt Receipt for transaction: 2017-007423
11/30/2017 DOC113017-11302017081513
11/30/2017 Letter DE-Daily Inspection Summary
12/01/2017 Letter DE-Daily Inspection Summary
12/04/2017 Letter DE-Daily Inspection Summary
12/05/2017 Letter DE-Daily Inspection Summary
12/06/2017 Letter DE-Daily Inspection Summary
12/07/2017 Letter DE-Daily Inspection Summary
12/08/2017 Letter DE-Site Visit Inspection
12/11/2017 Letter DE-Daily Inspection Summary
12/13/2017 Letter DE-Daily Inspection Summary
12/14/2017 Letter DE-Site Visit Inspection
12/15/2017 Letter DE-Site Visit Inspection
12/18/2017 Letter DE-Site Visit Inspection
12/19/2017 Letter DE-Daily Inspection Summary
12/20/2017 Letter DE-Daily Inspection Summary
12/21/2017 Letter DE-Site Visit Inspection
12/21/2017 Letter DE-Daily Inspection Summary
12/28/2017 Letter DE-Site Visit Inspection
12/29/2017 Letter DE-Site Visit Inspection
01/02/2018 Letter DE-Daily Inspection Summary
01/04/2018 Letter DE-Site Visit Inspection
01/05/2018 Letter DE-Daily Inspection Summary
01/05/2018 Letter DE-Daily Inspection Summary
01/05/2018 Letter DE-Daily Inspection Summary
01/05/2018 Letter DE-Daily Inspection Summary
01/08/2018 Letter DE-Site Visit Inspection
01/09/2018 Letter DE-Daily Inspection Summary
01/09/2018 Letter DE-Daily Inspection Summary
01/10/2018 Letter DE-Daily Inspection Summary
01/10/2018 Letter DE-Daily Inspection Summary
01/10/2018 Letter DE-Daily Inspection Summary
01/10/2018 Letter DE-Daily Inspection Summary
01/11/2018 Concrete Ticket For Encasement
01/11/2018 Letter DE-Site Visit Inspection
01/12/2018 Letter DE-Site Visit Inspection
01/16/2018 Letter DE-Site Visit Inspection
01/17/2018 Letter DE-Site Visit Inspection
01/18/2018 Letter DE-Daily Inspection Summary
01/18/2018 Storm Collar Concrete Ticket
01/22/2018 Letter DE-Daily Inspection Summary
01/23/2018 Letter DE-Site Visit Inspection
01/24/2018 Letter DE-Daily Inspection Summary
01/29/2018 Letter DE-Site Visit Inspection
01/30/2018 Letter DE-Daily Inspection Summary
01/30/2018 Letter DE-Daily Inspection Summary
01/31/2018 Letter DE-Daily Inspection Summary
01/31/2018 Letter DE-Daily Inspection Summary
02/01/2018 Letter DE-Daily Inspection Summary
02/02/2018 Letter DE-Daily Inspection Summary
02/05/2018 Letter DE-Site Visit Inspection
02/06/2018 Letter DE-Daily Inspection Summary
02/07/2018 Letter DE-Site Visit Inspection
02/08/2018 Letter DE-Daily Inspection Summary
02/09/2018 Letter DE-Daily Inspection Summary
02/12/2018 Letter DE-Daily Inspection Summary
02/13/2018 Letter DE-Daily Inspection Summary
02/13/2018 Letter DE-Daily Inspection Summary
02/14/2018 Letter DE-Daily Inspection Summary
02/15/2018 Letter DE-Daily Inspection Summary
02/15/2018 Letter DE-Daily Inspection Summary
02/16/2018 Letter DE-Daily Inspection Summary
02/19/2018 Letter DE-Daily Inspection Summary
02/20/2018 Letter DE-Daily Inspection Summary
02/21/2018 Letter DE-Daily Inspection Summary
02/23/2018 Letter DE-Daily Inspection Summary
02/23/2018 Letter DE-Daily Inspection Summary
02/28/2018 Letter DE-Daily Inspection Summary
03/01/2018 Letter DE-Daily Inspection Summary
03/01/2018 Letter DE-Daily Inspection Summary
03/01/2018 Letter DE-Daily Inspection Summary
03/02/2018 Letter DE-Daily Inspection Summary
03/02/2018 Letter DE-Daily Inspection Summary
03/02/2018 Letter DE-Daily Inspection Summary
03/05/2018 Letter DE-Daily Inspection Summary
03/06/2018 Letter DE-Daily Inspection Summary
03/07/2018 Letter DE-Daily Inspection Summary
03/07/2018 Letter DE-Daily Inspection Summary
03/09/2018 Letter DE-Daily Inspection Summary
03/12/2018 Letter DE-Daily Inspection Summary
03/12/2018 Letter DE-Certificate of Substantial Completion Multiple Lot
03/12/2018 Letter DE-Punch List
03/12/2018 Letter DE-Daily Inspection Summary
03/12/2018 Punch List & Substantial Completion
03/16/2018 Receipt Receipt for transaction: 2018-000982
03/16/2018 Letter DE-Daily Inspection Summary
03/19/2018 Letter DE-Daily Inspection Summary
03/20/2018 Letter DE-Daily Inspection Summary
03/20/2018 Flume
03/20/2018 Letter DE-Daily Inspection Summary
03/20/2018 Letter DE-Daily Inspection Summary
03/21/2018 Letter DE-Daily Inspection Summary
03/26/2018 Letter DE-Site Visit Inspection
03/26/2018 Letter DE-Site Visit Inspection
03/30/2018 Letter DE-Daily Inspection Summary
04/03/2018 Letter DE-Daily Inspection Summary
04/13/2018 Letter DE-Daily Inspection Summary
04/18/2018 Letter DE-Daily Inspection Summary
04/23/2018 Letter DE-Daily Inspection Summary
05/02/2018 Letter DE-Daily Inspection Summary
05/10/2018 Letter DE-Daily Inspection Summary
05/17/2018 Letter DE-Daily Inspection Summary
05/21/2018 Letter DE-Daily Inspection Summary
06/04/2018 Letter DE-Daily Inspection Summary
06/06/2018 Letter DE-Certificate of Final Acceptance (Commercial)
06/06/2018 Certification of Final Acceptance.
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home