Summary


PRPWFC20172852
Public Works Infrastructure Permit - Commercial
Final Acceptance
UNITY REALTY LLC
DEVELOPMENT COMPLETE
SUMMIT VILLAGE 1ST PLAT STREET, STORM, WATER LINE, SANITARY
08/23/2017
01/28/2019
Locations
Contacts
Not shown for privacy reasons.
UNITY REALTY LLC, Address:1901 NW BLUE PKWY, Phone:(816) 251-3593  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 08/23/2017 08/28/2017
Steve Robbins
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $1,078.65 $1,078.65 Paid 08/23/2017
91100C9-Water Insp Fee $1,304.67 $1,304.67 Paid 08/23/2017
9110072-Water Test Fee $200.00 $200.00 Paid 08/23/2017
9110068-Storm Fee $2,108.34 $2,108.34 Paid 08/23/2017
9110081-Paved Surface Inspection Fee $3,886.71 $3,886.71 Paid 08/23/2017
9110071-Site Grading Fee $659.26 $659.26 Paid 08/23/2017
$659.25
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Street - Striping Passed 12/14/2017 at 2:30 PM 12/14/2017
Informational
12/14/2017
On 12/13/17 the turn lane arrows on blue parkway and rosemary ct. were completed. The sidewalk crossing were also installed and all the stripiing, this was all done today because the temperature got up to 58 degrees. This completes all the striping.Steve Robbins 12/14/2017 3:27 PM
Storm - Pipe Failed 1/11/2018 at 7:15 AM 01/11/2018
PW-Misc
Corrective Action Required
01/11/2018
All the storm structures have been installed and are completed. At the end of Rosemary Ct. they did not install the road and the throat inlets for the storm boxes. I talked with Sue and there engineer is suppose to get with her about this situation. Steve Robbins 01/11/2018 7:42 AM
Storm - Pipe Partial 1/19/2018 at 11:00 AM 01/19/2018
PW-Misc
Corrective Action Required
01/11/2018
All the storm structures have been installed and are completed. At the end of Rosemary Ct. they did not install the road and the throat inlets for the storm boxes. I talked with Sue and there engineer is suppose to get with her about this situation. Steve Robbins 01/11/2018 7:42 AM
PW-Misc
Corrective Action Required
01/19/2018
They have not installed the inlets yet, the engineer for the project is suppose to send some revised plans to take care of this problem. Steve Robbins 01/19/2018 3:30 PM
Storm - Pipe Failed 1/25/2018 at 9:15 AM 01/25/2018
PW-Misc
Corrective Action Required
01/19/2018
All the storm structures have been installed and are completed. At the end of Rosemary Ct. they did not install the road and the throat inlets for the storm boxes. I talked with Sue and there engineer is suppose to get with her about this situation. Steve Robbins 01/11/2018 7:42 AM
PW-Misc
Corrective Action Required
01/19/2018
They have not installed the inlets yet, the engineer for the project is suppose to send some revised plans to take care of this problem. Steve Robbins 01/19/2018 3:30 PM
PW-Misc
Corrective Action Required
01/25/2018
The engineer for this project still needs to get with Sue to send a submittal over to make sure these storm boxes and curbs get finished properly.Steve Robbins 01/25/2018 3:41 PM
Storm - Pipe Partial 1/30/2018 at 11:30 AM 01/30/2018
PW-Misc
Corrective Action Required
01/25/2018
All the storm structures have been installed and are completed. At the end of Rosemary Ct. they did not install the road and the throat inlets for the storm boxes. I talked with Sue and there engineer is suppose to get with her about this situation. Steve Robbins 01/11/2018 7:42 AM
PW-Misc
Corrective Action Required
01/25/2018
They have not installed the inlets yet, the engineer for the project is suppose to send some revised plans to take care of this problem. Steve Robbins 01/19/2018 3:30 PM
PW-Misc
Corrective Action Required
01/25/2018
The engineer for this project still needs to get with Sue to send a submittal over to make sure these storm boxes and curbs get finished properly.Steve Robbins 01/25/2018 3:41 PM
PW-Misc
Corrective Action Required
01/30/2018
The storm boxes need to be grouted by the throat going into the inlet.Steve Robbins 01/30/2018 3:25 PM
Storm - Material Verification Passed 2/5/2018 at 2:30 PM 02/05/2018
Sanitary Sewer - Air Test Passed 02/05/2018
Storm - Swales Passed 12/18/2017 02/05/2018
Curb - Compression Strength Passed 02/05/2018
Install Street and Stop Signs Passed 02/05/2018
Street - Surface Course Passed 02/05/2018
Street - Wedge Lift Passed 02/05/2018
Pavement-Surface Passed 02/05/2018
Pavement-Proof Roll Passed 02/05/2018
Curb - Proof Roll Passed 02/05/2018
Sanitary Sewer Construction Inspection Passed 02/05/2018
Sanitary - Material Verification Passed 02/05/2018
Water Line - Construction Inspection Passed 02/05/2018
Water Line - Construction Taps Removed Passed 02/05/2018
Water Line - Thrust Restraint Passed 02/05/2018
Water Line - Fire Hydrant Passed 02/05/2018
Water Line - Valve Passed 02/05/2018
Water Line - Coliform Test 2 Passed 02/05/2018
Water Line - Coliform Test 1 Passed 02/05/2018
Water Line - Hydrostatic Test Passed 02/05/2018
Water - Material Verification Passed 02/05/2018
Storm - Rip Rap Passed 2/5/2018 02/05/2018
Storm - Outlet Structure Passed 02/05/2018
Grading/Excavation/Fill Inspection Passed 02/05/2018
Sanitary Sewer - Invert Passed 02/05/2018
Sanitary Sewer - Vacuum Passed 02/05/2018
Sanitary Sewer - Mandrel Passed 02/05/2018
Sanitary Sewer Construction Inspection Passed 02/05/2018
Water - Material Verification Passed 2/5/2018 02/05/2018
Storm - Pipe Partial 2/6/2018 at 1:15 PM 02/06/2018
PW-Misc
Corrective Action Required
01/30/2018
All the storm structures have been installed and are completed. At the end of Rosemary Ct. they did not install the road and the throat inlets for the storm boxes. I talked with Sue and there engineer is suppose to get with her about this situation. Steve Robbins 01/11/2018 7:42 AM
PW-Misc
Corrective Action Required
01/30/2018
They have not installed the inlets yet, the engineer for the project is suppose to send some revised plans to take care of this problem. Steve Robbins 01/19/2018 3:30 PM
PW-Misc
Corrective Action Required
01/30/2018
The engineer for this project still needs to get with Sue to send a submittal over to make sure these storm boxes and curbs get finished properly.Steve Robbins 01/25/2018 3:41 PM
PW-Misc
Corrective Action Required
01/30/2018
The storm boxes need to be grouted by the throat going into the inlet.Steve Robbins 01/30/2018 3:25 PM
PW-Misc
Corrective Action Required
02/06/2018
The storm box situation is not yet resolved. As far as I know the engineer has not yet sent over a new set of plans for the storm boxes.Steve Robbins 02/06/2018 1:32 PM
Storm - Pipe Partial 2/9/2018 at 9:30 AM 02/09/2018
PW-Misc
Corrective Action Required
02/06/2018
All the storm structures have been installed and are completed. At the end of Rosemary Ct. they did not install the road and the throat inlets for the storm boxes. I talked with Sue and there engineer is suppose to get with her about this situation. Steve Robbins 01/11/2018 7:42 AM
PW-Misc
Corrective Action Required
02/06/2018
They have not installed the inlets yet, the engineer for the project is suppose to send some revised plans to take care of this problem. Steve Robbins 01/19/2018 3:30 PM
PW-Misc
Corrective Action Required
02/06/2018
The engineer for this project still needs to get with Sue to send a submittal over to make sure these storm boxes and curbs get finished properly.Steve Robbins 01/25/2018 3:41 PM
PW-Misc
Corrective Action Required
02/06/2018
The storm boxes need to be grouted by the throat going into the inlet.Steve Robbins 01/30/2018 3:25 PM
PW-Misc
Corrective Action Required
02/06/2018
The storm box situation is not yet resolved. As far as I know the engineer has not yet sent over a new set of plans for the storm boxes.Steve Robbins 02/06/2018 1:32 PM
PW-Misc
Corrective Action Required
02/09/2018
Dan and Kent has sent an e-mail say the contractor is required to correct the storm box by installing curb, throat and bringing the road past the storm boxes.Steve Robbins 02/09/2018 1:59 PM
Storm - Pipe Partial 2/13/2018 at 11:20 AM 02/13/2018
PW-Misc
Corrective Action Required
02/09/2018
All the storm structures have been installed and are completed. At the end of Rosemary Ct. they did not install the road and the throat inlets for the storm boxes. I talked with Sue and there engineer is suppose to get with her about this situation. Steve Robbins 01/11/2018 7:42 AM
PW-Misc
Corrective Action Required
02/09/2018
They have not installed the inlets yet, the engineer for the project is suppose to send some revised plans to take care of this problem. Steve Robbins 01/19/2018 3:30 PM
PW-Misc
Corrective Action Required
02/09/2018
The engineer for this project still needs to get with Sue to send a submittal over to make sure these storm boxes and curbs get finished properly.Steve Robbins 01/25/2018 3:41 PM
PW-Misc
Corrective Action Required
02/09/2018
The storm boxes need to be grouted by the throat going into the inlet.Steve Robbins 01/30/2018 3:25 PM
PW-Misc
Corrective Action Required
02/09/2018
The storm box situation is not yet resolved. As far as I know the engineer has not yet sent over a new set of plans for the storm boxes.Steve Robbins 02/06/2018 1:32 PM
PW-Misc
Corrective Action Required
02/09/2018
Dan and Kent has sent an e-mail say the contractor is required to correct the storm box by installing curb, throat and bringing the road past the storm boxes.Steve Robbins 02/09/2018 1:59 PM
PW-Misc
Informational
02/13/2018
The contractor has formed the curb and throats for the 2 storm boxes at the end of rosemary ct. I talked with D.J. and he said he will get with his engineer and talk with Sue so they can get this approved.
Storm - Pipe Partial 2/15/2018 at 1:30 PM 02/15/2018
PW-Misc
Corrective Action Required
02/13/2018
All the storm structures have been installed and are completed. At the end of Rosemary Ct. they did not install the road and the throat inlets for the storm boxes. I talked with Sue and there engineer is suppose to get with her about this situation. Steve Robbins 01/11/2018 7:42 AM
PW-Misc
Corrective Action Required
02/13/2018
They have not installed the inlets yet, the engineer for the project is suppose to send some revised plans to take care of this problem. Steve Robbins 01/19/2018 3:30 PM
PW-Misc
Corrective Action Required
02/13/2018
The engineer for this project still needs to get with Sue to send a submittal over to make sure these storm boxes and curbs get finished properly.Steve Robbins 01/25/2018 3:41 PM
PW-Misc
Corrective Action Required
02/13/2018
The storm boxes need to be grouted by the throat going into the inlet.Steve Robbins 01/30/2018 3:25 PM
PW-Misc
Corrective Action Required
02/13/2018
The storm box situation is not yet resolved. As far as I know the engineer has not yet sent over a new set of plans for the storm boxes.Steve Robbins 02/06/2018 1:32 PM
PW-Misc
Corrective Action Required
02/13/2018
Dan and Kent has sent an e-mail say the contractor is required to correct the storm box by installing curb, throat and bringing the road past the storm boxes.Steve Robbins 02/09/2018 1:59 PM
PW-Misc
Informational
02/13/2018
The contractor has formed the curb and throats for the 2 storm boxes at the end of rosemary ct. I talked with D.J. and he said he will get with his engineer and talk with Sue so they can get this approved.
PW-Misc
Informational
02/15/2018
The plan was approved and all they need to do is install the asphalt 5' past the storm boxes.Steve Robbins 02/15/2018 2:33 PM
Storm - Pipe Partial 2/20/2018 at 2:00 PM 02/20/2018
PW-Misc
Corrective Action Required
02/15/2018
All the storm structures have been installed and are completed. At the end of Rosemary Ct. they did not install the road and the throat inlets for the storm boxes. I talked with Sue and there engineer is suppose to get with her about this situation. Steve Robbins 01/11/2018 7:42 AM
PW-Misc
Corrective Action Required
02/15/2018
They have not installed the inlets yet, the engineer for the project is suppose to send some revised plans to take care of this problem. Steve Robbins 01/19/2018 3:30 PM
PW-Misc
Corrective Action Required
02/15/2018
The engineer for this project still needs to get with Sue to send a submittal over to make sure these storm boxes and curbs get finished properly.Steve Robbins 01/25/2018 3:41 PM
PW-Misc
Corrective Action Required
02/15/2018
The storm boxes need to be grouted by the throat going into the inlet.Steve Robbins 01/30/2018 3:25 PM
PW-Misc
Corrective Action Required
02/15/2018
The storm box situation is not yet resolved. As far as I know the engineer has not yet sent over a new set of plans for the storm boxes.Steve Robbins 02/06/2018 1:32 PM
PW-Misc
Corrective Action Required
02/15/2018
Dan and Kent has sent an e-mail say the contractor is required to correct the storm box by installing curb, throat and bringing the road past the storm boxes.Steve Robbins 02/09/2018 1:59 PM
PW-Misc
Informational
02/15/2018
The contractor has formed the curb and throats for the 2 storm boxes at the end of rosemary ct. I talked with D.J. and he said he will get with his engineer and talk with Sue so they can get this approved.
PW-Misc
Informational
02/15/2018
The plan was approved and all they need to do is install the asphalt 5' past the storm boxes.Steve Robbins 02/15/2018 2:33 PM
PW-Misc
Corrective Action Required
02/20/2018
The contrators have put in the curb and throat for the inlets on the 2 storm boxes. I cannot give them a substantial completion until they get the asphalt base and surface installed. When I talked with D.J. he said they will put it in when they fix the parking lot.Steve Robbins 02/20/2018 2:56 PM
Storm - Pipe Passed 3/13/2018 at 10:45 AM 03/21/2018
PW-Misc
Corrective Action Required
02/20/2018
All the storm structures have been installed and are completed. At the end of Rosemary Ct. they did not install the road and the throat inlets for the storm boxes. I talked with Sue and there engineer is suppose to get with her about this situation. Steve Robbins 01/11/2018 7:42 AM
PW-Misc
Corrective Action Required
02/20/2018
They have not installed the inlets yet, the engineer for the project is suppose to send some revised plans to take care of this problem. Steve Robbins 01/19/2018 3:30 PM
PW-Misc
Corrective Action Required
02/20/2018
The engineer for this project still needs to get with Sue to send a submittal over to make sure these storm boxes and curbs get finished properly.Steve Robbins 01/25/2018 3:41 PM
PW-Misc
Corrective Action Required
02/20/2018
The storm boxes need to be grouted by the throat going into the inlet.Steve Robbins 01/30/2018 3:25 PM
PW-Misc
Corrective Action Required
02/20/2018
The storm box situation is not yet resolved. As far as I know the engineer has not yet sent over a new set of plans for the storm boxes.Steve Robbins 02/06/2018 1:32 PM
PW-Misc
Corrective Action Required
02/20/2018
Dan and Kent has sent an e-mail say the contractor is required to correct the storm box by installing curb, throat and bringing the road past the storm boxes.Steve Robbins 02/09/2018 1:59 PM
PW-Misc
Informational
02/20/2018
The contractor has formed the curb and throats for the 2 storm boxes at the end of rosemary ct. I talked with D.J. and he said he will get with his engineer and talk with Sue so they can get this approved.
PW-Misc
Informational
02/20/2018
The plan was approved and all they need to do is install the asphalt 5' past the storm boxes.Steve Robbins 02/15/2018 2:33 PM
PW-Misc
Corrective Action Required
02/20/2018
The contrators have put in the curb and throat for the inlets on the 2 storm boxes. I cannot give them a substantial completion until they get the asphalt base and surface installed. When I talked with D.J. he said they will put it in when they fix the parking lot.Steve Robbins 02/20/2018 2:56 PM
PW-Misc
Resolved
03/21/2018
The storm box inlets have been installed and the curb and throat also. The contractor has also installed the rest of the subgrade and the asphalt to finish the road. They also installed the end of road signs .Steve Robbins 03/21/2018 3:51 PM
ESC - (Vegetation/Ground Cover) Partial 3/26/2018 at 1:00 PM 03/26/2018
PW-Misc
Corrective Action Required
03/26/2018
The vegetaion has not yet been installed.Steve Robbins 03/26/2018 2:43 PM
ESC - (Vegetation/Ground Cover) Partial 3/29/2018 at 9:30 AM 04/03/2018
PW-Misc
Corrective Action Required
03/26/2018
The vegetaion has not yet been installed.Steve Robbins 03/26/2018 2:43 PM
PW-Misc
Informational
04/03/2018
It has been very muddy and wet the last week, they have not been able to get the seed and straw in yet.Steve Robbins 04/03/2018 3:23 PM
ESC - (Vegetation/Ground Cover) Partial 4/18/2018 at 8:30 AM 04/18/2018
PW-Misc
Corrective Action Required
04/03/2018
The vegetaion has not yet been installed.Steve Robbins 03/26/2018 2:43 PM
PW-Misc
Informational
04/03/2018
It has been very muddy and wet the last week, they have not been able to get the seed and straw in yet.Steve Robbins 04/03/2018 3:23 PM
PW-Misc
Informational
04/18/2018
Yesterday and today the contractors have been cleaning up the propery from rock and debris. They have also been hydroseeding the entire site. They have not yet finished everything yet, they still have about 20% left to complete.Steve Robbins 04/18/2018 2:12 PM
ESC - (Vegetation/Ground Cover) Partial 4/30/2018 at 9:45 AM 04/30/2018
PW-Misc
Corrective Action Required
04/18/2018
The vegetaion has not yet been installed.Steve Robbins 03/26/2018 2:43 PM
PW-Misc
Informational
04/18/2018
It has been very muddy and wet the last week, they have not been able to get the seed and straw in yet.Steve Robbins 04/03/2018 3:23 PM
PW-Misc
Informational
04/18/2018
Yesterday and today the contractors have been cleaning up the propery from rock and debris. They have also been hydroseeding the entire site. They have not yet finished everything yet, they still have about 20% left to complete.Steve Robbins 04/18/2018 2:12 PM
PW-Misc
Informational
04/30/2018
All the hydro-seeding has been completed on the entire site.Steve Robbins 04/30/2018 2:23 PM
Water - Material Verification Passed 05/04/2018
Water - Material Verification Passed 05/11/2018
ESC - (Vegetation/Ground Cover) Partial 5/31/2018 at 2:15 PM 05/30/2018
PW-Misc
Corrective Action Required
04/30/2018
The vegetaion has not yet been installed.Steve Robbins 03/26/2018 2:43 PM
PW-Misc
Informational
04/30/2018
It has been very muddy and wet the last week, they have not been able to get the seed and straw in yet.Steve Robbins 04/03/2018 3:23 PM
PW-Misc
Informational
04/30/2018
Yesterday and today the contractors have been cleaning up the propery from rock and debris. They have also been hydroseeding the entire site. They have not yet finished everything yet, they still have about 20% left to complete.Steve Robbins 04/18/2018 2:12 PM
PW-Misc
Informational
04/30/2018
All the hydro-seeding has been completed on the entire site.Steve Robbins 04/30/2018 2:23 PM
PW-Misc
Informational
05/30/2018
The vegetation has not been established yet.Steve Robbins 05/30/2018 4:03 PM
ESC - (Vegetation/Ground Cover) Partial 8/9/2018 at 8:15 AM 08/09/2018
PW-Misc
Corrective Action Required
05/30/2018
The vegetaion has not yet been installed.Steve Robbins 03/26/2018 2:43 PM
PW-Misc
Informational
05/30/2018
It has been very muddy and wet the last week, they have not been able to get the seed and straw in yet.Steve Robbins 04/03/2018 3:23 PM
PW-Misc
Informational
05/30/2018
Yesterday and today the contractors have been cleaning up the propery from rock and debris. They have also been hydroseeding the entire site. They have not yet finished everything yet, they still have about 20% left to complete.Steve Robbins 04/18/2018 2:12 PM
PW-Misc
Informational
05/30/2018
All the hydro-seeding has been completed on the entire site.Steve Robbins 04/30/2018 2:23 PM
PW-Misc
Informational
05/30/2018
The vegetation has not been established yet.Steve Robbins 05/30/2018 4:03 PM
PW-Misc
Informational
08/09/2018
The vegetation has not been established yet.Steve Robbins 08/09/2018 2:06 PM
ESC - (Vegetation/Ground Cover) Passed 12/26/2018 at 3:00 PM 01/22/2019
PW-Misc
Corrective Action Required
08/09/2018
The vegetaion has not yet been installed.Steve Robbins 03/26/2018 2:43 PM
PW-Misc
Informational
08/09/2018
It has been very muddy and wet the last week, they have not been able to get the seed and straw in yet.Steve Robbins 04/03/2018 3:23 PM
PW-Misc
Informational
08/09/2018
Yesterday and today the contractors have been cleaning up the propery from rock and debris. They have also been hydroseeding the entire site. They have not yet finished everything yet, they still have about 20% left to complete.Steve Robbins 04/18/2018 2:12 PM
PW-Misc
Informational
08/09/2018
All the hydro-seeding has been completed on the entire site.Steve Robbins 04/30/2018 2:23 PM
PW-Misc
Informational
08/09/2018
The vegetation has not been established yet.Steve Robbins 05/30/2018 4:03 PM
PW-Misc
Informational
08/09/2018
The vegetation has not been established yet.Steve Robbins 08/09/2018 2:06 PM
Storm - Inlets Clean Passed 01/28/2019
Erosion Control Inspection Passed 01/28/2019
Documents & Images
Date Uploaded File Type Document Name
08/23/2017 Receipt Receipt for transaction: 2017-005938
08/28/2017 Letter PW-Permit
09/06/2017 DOC090617-09062017071006
12/14/2017 Letter DE-Daily Inspection Summary
01/11/2018 Letter DE-Daily Inspection Summary
01/19/2018 Letter DE-Daily Inspection Summary
01/25/2018 Letter DE-Daily Inspection Summary
01/30/2018 Letter DE-Daily Inspection Summary
02/06/2018 Letter DE-Daily Inspection Summary
02/09/2018 Letter DE-Daily Inspection Summary
02/13/2018 Letter DE-Daily Inspection Summary
02/15/2018 Letter DE-Daily Inspection Summary
02/20/2018 Letter DE-Daily Inspection Summary
03/26/2018 Letter DE-Daily Inspection Summary
04/03/2018 Letter DE-Daily Inspection Summary
04/18/2018 Letter DE-Daily Inspection Summary
04/30/2018 Letter DE-Daily Inspection Summary
05/02/2018 Letter DE-Punch List
05/02/2018 Letter DE-Certificate of Substantial Completion Multiple Lot
05/04/2018 Summit Village Substantial and Punch List
05/30/2018 Letter DE-Daily Inspection Summary
08/09/2018 Letter DE-Daily Inspection Summary
01/22/2019 Summit Village Substantial and Punch List
01/28/2019 Letter DE-Certificate of Final Acceptance (Commercial)
01/28/2019 Summit Village Final Acceptance
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home