Summary


PRPWFC20162146
Public Works Infrastructure Permit - Commercial
Final Completion
TOWNSEND SUMMIT LLC
DEVELOPMENT COMPLETE
Commercial development improvements
08/24/2016
09/07/2016
03/17/2017
Locations
Contacts
TOWNSEND SUMMIT LLC, Address:1311 MCCORMICK RD STE 470, Phone:(303) 947-2044  
EMERY SAPP AND SONS INC, Address:2301 I-70 DR NW, Phone:(573) 445-8331  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 08/24/2016 08/30/2016
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $4,056.68 $4,056.68 Paid 08/26/2016
91100C9-Water Insp Fee $3,749.77 $3,749.77 Paid 10/03/2016
9110072-Water Test Fee $800.00 $800.00 Paid 10/03/2016
9110068-Storm Fee $7,349.76 $7,349.76 Paid 09/07/2016
9110081-Paved Surface Inspection Fee $22,813.13 $22,813.13 Paid 09/07/2016
9110071-Site Grading Fee $2,318.88 $2,318.88 Paid 09/07/2016
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sanitary Sewer Construction Inspection Passed 10/10/2016 10/10/2016
PW-Misc
Informational
10/07/2016
Everything has been backfilled after the core drill into the existing MH . MH A-1 has been installed after the sanitary pipe was connected to the bore, they are laying pipe up to MH A-2 which will probably be installed tomorrow. Steve Robbins 09/26/2016 4:13 PM
PW-Misc
Informational
10/07/2016
MH A-1 is completed, pipe is in inverts are poured. MH A-2 is also installed but the inverts are not in yet. Pipe is now being installed toward MH A-3, they have been hitting alot of rock. Steve Robbins 09/28/2016 4:19 PM
PW-Misc
Informational
10/07/2016
MH A-1 has been installed and invert has been poured and grouted. MH A-2 is installed and pipe has been installed and now are installing toward MH A-3 the inverts have not been poured yet Steve Robbins 09/28/2016 4:27 PM
PW-Misc
Informational
10/07/2016
MH A-3 was installed this morning, the pipe and rock was also installed. This afternoon the pipe and rock was installed along with MH A-5 . They are working their way toward MH A-4.Steve Robbins 10/03/2016 3:17 PM
PW-Misc
Informational
10/07/2016
Today the sanitary pipe was laid in with rock all the way up to MH A-3, They will install MH A-3 in the morning. Steve Robbins 09/29/2016 3:40 PM
PW-Misc
Informational
10/07/2016
The bore underneath the railroad tracks has been copleted and the pipe is through. Today they core drill into the existing MH on the other side of the railroad tracks. They had to remove a storm pipe that was in the way, so they connected it and put a new piece of storm pipe in. At the end of the day they were back on the west side of the tracks laying sanitary pipe up to the next MH. Steve Robbins 09/22/2016 4:49 PM
PW-Misc
Corrective Action Required
10/07/2016
On 9/19 and today they were putting the sanitary pipe through the steel encasement but are having trouble because the spacers are moving because they are hitting the spots where they welded the steel pipes together. They think they have the problem fixed and will finish getting it through by tomorrow. They are planning on core drilling into the MH tomorrow.Steve Robbins 09/20/2016 4:32 PM
PW-Misc
Informational
10/07/2016
Starting on friday 9/8/16 the boring company arrived and was setting up for the bore underneath the railroad tracks. 9/10/16 they started and as of today 9/13 they are about 15 ft. from getting through to the other side. They think they will be finished today. Steve Robbins 09/13/2016 12:06 PM
PW-Misc
Informational
10/07/2016
The bore underneath the railroad tracks has been completed , now emery will put the sanitary sewer pipe in . Steve Robbins 09/14/2016 2:25 PM
PW-Misc
Informational
10/07/2016
On 10/4/16 MH A-5 and sanitary pipe was installed. On 10/5/16 MH A-4 was installed with pipe and pipe was laid up to MH B-1. On 10/6/16 MH B-1 was installed and pipe was laid up to MH B-2.Steve Robbins 10/07/2016 9:17 AM
PW-Misc
Informational
10/10/2016
MH B-2 has been installed. That completes all the sanitary sewer, all the inverts have been poured. They did some preliminary testing on friday and today. Now we can wait 30 days for the testing.Steve Robbins 10/10/2016 5:04 PM
Sanitary Sewer Construction Inspection Passed 11/17/2016
Sanitary Sewer - Air Test Passed 11/17/2016
Sanitary Sewer - Mandrel Passed 11/17/2016
Sanitary Sewer - Vacuum Passed 11/17/2016
Sanitary Sewer - Invert Passed 11/17/2016
Grading/Excavation/Fill Inspection Passed 11/17/2016
Curb - Proof Roll Passed 11/17/2016
Pavement-Proof Roll Passed 11/17/2016
Pavement-Surface Passed 11/17/2016
Street - Wedge Lift Passed 11/17/2016
Street - Surface Course Passed 11/17/2016
Storm - Pipe Passed 10/10/2016 11/17/2016
PW-Misc
Informational
10/24/2016
Today structures b2 B3 and B4 have been installed,. Steve Robbins 10/24/2016 3:18 PM
Storm - Rip Rap Passed 11/17/2016
Storm - Pipe Passed 10/25/2016 12/02/2016
PW-Misc
Informational
10/24/2016
Today structures b2 B3 and B4 have been installed,. Steve Robbins 10/24/2016 3:18 PM
Water Line - Fire Hydrant Passed 10/26/2016 12/02/2016
PW-Misc
Informational
10/24/2016
The 8 " water main has been constructed from the connections point beginning at ward rd. continuing on donovan rd. All the fire hydrants , valves, and thrust blocks have also been installed. They made a tie in on chipman rd 10/19/16 , they shut the water down , used bleach to clean the pipes for the tie in and then poly wrapped all the joints . They used rock over the pipes , they used concrete on top to finish it off. The water main is completed except for 3 valve pipes at the end of donovan by chipman rd.Steve Robbins 10/24/2016 3:08 PM
Install Street and Stop Signs Passed 12/15/2016
Curb - Compression Strength Passed 12/15/2016
Storm - Inlets Clean Passed 12/15/2016
Storm - Outlet Structure Passed 12/15/2016
Storm - Swales Passed 12/15/2016
ESC - (Vegetation/Ground Cover) Passed 12/15/2016
Water Line - Fire Hydrant Passed 12/19/2016
Erosion Control Inspection Passed 12/19/2016
Water Line - Coliform Test 2 Passed 11/3/2016 12/19/2016
Water Line - Coliform Test 1 Passed 11/4/2016 12/19/2016
Water Line - Construction Taps Removed Passed 12/19/2016
Water Line - Fire Hydrant Passed 12/19/2016
Sanitary Sewer Construction Inspection Passed 03/15/2017
PW-Misc
Informational
09/13/2016
Starting on friday 9/8/16 the boring company arrived and was setting up for the bore underneath the railroad tracks. 9/10/16 they started and as of today 9/13 they are about 15 ft. from getting through to the other side. They think they will be finished today. Steve Robbins 09/13/2016 12:06 PM
Sanitary Sewer Construction Inspection Passed 9/14/2016 03/15/2017
PW-Misc
Informational
09/13/2016
Starting on friday 9/8/16 the boring company arrived and was setting up for the bore underneath the railroad tracks. 9/10/16 they started and as of today 9/13 they are about 15 ft. from getting through to the other side. They think they will be finished today. Steve Robbins 09/13/2016 12:06 PM
PW-Misc
Informational
09/14/2016
The bore underneath the railroad tracks has been completed , now emery will put the sanitary sewer pipe in . Steve Robbins 09/14/2016 2:25 PM
Sanitary Sewer Construction Inspection Passed 9/16/2016 03/15/2017
PW-Misc
Corrective Action Required
09/20/2016
On 9/19 and today they were putting the sanitary pipe through the steel encasement but are having trouble because the spacers are moving because they are hitting the spots where they welded the steel pipes together. They think they have the problem fixed and will finish getting it through by tomorrow. They are planning on core drilling into the MH tomorrow.Steve Robbins 09/20/2016 4:32 PM
PW-Misc
Informational
09/14/2016
Starting on friday 9/8/16 the boring company arrived and was setting up for the bore underneath the railroad tracks. 9/10/16 they started and as of today 9/13 they are about 15 ft. from getting through to the other side. They think they will be finished today. Steve Robbins 09/13/2016 12:06 PM
PW-Misc
Informational
09/14/2016
The bore underneath the railroad tracks has been completed , now emery will put the sanitary sewer pipe in . Steve Robbins 09/14/2016 2:25 PM
Sanitary Sewer Construction Inspection Passed 9/21/2016 03/15/2017
PW-Misc
Corrective Action Required
09/20/2016
On 9/19 and today they were putting the sanitary pipe through the steel encasement but are having trouble because the spacers are moving because they are hitting the spots where they welded the steel pipes together. They think they have the problem fixed and will finish getting it through by tomorrow. They are planning on core drilling into the MH tomorrow.Steve Robbins 09/20/2016 4:32 PM
PW-Misc
Informational
09/22/2016
The bore underneath the railroad tracks has been copleted and the pipe is through. Today they core drill into the existing MH on the other side of the railroad tracks. They had to remove a storm pipe that was in the way, so they connected it and put a new piece of storm pipe in. At the end of the day they were back on the west side of the tracks laying sanitary pipe up to the next MH. Steve Robbins 09/22/2016 4:49 PM
PW-Misc
Informational
09/20/2016
Starting on friday 9/8/16 the boring company arrived and was setting up for the bore underneath the railroad tracks. 9/10/16 they started and as of today 9/13 they are about 15 ft. from getting through to the other side. They think they will be finished today. Steve Robbins 09/13/2016 12:06 PM
PW-Misc
Informational
09/20/2016
The bore underneath the railroad tracks has been completed , now emery will put the sanitary sewer pipe in . Steve Robbins 09/14/2016 2:25 PM
Sanitary Sewer Construction Inspection Passed 9/26/2016 03/15/2017
PW-Misc
Informational
09/22/2016
The bore underneath the railroad tracks has been copleted and the pipe is through. Today they core drill into the existing MH on the other side of the railroad tracks. They had to remove a storm pipe that was in the way, so they connected it and put a new piece of storm pipe in. At the end of the day they were back on the west side of the tracks laying sanitary pipe up to the next MH. Steve Robbins 09/22/2016 4:49 PM
PW-Misc
Corrective Action Required
09/22/2016
On 9/19 and today they were putting the sanitary pipe through the steel encasement but are having trouble because the spacers are moving because they are hitting the spots where they welded the steel pipes together. They think they have the problem fixed and will finish getting it through by tomorrow. They are planning on core drilling into the MH tomorrow.Steve Robbins 09/20/2016 4:32 PM
PW-Misc
Informational
09/22/2016
Starting on friday 9/8/16 the boring company arrived and was setting up for the bore underneath the railroad tracks. 9/10/16 they started and as of today 9/13 they are about 15 ft. from getting through to the other side. They think they will be finished today. Steve Robbins 09/13/2016 12:06 PM
PW-Misc
Informational
09/22/2016
The bore underneath the railroad tracks has been completed , now emery will put the sanitary sewer pipe in . Steve Robbins 09/14/2016 2:25 PM
PW-Misc
Informational
09/26/2016
Everything has been backfilled after the core drill into the existing MH . MH A-1 has been installed after the sanitary pipe was connected to the bore, they are laying pipe up to MH A-2 which will probably be installed tomorrow. Steve Robbins 09/26/2016 4:13 PM
Sanitary Sewer Construction Inspection Passed 9/27/2016 03/15/2017
PW-Misc
Informational
09/26/2016
The bore underneath the railroad tracks has been copleted and the pipe is through. Today they core drill into the existing MH on the other side of the railroad tracks. They had to remove a storm pipe that was in the way, so they connected it and put a new piece of storm pipe in. At the end of the day they were back on the west side of the tracks laying sanitary pipe up to the next MH. Steve Robbins 09/22/2016 4:49 PM
PW-Misc
Corrective Action Required
09/26/2016
On 9/19 and today they were putting the sanitary pipe through the steel encasement but are having trouble because the spacers are moving because they are hitting the spots where they welded the steel pipes together. They think they have the problem fixed and will finish getting it through by tomorrow. They are planning on core drilling into the MH tomorrow.Steve Robbins 09/20/2016 4:32 PM
PW-Misc
Informational
09/26/2016
Starting on friday 9/8/16 the boring company arrived and was setting up for the bore underneath the railroad tracks. 9/10/16 they started and as of today 9/13 they are about 15 ft. from getting through to the other side. They think they will be finished today. Steve Robbins 09/13/2016 12:06 PM
PW-Misc
Informational
09/26/2016
The bore underneath the railroad tracks has been completed , now emery will put the sanitary sewer pipe in . Steve Robbins 09/14/2016 2:25 PM
PW-Misc
Informational
09/26/2016
Everything has been backfilled after the core drill into the existing MH . MH A-1 has been installed after the sanitary pipe was connected to the bore, they are laying pipe up to MH A-2 which will probably be installed tomorrow. Steve Robbins 09/26/2016 4:13 PM
PW-Misc
Informational
09/28/2016
MH A-1 is completed, pipe is in inverts are poured. MH A-2 is also installed but the inverts are not in yet. Pipe is now being installed toward MH A-3, they have been hitting alot of rock. Steve Robbins 09/28/2016 4:19 PM
Sanitary Sewer Construction Inspection Passed 9/28/2016 03/15/2017
PW-Misc
Informational
09/28/2016
The bore underneath the railroad tracks has been copleted and the pipe is through. Today they core drill into the existing MH on the other side of the railroad tracks. They had to remove a storm pipe that was in the way, so they connected it and put a new piece of storm pipe in. At the end of the day they were back on the west side of the tracks laying sanitary pipe up to the next MH. Steve Robbins 09/22/2016 4:49 PM
PW-Misc
Corrective Action Required
09/28/2016
On 9/19 and today they were putting the sanitary pipe through the steel encasement but are having trouble because the spacers are moving because they are hitting the spots where they welded the steel pipes together. They think they have the problem fixed and will finish getting it through by tomorrow. They are planning on core drilling into the MH tomorrow.Steve Robbins 09/20/2016 4:32 PM
PW-Misc
Informational
09/28/2016
Starting on friday 9/8/16 the boring company arrived and was setting up for the bore underneath the railroad tracks. 9/10/16 they started and as of today 9/13 they are about 15 ft. from getting through to the other side. They think they will be finished today. Steve Robbins 09/13/2016 12:06 PM
PW-Misc
Informational
09/28/2016
The bore underneath the railroad tracks has been completed , now emery will put the sanitary sewer pipe in . Steve Robbins 09/14/2016 2:25 PM
PW-Misc
Informational
09/28/2016
Everything has been backfilled after the core drill into the existing MH . MH A-1 has been installed after the sanitary pipe was connected to the bore, they are laying pipe up to MH A-2 which will probably be installed tomorrow. Steve Robbins 09/26/2016 4:13 PM
PW-Misc
Informational
09/28/2016
MH A-1 is completed, pipe is in inverts are poured. MH A-2 is also installed but the inverts are not in yet. Pipe is now being installed toward MH A-3, they have been hitting alot of rock. Steve Robbins 09/28/2016 4:19 PM
PW-Misc
Informational
09/28/2016
MH A-1 has been installed and invert has been poured and grouted. MH A-2 is installed and pipe has been installed and now are installing toward MH A-3 the inverts have not been poured yet Steve Robbins 09/28/2016 4:27 PM
Sanitary Sewer Construction Inspection Passed 9/29/2016 03/15/2017
PW-Misc
Informational
09/28/2016
The bore underneath the railroad tracks has been copleted and the pipe is through. Today they core drill into the existing MH on the other side of the railroad tracks. They had to remove a storm pipe that was in the way, so they connected it and put a new piece of storm pipe in. At the end of the day they were back on the west side of the tracks laying sanitary pipe up to the next MH. Steve Robbins 09/22/2016 4:49 PM
PW-Misc
Informational
09/29/2016
Today the sanitary pipe was laid in with rock all the way up to MH A-3, They will install MH A-3 in the morning. Steve Robbins 09/29/2016 3:40 PM
PW-Misc
Corrective Action Required
09/28/2016
On 9/19 and today they were putting the sanitary pipe through the steel encasement but are having trouble because the spacers are moving because they are hitting the spots where they welded the steel pipes together. They think they have the problem fixed and will finish getting it through by tomorrow. They are planning on core drilling into the MH tomorrow.Steve Robbins 09/20/2016 4:32 PM
PW-Misc
Informational
09/28/2016
Starting on friday 9/8/16 the boring company arrived and was setting up for the bore underneath the railroad tracks. 9/10/16 they started and as of today 9/13 they are about 15 ft. from getting through to the other side. They think they will be finished today. Steve Robbins 09/13/2016 12:06 PM
PW-Misc
Informational
09/28/2016
The bore underneath the railroad tracks has been completed , now emery will put the sanitary sewer pipe in . Steve Robbins 09/14/2016 2:25 PM
PW-Misc
Informational
09/28/2016
Everything has been backfilled after the core drill into the existing MH . MH A-1 has been installed after the sanitary pipe was connected to the bore, they are laying pipe up to MH A-2 which will probably be installed tomorrow. Steve Robbins 09/26/2016 4:13 PM
PW-Misc
Informational
09/28/2016
MH A-1 is completed, pipe is in inverts are poured. MH A-2 is also installed but the inverts are not in yet. Pipe is now being installed toward MH A-3, they have been hitting alot of rock. Steve Robbins 09/28/2016 4:19 PM
PW-Misc
Informational
09/28/2016
MH A-1 has been installed and invert has been poured and grouted. MH A-2 is installed and pipe has been installed and now are installing toward MH A-3 the inverts have not been poured yet Steve Robbins 09/28/2016 4:27 PM
Sanitary Sewer Construction Inspection Passed 9/30/2016 03/15/2017
PW-Misc
Informational
09/29/2016
Today the sanitary pipe was laid in with rock all the way up to MH A-3, They will install MH A-3 in the morning. Steve Robbins 09/29/2016 3:40 PM
PW-Misc
Informational
09/29/2016
The bore underneath the railroad tracks has been copleted and the pipe is through. Today they core drill into the existing MH on the other side of the railroad tracks. They had to remove a storm pipe that was in the way, so they connected it and put a new piece of storm pipe in. At the end of the day they were back on the west side of the tracks laying sanitary pipe up to the next MH. Steve Robbins 09/22/2016 4:49 PM
PW-Misc
Corrective Action Required
09/29/2016
On 9/19 and today they were putting the sanitary pipe through the steel encasement but are having trouble because the spacers are moving because they are hitting the spots where they welded the steel pipes together. They think they have the problem fixed and will finish getting it through by tomorrow. They are planning on core drilling into the MH tomorrow.Steve Robbins 09/20/2016 4:32 PM
PW-Misc
Informational
09/29/2016
Starting on friday 9/8/16 the boring company arrived and was setting up for the bore underneath the railroad tracks. 9/10/16 they started and as of today 9/13 they are about 15 ft. from getting through to the other side. They think they will be finished today. Steve Robbins 09/13/2016 12:06 PM
PW-Misc
Informational
09/29/2016
The bore underneath the railroad tracks has been completed , now emery will put the sanitary sewer pipe in . Steve Robbins 09/14/2016 2:25 PM
PW-Misc
Informational
09/29/2016
Everything has been backfilled after the core drill into the existing MH . MH A-1 has been installed after the sanitary pipe was connected to the bore, they are laying pipe up to MH A-2 which will probably be installed tomorrow. Steve Robbins 09/26/2016 4:13 PM
PW-Misc
Informational
09/29/2016
MH A-1 is completed, pipe is in inverts are poured. MH A-2 is also installed but the inverts are not in yet. Pipe is now being installed toward MH A-3, they have been hitting alot of rock. Steve Robbins 09/28/2016 4:19 PM
PW-Misc
Informational
09/29/2016
MH A-1 has been installed and invert has been poured and grouted. MH A-2 is installed and pipe has been installed and now are installing toward MH A-3 the inverts have not been poured yet Steve Robbins 09/28/2016 4:27 PM
PW-Misc
Informational
10/03/2016
MH A-3 was installed this morning, the pipe and rock was also installed. This afternoon the pipe and rock was installed along with MH A-5 . They are working their way toward MH A-4.Steve Robbins 10/03/2016 3:17 PM
Water Line - Coliform Test 1 Passed 11/2/2016 03/15/2017
Sanitary Sewer Construction Inspection Passed 10/4/2016 03/15/2017
PW-Misc
Informational
10/03/2016
Today the sanitary pipe was laid in with rock all the way up to MH A-3, They will install MH A-3 in the morning. Steve Robbins 09/29/2016 3:40 PM
PW-Misc
Informational
10/03/2016
The bore underneath the railroad tracks has been copleted and the pipe is through. Today they core drill into the existing MH on the other side of the railroad tracks. They had to remove a storm pipe that was in the way, so they connected it and put a new piece of storm pipe in. At the end of the day they were back on the west side of the tracks laying sanitary pipe up to the next MH. Steve Robbins 09/22/2016 4:49 PM
PW-Misc
Corrective Action Required
10/03/2016
On 9/19 and today they were putting the sanitary pipe through the steel encasement but are having trouble because the spacers are moving because they are hitting the spots where they welded the steel pipes together. They think they have the problem fixed and will finish getting it through by tomorrow. They are planning on core drilling into the MH tomorrow.Steve Robbins 09/20/2016 4:32 PM
PW-Misc
Informational
10/03/2016
Starting on friday 9/8/16 the boring company arrived and was setting up for the bore underneath the railroad tracks. 9/10/16 they started and as of today 9/13 they are about 15 ft. from getting through to the other side. They think they will be finished today. Steve Robbins 09/13/2016 12:06 PM
PW-Misc
Informational
10/03/2016
The bore underneath the railroad tracks has been completed , now emery will put the sanitary sewer pipe in . Steve Robbins 09/14/2016 2:25 PM
PW-Misc
Informational
10/03/2016
Everything has been backfilled after the core drill into the existing MH . MH A-1 has been installed after the sanitary pipe was connected to the bore, they are laying pipe up to MH A-2 which will probably be installed tomorrow. Steve Robbins 09/26/2016 4:13 PM
PW-Misc
Informational
10/03/2016
MH A-1 is completed, pipe is in inverts are poured. MH A-2 is also installed but the inverts are not in yet. Pipe is now being installed toward MH A-3, they have been hitting alot of rock. Steve Robbins 09/28/2016 4:19 PM
PW-Misc
Informational
10/03/2016
MH A-1 has been installed and invert has been poured and grouted. MH A-2 is installed and pipe has been installed and now are installing toward MH A-3 the inverts have not been poured yet Steve Robbins 09/28/2016 4:27 PM
PW-Misc
Informational
10/03/2016
MH A-3 was installed this morning, the pipe and rock was also installed. This afternoon the pipe and rock was installed along with MH A-5 . They are working their way toward MH A-4.Steve Robbins 10/03/2016 3:17 PM
PW-Misc
Informational
10/07/2016
On 10/4/16 MH A-5 and sanitary pipe was installed. On 10/5/16 MH A-4 was installed with pipe and pipe was laid up to MH B-1. On 10/6/16 MH B-1 was installed and pipe was laid up to MH B-2.Steve Robbins 10/07/2016 9:17 AM
Water Line - Fire Hydrant Passed 10/24/2016 03/15/2017
PW-Misc
Informational
10/24/2016
The 8 " water main has been constructed from the connections point beginning at ward rd. continuing on donovan rd. All the fire hydrants , valves, and thrust blocks have also been installed. They made a tie in on chipman rd 10/19/16 , they shut the water down , used bleach to clean the pipes for the tie in and then poly wrapped all the joints . They used rock over the pipes , they used concrete on top to finish it off. The water main is completed except for 3 valve pipes at the end of donovan by chipman rd.Steve Robbins 10/24/2016 3:08 PM
Documents & Images
Date Uploaded File Type Document Name
08/26/2016 Receipt Receipt for transaction: 2016-005673
08/30/2016 Letter PW-Permit
08/30/2016 Letter PW-Permit
08/31/2016 Letter PW-Permit
08/31/2016 Letter PW-Permit
09/01/2016 C001 - COVER
09/01/2016 C002 - STANDARD NOTES/LEGEND
09/01/2016 C101 - MASS GRADING PLAN
09/01/2016 C102 - EROSION CONTROL PLAN
09/01/2016 C103 - EROSION CONTROL PLAN
09/01/2016 C104 - EROSION CONTROL PLAN
09/01/2016 C105 - WARD RD WIDENING
09/01/2016 C106 - CHIPMAN RD WIDENING
09/01/2016 C107 - DONOVAN RD PLAN & PROFILE
09/01/2016 C108 - DONOVAN RD PLAN & PROFILE
09/01/2016 C109 - DONOVAN RD PLAN & PROFILE
09/01/2016 C110 -
09/01/2016 C111
09/01/2016 C112
09/01/2016 C113
09/01/2016 C201
09/01/2016 C202
09/01/2016 C203
09/01/2016 C204
09/01/2016 C205
09/01/2016 C206
09/01/2016 C207
09/01/2016 C208
09/01/2016 C209
09/01/2016 C210
09/01/2016 C211
09/01/2016 C501
09/01/2016 C502
09/01/2016 C503
09/01/2016 C504
09/01/2016 C505
09/01/2016 C601
09/01/2016 C602
09/01/2016 C603
09/01/2016 C604
09/01/2016 C605
09/01/2016 L101
09/01/2016 L102
09/01/2016 L103
09/01/2016 L104
09/01/2016 L105
09/01/2016 L106
09/01/2016 L107
09/01/2016 L108
09/01/2016 L109
09/01/2016 L110
09/01/2016 SL-1
09/01/2016 SL-2
09/01/2016 SL-3
09/01/2016 SL-4
09/01/2016 SL-5
09/07/2016 Receipt Receipt for transaction: 2016-005855
09/07/2016 Letter PW-Permit
09/13/2016 Letter PW-Daily Inspection Summary
09/14/2016 Letter PW-Daily Inspection Summary
09/20/2016 Letter PW-Daily Inspection Summary
09/22/2016 Letter PW-Daily Inspection Summary
09/26/2016 Letter PW-Daily Inspection Summary
09/28/2016 Letter PW-Daily Inspection Summary
09/29/2016 Letter PW-Daily Inspection Summary
10/03/2016 Receipt Receipt for transaction: 2016-006215
10/03/2016 Letter PW-Permit
10/03/2016 Letter PW-Daily Inspection Summary
10/07/2016 Letter PW-Daily Inspection Summary
10/10/2016 Letter PW-Daily Inspection Summary
10/24/2016 Letter PW-Daily Inspection Summary
10/24/2016 Letter PW-Daily Inspection Summary
01/19/2017 Letter PW-Certificate of Substantial Completion Multiple Lot
01/24/2017 Terracon report
03/16/2017 Letter PW-Final Acceptance Commercial
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home