Permit Application Status

PRPWFC20160726


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRPWFC20160726
Public Works Infrastructure Permit - Commercial
Final Acceptance
KRAFT THOMAS ANTHONY TRUST
DEVELOPMENT COMPLETE
Chapman Plaza 1st Phase
04/06/2016
04/06/2016
09/21/2017
07/03/2017
Locations
Contacts
KRAFT THOMAS ANTHONY TRUST, Address:1508 SW HOOK RD  
Not shown for privacy reasons.
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 04/06/2016 06/23/2017
Tom Chandler
Fees
Paid Fees Amount Paid Owing Date Paid
9110081-Paved Surface Inspection Fee $1,328.75 $1,328.75 Paid 04/06/2016
9110071-Site Grading Fee $8.25 $8.25 Paid 04/06/2016
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Proof roll parking lot Passed 11/30/2016 12/20/2016
Commercial Curb Inspection Passed 12/20/2016
Grading/Excavation/Fill Inspection Passed 01/05/2017
PW-Misc
Informational
01/05/2017
Tom Chandler 01/05/2017 10:16 AM Grading has been completed. Established vegetation will need to be completed for Final Acceptance. Remaining stockpile of soil will need to be removed or vegetated as well.
Miscellaneous PWORKS Inspection Passed 01/05/2017
PW-Misc
Informational
12/20/2016
Tom Chandler 12/20/2016 1:50 PM Concrete parking lot has been installled.
Site Visit Partial 1/23/2017 01/24/2017
PW-Misc
Informational
01/18/2017
Tom Chandler 01/18/2017 9:11 AM Rough Grading has been completed. Tom Chandler 01/24/2017 1:50 PM Talked to Tom Kraft about timeline of finishing the phase I construction. Still need to do some fine grading and vegetation. Rip Rap to be installed at end of parking lot as well. Striping still needs to be completed as well.
Site Visit Partial 3/14/2017 03/14/2017
PW-Misc
Informational
01/24/2017
Tom Chandler 01/18/2017 9:11 AM Rough Grading has been completed. Tom Chandler 01/24/2017 1:50 PM Talked to Tom Kraft about timeline of finishing the phase I construction. Still need to do some fine grading and vegetation. Rip Rap to be installed at end of parking lot as well. Striping still needs to be completed as well. Tom Chandler 03/14/2017 3:04 PM Seeding has been done. Striping for parking lot will happen in the next week or two depending on weather.
Site Visit Partial 4/27/2017 04/27/2017
PW-Misc
Informational
03/14/2017
Tom Chandler 01/18/2017 9:11 AM Rough Grading has been completed. Tom Chandler 01/24/2017 1:50 PM Talked to Tom Kraft about timeline of finishing the phase I construction. Still need to do some fine grading and vegetation. Rip Rap to be installed at end of parking lot as well. Striping still needs to be completed as well. Tom Chandler 03/14/2017 3:04 PM Seeding has been done. Striping for parking lot will happen in the next week or two depending on weather. Tom Chandler 04/27/2017 3:08 PM Striping for parking lot has been completed. Still need to install Handicap signs and rip-rap.
Site Visit Complete 6/23/2017 06/23/2017
PW-Misc
Informational
04/27/2017
Tom Chandler 01/18/2017 9:11 AM Rough Grading has been completed. Tom Chandler 01/24/2017 1:50 PM Talked to Tom Kraft about timeline of finishing the phase I construction. Still need to do some fine grading and vegetation. Rip Rap to be installed at end of parking lot as well. Striping still needs to be completed as well. Tom Chandler 03/14/2017 3:04 PM Seeding has been done. Striping for parking lot will happen in the next week or two depending on weather. Tom Chandler 04/27/2017 3:08 PM Striping for parking lot has been completed. Still need to install Handicap signs and rip-rap. Tom Chandler 06/23/2017 8:35 AM Rip-rap has been completed.
Erosion Control Inspection Passed 06/23/2017
Informational
06/23/2017
Tom Chandler 06/23/2017 8:37 AM Seeding has been established and rip-rap has been installed.
Verify Substantial Completion Substantial Completion 6/23/2017 06/23/2017
Documents & Images
Date Uploaded File Type Document Name
04/06/2016 Receipt Receipt for transaction: 2016-001002
04/06/2016 Letter PW-Permit
01/05/2017 Letter PW-Daily Inspection Summary
01/05/2017 Letter PW-Daily Inspection Summary
01/24/2017 Letter PW-Daily Inspection Summary
03/14/2017 Letter PW-Daily Inspection Summary
04/27/2017 Letter PW-Daily Inspection Summary
06/23/2017 Letter PW-Daily Inspection Summary
06/23/2017 Letter PW-Certificate of Substantial Completion Multiple Lot
06/26/2017 DOC062617-06262017144914
07/03/2017 Letter PW-Final Acceptance Commercial
07/03/2017 DOC070317-07032017135246
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home