| Review Type |
Outcome |
Est. Completion Date |
Completed |
|
Building Plan Review
|
Approved with Conditions
|
01/21/2026
|
01/21/2026
|
|
|
Joe Frogge
|
|
|
License Tax - Payment
Corrective Action Required
A one-time impact fee in the form of an excise tax must be collected before occupancy can be granted. Please be advised that additional application, review, and inspection fees do apply and additional information pertaining to this will be provided during that stage of your approval process.
Action required: Comment is informational. The fee will exceed $60,000. Final number will be calculated after square footage information is revised to reflect upper level.
1/21/2026 - Acknowledged in letter.
|
|
|
Code analysis required
A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed.
Action required: Update Code Analysis on A-001 to reflect B occupancy. This building was originally approved for warehouse occupancy.
|
|
|
Planning - Screening of ground mounted equipment
Unified Development Ordinance Article 8, Section 8.180.F
Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened.
Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section. Materials must be listed on plans. Coordinate directly with our Planning Department.
1/21/2026 - Must be either masonry or approved evergreen plantings.
|
|
|
IBC 1606.2 Design dead load - structural
2018 IBC 1606.2 Design dead load. For purposes of design, the actual weights of materials of construction and fixed service equipment shall be used. In the absence of definite information, values used shall be subject to the approval of the building official.
Action required: Provide letter from structural engineer that verifies that existing slab is sufficient to support new walls and floor. (i.e. no column pads or grade beams?)
|
|
|
IMC 606.2.1 Duct detector
2018 IMC 606.2.1 Return air systems. Smoke detectors shall be installed in return air systems with a design capacity greater than 2,000 cfm, in the return air duct or plenum upstream of any filters, exhaust air connections, outdoor air connections, or decontamination equipment and appliances.
Exception: Smoke detectors are not required in the return air system where all portions of the building served by the air distribution system are protected by area smoke detectors connected to a fire alarm system in accordance with the International Fire Code. The area smoke detection system shall comply with Section 606.4.
Action required: Provide duct mounted smoke detectors at all 3 RTUs.
|
|
|
|
|
Fire Plan Review
|
Approved with Conditions
|
01/21/2026
|
01/21/2026
|
|
|
Craig Hill
|
|
|
Construction documents for fire alarm systems
Corrective Action Required
2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.
Action Required: Provide deferred submittal for fire alarm system.
|
|
|
Construction documents - Fire protection systems
Corrective Action Required
2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation.
Action Required: Provide deferred submittal for fire protection system.
|
|
|
|
|
Licensed Contractors
|
Approved
|
01/21/2026
|
01/21/2026
|
|
|
Joe Frogge
|
|
|
|
|
Sprinkler Plan Review
|
Released for Construction
|
01/21/2026
|
01/21/2026
|
|
|
Craig Hill
|
|
|
|
|
Fire Plan Review
|
Approved with Conditions
|
01/07/2026
|
01/09/2026
|
|
|
Joe Frogge
|
|
|
Construction documents for fire alarm systems
Corrective Action Required
2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.
Action Required: Provide deferred submittal for fire alarm system.
|
|
|
Construction documents - Fire protection systems
Corrective Action Required
2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation.
Action Required: Provide deferred submittal for fire protection system.
|
|
|
|
|
Building Plan Review
|
Rejected
|
01/07/2026
|
01/05/2026
|
|
|
Joe Frogge
|
|
|
Project cost
The project cost, which is used to establish the permit fee, is lower than expected.
Action required: Provide cost breakdown for project. $4k seems unlikely to cover this scope of work.
|
|
|
License Tax - Payment
Corrective Action Required
A one-time impact fee in the form of an excise tax must be collected before occupancy can be granted. Please be advised that additional application, review, and inspection fees do apply and additional information pertaining to this will be provided during that stage of your approval process.
Action required: Comment is informational. The fee will exceed $60,000. Final number will be calculated after square footage information is revised to reflect upper level.
|
|
|
IBC 1004.1 Design occupant load
2018 IBC 1004.1 Design occupant load. In determining means of egress requirements, the number of occupants for whom means of egress facilities shall be provided shall be determined in accordance with this section.
Action required: Recalculate occupant load using 1:50 calculation in practice areas. Amend Code Analysis on A-001 and re-calculate plumbing fixture calculations.
|
|
|
Code analysis required
Corrective Action Required
A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed.
Action required: Update Code Analysis on A-001 to reflect B occupancy. This building was originally approved for warehouse occupancy.
|
|
|
IBC 1010.1.10 Panic and fire exit hardware
2018 IBC 1010.1.10 Panic and fire exit hardware. Swinging doors serving a Group H occupancy and swinging doors serving rooms or spaces with an occupant load of 50 or more in a Group A or E occupancy shall not be provided with a latch or lock other than panic hardware or fire exit hardware.
Exceptions:
1. A main exit of a Group A occupancy shall be permitted to have locking devices in accordance with Section 1010.1.9.4, Item 2.
2. Doors provided with panic hardware or fire exit hardware and serving a Group A or E occupancy shall be permitted to be electrically locked in accordance with Section 1010.1.9.9 or 1010.1.9.10.
Action required: Provide panic hardware on doors out of Practice Area 103.0.
|
|
|
Planning - Screening of ground mounted equipment
Corrective Action Required
Unified Development Ordinance Article 8, Section 8.180.F
Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened.
Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section. Materials must be listed on plans. Coordinate directly with our Planning Department.
|
|
|
IBC 1606.2 Design dead load - structural
Corrective Action Required
2018 IBC 1606.2 Design dead load. For purposes of design, the actual weights of materials of construction and fixed service equipment shall be used. In the absence of definite information, values used shall be subject to the approval of the building official.
Action required: Provide letter from structural engineer that verifies that existing slab is sufficient to support new walls and floor. (i.e. no column pads or grade beams?)
|
|
|
IMC 606.2.1 Duct detector
Corrective Action Required
2018 IMC 606.2.1 Return air systems. Smoke detectors shall be installed in return air systems with a design capacity greater than 2,000 cfm, in the return air duct or plenum upstream of any filters, exhaust air connections, outdoor air connections, or decontamination equipment and appliances.
Exception: Smoke detectors are not required in the return air system where all portions of the building served by the air distribution system are protected by area smoke detectors connected to a fire alarm system in accordance with the International Fire Code. The area smoke detection system shall comply with Section 606.4.
Action required: Provide duct mounted smoke detectors at all 3 RTUs.
|
|
|
|
|
Licensed Contractors
|
Approved
|
01/07/2026
|
01/05/2026
|
|
|
Joe Frogge
|
|
|
|
|
Zoning Review
|
Approved
|
01/07/2026
|
01/01/2026
|
|
|
Joe Frogge
|
|
|
|
|
Alarm Plan Review
|
Pending
|
|
|
|
|
Craig Hill
|
|
|
|