Permit Application Status

PRCOM20231726


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20231726
Building Permit - Commercial
Final Completion
ALTERATION COMMERCIAL
Replacement/upgrade of an existing 100KW natural gas generator with a new 250KW diesel generator. Installation of a new 400A generator connection cabinet. Replacement of 2 and addition of a 3rd Automatic Transfer switch - INCLUDES MASONRY SCREEN WALL.
04/18/2023
05/08/2023
10/23/2023
06/27/2023
Locations
Contacts
NORTH KANSAS CITY ELECTRIC CO INC, Address:PO BOX 12442, Phone:(816) 421-2352  
SRUSSELL@NKCE.COM  
Reviews
Review Type Outcome Est. Completion Date Completed
Fire Plan Review Approved 05/05/2023 05/04/2023
Jim Eden
Miscellaneous Correction
Resolved
05/02/2023

Provide specifications and UL listing for the generator and tank set.
Licensed Contractors Approved 05/05/2023 05/02/2023
Joe Frogge
Building Plan Review Approved 05/05/2023 05/02/2023
Joe Frogge
Building Plan Review Approved 04/28/2023 04/26/2023
Joe Frogge
Project cost
Resolved
04/26/2023

The project cost, which is used to establish the permit fee, has not been provided. Action required: Comment is informational.
Fire Plan Review Rejected 04/28/2023 04/26/2023
Jim Eden
Miscellaneous Correction
Corrective Action Required
04/26/2023

Provide specifications and UL listing for the generator and tank set.
Zoning Review Rejected 04/28/2023 04/19/2023
Shannon McGuire
Licensed Contractors Approved 04/28/2023 04/18/2023
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for Alteration to Commercial $220.00 $220.00 Paid 05/08/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underground Electrical Inspection - Commercial Passed 6/7/2023 6/7/2023 06/07/2023
Footing Inspection - Commercial Passed 6/8/2023 (8:00) 6/8/2023 06/08/2023
Electrical Service Inspection Passed 6/26/2023 6/26/2023 06/26/2023
Final Electrical Inspection - Commercial Passed 6/26/2023 6/26/2023 06/26/2023
Documents & Images
Date Uploaded File Type Document Name
04/18/2023 Scope of Work SCOPE OF WORK
04/18/2023 Photograph 20220919_113646
04/18/2023 Photograph 20220919_113958
04/18/2023 Photograph 20220919_113944
04/18/2023 Photograph 20220919_114003
04/18/2023 Plans Gen Set Home Depot 3026
04/26/2023 Letter DS P/R Corrections Document
04/26/2023 Specifications THD #3026 Generator-GCC-ATS Submittals
04/28/2023 Drawing THD #3026 - New Generator Comppund Drawing
05/02/2023 Drawing THD #3026 - Screening Wall - Engineered Drawings
05/05/2023 Approved Plans Approved - Gen Set Home Depot 3026
05/08/2023 Receipt Receipt for transaction:2023-002914
05/08/2023 Letter DS Building Permit
06/07/2023 Letter INSPECTION SUMMARY
06/08/2023 Letter INSPECTION SUMMARY
06/26/2023 Letter INSPECTION SUMMARY
06/26/2023 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home