Permit Application Status

PRCOM20226235


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20226235
Building Permit - Commercial
Certificate of Occupancy
LANGSFORD DEVELOPMENT INC
CHANGE OF TENANT
TENANT FINISH FOR GROUP EXERCISE BUSINESS
12/27/2022
01/23/2023
07/08/2023
02/27/2023
Locations
Contacts
LANGSFORD DEVELOPMENT INC, Address:616 SW 3RD ST  
CAMM CONSTRUCTION INC, Address:PO BOX 1417, Phone:(816) 607-3602  
paul@mid-westinteriors.com  
CHIEF HEATING & COOLING INC, Address:920 NW TECHNOLOGY DR, Phone:(816) 246-4646  
KASA ELECTRIC LLC, Address:1206 NW VALLEY RIDGE DR, Phone:(816) 228-4886  
RODINA COMPANY INC, Address:1204 N 59TH ST, Phone:(913) 334-5336  
COLLINS WEBB ARCHITECTURE LLC, Address:307 SW MARKET ST, Unit B, Phone:(816) 249-2270  
Reviews
Review Type Outcome Est. Completion Date Completed
Fire Plan Review Approved with Conditions 01/23/2023 01/20/2023
Jim Eden
Misc
Resolved
01/20/2023

Informational: Complete code analysis
Miscellaneous Correction
Informational
01/20/2023

Compliance of all new and existing conditions to be verified at time of inspection.
Building Plan Review Approved 01/23/2023 01/19/2023
Joe Frogge
Code analysis required
Resolved
01/19/2023

A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed. Action required: Clarification needed - square footage indicated for occupant loads don't appear to match floor plan.
IBC 1209.2 Finish materials
Resolved
01/19/2023

2018 IBC 1209.2 Finish Materials. Walls, Floors and partitions in toilet and bathrooms shall comply with Sections 209.2.1 through 1209.2.4. 2018 1209.2.1 Floors and wall bases. In other than dwelling units, toilet, bathing and shower room floor finish materials shall have a smooth, hard, nonabsorbent surface. The intersections of such floors with walls shall have a smooth, hard, nonabsorbent vertical base that extends upward onto the walls not less than 4 inches. 2018 1209.2.2 Walls and partitions. Walls and partitions within 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.) Action required: Specify compliant wall finish material on side wall adjacent to water closets.
IMC 403.2 Outdoor air required
Resolved
01/19/2023

2018 IMC 403.2 Outdoor air required. The minimum outdoor airflow rate shall be determined in accordance with Section 403.3. (see code for exception) Action required: Revise drawings to show outside air calculations as well as method of delivery. Action required: Provide outside air calculation and means of delivery.
IPC 403.1 Minimum number of fixtures
Resolved
01/19/2023

2018 IPC 403.1 Minimum number of fixtures. Plumbing fixtures shall be provided in the minimum number shown in Table 403.1, based on the actual use of the building or space. Uses not shown in Table 403.1 shall be considered individually by the code official. The number of occupants shall be determined by the International Building Code. Action required: Provide mop sink.
IMC 602.2.1 Materials within plenums
Resolved
01/19/2023

2018 IMC 602.2.1 Materials within plenums. Except as required by Sections 602.2.1.1 through 602.2.1.5, materials within plenums shall be noncombustible or shall be listed and labeled as having a flame spread index of not more than 25 and a smoke-developed index of not more than 50 when tested in accordance with ASTM E84 or UL 723. (see code section for exceptions) Action required: Comment is informational. PVC is specified but plans don't show whether the return air is ducted or not. To be field verified. (PVC will not be allowed if the return air is via a plenum space)
Licensed Contractors Approved 01/23/2023 01/18/2023
Joe Frogge
Fire Plan Review Rejected 01/10/2023 01/06/2023
Ben Hicks
Misc
Corrective Action Required
01/06/2023

Informational: Complete code analysis
Building Plan Review Rejected 01/10/2023 01/06/2023
Joe Frogge
Code analysis required
Corrective Action Required
01/06/2023

A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed. Action required: Clarification needed - square footage indicated for occupant loads don't appear to match floor plan.
IBC 1209.2 Finish materials
Corrective Action Required
01/06/2023

2018 IBC 1209.2 Finish Materials. Walls, Floors and partitions in toilet and bathrooms shall comply with Sections 209.2.1 through 1209.2.4. 2018 1209.2.1 Floors and wall bases. In other than dwelling units, toilet, bathing and shower room floor finish materials shall have a smooth, hard, nonabsorbent surface. The intersections of such floors with walls shall have a smooth, hard, nonabsorbent vertical base that extends upward onto the walls not less than 4 inches. 2018 1209.2.2 Walls and partitions. Walls and partitions within 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.) Action required: Specify compliant wall finish material on side wall adjacent to water closets.
IMC 403.2 Outdoor air required
Corrective Action Required
01/06/2023

2018 IMC 403.2 Outdoor air required. The minimum outdoor airflow rate shall be determined in accordance with Section 403.3. (see code for exception) Action required: Revise drawings to show outside air calculations as well as method of delivery. Action required: Provide outside air calculation and means of delivery.
IPC 403.1 Minimum number of fixtures
Corrective Action Required
01/06/2023

2018 IPC 403.1 Minimum number of fixtures. Plumbing fixtures shall be provided in the minimum number shown in Table 403.1, based on the actual use of the building or space. Uses not shown in Table 403.1 shall be considered individually by the code official. The number of occupants shall be determined by the International Building Code. Action required: Provide mop sink.
IMC 602.2.1 Materials within plenums
Corrective Action Required
01/06/2023

2018 IMC 602.2.1 Materials within plenums. Except as required by Sections 602.2.1.1 through 602.2.1.5, materials within plenums shall be noncombustible or shall be listed and labeled as having a flame spread index of not more than 25 and a smoke-developed index of not more than 50 when tested in accordance with ASTM E84 or UL 723. (see code section for exceptions) Action required: Comment is informational. PVC is specified but plans don't show whether the return air is ducted or not. To be field verified. (PVC will not be allowed if the return air is via a plenum space)
Licensed Contractors Approved 01/10/2023 01/06/2023
Joe Frogge
Zoning Review Approved 01/10/2023 01/03/2023
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for Change of Tenant $184.00 $184.00 Paid 01/23/2023
7232302-Commercial License Tax Fee $4,413.75 $4,413.75 Paid 01/23/2023
$1,650.00
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underslab Plumbing Inspection - Commercial Passed 01/27/2023
Rough Plumbing Inspection - Commercial Passed 1/27/2023 1/27/2023 01/27/2023
In-wall Inspection Passed 2/2/2023 2/2/2023 02/02/2023
Above Ceiling Inspection Failed 2/9/2023 2/9/2023 02/09/2023
Misc
Corrective Action Required
02/09/2023
-Coplete mechanical in bathrooms -Complete electrical at bath fans -Kockout cover at j box in east restroom -Secure mc off of grid near stage -Secure mc within 12" of boxes near stage -Opne J box in center -Land mc at west side
Above Ceiling Inspection Passed 2/13/2023 02/13/2023
Misc
Resolved
02/13/2023
-Coplete mechanical in bathrooms -Complete electrical at bath fans -Kockout cover at j box in east restroom -Secure mc off of grid near stage -Secure mc within 12" of boxes near stage -Opne J box in center -Land mc at west side
Occupancy Inspection - Codes Commercial Full C of O 2/27/2023 2/27/2023 02/27/2023
Occupancy Inspection - Fire Passed 2/27/2023 2/27/2023 02/28/2023
Documents & Images
Date Uploaded File Type Document Name
12/27/2022 Application Form APPLICATION
01/03/2023 Plans 23010_JazzerciseLSMO_PermitDocuments_230103
01/06/2023 Letter Fire Building Plan Review
01/09/2023 Letter DS P/R Corrections Document
01/13/2023 Plans 23010_Jazzercise LSMO_PermitSet_Rev1_230113
01/13/2023 Letter 23010_Jazzercise LSMO - City Comments Responses_230113
01/18/2023 Letter License Tax Bill
01/20/2023 Letter Fire Building Plan Review
01/23/2023 Receipt Receipt for transaction:2023-000409
01/25/2023 Approved Plans approved jazzercise plans
01/25/2023 Letter DS Building Permit
01/27/2023 Letter INSPECTION SUMMARY
01/27/2023 Letter INSPECTION SUMMARY
02/02/2023 Letter INSPECTION SUMMARY
02/02/2023 Letter Fire Building Plan Review
02/09/2023 Letter INSPECTION SUMMARY
02/13/2023 Letter INSPECTION SUMMARY
02/27/2023 Letter Fire Building Plan Review
02/27/2023 Letter Codes Final Certificate of Occupancy
02/27/2023 Letter Field Certificate of Occupancy
02/28/2023 Letter Fire Loss Reduction Form
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home