Summary
PRCOM20212570
Building Permit - Commercial
Certificate of Occupancy
BRAIN DEV 3 LLC
CHANGE OF TENANT
TENANT FINISH FOR AMAZON RESELLER
05/19/2021
05/25/2021
11/17/2021
06/30/2021
Locations
Contacts
CAPITAL CONSTRUCTION SERVICES LLC, Address:2642 NE HAGAN RD, Phone:(816) 875-0018  
DROTHFUSS@CAPITALCONST.COM  
BLUE SPRINGS ELECTRICAL SERVICE, Address:3402 LAKE SHORE DR, Phone:(816) 224-9911  
A BRIGHT PLUMBING LLC, Address:18107 E 18TH TER N, Phone:(816) 215-0730  
DAVIDSON ARCHITECTURE & ENGINEERING, Address:11301 STRANG LINE ROAD  
BRAIN DEV 3 LLC, Address:300 E 39TH ST  
Reviews
Review Type Outcome Est. Completion Date Completed
Fire Plan Review Approved with Conditions 06/01/2021 05/25/2021
Michael Weissenbach
Miscellaneous Correction
Resolved
05/25/2021

(Action Required) 1. No PE stamp on plans 2. 840 SW Blue Pkwy is non-sprinkled. Plans indicate suppression. 3. Show emergency/exit lighting
Illumination required
Corrective Action Required
05/25/2021

2018 IFC 1008.1 Illumination required. The means of egress, shall be illuminated at all times the building space served by the means of egress is occupied. (Verified At Inspection) Provide Exit/Emergency lighting at Door 01.
Building Plan Review Approved 06/01/2021 05/24/2021
Joe Frogge
Gen - Design professional seals
Resolved
05/24/2021

Missouri Board for Architects, Professional Engineers, Professional Land Surveyors and Professional Landscape Architects – Board Rules, Division 2030 – Chapter 3, 20 CSR 2030-3.060 Licensees Seal Documents must bear design professionals original seal with signature and date. (relevant portion paraphrased – reference original document for additional information) Action required: All drawings are to bear dated seal and signature from architect/engineer of record. Also, remove "not for construction" from title block.
Code analysis required
Resolved
05/24/2021

A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed. Action required: Update project synopsis to show that building is not sprinklered or provide verification that building truly is sprinklered.
IBC 1209.2 Finish materials
Resolved
05/24/2021

2018 IBC 1209.2 Finish Materials. Walls, Floors and partitions in toilet and bathrooms shall comply with Sections 209.2.1 through 1209.2.4. 2018 1209.2.1 Floors and wall bases. In other than dwelling units, toilet, bathing and shower room floor finish materials shall have a smooth, hard, nonabsorbent surface. The intersections of such floors with walls shall have a smooth, hard, nonabsorbent vertical base that extends upward onto the walls not less than 4 inches. 2018 1209.2.2 Walls and partitions. Walls and partitions within 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.) 1209.2.3 Showers. (see code for details) 1209.2.4 Waterproof joints. (see code for details) Action required: Specify compliant wall finish at mop sink. If paint is used it must be epoxy based.
IMC 602.2.1 Materials within plenums
Resolved
05/24/2021

2018 IMC 602.2.1 Materials within plenums. Except as required by Sections 602.2.1.1 through 602.2.1.5, materials within plenums shall be noncombustible or shall be listed and labeled as having a flame spread index of not more than 25 and a smoke-developed index of not more than 50 when tested in accordance with ASTM E84 or UL 723. (see code section for exceptions) Action required: Comment is for informational purposes. PVC not allowed in plenum. (unable to verify as there are not mechanical designs) To be field verified.
Licensed Contractors Approved 05/24/2021 05/24/2021
Joe Frogge
Building Plan Review Rejected 06/01/2021 05/21/2021
Joe Frogge
Gen - Design professional seals
Corrective Action Required
05/21/2021

Missouri Board for Architects, Professional Engineers, Professional Land Surveyors and Professional Landscape Architects – Board Rules, Division 2030 – Chapter 3, 20 CSR 2030-3.060 Licensees Seal Documents must bear design professionals original seal with signature and date. (relevant portion paraphrased – reference original document for additional information) Action required: All drawings are to bear dated seal and signature from architect/engineer of record. Also, remove "not for construction" from title block.
Code analysis required
Corrective Action Required
05/21/2021

A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed. Action required: Update project synopsis to show that building is not sprinklered or provide verification that building truly is sprinklered.
IBC 1209.2 Finish materials
Corrective Action Required
05/21/2021

2018 IBC 1209.2 Finish Materials. Walls, Floors and partitions in toilet and bathrooms shall comply with Sections 209.2.1 through 1209.2.4. 2018 1209.2.1 Floors and wall bases. In other than dwelling units, toilet, bathing and shower room floor finish materials shall have a smooth, hard, nonabsorbent surface. The intersections of such floors with walls shall have a smooth, hard, nonabsorbent vertical base that extends upward onto the walls not less than 4 inches. 2018 1209.2.2 Walls and partitions. Walls and partitions within 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.) 1209.2.3 Showers. (see code for details) 1209.2.4 Waterproof joints. (see code for details) Action required: Specify compliant wall finish at mop sink. If paint is used it must be epoxy based.
IMC 602.2.1 Materials within plenums
Corrective Action Required
05/21/2021

2018 IMC 602.2.1 Materials within plenums. Except as required by Sections 602.2.1.1 through 602.2.1.5, materials within plenums shall be noncombustible or shall be listed and labeled as having a flame spread index of not more than 25 and a smoke-developed index of not more than 50 when tested in accordance with ASTM E84 or UL 723. (see code section for exceptions) Action required: Comment is for informational purposes. PVC not allowed in plenum. (unable to verify as there are not mechanical designs) To be field verified.
Fire Plan Review Rejected 06/01/2021 05/19/2021
Michael Weissenbach
Miscellaneous Correction
Corrective Action Required
05/19/2021

(Action Required) 1. No PE stamp on plans 2. 840 SW Blue Pkwy is non-sprinkled. Plans indicate suppression. 3. Show emergency/exit lighting
Licensed Contractors Approved 06/01/2021 05/19/2021
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for Change of Tenant $480.00 $480.00 Paid 05/25/2021
$35,235.00
7232302-Commercial License Tax Fee $17,617.50 $17,617.50 Paid 05/25/2021
$17,617.50
8331507-Sewer Connection Fee $180.00 $180.00 Paid 05/25/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underslab Plumbing Inspection - Commercial Passed 6/9/2021 06/09/2021
In-wall Inspection Passed 6/9/2021 6/9/2021 06/09/2021
Occupancy Inspection - Fire Passed 6/29/2021 6/30/2021 06/30/2021
Occupancy Inspection - Codes Commercial Full C of O 6/30/2021 6/30/2021 06/30/2021
Documents & Images
Date Uploaded File Type Document Name
05/19/2021 Application Form 20173 Permit Application FULLY EXECUTED
05/19/2021 Application Form lt form
05/19/2021 Plans MEP - 840 SW BLUE PKWY - PE1
05/19/2021 Plans A1-0 - Full Set
05/19/2021 Letter License Tax Bill
05/19/2021 Letter Fire Building Plan Review
05/21/2021 Letter DS P/R Corrections Document
05/24/2021 Letter 840 SW Blue Pkwy MEP Response
05/24/2021 Drawing 21108 - 840 SW BLUE PKWY - PE1-rev1
05/24/2021 Plans 840 SW Blue Parkway Final Set R1 2021-05-24
05/24/2021 Letter PRCOM20212570 Plan Review Comments - Response Letter 20210524
05/25/2021 Letter Fire Building Plan Review
05/25/2021 Approved Plans approved - 840 SW Blue Parkway Final Set
05/25/2021 Receipt Receipt for transaction:2021-003487
05/25/2021 Letter DS Building Permit
06/09/2021 Letter INSPECTION SUMMARY
06/09/2021 Letter INSPECTION SUMMARY
06/30/2021 Letter Fire Loss Reduction Form
06/30/2021 Letter Codes Final Certificate of Occupancy
06/30/2021 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home