Permit Application Status

PRCOM20212128


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20212128
Building Permit - Commercial
Certificate of Occupancy
Consolidated Library Dist #3
ADDITION COMMERCIAL
ADDITION TO EXISTING LIBRARY INCLUDING INTERIOR ALTERATIONS
04/29/2021
06/23/2021
11/02/2021
12/08/2022
Locations
Contacts
JE DUNN CONSTRUCTION CO, Address:120 S CENTRAL AVE STE 350, Phone:(816) 474-8600  
STANGER INDUSTRIES, Address:4911 ELMWOOD AVE, Phone:(816) 861-2800  
STACO ELECTRIC CONSTRUCTION COMPANY INC, Address:11030 HICKMAN MILLS DR, Phone:(816) 765-7112  
KANSAS CITY MECHANICAL INC, Address:6822 KANSAS AVE, Phone:(913) 334-1101  
Eric.Nickeson@jedunn.com, Address:Eric.Nickeson@jedunn.com  
Jim Stufflebeam, Address:Sapp Design Architects, Phone:(417) 877-9600  
Consolidated Library Dist #3, Address:15616 E US 24 Hwy  
Reviews
Review Type Outcome Est. Completion Date Completed
Alarm Plan Review Released for Construction 03/15/2022 03/15/2022
Jim Eden
Installation acceptance testing
Corrective Action Required
03/15/2022

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Coordinate with the sprinkler contractor and schedule a test. Call (816) 969-1300.
Sprinkler Plan Review Released for Construction 10/13/2021 10/13/2021
Michael Weissenbach
Installation acceptance testing
Corrective Action Required
10/13/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule a hydrostatic and water flow test.
Alarm Plan Review Released for Construction 07/26/2021 07/26/2021
Michael Weissenbach
Installation acceptance testing
Corrective Action Required
07/26/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Verified At Inspection) Call (816)969-1300
Misc
Corrective Action Required
07/26/2021

(Informational Purposes) Mount the outside horn/strobe by the FDC.
Final Development Plan Review Approved 06/21/2021
Mike Weisenborn
Building Plan Review Approved 06/03/2021 06/21/2021
Mike Weisenborn
Final Development Plan
Resolved
06/21/2021

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes. 5/56/21 - acknowledged in letter.
IBC 1013.1 Where required - exit sign
Resolved
05/26/2021

2018 IBC Exit Signs 1013.1 Where Required. Exits and exit access doors shall be marked by an approved exit sign readily visible from any direction of egress travel. The path of egress travel to exits and within exits shall be marked by readily visible exit signs to clearly indicate the direction of egress travel in cases where the exit of the path of egress travel is not immediately visible to the occupants. Intervening means of egress doors within exits shall be marked by exit signs. Exit sign placement shall be such that no point in an exit access corridor or exit passageway is more than 100 feet or the listed viewing distance for the sign, whichever is less, from the nearest visible exit sign. (see code section for exceptions) Action required: Provide exit signage at door in retractable wall between split community room.
IBC 1010.1.10 Panic and fire exit hardware
Resolved
05/26/2021

2018 IBC 1010.1.10 Panic and fire exit hardware. Swinging doors serving a Group H occupancy and swinging doors serving rooms or spaces with an occupant load of 50 or more in a Group A or E occupancy shall not be provided with a latch or lock other than panic hardware or fire exit hardware. Exceptions: 1. A main exit of a Group A occupancy shall be permitted to have locking devices in accordance with Section 1010.1.9.4, Item 2. 2. Doors provided with panic hardware or fire exit hardware and serving a Group A or E occupancy shall be permitted to be electrically locked in accordance with Section 1010.1.9.9 or 1010.1.9.10. Action required: Provide panic hardware at door in retractable wall between split community room. 5/56/21 - covered in spec
IPC 425.3 Water closet seats
Resolved
05/26/2021

2018 IPC 424.2 Substitution for water closets. In each bathroom or toilet room, urinals shall not be substituted for more than 67 percent of the required water closets in assembly and educational occupancies. Urinals shall not be substituted for more than 50 percent of the required water closets in all other occupancies. Action required: Replace one of the urinals with a water closet to comply. 5/56/21 - exception met
IMC 306.5 Equipment on roofs
Resolved
05/26/2021

2018 IMC 306.5 Equipment and appliances on roofs or elevated structures. Where equipment requiring access or appliances are located on an elevated structure or the roof of a building such that personnel will have to climb higher than 16 feet above grade to access such equipment or appliances, an interior or exterior means of access shall be provided. Such access shall not require climbing over obstructions greater than 30 inches in height or walking on roofs having a slope greater than 4 units vertical in 12 units horizontal. Such access shall not require the use of portable ladders. Where access involves climbing over parapet walls, the height shall be measured to the top of the parapet wall. Permanent ladders installed to provide the required access shall comply with the following minimum design criteria: 1. The side railing shall extend above the parapet or roof edge not less than 30" (see code section for additional construction requirements) Action required: Provide side rail extender to comply. 5/56/21 - covered in spec
NEC Article 210.63 Heating, air-conditioning and refrigeration outlet
Resolved
05/26/2021

2017 NEC Article 210.63 Heating, Air-Conditioning, and Refrigeration Equipment Outlet. A 125-volt, single-phase, 15- or 20-ampere-rated receptacle outlet shall be installed at an accessible location for the servicing of heating, air-conditioning, and refrigeration equipment. The receptacle shall be located on the same level and within 25 feet of the heating, air-conditioning, and refrigeration equipment. The receptacle outlet shall not be connected to the load side of the equipment disconnecting means. Action required: Provide additional receptacle on roof to ensure that all maintainable equipment is within 25'. (currently scaled at >30')
NEC Article 110.26 (C)(2) Large equipment
Resolved
05/26/2021

2017 NEC Article 110.26 (C)(3) Personnel Doors. Where equipment rated 800 A or more that contains overcurrent devices, switching devices, or control devices is installed and there is a personnel door(s) intended for entrance to and egress from the working space less than 25 feet from the nearest edge of the working space, the door(s) shall open in the direction of egress and be equipped with panic hardware. Action required: Door #115 out of Data/Storage Room 115 is required to swing outwards and be equipped with panic hardware.
r
Licensed Contractors Approved 06/03/2021 05/26/2021
Joe Frogge
Fire Plan Review Approved with Conditions 06/03/2021 05/26/2021
Michael Weissenbach
Construction documents for fire alarm systems
Corrective Action Required
05/26/2021

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. (Action Required) Provide PE stamped electronic shop drawings for the fire alarm system to mike.weissenbach@cityofls.net
Address numbers required
Corrective Action Required
05/26/2021

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection)
Knox box required
Corrective Action Required
05/26/2021

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. (Action Required) Order a Knox box from knoxbox.com. Placement to be made by the FDC.
Construction documents - Fire protection systems
Corrective Action Required
05/26/2021

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. (Action Required) Provide PE stamped electronic shop drawings for the fire sprinkler system to mike.weissenbach@cityofls.net
Installation acceptance testing
Corrective Action Required
05/26/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Fire Plan Review Approved with Conditions 05/13/2021 05/06/2021
Joe Frogge
Construction documents for fire alarm systems
Corrective Action Required
05/06/2021

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. (Action Required) Provide PE stamped electronic shop drawings for the fire alarm system to mike.weissenbach@cityofls.net
Address numbers required
Corrective Action Required
05/06/2021

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection)
Knox box required
Corrective Action Required
05/06/2021

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. (Action Required) Order a Knox box from knoxbox.com. Placement to be made by the FDC.
Construction documents - Fire protection systems
Corrective Action Required
05/06/2021

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. (Action Required) Provide PE stamped electronic shop drawings for the fire sprinkler system to mike.weissenbach@cityofls.net
Installation acceptance testing
Corrective Action Required
05/06/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Building Plan Review Rejected 05/13/2021 05/06/2021
Joe Frogge
Final Development Plan
Corrective Action Required
05/06/2021

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes.
Code analysis required
Resolved
05/18/2021

A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed. Action required: Update code analysis to show correct occupancy at allowable area. (Should be A3, not S1.)
IBC 1013.1 Where required - exit sign
Corrective Action Required
05/06/2021

2018 IBC Exit Signs 1013.1 Where Required. Exits and exit access doors shall be marked by an approved exit sign readily visible from any direction of egress travel. The path of egress travel to exits and within exits shall be marked by readily visible exit signs to clearly indicate the direction of egress travel in cases where the exit of the path of egress travel is not immediately visible to the occupants. Intervening means of egress doors within exits shall be marked by exit signs. Exit sign placement shall be such that no point in an exit access corridor or exit passageway is more than 100 feet or the listed viewing distance for the sign, whichever is less, from the nearest visible exit sign. (see code section for exceptions) Action required: Provide exit signage at door in retractable wall between split community room.
IBC 1010.1.10 Panic and fire exit hardware
Corrective Action Required
05/06/2021

2018 IBC 1010.1.10 Panic and fire exit hardware. Swinging doors serving a Group H occupancy and swinging doors serving rooms or spaces with an occupant load of 50 or more in a Group A or E occupancy shall not be provided with a latch or lock other than panic hardware or fire exit hardware. Exceptions: 1. A main exit of a Group A occupancy shall be permitted to have locking devices in accordance with Section 1010.1.9.4, Item 2. 2. Doors provided with panic hardware or fire exit hardware and serving a Group A or E occupancy shall be permitted to be electrically locked in accordance with Section 1010.1.9.9 or 1010.1.9.10. Action required: Provide panic hardware at door in retractable wall between split community room.
IPC 425.3 Water closet seats
Corrective Action Required
05/06/2021

2018 IPC 424.2 Substitution for water closets. In each bathroom or toilet room, urinals shall not be substituted for more than 67 percent of the required water closets in assembly and educational occupancies. Urinals shall not be substituted for more than 50 percent of the required water closets in all other occupancies. Action required: Replace one of the urinals with a water closet to comply.
IMC 306.5 Equipment on roofs
Corrective Action Required
05/06/2021

2018 IMC 306.5 Equipment and appliances on roofs or elevated structures. Where equipment requiring access or appliances are located on an elevated structure or the roof of a building such that personnel will have to climb higher than 16 feet above grade to access such equipment or appliances, an interior or exterior means of access shall be provided. Such access shall not require climbing over obstructions greater than 30 inches in height or walking on roofs having a slope greater than 4 units vertical in 12 units horizontal. Such access shall not require the use of portable ladders. Where access involves climbing over parapet walls, the height shall be measured to the top of the parapet wall. Permanent ladders installed to provide the required access shall comply with the following minimum design criteria: 1. The side railing shall extend above the parapet or roof edge not less than 30" (see code section for additional construction requirements) Action required: Provide side rail extender to comply.
NEC Article 210.63 Heating, air-conditioning and refrigeration outlet
Corrective Action Required
05/06/2021

2017 NEC Article 210.63 Heating, Air-Conditioning, and Refrigeration Equipment Outlet. A 125-volt, single-phase, 15- or 20-ampere-rated receptacle outlet shall be installed at an accessible location for the servicing of heating, air-conditioning, and refrigeration equipment. The receptacle shall be located on the same level and within 25 feet of the heating, air-conditioning, and refrigeration equipment. The receptacle outlet shall not be connected to the load side of the equipment disconnecting means. Action required: Provide additional receptacle on roof to ensure that all maintainable equipment is within 25'. (currently scaled at >30')
NEC Article 110.26 (C)(2) Large equipment
Corrective Action Required
05/06/2021

2017 NEC Article 110.26 (C)(3) Personnel Doors. Where equipment rated 800 A or more that contains overcurrent devices, switching devices, or control devices is installed and there is a personnel door(s) intended for entrance to and egress from the working space less than 25 feet from the nearest edge of the working space, the door(s) shall open in the direction of egress and be equipped with panic hardware. Action required: Door #115 out of Data/Storage Room 115 is required to swing outwards and be equipped with panic hardware.
r
Building Plan Review Rejected 05/13/2021 05/06/2021
Joe Frogge
Final Development Plan
Corrective Action Required
05/05/2021

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes.
Code analysis required
Corrective Action Required
05/05/2021

A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed. Action required: Update code analysis to show correct occupancy at allowable area. (Should be A3, not S1.)
IBC 1013.1 Where required - exit sign
Corrective Action Required
05/05/2021

2018 IBC Exit Signs 1013.1 Where Required. Exits and exit access doors shall be marked by an approved exit sign readily visible from any direction of egress travel. The path of egress travel to exits and within exits shall be marked by readily visible exit signs to clearly indicate the direction of egress travel in cases where the exit of the path of egress travel is not immediately visible to the occupants. Intervening means of egress doors within exits shall be marked by exit signs. Exit sign placement shall be such that no point in an exit access corridor or exit passageway is more than 100 feet or the listed viewing distance for the sign, whichever is less, from the nearest visible exit sign. (see code section for exceptions) Action required: Provide exit signage at door in retractable wall between split community room.
IBC 1010.1.10 Panic and fire exit hardware
Corrective Action Required
05/05/2021

2018 IBC 1010.1.10 Panic and fire exit hardware. Swinging doors serving a Group H occupancy and swinging doors serving rooms or spaces with an occupant load of 50 or more in a Group A or E occupancy shall not be provided with a latch or lock other than panic hardware or fire exit hardware. Exceptions: 1. A main exit of a Group A occupancy shall be permitted to have locking devices in accordance with Section 1010.1.9.4, Item 2. 2. Doors provided with panic hardware or fire exit hardware and serving a Group A or E occupancy shall be permitted to be electrically locked in accordance with Section 1010.1.9.9 or 1010.1.9.10. Action required: Provide panic hardware at door in retractable wall between split community room.
IPC 425.3 Water closet seats
Corrective Action Required
05/05/2021

2018 IPC 424.2 Substitution for water closets. In each bathroom or toilet room, urinals shall not be substituted for more than 67 percent of the required water closets in assembly and educational occupancies. Urinals shall not be substituted for more than 50 percent of the required water closets in all other occupancies. Action required: Replace one of the urinals with a water closet to comply.
IMC 306.5 Equipment on roofs
Corrective Action Required
05/05/2021

2018 IMC 306.5 Equipment and appliances on roofs or elevated structures. Where equipment requiring access or appliances are located on an elevated structure or the roof of a building such that personnel will have to climb higher than 16 feet above grade to access such equipment or appliances, an interior or exterior means of access shall be provided. Such access shall not require climbing over obstructions greater than 30 inches in height or walking on roofs having a slope greater than 4 units vertical in 12 units horizontal. Such access shall not require the use of portable ladders. Where access involves climbing over parapet walls, the height shall be measured to the top of the parapet wall. Permanent ladders installed to provide the required access shall comply with the following minimum design criteria: 1. The side railing shall extend above the parapet or roof edge not less than 30" (see code section for additional construction requirements) Action required: Provide side rail extender to comply.
NEC Article 210.63 Heating, air-conditioning and refrigeration outlet
Corrective Action Required
05/06/2021

2017 NEC Article 210.63 Heating, Air-Conditioning, and Refrigeration Equipment Outlet. A 125-volt, single-phase, 15- or 20-ampere-rated receptacle outlet shall be installed at an accessible location for the servicing of heating, air-conditioning, and refrigeration equipment. The receptacle shall be located on the same level and within 25 feet of the heating, air-conditioning, and refrigeration equipment. The receptacle outlet shall not be connected to the load side of the equipment disconnecting means. Action required: Provide additional receptacle on roof to ensure that all maintainable equipment is within 25'. (currently scaled at >30')
NEC Article 110.26 (C)(2) Large equipment
Corrective Action Required
05/06/2021

2017 NEC Article 110.26 (C)(3) Personnel Doors. Where equipment rated 800 A or more that contains overcurrent devices, switching devices, or control devices is installed and there is a personnel door(s) intended for entrance to and egress from the working space less than 25 feet from the nearest edge of the working space, the door(s) shall open in the direction of egress and be equipped with panic hardware. Action required: Door #115 out of Data/Storage Room 115 is required to swing outwards and be equipped with panic hardware.
Fire Plan Review Approved with Conditions 05/13/2021 05/04/2021
Michael Weissenbach
Construction documents for fire alarm systems
Corrective Action Required
05/04/2021

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. (Action Required) Provide PE stamped electronic shop drawings for the fire alarm system to mike.weissenbach@cityofls.net
Address numbers required
Corrective Action Required
05/04/2021

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection)
Knox box required
Corrective Action Required
05/04/2021

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. (Action Required) Order a Knox box from knoxbox.com. Placement to be made by the FDC.
Construction documents - Fire protection systems
Corrective Action Required
05/04/2021

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. (Action Required) Provide PE stamped electronic shop drawings for the fire sprinkler system to mike.weissenbach@cityofls.net
Installation acceptance testing
Corrective Action Required
05/04/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Licensed Contractors Approved 05/13/2021 04/30/2021
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for Addition to Commercial $11,511.15 $11,511.15 Paid 06/23/2021
$31,395.00
8331507-Sewer Connection Fee $120.00 $120.00 Paid 06/23/2021
Commercial Excise Tax Fee $31,395.00 $31,395.00 Paid 04/30/2021
$31,395.00
Site Grading Fee $1,939.23 $1,939.23 Paid 06/23/2021
Storm Sewer Inspection Fee $3,820.77 $3,820.77 Paid 06/23/2021
Water Test Fee $200.00 $200.00 Paid 06/23/2021
Water Insp Fee $124.20 $124.20 Paid 06/23/2021
Sanitary Sewer Insp Fees $192.00 $192.00 Paid 06/23/2021
Paved Surface Inspection Fee $20,322.54 $20,322.54 Paid 06/23/2021
Right of Way Permit Fee $80.00 $80.00 Paid 06/23/2021
Not Ready Inspection Fee $50.00 $50.00 Paid 04/27/2022
Not Ready Inspection Fee $50.00 $50.00 Paid 04/27/2022
Water Meter Fee $1,952.05 $1,952.05 Paid 04/27/2022
$3,145.40
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Site Visit Partial 8/20/2021 08/20/2021
Misc
Informational
08/20/2021
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Erosion Control Inspection Failed 8/20/2021 08/20/2021
Misc
Corrective Action Required
08/20/2021
Trench and catch basin will collect some of the runoff, but not enough erosion control in place to catch the south runoff. Talked with Rick Meyer about concerns and possible solutions. RP 8-20-21
Erosion Control Inspection Partial 8/24/2021 8/24/2021 08/24/2021
Misc
Corrective Action Required
08/20/2021
Trench and catch basin will collect some of the runoff, but not enough erosion control in place to catch the south runoff. Talked with Rick Meyer about concerns and possible solutions. RP 8-20-21
Misc
Corrective Action Required
08/24/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. RP 8-24-21
Site Visit Partial 8/24/2021 8/24/2021 08/24/2021
Misc
Informational
08/20/2021
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
08/24/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Site Visit Partial 8/25/2021 8/25/2021 08/25/2021
Misc
Informational
08/24/2021
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
08/24/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
08/25/2021
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Site Visit Partial 8/26/2021 8/26/2021 08/26/2021
Misc
Informational
08/25/2021
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
08/25/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
08/25/2021
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
08/26/2021
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Erosion Control Inspection Partial 8/27/2021 8/27/2021 08/27/2021
Misc
Corrective Action Required
08/24/2021
Trench and catch basin will collect some of the runoff, but not enough erosion control in place to catch the south runoff. Talked with Rick Meyer about concerns and possible solutions. RP 8-20-21
Misc
Corrective Action Required
08/24/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. RP 8-24-21
Misc
Informational
08/27/2021
Controls are in place and they are going to add straw wattles in front of the drain pipe. RP 8-27-21
Site Visit Partial 8/27/2021 8/27/2021 08/27/2021
Misc
Informational
08/26/2021
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
08/26/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
08/26/2021
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
08/26/2021
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
08/27/2021
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Erosion Control Inspection Partial 8/30/2021 8/30/2021 08/30/2021
Misc
Corrective Action Required
08/27/2021
Trench and catch basin will collect some of the runoff, but not enough erosion control in place to catch the south runoff. Talked with Rick Meyer about concerns and possible solutions. RP 8-20-21
Misc
Corrective Action Required
08/27/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. RP 8-24-21
Misc
Informational
08/27/2021
Controls are in place and they are going to add straw wattles in front of the drain pipe. RP 8-27-21
Misc
Informational
08/30/2021
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. RP 8-30-21
Site Visit Partial 8/30/2021 8/30/2021 08/30/2021
Misc
Informational
08/27/2021
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
08/27/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
08/27/2021
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
08/27/2021
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
08/27/2021
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
08/30/2021
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Erosion Control Inspection Failed 8/31/2021 8/31/2021 08/31/2021
Misc
Corrective Action Required
08/30/2021
Trench and catch basin will collect some of the runoff, but not enough erosion control in place to catch the south runoff. Talked with Rick Meyer about concerns and possible solutions. RP 8-20-21
Misc
Corrective Action Required
08/30/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. RP 8-24-21
Misc
Informational
08/30/2021
Controls are in place and they are going to add straw wattles in front of the drain pipe. RP 8-27-21
Misc
Informational
08/30/2021
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. RP 8-30-21
Misc
Corrective Action Required
08/31/2021
Silt breached the silt fencing again. Notified Rick and will tell KAW Valley also. RP 8-31-21
Site Visit Partial 8/31/2021 8/31/2021 08/31/2021
Misc
Informational
08/30/2021
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
08/30/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
08/30/2021
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
08/30/2021
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
08/30/2021
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
08/30/2021
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
08/31/2021
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Site Visit Partial 9/1/2021 9/1/2021 09/01/2021
Misc
Informational
08/31/2021
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
08/31/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
08/31/2021
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
08/31/2021
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
08/31/2021
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
08/31/2021
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
08/31/2021
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
09/01/2021
Site was still too wet to work this morning. RP 9-1-21
Erosion Control Inspection Partial 9/2/2021 9/2/2021 09/02/2021
Misc
Corrective Action Required
08/31/2021
Trench and catch basin will collect some of the runoff, but not enough erosion control in place to catch the south runoff. Talked with Rick Meyer about concerns and possible solutions. RP 8-20-21
Misc
Corrective Action Required
08/31/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. RP 8-24-21
Misc
Informational
08/31/2021
Controls are in place and they are going to add straw wattles in front of the drain pipe. RP 8-27-21
Misc
Informational
08/31/2021
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. RP 8-30-21
Misc
Corrective Action Required
08/31/2021
Silt breached the silt fencing again. Notified Rick and will tell KAW Valley also. RP 8-31-21
Misc
Informational
09/02/2021
Talked with KAW Valley about erosion issues. They are going to add rock checks through the trench and trouble spots. RP 9-2-21
Site Visit Partial 9/2/2021 9/2/2021 09/02/2021
Misc
Informational
09/01/2021
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
09/01/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
09/01/2021
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
09/01/2021
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
09/01/2021
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
09/01/2021
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
09/01/2021
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
09/01/2021
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
09/02/2021
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Site Visit Partial 9/3/2021 9/3/2021 09/03/2021
Misc
Informational
09/02/2021
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
09/02/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
09/02/2021
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
09/02/2021
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
09/02/2021
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
09/02/2021
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
09/02/2021
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
09/02/2021
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
09/02/2021
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
09/03/2021
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Erosion Control Inspection Partial 9/7/2021 9/7/2021 09/07/2021
Misc
Corrective Action Required
09/02/2021
Trench and catch basin will collect some of the runoff, but not enough erosion control in place to catch the south runoff. Talked with Rick Meyer about concerns and possible solutions. RP 8-20-21
Misc
Corrective Action Required
09/02/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. RP 8-24-21
Misc
Informational
09/02/2021
Controls are in place and they are going to add straw wattles in front of the drain pipe. RP 8-27-21
Misc
Informational
09/02/2021
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. RP 8-30-21
Misc
Corrective Action Required
09/02/2021
Silt breached the silt fencing again. Notified Rick and will tell KAW Valley also. RP 8-31-21
Misc
Informational
09/02/2021
Talked with KAW Valley about erosion issues. They are going to add rock checks through the trench and trouble spots. RP 9-2-21
Misc
Informational
09/07/2021
Rock checks did their job. KAW Valley to readjust straw wattles in front of storm pipe. RP 9-7-21
Site Visit Partial 9/7/2021 9/7/2021 09/07/2021
Misc
Informational
09/03/2021
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
09/03/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
09/03/2021
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
09/03/2021
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
09/03/2021
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
09/03/2021
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
09/03/2021
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
09/03/2021
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
09/03/2021
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
09/03/2021
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
09/07/2021
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Site Visit Partial 9/8/2021 9/8/2021 09/08/2021
Misc
Informational
09/07/2021
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
09/07/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
09/07/2021
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
09/07/2021
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
09/07/2021
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
09/07/2021
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
09/07/2021
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
09/07/2021
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
09/07/2021
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
09/07/2021
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
09/07/2021
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
09/08/2021
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Storm Sewer Construction Inspection Partial 9/9/2021 9/9/2021 09/09/2021
Misc
Informational
09/09/2021
They laid 150 feet of 24 inch HDPE storm pipe and set grate inlet B-1. RP 9-9-21
Storm Sewer Construction Inspection Partial 9/10/2021 9/10/2021 09/10/2021
Misc
Informational
09/09/2021
They laid 150 feet of 24 inch HDPE storm pipe and set grate inlet B-1. RP 9-9-21
Misc
Informational
09/10/2021
They poured collars and inverts and back filled today. RP 9-10-21
Storm Sewer Construction Inspection Partial 9/13/2021 9/13/2021 09/14/2021
Misc
Informational
09/10/2021
They laid 150 feet of 24 inch HDPE storm pipe and set grate inlet B-1. RP 9-9-21
Misc
Informational
09/10/2021
They poured collars and inverts and back filled today. RP 9-10-21
Misc
Informational
09/14/2021
Rodriguez Mechanical set structures A-2 and B-2. Noticed the existing storm pipe was CMP instead of HDPE that is listed on the plans. Engineering is reaching out to the Design Engineer to see if the different pipe material is ok. RP 9-13-21
Storm Sewer Construction Inspection Partial 9/14/2021 9/14/2021 09/14/2021
Misc
Informational
09/14/2021
They laid 150 feet of 24 inch HDPE storm pipe and set grate inlet B-1. RP 9-9-21
Misc
Informational
09/14/2021
They poured collars and inverts and back filled today. RP 9-10-21
Misc
Informational
09/14/2021
Rodriguez Mechanical set structures A-2 and B-2. Noticed the existing storm pipe was CMP instead of HDPE that is listed on the plans. Engineering is reaching out to the Design Engineer to see if the different pipe material is ok. RP 9-13-21
Misc
Informational
09/14/2021
Their engineer said that CMP storm pipe is okay. Rodriguez laid 90 feet of 15 inch HDPE storm pipe and poured collars and inverts for structures A-2 and B-2. RP 9-14-21
Storm Sewer Construction Inspection Partial 9/15/2021 9/15/2021 09/15/2021
Misc
Informational
09/14/2021
They laid 150 feet of 24 inch HDPE storm pipe and set grate inlet B-1. RP 9-9-21
Misc
Informational
09/14/2021
They poured collars and inverts and back filled today. RP 9-10-21
Misc
Informational
09/14/2021
Rodriguez Mechanical set structures A-2 and B-2. Noticed the existing storm pipe was CMP instead of HDPE that is listed on the plans. Engineering is reaching out to the Design Engineer to see if the different pipe material is ok. RP 9-13-21
Misc
Informational
09/14/2021
Their engineer said that CMP storm pipe is okay. Rodriguez laid 90 feet of 15 inch HDPE storm pipe and poured collars and inverts for structures A-2 and B-2. RP 9-14-21
Misc
Informational
09/15/2021
They laid 50 feet of 15 inch HDPE storm pipe and set curb inlets C-1 and B-4 along with grate inlet B-3. RP 9-15-21
Storm Sewer Construction Inspection Partial 9/17/2021 9/17/2021 09/17/2021
Misc
Informational
09/15/2021
They laid 150 feet of 24 inch HDPE storm pipe and set grate inlet B-1. RP 9-9-21
Misc
Informational
09/15/2021
They poured collars and inverts and back filled today. RP 9-10-21
Misc
Informational
09/15/2021
Rodriguez Mechanical set structures A-2 and B-2. Noticed the existing storm pipe was CMP instead of HDPE that is listed on the plans. Engineering is reaching out to the Design Engineer to see if the different pipe material is ok. RP 9-13-21
Misc
Informational
09/15/2021
Their engineer said that CMP storm pipe is okay. Rodriguez laid 90 feet of 15 inch HDPE storm pipe and poured collars and inverts for structures A-2 and B-2. RP 9-14-21
Misc
Informational
09/15/2021
They laid 50 feet of 15 inch HDPE storm pipe and set curb inlets C-1 and B-4 along with grate inlet B-3. RP 9-15-21
Misc
Informational
09/17/2021
They cut into existing storm pipe and set junction box A-3. They also poured collars and inverts. RP 9-17-21
Footing Inspection - Commercial Partial 9/23/2021 (8:30) 9/23/2021 09/23/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
09/23/2021
- (3) COLUMN PADS LINE EA,EB ON LINE E6 -
Storm Sewer Construction Inspection Partial 9/20/2021 9/24/2021 09/24/2021
Misc
Informational
09/17/2021
They laid 150 feet of 24 inch HDPE storm pipe and set grate inlet B-1. RP 9-9-21
Misc
Informational
09/17/2021
They poured collars and inverts and back filled today. RP 9-10-21
Misc
Informational
09/17/2021
Rodriguez Mechanical set structures A-2 and B-2. Noticed the existing storm pipe was CMP instead of HDPE that is listed on the plans. Engineering is reaching out to the Design Engineer to see if the different pipe material is ok. RP 9-13-21
Misc
Informational
09/17/2021
Their engineer said that CMP storm pipe is okay. Rodriguez laid 90 feet of 15 inch HDPE storm pipe and poured collars and inverts for structures A-2 and B-2. RP 9-14-21
Misc
Informational
09/17/2021
They laid 50 feet of 15 inch HDPE storm pipe and set curb inlets C-1 and B-4 along with grate inlet B-3. RP 9-15-21
Misc
Informational
09/17/2021
They cut into existing storm pipe and set junction box A-3. They also poured collars and inverts. RP 9-17-21
Misc
Informational
09/24/2021
Installed box A-2 and A-1.
Footing Inspection - Commercial Partial 9/28/2021 (9:00) 9/28/2021 09/28/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
09/23/2021
- (3) COLUMN PADS LINE EA,EB ON LINE E6 - - A LINE TO EXISTING BLDG, LINE 5 A TO B -
Footing Inspection - Commercial Partial 10/1/2021 10/01/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
09/28/2021
- (3) COLUMN PADS LINE EA,EB ON LINE E6 - - A LINE TO EXISTING BLDG, LINE 5 A TO B - - LINE DA D3.5 TO D4, LINE D4 DA TO D6 -
Foundation Inspection - Commercial Partial 10/4/2021 (9:00) 10/4/2021 10/04/2021
Misc
Informational
10/04/2021
: THE FOLLOWING AREAS ARE APPROVED : - A LINE D2 TO D5 -
Storm Sewer Construction Inspection Partial 10/05/2021
Misc
Informational
09/24/2021
They laid 150 feet of 24 inch HDPE storm pipe and set grate inlet B-1. RP 9-9-21
Misc
Informational
09/24/2021
They poured collars and inverts and back filled today. RP 9-10-21
Misc
Informational
09/24/2021
Rodriguez Mechanical set structures A-2 and B-2. Noticed the existing storm pipe was CMP instead of HDPE that is listed on the plans. Engineering is reaching out to the Design Engineer to see if the different pipe material is ok. RP 9-13-21
Misc
Informational
09/24/2021
Their engineer said that CMP storm pipe is okay. Rodriguez laid 90 feet of 15 inch HDPE storm pipe and poured collars and inverts for structures A-2 and B-2. RP 9-14-21
Misc
Informational
09/24/2021
They laid 50 feet of 15 inch HDPE storm pipe and set curb inlets C-1 and B-4 along with grate inlet B-3. RP 9-15-21
Misc
Informational
09/24/2021
They cut into existing storm pipe and set junction box A-3. They also poured collars and inverts. RP 9-17-21
Misc
Informational
09/24/2021
Installed box A-2 and A-1.
Misc
Informational
10/05/2021
The storm has been installed, we are waiting on the approved plans to make sure what they did is acceptable. Talked to Rick and he said contractor will not be Back for a bit until they get foundation in.
Footing Inspection - Commercial Partial 10/5/2021 (1:00) 10/5/2021 10/05/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
10/01/2021
- (3) COLUMN PADS LINE EA,EB ON LINE E6 - - A LINE TO EXISTING BLDG, LINE 5 A TO B - - LINE DA D3.5 TO D4, LINE D4 DA TO D6 - - PADS & FOOTINGS LINE DA LINE 2 TO 3.5 -
Foundation Inspection - Commercial Partial 10/8/2021 (8:00) 10/8/2021 10/08/2021
Misc
Informational
10/04/2021
: THE FOLLOWING AREAS ARE APPROVED : - A LINE D2 TO D5 - - LINE DA 1 TO D4, LINE D4 DA TO D6 -
Underslab Plumbing Inspection - Commercial Passed 10/20/2021 10/20/2021 10/20/2021
Underslab Electrical Inspection - Commercial Passed 10/20/2021 10/20/2021 10/20/2021
Site Visit Partial 10/20/2021 10/20/2021 10/20/2021
Misc
Informational
09/08/2021
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
09/08/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
09/08/2021
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
09/08/2021
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
09/08/2021
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
09/08/2021
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
09/08/2021
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
09/08/2021
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
09/08/2021
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
09/08/2021
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
09/08/2021
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
09/08/2021
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
10/20/2021
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Water Line - Fire Hydrant Partial 11/4/2021 11/4/2021 11/04/2021
Misc
Informational
11/04/2021
Rodriguez Mechanical relocated old fire hydrant to the new location. Thrust blocks were poured on 45 bend and fire hydrant. Asked him to add tracer wire for the new section along with utility marking tape. Also informed him on his choices for the valve riser. RP 11-4-21
Fire Line - Hydrostatic Test Passed 11/5/2021 11/5/2021 11/06/2021
Misc
Informational
11/06/2021
Nathan from Rodriguez Mechanical tested the new fire hydrant at 200 psi for 2 hours. It held pressure. RP 11-5-21
Footing Inspection - Commercial Partial 11/9/2021 (2:30) 11/9/2021 11/09/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
10/05/2021
- (3) COLUMN PADS LINE EA,EB ON LINE E6 - - A LINE TO EXISTING BLDG, LINE 5 A TO B - - LINE DA D3.5 TO D4, LINE D4 DA TO D6 - - PADS & FOOTINGS LINE DA LINE 2 TO 3.5 - - (2) COLUMN PADS AT CANOPY, (1) NW CORNER -
Underslab Electrical Inspection - Commercial Partial 12/27/2021 12/27/2021 12/27/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/27/2021
- CONDUIT FOR (9) FLOOR BOXES, RECEPTION COUNTER, COMPUTER STATIONS -
Piers/Caissons Inspection - Commercial Not Ready 12/27/2021 (2:00) 12/27/2021 12/27/2021
Underground Electrical Inspection - Commercial Partial 12/29/2021 12/29/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/29/2021
- underground conduit (3) light pole bases front of bldg, IT conduit NE corner of bldg to quazite box at curb front of bldg -
Underground Electrical Inspection - Commercial Partial 12/30/2021 12/30/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/29/2021
- underground conduit (3) light pole bases front of bldg, IT conduit NE corner of bldg to quazite box at curb front of bldg - - 12/30/21 (1) LIGHT POLE BASE NORTH SIDE OF BLDG TO EXISTING POLE BASE SOUTH (REAR OF BLDG -
In-wall Inspection Partial 1/5/2022 01/05/2022
Miscellaneous Correction
Corrective Action Required
01/05/2022
PROVIDE BOCA PLATES THROUGHOUT PROVIDE MID POINT SUPPORT VERTICAL DWV 2" & SMALLER COMPLETE ELECTRICAL NORTH WALL
All Rough Inspection - Commercial Partial 1/5/2022 01/05/2022
Miscellaneous Correction
Corrective Action Required
01/05/2022
COMPLETE METAL STUD FRAMING AT TEMP WALL @ WORK ROOM / DATA STORAGE
In-wall Inspection Passed 1/6/2022 01/06/2022
Miscellaneous Correction
Resolved
01/06/2022
All Rough Inspection - Commercial Partial 1/6/2022 1/6/2022 01/06/2022
Miscellaneous Correction
Corrective Action Required
01/05/2022
INSTALL BACKORDERED WINDOWS & DOORS
Electrical Service Inspection Passed 1/14/2022 1/14/2022 01/14/2022
Erosion Control Inspection Failed 9/9/2021 9/9/2021 01/19/2022
Misc
Corrective Action Required
09/07/2021
Trench and catch basin will collect some of the runoff, but not enough erosion control in place to catch the south runoff. Talked with Rick Meyer about concerns and possible solutions. RP 8-20-21
Misc
Corrective Action Required
09/07/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. RP 8-24-21
Misc
Informational
09/07/2021
Controls are in place and they are going to add straw wattles in front of the drain pipe. RP 8-27-21
Misc
Informational
09/07/2021
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. RP 8-30-21
Misc
Corrective Action Required
09/07/2021
Silt breached the silt fencing again. Notified Rick and will tell KAW Valley also. RP 8-31-21
Misc
Informational
09/07/2021
Talked with KAW Valley about erosion issues. They are going to add rock checks through the trench and trouble spots. RP 9-2-21
Misc
Informational
09/07/2021
Rock checks did their job. KAW Valley to readjust straw wattles in front of storm pipe. RP 9-7-21
Misc
Corrective Action Required
01/19/2022
Mud is on McClendon and Oldham. Notified Rick from JE Dunn about the mess. He thinks it was his dumpster driver, but will get his foreman to clean it up. RP 1-19-22
Site Visit Partial 10/25/2021 10/25/2021 02/04/2022
Misc
Informational
10/20/2021
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
10/20/2021
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
10/20/2021
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
10/20/2021
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
10/20/2021
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
10/20/2021
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
10/20/2021
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
10/20/2021
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
10/20/2021
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
10/20/2021
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
10/20/2021
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
10/20/2021
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
10/20/2021
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
02/04/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Above Ceiling Inspection Partial 2/14/2022 2/14/2022 02/14/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
02/14/2022
- 2/14/22 HARD LIDS ROOMS 103,106,107,108 -
Site Visit Partial 2/7/2022 2/7/2022 02/14/2022
Misc
Informational
02/04/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
02/04/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
02/04/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
02/04/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
02/04/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
02/04/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
02/04/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
02/04/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
02/04/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
02/04/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
02/04/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
02/04/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
02/04/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
02/04/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
02/14/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Above Ceiling Inspection Partial 2/15/2022 2/15/2022 02/15/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
02/14/2022
- 2/14/22 HARD LIDS ROOMS 103,106,107,108 - - 2/15/22 HARD LIDS ROOMS 114, 116
Site Visit Partial 2/16/2022 2/16/2022 02/16/2022
Misc
Informational
02/14/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
02/14/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
02/14/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
02/14/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
02/14/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
02/14/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
02/14/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
02/14/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
02/14/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
02/14/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
02/14/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
02/14/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
02/14/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
02/14/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
02/14/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
02/16/2022
No exterior work being done today that needs inspection. RP 2-16-22
Erosion Control Inspection Residential Partial 02/16/2022
Misc
Informational
02/16/2022
Erosion controls are in place. No erosion issues were spotted. RP 2-16-22
Site Visit Partial 2/17/2022 2/17/2022 02/21/2022
Misc
Informational
02/16/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
02/16/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
02/16/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
02/16/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
02/16/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
02/16/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
02/16/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
02/16/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
02/16/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
02/16/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
02/16/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
02/16/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
02/16/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
02/16/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
02/16/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
02/16/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
02/21/2022
No work being done due to the snow storm. RP 2-17-22
Sprinkler - Hydrostatic Test Passed 2/22/2022 02/22/2022
Site Visit Partial 2/22/2022 2/22/2022 02/22/2022
Misc
Informational
02/21/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
02/21/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
02/21/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
02/21/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
02/21/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
02/21/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
02/21/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
02/21/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
02/21/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
02/21/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
02/21/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
02/21/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
02/21/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
02/21/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
02/21/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
02/21/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
02/21/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/22/2022
No utility or exterior work being done today. RP 2-22-22
Site Visit Partial 2/24/2022 2/24/2022 02/24/2022
Misc
Informational
02/22/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
02/22/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
02/22/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
02/22/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
02/22/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
02/22/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
02/22/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
02/22/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
02/22/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
02/22/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
02/22/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
02/22/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
02/22/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
02/22/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
02/22/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
02/22/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
02/22/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/22/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
02/24/2022
No work being done today due to the snow. RP 2-24-22
Site Visit Partial 2/25/2022 2/25/2022 02/25/2022
Misc
Informational
02/24/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
02/24/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
02/24/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
02/24/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
02/24/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
02/24/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
02/24/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
02/24/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
02/24/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
02/24/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
02/24/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
02/24/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
02/24/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
02/24/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
02/24/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
02/24/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
02/24/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/24/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
02/24/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
02/25/2022
No work being done today that needs inspection. RP 2-25-22
Above Ceiling Inspection Partial 3/1/2022 3/1/2022 03/01/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
02/15/2022
- 2/14/22 HARD LIDS ROOMS 103,106,107,108 - - 2/15/22 HARD LIDS ROOMS 114, 116 - 3/1/22 ROOM 101 SOUTH END LINE E3 TO E1 OK TO DROP CEILING TILE, SOFFITS AT NORTH & EAST DOORS -
Storm Sewer Construction Inspection Passed 03/01/2022
Misc
Informational
10/05/2021
They laid 150 feet of 24 inch HDPE storm pipe and set grate inlet B-1. RP 9-9-21
Misc
Informational
10/05/2021
They poured collars and inverts and back filled today. RP 9-10-21
Misc
Informational
10/05/2021
Rodriguez Mechanical set structures A-2 and B-2. Noticed the existing storm pipe was CMP instead of HDPE that is listed on the plans. Engineering is reaching out to the Design Engineer to see if the different pipe material is ok. RP 9-13-21
Misc
Informational
10/05/2021
Their engineer said that CMP storm pipe is okay. Rodriguez laid 90 feet of 15 inch HDPE storm pipe and poured collars and inverts for structures A-2 and B-2. RP 9-14-21
Misc
Informational
10/05/2021
They laid 50 feet of 15 inch HDPE storm pipe and set curb inlets C-1 and B-4 along with grate inlet B-3. RP 9-15-21
Misc
Informational
10/05/2021
They cut into existing storm pipe and set junction box A-3. They also poured collars and inverts. RP 9-17-21
Misc
Informational
10/05/2021
Installed box A-2 and A-1.
Misc
Informational
10/05/2021
The storm has been installed, we are waiting on the approved plans to make sure what they did is acceptable. Talked to Rick and he said contractor will not be Back for a bit until they get foundation in.
Misc
Informational
03/01/2022
All storm lines have been installed. RP 3-1-22
Site Visit Partial 2/28/2022 2/28/2022 03/01/2022
Misc
Informational
02/25/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
02/25/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
02/25/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
02/25/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
02/25/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
02/25/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
02/25/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
02/25/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
02/25/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
02/25/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
02/25/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
02/25/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
02/25/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
02/25/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
02/25/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
02/25/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
02/25/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/25/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
02/25/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
02/25/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Corrective Action Required
03/01/2022
Stopped by and talked with Rick from JE Dunn and Kenny from KAW Valley about the parking lot and curbing. Also informed Rick that his subcontractor hooked up his sanitary line without an inspection. RP 3-1-22
Site Visit Partial 3/2/2022 3/2/2022 03/02/2022
Misc
Informational
03/01/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
03/01/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
03/01/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
03/01/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
03/01/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
03/01/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
03/01/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
03/01/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
03/01/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
03/01/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
03/01/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
03/01/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
03/01/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
03/01/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
03/01/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
03/01/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
03/01/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/01/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/01/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
03/01/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Corrective Action Required
03/01/2022
Stopped by and talked with Rick from JE Dunn and Kenny from KAW Valley about the parking lot and curbing. Also informed Rick that his subcontractor hooked up his sanitary line without an inspection. RP 3-1-22
Misc
Informational
03/02/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. Rick also informed me that Rodriguez Mechanical is looking for pictures concerning the sanitary connections. RP 3-2-22
Pavement-Aggregate Base Partial 03/02/2022
Misc
Informational
03/02/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. RP 3-2-22
Site Visit Partial 3/3/2022 3/3/2022 03/03/2022
Misc
Informational
03/02/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
03/02/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
03/02/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
03/02/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
03/02/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
03/02/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
03/02/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
03/02/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
03/02/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
03/02/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
03/02/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
03/02/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
03/02/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
03/02/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
03/02/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
03/02/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
03/02/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/02/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/02/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
03/02/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Corrective Action Required
03/02/2022
Stopped by and talked with Rick from JE Dunn and Kenny from KAW Valley about the parking lot and curbing. Also informed Rick that his subcontractor hooked up his sanitary line without an inspection. RP 3-1-22
Misc
Informational
03/02/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. Rick also informed me that Rodriguez Mechanical is looking for pictures concerning the sanitary connections. RP 3-2-22
Misc
Informational
03/03/2022
Talked with Rick about parking lot. Subcontractor isn’t available tomorrow, so they are planning on curbing next Tuesday depending on the weather this weekend. RP 3-3-22
Pavement-Aggregate Base Partial 3/3/2022 3/3/2022 03/03/2022
Misc
Informational
03/02/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. RP 3-2-22
Misc
Informational
03/03/2022
KAW Valley started rolling out geogrid and covering it with 6 inches of AB3 until the ran out of material. RP 3-3-22
Pavement-Aggregate Base Partial 3/4/2022 3/4/2022 03/04/2022
Misc
Informational
03/03/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. RP 3-2-22
Misc
Informational
03/03/2022
KAW Valley started rolling out geogrid and covering it with 6 inches of AB3 until the ran out of material. RP 3-3-22
Misc
Informational
03/04/2022
KAW Valley still laying down geogrid and AB3. RP 3-4-22
Sewer Service Inspection Passed 03/04/2022
Misc
Informational
03/04/2022
Rodriguez Mechanical used hard back Fernco’s and a wye when connecting the sanitary line. RP 3-4-22
Above Ceiling Inspection Partial 3/8/2022 3/8/2022 03/08/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
03/01/2022
- 2/14/22 HARD LIDS ROOMS 103,106,107,108 - - 2/15/22 HARD LIDS ROOMS 114, 116 - 3/1/22 ROOM 101 SOUTH END LINE E3 TO E1 OK TO DROP CEILING TILE, SOFFITS AT NORTH & EAST DOORS --- - 3/8/22 ROOMS 103,116,117, ROOM 101 COLUMN LINE C TO REAR OF BLDG -
Above Ceiling Inspection Partial 3/11/2022 3/11/2022 03/11/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
03/08/2022
- 2/14/22 HARD LIDS ROOMS 103,106,107,108 - - 2/15/22 HARD LIDS ROOMS 114, 116 - 3/1/22 ROOM 101 SOUTH END LINE E3 TO E1 OK TO DROP CEILING TILE, SOFFITS AT NORTH & EAST DOORS --- - 3/8/22 ROOMS 103,116,117, ROOM 101 COLUMN LINE C TO REAR OF BLDG - - 3/11/22 ROOMS 101 LINE C TO FRONT OF BLDG,109,110,111,112,113 -
Site Visit Partial 3/4/2022 3/4/2022 03/14/2022
Misc
Informational
03/03/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
03/03/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
03/03/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
03/03/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
03/03/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
03/03/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
03/03/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
03/03/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
03/03/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
03/03/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
03/03/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
03/03/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
03/03/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
03/03/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
03/03/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
03/03/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
03/03/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/03/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/03/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
03/03/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Corrective Action Required
03/03/2022
Stopped by and talked with Rick from JE Dunn and Kenny from KAW Valley about the parking lot and curbing. Also informed Rick that his subcontractor hooked up his sanitary line without an inspection. RP 3-1-22
Misc
Informational
03/03/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. Rick also informed me that Rodriguez Mechanical is looking for pictures concerning the sanitary connections. RP 3-2-22
Misc
Informational
03/03/2022
Talked with Rick about parking lot. Subcontractor isn’t available tomorrow, so they are planning on curbing next Tuesday depending on the weather this weekend. RP 3-3-22
Misc
Informational
03/14/2022
No work being done on site today. RP 3-10-22
Site Visit Partial 03/14/2022
Misc
Informational
03/14/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
03/14/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
03/14/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
03/14/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
03/14/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
03/14/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
03/14/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
03/14/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
03/14/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
03/14/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
03/14/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
03/14/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
03/14/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
03/14/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
03/14/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
03/14/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
03/14/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/14/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/14/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
03/14/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Corrective Action Required
03/14/2022
Stopped by and talked with Rick from JE Dunn and Kenny from KAW Valley about the parking lot and curbing. Also informed Rick that his subcontractor hooked up his sanitary line without an inspection. RP 3-1-22
Misc
Informational
03/14/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. Rick also informed me that Rodriguez Mechanical is looking for pictures concerning the sanitary connections. RP 3-2-22
Misc
Informational
03/14/2022
Talked with Rick about parking lot. Subcontractor isn’t available tomorrow, so they are planning on curbing next Tuesday depending on the weather this weekend. RP 3-3-22
Misc
Informational
03/14/2022
No work being done on site today. RP 3-10-22
Misc
Informational
03/14/2022
No exterior work being done on site today. Talked with Rick, they hope the subgrade will dry out enough to get some more rock down before the next rain event (Thursday?). RP 3-14-22
Above Ceiling Inspection Partial 3/18/2022 3/18/2022 03/18/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
03/11/2022
- 2/14/22 HARD LIDS ROOMS 103,106,107,108 - - 2/15/22 HARD LIDS ROOMS 114, 116 - 3/1/22 ROOM 101 SOUTH END LINE E3 TO E1 OK TO DROP CEILING TILE, SOFFITS AT NORTH & EAST DOORS --- - 3/8/22 ROOMS 103,116,117, ROOM 101 COLUMN LINE C TO REAR OF BLDG - - 3/11/22 ROOMS 101 LINE C TO FRONT OF BLDG,109,110,111,112,113 - - 3/18/22 ROOMS 104 & 110 COMPLETE -
Site Visit Partial 3/21/2022 3/21/2022 03/21/2022
Misc
Informational
03/14/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
03/14/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
03/14/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
03/14/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
03/14/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
03/14/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
03/14/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
03/14/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
03/14/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
03/14/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
03/14/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
03/14/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
03/14/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
03/14/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
03/14/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
03/14/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
03/14/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/14/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/14/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
03/14/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Corrective Action Required
03/14/2022
Stopped by and talked with Rick from JE Dunn and Kenny from KAW Valley about the parking lot and curbing. Also informed Rick that his subcontractor hooked up his sanitary line without an inspection. RP 3-1-22
Misc
Informational
03/14/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. Rick also informed me that Rodriguez Mechanical is looking for pictures concerning the sanitary connections. RP 3-2-22
Misc
Informational
03/14/2022
Talked with Rick about parking lot. Subcontractor isn’t available tomorrow, so they are planning on curbing next Tuesday depending on the weather this weekend. RP 3-3-22
Misc
Informational
03/14/2022
No work being done on site today. RP 3-10-22
Misc
Informational
03/14/2022
No exterior work being done on site today. Talked with Rick, they hope the subgrade will dry out enough to get some more rock down before the next rain event (Thursday?). RP 3-14-22
Misc
Informational
03/21/2022
KAW Valley was on site laying down more geogrid and AB3 for the subgrade until it starts raining. RP 3-21-22
Pavement-Aggregate Base Partial 3/7/2022 3/7/2022 03/21/2022
Misc
Informational
03/04/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. RP 3-2-22
Misc
Informational
03/04/2022
KAW Valley started rolling out geogrid and covering it with 6 inches of AB3 until the ran out of material. RP 3-3-22
Misc
Informational
03/04/2022
KAW Valley still laying down geogrid and AB3. RP 3-4-22
Misc
Informational
03/21/2022
KAW Valley was on site laying down more geogrid and AB3 for the subgrade until it starts raining. RP 3-21-22
Erosion Control Inspection Partial 03/24/2022
Misc
Corrective Action Required
01/19/2022
Trench and catch basin will collect some of the runoff, but not enough erosion control in place to catch the south runoff. Talked with Rick Meyer about concerns and possible solutions. RP 8-20-21
Misc
Corrective Action Required
01/19/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. RP 8-24-21
Misc
Informational
01/19/2022
Controls are in place and they are going to add straw wattles in front of the drain pipe. RP 8-27-21
Misc
Informational
01/19/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. RP 8-30-21
Misc
Corrective Action Required
01/19/2022
Silt breached the silt fencing again. Notified Rick and will tell KAW Valley also. RP 8-31-21
Misc
Informational
01/19/2022
Talked with KAW Valley about erosion issues. They are going to add rock checks through the trench and trouble spots. RP 9-2-21
Misc
Informational
01/19/2022
Rock checks did their job. KAW Valley to readjust straw wattles in front of storm pipe. RP 9-7-21
Misc
Corrective Action Required
01/19/2022
Mud is on McClendon and Oldham. Notified Rick from JE Dunn about the mess. He thinks it was his dumpster driver, but will get his foreman to clean it up. RP 1-19-22
Misc
Informational
03/24/2022
Another rain day, still no erosion issues to report. RP 3-24-22
Pavement-Proof Roll Failed 03/28/2022
Misc
Informational
03/28/2022
KAW Valley had a tandem dump truck with a 20.11 ton load. PSI was also on site to witness the proof roll of the curb line. There were numerous areas that failed and need to be reworked. RP 3-28-22
Pavement-Aggregate Base Partial 3/24/2022 3/24/2022 03/28/2022
Misc
Informational
03/21/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. RP 3-2-22
Misc
Informational
03/21/2022
KAW Valley started rolling out geogrid and covering it with 6 inches of AB3 until the ran out of material. RP 3-3-22
Misc
Informational
03/21/2022
KAW Valley still laying down geogrid and AB3. RP 3-4-22
Misc
Informational
03/21/2022
KAW Valley was on site laying down more geogrid and AB3 for the subgrade until it starts raining. RP 3-21-22
Misc
Informational
03/28/2022
Proof roll for the curb line failed, So KAW Valley reworked those areas continued adding more rock to the subgrade. RP 3-28-22
Pavement-Proof Roll Failed 04/08/2022
Misc
Informational
03/28/2022
KAW Valley had a tandem dump truck with a 20.11 ton load. PSI was also on site to witness the proof roll of the curb line. There were numerous areas that failed and need to be reworked. RP 3-28-22
Misc
Corrective Action Required
04/08/2022
KAW Valley had a tandem dump truck with a 20.99 ton load. Proof roll was a little better than last time, but there is still too many areas that failed. I showed Rick the 3 sections that he could place curbing tomorrow. PSI wasn’t present during this test. RP 4-8-22
Site Visit Partial 3/28/2022 3/28/2022 04/08/2022
Misc
Informational
03/21/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
03/21/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
03/21/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
03/21/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
03/21/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
03/21/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
03/21/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
03/21/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
03/21/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
03/21/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
03/21/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
03/21/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
03/21/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
03/21/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
03/21/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
03/21/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
03/21/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/21/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/21/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
03/21/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Corrective Action Required
03/21/2022
Stopped by and talked with Rick from JE Dunn and Kenny from KAW Valley about the parking lot and curbing. Also informed Rick that his subcontractor hooked up his sanitary line without an inspection. RP 3-1-22
Misc
Informational
03/21/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. Rick also informed me that Rodriguez Mechanical is looking for pictures concerning the sanitary connections. RP 3-2-22
Misc
Informational
03/21/2022
Talked with Rick about parking lot. Subcontractor isn’t available tomorrow, so they are planning on curbing next Tuesday depending on the weather this weekend. RP 3-3-22
Misc
Informational
03/21/2022
No work being done on site today. RP 3-10-22
Misc
Informational
03/21/2022
No exterior work being done on site today. Talked with Rick, they hope the subgrade will dry out enough to get some more rock down before the next rain event (Thursday?). RP 3-14-22
Misc
Informational
03/21/2022
KAW Valley was on site laying down more geogrid and AB3 for the subgrade until it starts raining. RP 3-21-22
Misc
Informational
04/08/2022
KAW Valley is still working on the subgrade for the curb line and parking lot. RP 4-8-22
Pavement-Aggregate Base Partial 3/29/2022 3/29/2022 04/08/2022
Misc
Informational
03/28/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. RP 3-2-22
Misc
Informational
03/28/2022
KAW Valley started rolling out geogrid and covering it with 6 inches of AB3 until the ran out of material. RP 3-3-22
Misc
Informational
03/28/2022
KAW Valley still laying down geogrid and AB3. RP 3-4-22
Misc
Informational
03/28/2022
KAW Valley was on site laying down more geogrid and AB3 for the subgrade until it starts raining. RP 3-21-22
Misc
Informational
03/28/2022
Proof roll for the curb line failed, So KAW Valley reworked those areas continued adding more rock to the subgrade. RP 3-28-22
Misc
Informational
04/08/2022
KAW Valley is still reworking on the subgrade for the curb line and parking lot, where it failed the proof roll. RP 4-8-22
Above Ceiling Inspection Passed 4/8/2022 4/8/2022 04/08/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
03/18/2022
- 2/14/22 HARD LIDS ROOMS 103,106,107,108 - - 2/15/22 HARD LIDS ROOMS 114, 116 - 3/1/22 ROOM 101 SOUTH END LINE E3 TO E1 OK TO DROP CEILING TILE, SOFFITS AT NORTH & EAST DOORS --- - 3/8/22 ROOMS 103,116,117, ROOM 101 COLUMN LINE C TO REAR OF BLDG - - 3/11/22 ROOMS 101 LINE C TO FRONT OF BLDG,109,110,111,112,113 - - 3/18/22 ROOMS 104 & 110 COMPLETE - - 4/8/22 ROOM 100 -
All Rough Inspection - Commercial Passed 4/8/2022 04/08/2022
Miscellaneous Correction
Resolved
04/08/2022
Site Visit Partial 04/14/2022
Misc
Informational
04/08/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
04/08/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
04/08/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
04/08/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
04/08/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
04/08/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
04/08/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
04/08/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
04/08/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
04/08/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
04/08/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
04/08/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
04/08/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
04/08/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
04/08/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
04/08/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
04/08/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
04/08/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
04/08/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
04/08/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Corrective Action Required
04/08/2022
Stopped by and talked with Rick from JE Dunn and Kenny from KAW Valley about the parking lot and curbing. Also informed Rick that his subcontractor hooked up his sanitary line without an inspection. RP 3-1-22
Misc
Informational
04/08/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. Rick also informed me that Rodriguez Mechanical is looking for pictures concerning the sanitary connections. RP 3-2-22
Misc
Informational
04/08/2022
Talked with Rick about parking lot. Subcontractor isn’t available tomorrow, so they are planning on curbing next Tuesday depending on the weather this weekend. RP 3-3-22
Misc
Informational
04/08/2022
No work being done on site today. RP 3-10-22
Misc
Informational
04/08/2022
No exterior work being done on site today. Talked with Rick, they hope the subgrade will dry out enough to get some more rock down before the next rain event (Thursday?). RP 3-14-22
Misc
Informational
04/08/2022
KAW Valley was on site laying down more geogrid and AB3 for the subgrade until it starts raining. RP 3-21-22
Misc
Informational
04/08/2022
KAW Valley is still working on the subgrade for the curb line and parking lot. RP 4-8-22
Misc
Informational
04/14/2022
Stopped by and talked with Rick from JE Dunn about the parking lot. Planning on doing another proof roll tomorrow, weather permitting. Also talked with Epic Concrete about the curbing around the parking lot perimeter. RP 4-14-22
Pavement-Proof Roll Passed 4/15/2022 4/15/2022 04/15/2022
Misc
Informational
04/08/2022
KAW Valley had a tandem dump truck with a 20.11 ton load. PSI was also on site to witness the proof roll of the curb line. There were numerous areas that failed and need to be reworked. RP 3-28-22
Misc
Corrective Action Required
04/08/2022
KAW Valley had a tandem dump truck with a 20.99 ton load. Proof roll was a little better than last time, but there is still too many areas that failed. I showed Rick the 3 sections that he could place curbing tomorrow. PSI wasn’t present during this test. RP 4-8-22
Misc
Informational
04/15/2022
KAW Valley had a tandem dump truck with a 20.46 ton load. PSI was also on site to witness the proof roll. The curb line passed all areas of the proof roll. RP 4-15-22
Pavement-Curb Construction Partial 4/18/2022 4/18/2022 04/18/2022
Misc
Informational
04/18/2022
Epic Concrete started forming and pouring curbing. RP 4-18-22
Pavement-Curb Construction Partial 4/19/2022 4/19/2022 04/19/2022
Misc
Informational
04/18/2022
Epic Concrete started forming and pouring curbing. RP 4-18-22
Misc
Informational
04/19/2022
Epic is still forming and pouring curbing for the parking lot. Verified that they are using 4K KCMMB mix. RP 4-19-22
Pavement-Curb Construction Partial 4/20/2022 4/20/2022 04/21/2022
Misc
Informational
04/19/2022
Epic Concrete started forming and pouring curbing. RP 4-18-22
Misc
Informational
04/19/2022
Epic is still forming and pouring curbing for the parking lot. Verified that they are using 4K KCMMB mix. RP 4-19-22
Misc
Informational
04/21/2022
Epic still forming and pouring curbing for the parking lot. Discussed the sidewalk along McClendon and running through the parking lot. JE Dunn is going to follow up with the engineers. RP 4-21-22
Piers/Caissons Inspection - Commercial Not Ready 4/22/2022 (1:00) 4/22/2022 04/22/2022
Sprinkler - Flow Test Passed 4/25/2022 04/25/2022
Alarm Test Failed 4/25/2022 04/25/2022
Sidewalk Inspection Partial 04/25/2022
Misc
Informational
04/25/2022
Met with Mike from Epic concrete on-site. Went over the speed check/raised walk going through parking lot. Inspected this area and it was framed up with aggregate in and compacted. 4/25/22 ES
Pavement-Aggregate Base Partial 04/25/2022
Misc
Informational
04/08/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. RP 3-2-22
Misc
Informational
04/08/2022
KAW Valley started rolling out geogrid and covering it with 6 inches of AB3 until the ran out of material. RP 3-3-22
Misc
Informational
04/08/2022
KAW Valley still laying down geogrid and AB3. RP 3-4-22
Misc
Informational
04/08/2022
KAW Valley was on site laying down more geogrid and AB3 for the subgrade until it starts raining. RP 3-21-22
Misc
Informational
04/08/2022
Proof roll for the curb line failed, So KAW Valley reworked those areas continued adding more rock to the subgrade. RP 3-28-22
Misc
Informational
04/08/2022
KAW Valley is still reworking on the subgrade for the curb line and parking lot, where it failed the proof roll. RP 4-8-22
Misc
Informational
04/25/2022
Spoke with Mike with Epic concrete. They are going to be pouring the dumpster pad and drive area coming out from it tomorrow with 8” thick KCMMB concrete. 4/25/22 ES
Piers/Caissons Inspection - Commercial Partial 4/27/2022 04/27/2022
Misc
Corrective Action Required
04/27/2022
(3) OF (4) LIGHT POLE BASES EAST SIDE ( FRONT OF BLDG) DRIVEN GROUND ROD IN PLACE HIT ROCK ON 4TH AT NORTH SIDE WILL CALL FOR RE INSPECT WHEN READY
Footing Inspection - Commercial Passed 5/5/2022 05/05/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
11/09/2021
- (3) COLUMN PADS LINE EA,EB ON LINE E6 - - A LINE TO EXISTING BLDG, LINE 5 A TO B - - LINE DA D3.5 TO D4, LINE D4 DA TO D6 - - PADS & FOOTINGS LINE DA LINE 2 TO 3.5 - - (2) COLUMN PADS AT CANOPY, (1) NW CORNER -
Foundation Inspection - Commercial Passed 5/5/2022 05/05/2022
Misc
Informational
10/08/2021
: THE FOLLOWING AREAS ARE APPROVED : - A LINE D2 TO D5 - - LINE DA 1 TO D4, LINE D4 DA TO D6 -
Underslab Electrical Inspection - Commercial Passed 5/5/2022 05/05/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/27/2021
- CONDUIT FOR (9) FLOOR BOXES, RECEPTION COUNTER, COMPUTER STATIONS -
Miscellaneous Inspection Failed 5/5/2022 5/5/2022 05/05/2022
Miscellaneous Correction
Corrective Action Required
05/05/2022
: STOCK & TRAIN INSPECTION FAILED CODES COMPLETE INSIDE BLDG FIRE ALARM FAILED BELOW DEPTS NOT PRESENT FIELD ENGINEERING ? PLANNING ? WATER ? Fire alarm 4th light pole Pier ? Call when ready to inspect Provide address Complete & inspect Light poles Pave parking lot
Occupancy Inspection - Codes Commercial Failed 5/6/2022 05/06/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
05/06/2022
This Final Occupancy was scheduled with Fire and Codes only for STOCK & TRAIN approval. As per Fire and Codes Dept. we are approving the interior for set up of shelving, permanent furniture, equipment. The Building is not to be occupied or used by the public. This is not a Temporary Certificate of Occupancy. When ready please schedule a full final inspection at 969-1200 2 full business days prior to the desired inspection date. Items remaining but not limited to: 4th light pole Pier - Call when ready to inspect Provide address Complete & inspect Light poles Pave parking lot , Planning requirements.
Site Visit Partial 4/15/2022 05/06/2022
Misc
Informational
04/14/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
04/14/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
04/14/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
04/14/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
04/14/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
04/14/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
04/14/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
04/14/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
04/14/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
04/14/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
04/14/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
04/14/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
04/14/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
04/14/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
04/14/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
04/14/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
04/14/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
04/14/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
04/14/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
04/14/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Corrective Action Required
04/14/2022
Stopped by and talked with Rick from JE Dunn and Kenny from KAW Valley about the parking lot and curbing. Also informed Rick that his subcontractor hooked up his sanitary line without an inspection. RP 3-1-22
Misc
Informational
04/14/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. Rick also informed me that Rodriguez Mechanical is looking for pictures concerning the sanitary connections. RP 3-2-22
Misc
Informational
04/14/2022
Talked with Rick about parking lot. Subcontractor isn’t available tomorrow, so they are planning on curbing next Tuesday depending on the weather this weekend. RP 3-3-22
Misc
Informational
04/14/2022
No work being done on site today. RP 3-10-22
Misc
Informational
04/14/2022
No exterior work being done on site today. Talked with Rick, they hope the subgrade will dry out enough to get some more rock down before the next rain event (Thursday?). RP 3-14-22
Misc
Informational
04/14/2022
KAW Valley was on site laying down more geogrid and AB3 for the subgrade until it starts raining. RP 3-21-22
Misc
Informational
04/14/2022
KAW Valley is still working on the subgrade for the curb line and parking lot. RP 4-8-22
Misc
Informational
04/14/2022
Stopped by and talked with Rick from JE Dunn about the parking lot. Planning on doing another proof roll tomorrow, weather permitting. Also talked with Epic Concrete about the curbing around the parking lot perimeter. RP 4-14-22
Misc
Informational
05/06/2022
Met with Rick from JE Dunn and Mike with Epic concrete about sidewalk design and ADA requirements. Spoke with Sue about plans, they had previous approval for sidewalk. They will have ADA access in front of building and at handicap parking areas only. Other sidewalks are private and not required to conform. 4/6/22 ES
Sidewalk Inspection Partial 05/06/2022
Misc
Informational
04/25/2022
Met with Mike from Epic concrete on-site. Went over the speed check/raised walk going through parking lot. Inspected this area and it was framed up with aggregate in and compacted. 4/25/22 ES
Misc
Informational
05/06/2022
Spoke with Mike at Epic concrete, they poured upper portion of sidewalk and framed up curbing and other areas. 5/4/22 ES
Pavement-Curb Construction Partial 4/25/2022 4/25/2022 05/10/2022
Misc
Informational
04/21/2022
Epic Concrete started forming and pouring curbing. RP 4-18-22
Misc
Informational
04/21/2022
Epic is still forming and pouring curbing for the parking lot. Verified that they are using 4K KCMMB mix. RP 4-19-22
Misc
Informational
04/21/2022
Epic still forming and pouring curbing for the parking lot. Discussed the sidewalk along McClendon and running through the parking lot. JE Dunn is going to follow up with the engineers. RP 4-21-22
Misc
Informational
05/10/2022
Mike’s, Epic concrete crew continued working on forming up curbing and working on sidewalk crosswalks. 5/9/22 ES
Pavement-Aggregate Base Partial 05/10/2022
Misc
Informational
04/25/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. RP 3-2-22
Misc
Informational
04/25/2022
KAW Valley started rolling out geogrid and covering it with 6 inches of AB3 until the ran out of material. RP 3-3-22
Misc
Informational
04/25/2022
KAW Valley still laying down geogrid and AB3. RP 3-4-22
Misc
Informational
04/25/2022
KAW Valley was on site laying down more geogrid and AB3 for the subgrade until it starts raining. RP 3-21-22
Misc
Informational
04/25/2022
Proof roll for the curb line failed, So KAW Valley reworked those areas continued adding more rock to the subgrade. RP 3-28-22
Misc
Informational
04/25/2022
KAW Valley is still reworking on the subgrade for the curb line and parking lot, where it failed the proof roll. RP 4-8-22
Misc
Informational
04/25/2022
Spoke with Mike with Epic concrete. They are going to be pouring the dumpster pad and drive area coming out from it tomorrow with 8” thick KCMMB concrete. 4/25/22 ES
Misc
Informational
05/10/2022
Performed proof roll for parking lot with Kaw Valley and Rick from JE Dunn. All areas of parking lot were solid and ready for final grading/paving. 5/9/22 ES
Pavement-Proof Roll Passed 05/10/2022
Misc
Informational
05/10/2022
Performed proof roll for parking lot with Kaw Valley and Rick from JE Dunn. All areas of parking lot were solid and ready for final grading/paving. 5/9/22 ES
Sidewalk Inspection Partial 05/10/2022
Misc
Informational
05/06/2022
Met with Mike from Epic concrete on-site. Went over the speed check/raised walk going through parking lot. Inspected this area and it was framed up with aggregate in and compacted. 4/25/22 ES
Misc
Informational
05/06/2022
Spoke with Mike at Epic concrete, they poured upper portion of sidewalk and framed up curbing and other areas. 5/4/22 ES
Misc
Informational
05/10/2022
Mike’s crew poured more sections of sidewalk today along north side of building and in front of building. 5/9/22 ES
Pavement-Surface Partial 05/12/2022
Misc
Informational
05/12/2022
Hanrahan put down 1,009 tons of type 1-01 base asphalt. 5/11/22 ES
Pavement-Surface Partial 05/12/2022
Misc
Informational
05/12/2022
Hanrahan put down 1,009 tons of type 1-01 base asphalt. 5/11/22 ES
Misc
Informational
05/12/2022
5-12-22 AN crew was putting down surface and it is looking good. Asphalt temp going into the paver was 280deg
Site Visit Partial 05/16/2022
Misc
Informational
05/06/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
05/06/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
05/06/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
05/06/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
05/06/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
05/06/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
05/06/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
05/06/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
05/06/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
05/06/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
05/06/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
05/06/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
05/06/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
05/06/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
05/06/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
05/06/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
05/06/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
05/06/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
05/06/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
05/06/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Corrective Action Required
05/06/2022
Stopped by and talked with Rick from JE Dunn and Kenny from KAW Valley about the parking lot and curbing. Also informed Rick that his subcontractor hooked up his sanitary line without an inspection. RP 3-1-22
Misc
Informational
05/06/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. Rick also informed me that Rodriguez Mechanical is looking for pictures concerning the sanitary connections. RP 3-2-22
Misc
Informational
05/06/2022
Talked with Rick about parking lot. Subcontractor isn’t available tomorrow, so they are planning on curbing next Tuesday depending on the weather this weekend. RP 3-3-22
Misc
Informational
05/06/2022
No work being done on site today. RP 3-10-22
Misc
Informational
05/06/2022
No exterior work being done on site today. Talked with Rick, they hope the subgrade will dry out enough to get some more rock down before the next rain event (Thursday?). RP 3-14-22
Misc
Informational
05/06/2022
KAW Valley was on site laying down more geogrid and AB3 for the subgrade until it starts raining. RP 3-21-22
Misc
Informational
05/06/2022
KAW Valley is still working on the subgrade for the curb line and parking lot. RP 4-8-22
Misc
Informational
05/06/2022
Stopped by and talked with Rick from JE Dunn about the parking lot. Planning on doing another proof roll tomorrow, weather permitting. Also talked with Epic Concrete about the curbing around the parking lot perimeter. RP 4-14-22
Misc
Informational
05/06/2022
Met with Rick from JE Dunn and Mike with Epic concrete about sidewalk design and ADA requirements. Spoke with Sue about plans, they had previous approval for sidewalk. They will have ADA access in front of building and at handicap parking areas only. Other sidewalks are private and not required to conform. 4/6/22 ES
Misc
Informational
05/16/2022
Epic concrete working on sidewalks. Asphalt was completed last week. 5/16/22 ES
Sidewalk Inspection Partial 05/16/2022
Misc
Informational
05/10/2022
Met with Mike from Epic concrete on-site. Went over the speed check/raised walk going through parking lot. Inspected this area and it was framed up with aggregate in and compacted. 4/25/22 ES
Misc
Informational
05/10/2022
Spoke with Mike at Epic concrete, they poured upper portion of sidewalk and framed up curbing and other areas. 5/4/22 ES
Misc
Informational
05/10/2022
Mike’s crew poured more sections of sidewalk today along north side of building and in front of building. 5/9/22 ES
Misc
Informational
05/16/2022
Mike’s crew with Epic was working on sidewalks leading into parking lot area. 5/16/22 ES
Piers/Caissons Inspection - Commercial Passed 5/16/2022 05/16/2022
Misc
Informational
05/16/2022
(4) OF (4) LIGHT POLE BASES EAST SIDE ( FRONT OF BLDG & (1) north ) DRIVEN GROUND ROD IN PLACe
Sidewalk Inspection Partial 05/19/2022
Misc
Informational
05/16/2022
Met with Mike from Epic concrete on-site. Went over the speed check/raised walk going through parking lot. Inspected this area and it was framed up with aggregate in and compacted. 4/25/22 ES
Misc
Informational
05/16/2022
Spoke with Mike at Epic concrete, they poured upper portion of sidewalk and framed up curbing and other areas. 5/4/22 ES
Misc
Informational
05/16/2022
Mike’s crew poured more sections of sidewalk today along north side of building and in front of building. 5/9/22 ES
Misc
Informational
05/16/2022
Mike’s crew with Epic was working on sidewalks leading into parking lot area. 5/16/22 ES Mike’s crew continued working on sidewalks on side and front parking lot areas of building. 5/17/22 ES
Sidewalk Inspection Partial 05/19/2022
Misc
Informational
05/19/2022
Met with Mike from Epic concrete on-site. Went over the speed check/raised walk going through parking lot. Inspected this area and it was framed up with aggregate in and compacted. 4/25/22 ES
Misc
Informational
05/19/2022
Spoke with Mike at Epic concrete, they poured upper portion of sidewalk and framed up curbing and other areas. 5/4/22 ES
Misc
Informational
05/19/2022
Mike’s crew poured more sections of sidewalk today along north side of building and in front of building. 5/9/22 ES
Misc
Informational
05/19/2022
Mike’s crew with Epic was working on sidewalks leading into parking lot area. 5/16/22 ES Mike’s crew continued working on sidewalks on side and front parking lot areas of building. 5/17/22 ES Mike’s crew continued working on sidewalks in middle of parking area and front of building. 5/18/22 ES
Pavement-Surface Partial 05/19/2022
Misc
Informational
05/12/2022
Hanrahan put down 1,009 tons of type 1-01 base asphalt. 5/11/22 ES
Misc
Informational
05/12/2022
5-12-22 AN crew was putting down surface and it is looking good. Asphalt temp going into the paver was 280deg
Misc
Informational
05/19/2022
Asphalt surface was all laid and striping has been completed. 5/16/22 ES
Occupancy Inspection - Fire Temporary C of O 5/6/2022 05/20/2022
Alarm Test Passed 5/5/2022 05/20/2022
Site Visit Partial 05/31/2022
Misc
Informational
05/16/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
05/16/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
05/16/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
05/16/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
05/16/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
05/16/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
05/16/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
05/16/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
05/16/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
05/16/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
05/16/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
05/16/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
05/16/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
05/16/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
05/16/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
05/16/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
05/16/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
05/16/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
05/16/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
05/16/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Corrective Action Required
05/16/2022
Stopped by and talked with Rick from JE Dunn and Kenny from KAW Valley about the parking lot and curbing. Also informed Rick that his subcontractor hooked up his sanitary line without an inspection. RP 3-1-22
Misc
Informational
05/16/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. Rick also informed me that Rodriguez Mechanical is looking for pictures concerning the sanitary connections. RP 3-2-22
Misc
Informational
05/16/2022
Talked with Rick about parking lot. Subcontractor isn’t available tomorrow, so they are planning on curbing next Tuesday depending on the weather this weekend. RP 3-3-22
Misc
Informational
05/16/2022
No work being done on site today. RP 3-10-22
Misc
Informational
05/16/2022
No exterior work being done on site today. Talked with Rick, they hope the subgrade will dry out enough to get some more rock down before the next rain event (Thursday?). RP 3-14-22
Misc
Informational
05/16/2022
KAW Valley was on site laying down more geogrid and AB3 for the subgrade until it starts raining. RP 3-21-22
Misc
Informational
05/16/2022
KAW Valley is still working on the subgrade for the curb line and parking lot. RP 4-8-22
Misc
Informational
05/16/2022
Stopped by and talked with Rick from JE Dunn about the parking lot. Planning on doing another proof roll tomorrow, weather permitting. Also talked with Epic Concrete about the curbing around the parking lot perimeter. RP 4-14-22
Misc
Informational
05/16/2022
Met with Rick from JE Dunn and Mike with Epic concrete about sidewalk design and ADA requirements. Spoke with Sue about plans, they had previous approval for sidewalk. They will have ADA access in front of building and at handicap parking areas only. Other sidewalks are private and not required to conform. 4/6/22 ES
Misc
Informational
05/16/2022
Epic concrete working on sidewalks. Asphalt was completed last week. 5/16/22 ES No outside utility work being performed with rain. 5/31/22 ES
Pavement-Aggregate Base Passed 06/07/2022
Misc
Informational
05/10/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. RP 3-2-22
Misc
Informational
05/10/2022
KAW Valley started rolling out geogrid and covering it with 6 inches of AB3 until the ran out of material. RP 3-3-22
Misc
Informational
05/10/2022
KAW Valley still laying down geogrid and AB3. RP 3-4-22
Misc
Informational
05/10/2022
KAW Valley was on site laying down more geogrid and AB3 for the subgrade until it starts raining. RP 3-21-22
Misc
Informational
05/10/2022
Proof roll for the curb line failed, So KAW Valley reworked those areas continued adding more rock to the subgrade. RP 3-28-22
Misc
Informational
05/10/2022
KAW Valley is still reworking on the subgrade for the curb line and parking lot, where it failed the proof roll. RP 4-8-22
Misc
Informational
05/10/2022
Spoke with Mike with Epic concrete. They are going to be pouring the dumpster pad and drive area coming out from it tomorrow with 8” thick KCMMB concrete. 4/25/22 ES
Misc
Informational
05/10/2022
Performed proof roll for parking lot with Kaw Valley and Rick from JE Dunn. All areas of parking lot were solid and ready for final grading/paving. 5/9/22 ES Pavement installed after aggregate proof roll passed. Closing inspection as passed for final. 6/7/22 ES
Pavement-Curb Construction Passed 06/07/2022
Misc
Informational
05/10/2022
Epic Concrete started forming and pouring curbing. RP 4-18-22
Misc
Informational
05/10/2022
Epic is still forming and pouring curbing for the parking lot. Verified that they are using 4K KCMMB mix. RP 4-19-22
Misc
Informational
05/10/2022
Epic still forming and pouring curbing for the parking lot. Discussed the sidewalk along McClendon and running through the parking lot. JE Dunn is going to follow up with the engineers. RP 4-21-22
Misc
Informational
05/10/2022
Mike’s, Epic concrete crew continued working on forming up curbing and working on sidewalk crosswalks. 5/9/22 ES All sidewalk and walking areas are poured and completed. 6/7/22 ES
ESC - (Vegetation/Ground Cover) Partial 06/07/2022
Misc
Corrective Action Required
06/07/2022
Landscape company on site delivering and planting plants and trees. Still no seeding/sod down. 6/7/22 ES
Erosion Control Inspection Residential Partial 2/21/2022 06/07/2022
Misc
Informational
02/16/2022
Erosion controls are in place. No erosion issues were spotted. RP 2-16-22
Misc
Informational
06/07/2022
Landscapers on site planting trees and bushes. No current erosion control items on site. Will monitor as landscapers progress. 6/7/22 ES
Pavement-Surface Passed 06/07/2022
Misc
Informational
05/19/2022
Hanrahan put down 1,009 tons of type 1-01 base asphalt. 5/11/22 ES
Misc
Informational
05/19/2022
5-12-22 AN crew was putting down surface and it is looking good. Asphalt temp going into the paver was 280deg
Misc
Informational
05/19/2022
Asphalt surface was all laid and striping has been completed. 5/16/22 ES Asphalt surfaces and striping still in good shape. 6/7/22 ES
Sidewalk Inspection Passed 06/07/2022
Misc
Informational
05/19/2022
Met with Mike from Epic concrete on-site. Went over the speed check/raised walk going through parking lot. Inspected this area and it was framed up with aggregate in and compacted. 4/25/22 ES
Misc
Informational
05/19/2022
Spoke with Mike at Epic concrete, they poured upper portion of sidewalk and framed up curbing and other areas. 5/4/22 ES
Misc
Informational
05/19/2022
Mike’s crew poured more sections of sidewalk today along north side of building and in front of building. 5/9/22 ES
Misc
Informational
05/19/2022
Mike’s crew with Epic was working on sidewalks leading into parking lot area. 5/16/22 ES Mike’s crew continued working on sidewalks on side and front parking lot areas of building. 5/17/22 ES Mike’s crew continued working on sidewalks in middle of parking area and front of building. 5/18/22 ES All sidewalk and path areas are completed and meet LS spec. 6/7/22 ES
Water Line - Construction Inspection Passed 06/07/2022
Misc
Informational
06/07/2022
Rodriquez Mechanical installed, new pipe for hydrant behind building and also reinstalled connection into building. Line was inspected and hydrostatic tested by RP previously and passed. 6/7/22 ES
Water Line - Hydrostatic Test Passed 06/07/2022
Misc
Informational
06/07/2022
Rodriquez Mechanical installed, new pipe for hydrant behind building and also reinstalled connection into building. Line was inspected and hydrostatic tested by RP previously and passed. 6/7/22 ES
Water Line - Fire Hydrant Passed 06/07/2022
Misc
Informational
11/04/2021
Rodriguez Mechanical relocated old fire hydrant to the new location. Thrust blocks were poured on 45 bend and fire hydrant. Asked him to add tracer wire for the new section along with utility marking tape. Also informed him on his choices for the valve riser. RP 11-4-21
Misc
Informational
06/07/2022
Fire hydrant was installed and all inspections completed previously by RP. 6/7/22 ES
Water Line - Coliform Test 1 Passed 06/07/2022
Misc
Informational
06/07/2022
Testing not required due to this being just a fire line and beyond the back flow and a small addition to move fire hydrant. 6/7/22 ES
Water Line - Coliform Test 2 Passed 06/07/2022
Misc
Informational
06/07/2022
Testing not required due to this being just a fire line and beyond the back flow and a small addition to move fire hydrant. 6/7/22 ES
Occupancy Inspection - Engineering Temporary C of O 6/7/2022 6/7/2022 06/07/2022
Misc
Corrective Action Required
06/07/2022
OK with TCO, with areas below needing addressed: 1. Vegetation needs fully established(landscapers working currently). 2. Erosion control measures should be maintained until vegetation is established. 3. Storm inlet lid on south side of building will need cleared off once vegetation is established and line might need cleaned depending on sediment build up. 6/7/22 ES
Occupancy Inspection - Codes Commercial Temporary C of O 6/7/2022 6/7/2022 06/07/2022
Miscellaneous Correction
Corrective Action Required
05/06/2022
Codes complete, see corrections from other departments
Occupancy Inspection - Water Utilities Passed 10/27/2022
Corrective Action Required
10/26/2022
Underground Electrical Inspection - Commercial Passed 10/27/2022 10/27/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/30/2021
- underground conduit (3) light pole bases front of bldg, IT conduit NE corner of bldg to quazite box at curb front of bldg - - 12/30/21 (1) LIGHT POLE BASE NORTH SIDE OF BLDG TO EXISTING POLE BASE SOUTH (REAR OF BLDG -
Miscellaneous Inspection Passed 10/27/2022 10/27/2022
Miscellaneous Correction
Resolved
10/27/2022
Occupancy Inspection - Engineering Failed 10/27/2022
Misc
Corrective Action Required
06/07/2022
OK with TCO, with areas below needing addressed: 1. Vegetation needs fully established(landscapers working currently). 2. Erosion control measures should be maintained until vegetation is established. 3. Storm inlet lid on south side of building will need cleared off once vegetation is established and line might need cleaned depending on sediment build up. 6/7/22 ES None of the above mentioned items have been completed. 10/27/22 ES
Occupancy Inspection - Planning Passed 6/7/2022 10/28/2022
Occupancy Inspection - Fire Passed 6/7/2022 11/01/2022
ESC - (Vegetation/Ground Cover) Partial 11/08/2022
Misc
Corrective Action Required
06/07/2022
Landscape company on site delivering and planting plants and trees. Still no seeding/sod down. 6/7/22 ES Vegetation is still lacking with areas behind and around building having sparse to no vegetation. 11/3/22 ES
Erosion Control Inspection Residential Partial 11/08/2022
Misc
Informational
06/07/2022
Erosion controls are in place. No erosion issues were spotted. RP 2-16-22
Misc
Informational
06/07/2022
Landscapers on site planting trees and bushes. No current erosion control items on site. Will monitor as landscapers progress. 6/7/22 ES Still have silt wattle over drain on south side of building and no significant vegetation on that side of building. 11/3/22 ES
Water Service Inspection Partial 11/08/2022
Misc
Informational
11/08/2022
WU has signed off on meter pits and meters. 11/3/22 ES
Water Service Inspection Passed 12/01/2022
Misc
Informational
11/08/2022
WU has signed off on meter pits and meters. 11/3/22 ES.
Site Visit Complete 12/01/2022
Misc
Informational
05/31/2022
They are ripping out the old parking lot and hauling it away. They dug a trench and catch basin for the center section, but need more erosion control on the south end. RP 8-20-21
Misc
Informational
05/31/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. KAW Valley is removing more asphalt on the north side of the building. RP 8-24-21
Misc
Informational
05/31/2022
KAW Valley removed the rest of the asphalt today. RP 8-25-21
Misc
Informational
05/31/2022
KAW Valley has removed the trees and light poles. Current erosion issues have been corrected. RP 8-26-21
Misc
Informational
05/31/2022
KAW Valley stripped all vegetation in preparation for Rodriguez to start storm work. RP 8-27-21
Misc
Informational
05/31/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. They have started demolition of the north corner of the building. RP 8-30-21
Misc
Informational
05/31/2022
KAW Valley was removing construction debris before they were rained out. One area of silt fencing was breached. RP 8-31-21
Misc
Informational
05/31/2022
Site was still too wet to work this morning. RP 9-1-21
Misc
Informational
05/31/2022
KAW Valley is still working on demoing the building. Talked to them about needing additional erosion controls to prevent breaches. RP 9-2-21
Misc
Informational
05/31/2022
Rock checks did their job!!! No erosion issues to report. RP 9-3-21
Misc
Informational
05/31/2022
No erosion issues. KAW Valley still demoing the outside of the building. RP 9-7-21
Misc
Informational
05/31/2022
Met Brent from Rodriguez, talked about the storm line and erosion issues. RP 9-8-21
Misc
Informational
05/31/2022
Have Sue Pyles come on site to discuss grading and storm changes. She explained that everything looked correct, but will re-evaluate when it’s time for final grading. RP 10-20-21
Misc
Informational
05/31/2022
Still waiting on a resolution for the parking lot subgrade. It is now in the hands of the City Engineer and Planning. RP 2-1-22
Misc
Informational
05/31/2022
Met with Rick from JE Dunn to go over the alternative waiver they got for the parking lot. After talking about the requirements that are needed with the waiver, Rick called another person with JE Dunn. Sounds like they decided to revert back to the original installation of the parking lot. RP 2-11-22
Misc
Informational
05/31/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
05/31/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
05/31/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
05/31/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
05/31/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Corrective Action Required
05/31/2022
Stopped by and talked with Rick from JE Dunn and Kenny from KAW Valley about the parking lot and curbing. Also informed Rick that his subcontractor hooked up his sanitary line without an inspection. RP 3-1-22
Misc
Informational
05/31/2022
Geogrid Tenax 302 was delivered on site. KAW Valley is preparing the subgrade before laying the stabilization material. Rick also informed me that Rodriguez Mechanical is looking for pictures concerning the sanitary connections. RP 3-2-22
Misc
Informational
05/31/2022
Talked with Rick about parking lot. Subcontractor isn’t available tomorrow, so they are planning on curbing next Tuesday depending on the weather this weekend. RP 3-3-22
Misc
Informational
05/31/2022
No work being done on site today. RP 3-10-22
Misc
Informational
05/31/2022
No exterior work being done on site today. Talked with Rick, they hope the subgrade will dry out enough to get some more rock down before the next rain event (Thursday?). RP 3-14-22
Misc
Informational
05/31/2022
KAW Valley was on site laying down more geogrid and AB3 for the subgrade until it starts raining. RP 3-21-22
Misc
Informational
05/31/2022
KAW Valley is still working on the subgrade for the curb line and parking lot. RP 4-8-22
Misc
Informational
05/31/2022
Stopped by and talked with Rick from JE Dunn about the parking lot. Planning on doing another proof roll tomorrow, weather permitting. Also talked with Epic Concrete about the curbing around the parking lot perimeter. RP 4-14-22
Misc
Informational
05/31/2022
Met with Rick from JE Dunn and Mike with Epic concrete about sidewalk design and ADA requirements. Spoke with Sue about plans, they had previous approval for sidewalk. They will have ADA access in front of building and at handicap parking areas only. Other sidewalks are private and not required to conform. 4/6/22 ES
Misc
Informational
05/31/2022
Epic concrete working on sidewalks. Asphalt was completed last week. 5/16/22 ES No outside utility work being performed with rain. 5/31/22 ES.
Erosion Control Inspection Passed 12/01/2022
Misc
Corrective Action Required
03/24/2022
Trench and catch basin will collect some of the runoff, but not enough erosion control in place to catch the south runoff. Talked with Rick Meyer about concerns and possible solutions. RP 8-20-21
Misc
Corrective Action Required
03/24/2022
Talked with Rick about the breach that occurred over the weekend at the previous troubled spot. We also talked about another potential bad spot where they are removing more asphalt. Rick is going to get with KAW Valley to see about making corrections to the erosion plan. RP 8-24-21
Misc
Informational
03/24/2022
Controls are in place and they are going to add straw wattles in front of the drain pipe. RP 8-27-21
Misc
Informational
03/24/2022
Controls are in place. They added the straw wattle to the entrance of the storm pipe and added rock to the construction entrance. RP 8-30-21
Misc
Corrective Action Required
03/24/2022
Silt breached the silt fencing again. Notified Rick and will tell KAW Valley also. RP 8-31-21
Misc
Informational
03/24/2022
Talked with KAW Valley about erosion issues. They are going to add rock checks through the trench and trouble spots. RP 9-2-21
Misc
Informational
03/24/2022
Rock checks did their job. KAW Valley to readjust straw wattles in front of storm pipe. RP 9-7-21
Misc
Corrective Action Required
03/24/2022
Mud is on McClendon and Oldham. Notified Rick from JE Dunn about the mess. He thinks it was his dumpster driver, but will get his foreman to clean it up. RP 1-19-22
Misc
Informational
03/24/2022
Another rain day, still no erosion issues to report. RP 3-24-22 12-1-22 AN. No erosion control issues. Site vegetated
ESC - (Vegetation/Ground Cover) Passed 12/01/2022
Misc
Corrective Action Required
11/08/2022
Landscape company on site delivering and planting plants and trees. Still no seeding/sod down. 6/7/22 ES Vegetation is still lacking with areas behind and around building having sparse to no vegetation. 11/3/22 ES 12-1-22 AN site is vegetated
Erosion Control Inspection Residential Passed 12/08/2022
Misc
Informational
11/08/2022
Erosion controls are in place. No erosion issues were spotted. RP 2-16-22
Misc
Informational
11/08/2022
Landscapers on site planting trees and bushes. No current erosion control items on site. Will monitor as landscapers progress. 6/7/22 ES Still have silt wattle over drain on south side of building and no significant vegetation on that side of building. 11/3/22 ES 12-8-22 AN no more erosion control issues
Occupancy Inspection - Engineering Passed 12/08/2022
Misc
Corrective Action Required
10/27/2022
OK with TCO, with areas below needing addressed: 1. Vegetation needs fully established(landscapers working currently). 2. Erosion control measures should be maintained until vegetation is established. 3. Storm inlet lid on south side of building will need cleared off once vegetation is established and line might need cleaned depending on sediment build up. 6/7/22 ES None of the above mentioned items have been completed. 10/27/22 ES 12-8-22 AN all items have been competed
Occupancy Inspection - Engineering Passed 12/08/2022
Misc
Corrective Action Required
10/27/2022
OK with TCO, with areas below needing addressed: 1. Vegetation needs fully established(landscapers working currently). 2. Erosion control measures should be maintained until vegetation is established. 3. Storm inlet lid on south side of building will need cleared off once vegetation is established and line might need cleaned depending on sediment build up. 6/7/22 ES None of the above mentioned items have been completed. 10/27/22 ES 12-8-22 AN all items have been completed
Occupancy Inspection - Codes Commercial Full C of O 12/08/2022
Miscellaneous Correction
Resolved
12/08/2022
Codes complete, see corrections from other departments
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home