Permit Application Status

PRCOM20151437


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20151437
Building Permit - Commercial
Final Completion
GREEN MILL II LLC
NEW OTHER (COMMERCIAL)
FREE-STANDING CANOPY AS ACCESSORY TO EXISTING CONVENIENCE STORE
06/25/2015
10/27/2015
02/17/2016
09/06/2016
Locations
Contacts
TEMP-STOP LLC, Address:331 NW CAPITAL DR, Phone:(816) 554-3352  
FATBOY ELECTRIC INC, Address:P O BOX 300198, Phone:(816) 861-6600  
CL ARCHITECTURE (CRAIG LUEBBERT), Address:396 SW WINTERGARDEN, Phone:(816) 536-3472  
GREEN MILL II LLC, Address:331 NW CAPITAL DR  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 08/21/2015 10/13/2015
Codes Admin
LC - General Contractor
Resolved
10/13/2015

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor.
LC - MEP Subs
Resolved
08/24/2015

No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Excerpt from Sec. 7-130, Lees Summit Code of Ordinances. Action required: MEP subcontractors are required to be listed on permit. Provide company names of MEP contractors.
Final Development Plan Review Approved 10/22/2015 10/13/2015
Codes Admin
Fire Plan Review Approved with Conditions 08/28/2015 08/27/2015
Joe Dir
Misc
Corrective Action Required
08/21/2015

Provide a copy of the approval letter from the Missouri Department of Natural Resource for the installation. Letter Received
Misc
Corrective Action Required
08/21/2015

Provide a product piping, vent and vapor recovery system plan. Show the location and a detail for the vent stack. Vent and vapor recovery plan received Provide specifications for the tank. Specs on tank received
Misc
Corrective Action Required
08/21/2015

Provide a Hazardous Materials Permit Application for review and approval. It is the applicants responsibility to complete the Hazardous Materials Permit application and provide SDS's , tank specifications, appurtenance specifications, and a site plan. An application may be obtained from the fire department. Permit application needs to be filled out and returned submitted for approval.
Building Plan Review Approved with Conditions 08/28/2015 08/24/2015
Joe Frogge
Gen - Submittal documents 7-137
Resolved
08/21/2015

Lee's Summit Code Of Ordinances 7-137. - Submittal Documents. Construction documents, special inspection and structural observation programs, and other data shall be submitted in two (2) or more sets with each application for a permit. A registered design professional licensed by the State of Missouri shall prepare the construction documents. Where special conditions exist, the Building Official is authorized to require additional construction documents to be prepared by a registered design professional licensed by the State of Missouri. Actions required: - - Provide complete electrical design that includes, but is not limited to, Class 1 Div 1 information. 7/30/15 - scope document provided was a request to electricians, not an actual scope. 8/21/15 - RECEIVED
Final Development Plan
Resolved
10/01/2015

The building permit for this project can not be issued until the Codes Administration Department has received the approved Final Development Plan from the Planning and Development Department. Action required: Comment is informational. Permit will not be released until FDP has been approved and processed.
Licensed Contractors Rejected 07/27/2015 07/30/2015
Joe Frogge
LC - General Contractor
Corrective Action Required
07/27/2015

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor.
LC - MEP Subs
Corrective Action Required
07/27/2015

No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Excerpt from Sec. 7-130, Lees Summit Code of Ordinances. Action required: MEP subcontractors are required to be listed on permit. Provide company names of MEP contractors.
Building Plan Review Rejected 08/03/2015 07/30/2015
Joe Frogge
Gen - Submittal documents 7-137
Corrective Action Required
07/27/2015

Lee's Summit Code Of Ordinances 7-137. - Submittal Documents. Construction documents, special inspection and structural observation programs, and other data shall be submitted in two (2) or more sets with each application for a permit. A registered design professional licensed by the State of Missouri shall prepare the construction documents. Where special conditions exist, the Building Official is authorized to require additional construction documents to be prepared by a registered design professional licensed by the State of Missouri. Actions required: - - Provide complete electrical design that includes, but is not limited to, Class 1 Div 1 information. 7/30/15 - scope document provided was a request to electricians, not an actual scope.
Final Development Plan
Corrective Action Required
07/27/2015

The building permit for this project can not be issued until the Codes Administration Department has received the approved Final Development Plan from the Planning and Development Department. Action required: Comment is informational. Permit will not be released until FDP has been approved and processed.
Fire Plan Review Rejected 08/03/2015 07/28/2015
Jim Eden
Misc
Corrective Action Required
07/27/2015

Provide a copy of the approval letter from the Missouri Department of Natural Resource for the installation.
Misc
Resolved
07/28/2015

2303.2 Emergency disconnect switches. An approved, clearly identified and readily accessible emergency disconnect switch shall be provided at an approved location to stop the transfer of fuel to the fuel dispensers in the event of a fuel spill or other emergency. An emergency disconnect switch for exterior fuel dispensers shall be located within 100 feet (30 480 mm) of, but not less than 20 feet (6096 mm) from, the fuel dispensers. For interior fuel-dispensing operations, the emergency disconnect switch shall be installed at an approved location. Such devices shall be distinctly labeled as: EMERGENCY FUEL SHUTOFF. Signs shall be provided in approved locations. Show the location of the shut off switch.
Misc
Resolved
07/28/2015

2304.2.4 Obstructions to view. Dispensing devices shall be in clear view of the attendant at all times. Obstructions shall not be placed between the dispensing area and the attendant. 2304.2.5 Communications. The attendant shall be able to communicate with persons in the dispensing area at all times. An approved method of communicating with the fire department shall be provided for the attendant. Provide a camera and voice communication.
Misc
Resolved
07/28/2015

2303.1 Location of dispensing devices. Dispensing devices shall be located as follows: 1. Ten feet (3048 mm) or more from lot lines. 2. Ten feet (3048 mm) or more from buildings having combustible exterior wall surfaces or buildings having noncombustible exterior wall surfaces that are not part of a 1-hour fire-resistance-rated assembly or buildings having combustible overhangs. Exception: Canopies constructed in accordance with the International Building Code providing weather protection for the fuel islands. 3. Such that all portions of the vehicle being fueled will be on the premises of the motor fuel-dispensing facility. 4. Such that the nozzle, when the hose is fully extended, will not reach within 5 feet (1524 mm) of building openings. 5. Twenty feet (6096 mm) or more from fixed sources of ignition. Action required: Item #4 will be verified at inspection.
Misc
Resolved
07/28/2015

Are you installing one tank or two?
Misc
Corrective Action Required
07/27/2015

Provide a product piping, vent and vapor recovery system plan. Show the location and a detail for the vent stack. Provide specifications for the tank.
Misc
Corrective Action Required
07/27/2015

Provide a Hazardous Materials Permit Application for review and approval. It is the applicants responsibility to complete the Hazardous Materials Permit application and provide SDS's , tank specifications, appurtenance specifications, and a site plan. An application may be obtained from the fire department.
Misc
Resolved
07/28/2015

2305.5 Fire extinguishers. Approved portable fire extinguishers complying with Section 906 with a minimum rating of 2-A:20-B:C shall be provided and located such that an extinguisher is not more than 75 feet (23 860 mm) from pumps, dispensers or storage tank fill-pipe openings. Show location.
Misc
Resolved
07/28/2015

The fire department shall witness the testing of the UST(s), piping, and shut offs. Call (816) 969-1300 to schedule tests.
Fire Plan Review Rejected 07/10/2015 07/09/2015
Jim Eden
Misc
Corrective Action Required
07/09/2015

Provide a copy of the approval letter from the Missouri Department of Natural Resource for the installation.
Misc
Corrective Action Required
07/09/2015

2303.2 Emergency disconnect switches. An approved, clearly identified and readily accessible emergency disconnect switch shall be provided at an approved location to stop the transfer of fuel to the fuel dispensers in the event of a fuel spill or other emergency. An emergency disconnect switch for exterior fuel dispensers shall be located within 100 feet (30 480 mm) of, but not less than 20 feet (6096 mm) from, the fuel dispensers. For interior fuel-dispensing operations, the emergency disconnect switch shall be installed at an approved location. Such devices shall be distinctly labeled as: EMERGENCY FUEL SHUTOFF. Signs shall be provided in approved locations. Show the location of the shut off switch.
Misc
Corrective Action Required
07/09/2015

2304.2.4 Obstructions to view. Dispensing devices shall be in clear view of the attendant at all times. Obstructions shall not be placed between the dispensing area and the attendant. 2304.2.5 Communications. The attendant shall be able to communicate with persons in the dispensing area at all times. An approved method of communicating with the fire department shall be provided for the attendant. Provide a camera and voice communication.
Misc
Corrective Action Required
07/09/2015

2303.1 Location of dispensing devices. Dispensing devices shall be located as follows: 1. Ten feet (3048 mm) or more from lot lines. 2. Ten feet (3048 mm) or more from buildings having combustible exterior wall surfaces or buildings having noncombustible exterior wall surfaces that are not part of a 1-hour fire-resistance-rated assembly or buildings having combustible overhangs. Exception: Canopies constructed in accordance with the International Building Code providing weather protection for the fuel islands. 3. Such that all portions of the vehicle being fueled will be on the premises of the motor fuel-dispensing facility. 4. Such that the nozzle, when the hose is fully extended, will not reach within 5 feet (1524 mm) of building openings. 5. Twenty feet (6096 mm) or more from fixed sources of ignition. Action required: Item #4 will be verified at inspection.
Misc
Corrective Action Required
07/09/2015

Are you installing one tank or two?
Misc
Corrective Action Required
07/09/2015

Provide a product piping, vent and vapor recovery system plan. Show the location of the vent stack.
Misc
Corrective Action Required
07/09/2015

Provide a Hazardous Materials Permit Application for review and approval.
Misc
Corrective Action Required
07/09/2015

2305.5 Fire extinguishers. Approved portable fire extinguishers complying with Section 906 with a minimum rating of 2-A:20-B:C shall be provided and located such that an extinguisher is not more than 75 feet (23 860 mm) from pumps, dispensers or storage tank fill-pipe openings. Show location.
Misc
Corrective Action Required
07/09/2015

The fire department shall witness the testing of the UST(s), piping, and shut offs. Call (816) 969-1300 to schedule tests.
Building Plan Review Rejected 07/10/2015 07/02/2015
Joe Frogge
Gen - Submittal documents 7-137
Corrective Action Required
07/02/2015

Lee's Summit Code Of Ordinances 7-137. - Submittal Documents. Construction documents, special inspection and structural observation programs, and other data shall be submitted in two (2) or more sets with each application for a permit. A registered design professional licensed by the State of Missouri shall prepare the construction documents. Where special conditions exist, the Building Official is authorized to require additional construction documents to be prepared by a registered design professional licensed by the State of Missouri. Actions required: - - Provide complete electrical design that includes, but is not limited to, Class 1 Div 1 information.
Final Development Plan
Corrective Action Required
07/02/2015

The building permit for this project can not be issued until the Codes Administration Department has received the approved Final Development Plan from the Planning and Development Department. Action required: Comment is informational. Permit will not be released until FDP has been approved and processed.
Licensed Contractors Rejected 07/10/2015 07/02/2015
Joe Frogge
LC - General Contractor
Corrective Action Required
07/02/2015

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor.
LC - MEP Subs
Corrective Action Required
07/02/2015

No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Excerpt from Sec. 7-130, Lees Summit Code of Ordinances. Action required: MEP subcontractors are required to be listed on permit. Provide company names of MEP contractors.
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for New Other $90.16 $90.16 Paid 10/27/2015
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underground Plumbing Inspection - Commercial Partial 3/4/2016 03/04/2016
Storage Tanks Inspection Passed 3/8/2016 03/08/2016
Underground Plumbing Inspection - Commercial Partial 3/8/2016 03/08/2016
Piers/Caissons Inspection - Commercial Passed 3/9/2016 (1:00) 3/9/2016 03/09/2016
Underground Plumbing Inspection - Commercial Partial 3/11/2016 03/11/2016
Underground Plumbing Inspection - Commercial Partial 3/15/2016 03/15/2016
Underground Plumbing Inspection - Commercial Partial 3/16/2016 03/16/2016
Underground Electrical Inspection - Commercial Partial 3/17/2016 03/17/2016
Underground Plumbing Inspection - Commercial Partial 3/23/2016 03/23/2016
Underground Plumbing Inspection - Commercial Partial 3/24/2016 03/24/2016
Underground Plumbing Inspection - Commercial Partial 3/25/2016 03/25/2016
Underground Plumbing Inspection - Commercial Passed 3/25/2016 03/26/2016
Underground Electrical Inspection - Commercial Passed 3/25/2016 03/26/2016
Investigation Inspection Complete 5/11/2016 07/06/2016
Final Inspection - Commercial Partial 7/7/2016 07/07/2016
Misc
Partial Correction
07/07/2016
CANOPY FRAME ERECTED. WIP ON CANOPY SOFFIT/FACIA..
Final Inspection - Commercial Partial 7/8/2016 07/08/2016
Misc
Partial Correction
07/07/2016
CANOPY FRAME ERECTED. WIP ON CANOPY FACIA
Final Inspection - Commercial Partial 7/11/2016 07/11/2016
Misc
Partial Correction
07/08/2016
CANOPY FRAME ERECTED. WIP ON CANOPY FACIA
Final Inspection - Commercial Passed 9/2/2016 9/2/2016 09/02/2016
Misc
Resolved
09/02/2016
CANOPY FRAME ERECTED. WIP ON CANOPY FACIA
Occupancy Inspection - Planning Passed 09/02/2016
Documents & Images
Date Uploaded File Type Document Name
07/10/2015 Letter Codes P/R Corrections Document
07/30/2015 Letter Codes P/R Corrections Document
08/27/2015 Letter Fire Building Plan Review
10/27/2015 Receipt Receipt for transaction: 2015-005933
10/27/2015 Letter Codes Plan Review Conditions
10/27/2015 Letter Codes Building Permit
03/09/2016 Letter Inspection Summary
09/02/2016 Letter Inspection Summary
09/13/2016 Engineer Report/Study DOC091316
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide: