Permit Application Status

PRCOM20111353


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20111353
Building Permit - Commercial
Certificate of Occupancy
LANGSFORD DEV INC
CHANGE OF TENANT
TENANT FINISH
05/06/2011
06/06/2011
11/13/2011
09/07/2011
Locations
Contacts
INTEGRAL CONSTRUCTION SERVICES, INC, Address:303 SW MARKET ST, Phone:(816) 246-5655  
GREEN FIELD ENERGY GROUP INC, Address:5 SW 4TH ST, Phone:(816) 524-5616  
CL HOWERTON ENTERPRISES LLC, Address:224 NW AA HWY, Phone:(816) 237-6338  
LANGSFORD DEV INC, Address:616 SW 3RD ST  
THE HOLLIS & MILLER GROUP, Address:1828 WALNUT ST STE 922, Phone:(816) 525-5600  
ALLEN'S ELECTRIC & HVAC, Address:132 SOUTH HIGH, Phone:(816) 935-8684  
Reviews
Review Type Outcome Est. Completion Date Completed
Internal Plan Review (Res) Approved 06/10/2011 06/06/2011
Mike Weisenborn
Building Plan Review Approved 06/03/2011 06/06/2011
Mike Weisenborn
Misc
Resolved
06/02/2011

Adequate mechanical, electrical and plumbing plans have not been provided. Action required - Provide complete plans for the plumbing, electrical and mechanical work which have been sealed by an engineer. Mike Weisenborn June 02, 2011 - Plans have been submitted.
Misc
Resolved
06/02/2011

The plans do not provide complete accessiblitlity details for the restrooms. Action required - Provide details for all required grab bars, clearances and fixture installation. Mike Weisenborn June 02, 2011 - Additional information provided.
Bldg - Accessibility - Point of sale and service counters 1109.12.3
Resolved
06/02/2011

2006 IBC 1109.12.3 - Point of sale and service counters. Where counters are provided for sales or distribution of goods or services, at least one of each type provided shall be accessible. Where such counters are dispersed throughout the building or facility, accessible counters shall also be dispersed. Action required - Provide an accessible sales and service counter. Mike Weisenborn June 02, 2011 - Per resubmittal.
Misc
Resolved
06/02/2011

The plans indicate that pedistal sinks are to be installed in the restrooms but details showing how they meet accessiblity requirements are not provided. Action required - Provide additional information. Mike Weisenborn June 02, 2011 - The pedestal sinks have been removed.
Misc
Resolved
06/02/2011

Information on the fireplace being installed have not been provided. Action required - Provide manufactures specifications and installation requirements. Mike Weisenborn June 02, 2011 - Per the resubmittal letter, the fireplace is for visual effect only. No heat or flame.
Bldg - Doors - Door hardware
Resolved
06/02/2011

2006 IBC 1008.1.8.1 - Hardware. Door handles, pulls, latches, locks and other operating devices on doors required to be accessible by Chapter 11 shall not require tight grasping, tight pinching or twisting of the wrist to operate. Action required - Provide information on the door hardware to be installed. Mike Weisenborn June 02, 2011 - Additional information provided on the plans.
Bldg - Glazing - Human impact loads
Resolved
06/02/2011

2006 IBC 2406.1 - Human impact loads. Individual glazed areas, including glass mirrors, in hazardous locations as defined in Section 2406.3 shall comply with Sections 2406.1 through 2406.1.4. Action required - Indicate location of required safety glazing. Mike Weisenborn June 02, 2011 - Additional information provided on the plans.
Misc
Resolved
06/02/2011

I am unable to locate details on the wall constuction. Action required - Provide additional information. Mike Weisenborn June 02, 2011 - Additional information provided on the plans.
Plumb - Required public toilet facilities
Corrective Action Required
06/02/2011

2006 IPC 403.4 - Required public toilet facilities. Customers, patrons and visitors shall be provided with public toilet facilities in structures and tenant spaces intended for public utilization. The accessible route to public facilities shall not pass through kitchens, storage rooms, closets or similar spaces. Employees shall be provided with toilet facilities in all occupancies. Employee toilet facilities shall be either separate or combined employee and public toilet facilities. Mike Weisenborn June 02, 2011 - This comment is for information purposes.
Plumb - Separate facilities
Corrective Action Required
06/02/2011

2006 IPC 403.2 - Separate facilities. Where plumbing fixtures are required, separate facilities shall be provided for each sex. (See code for possible exceptions.) Mike Weisenborn June 02, 2011 - Signage whall be provided. This will be verified on inspection.
Bldg - Egress through intervening spaces
Resolved
06/06/2011

2006 IBC 1014.2 Egress through intervening spaces. Egress trough intervening spaces shall comply with this section. 1. Egress from a room or spaces shall not pass through adjoining or intervening rooms or areas, except where such adjoining rooms or areas are accessory to the area served, are not a high-hazard occupancy and provide a discernible path of egress travel to an exit. (See possible exceptions.) 2. Egress shall not pass through kitchens, storage rooms, closets or spaces used for similar purposes. (See possible exceptions.) 3. An exit access shall not pass through a room tha can be locked to prevent egress. 4. Means of egress from dwelling units or sleeping areas shall not lead through other sleeping areas, toilet rooms or bathrooms. Mike Weisenborn June 02, 2011 - The revised electrical plans show an egress path through the office/storage area. If this is to be used as a means of egress than the door can not be locked at any time the space is occupied and a clear path 36 inches wide shall be maintained through the space. Or the exit sign can be removed as only one means of egress is required from the meeting room. Make needed corrections. Mike Weisenborn June 06, 2011 - Provided a letter removing the exit sign.
Bldg - Posting of occupant load
Corrective Action Required
06/02/2011

2006 IBC 1004.3 - Posting of occupant load. Every room or space that is an assembly occupancy shall have the occupant load of the room or space posted in a conspicuous place, near the main exit or exit access doorway from the room or space. Posted signs shall be of an approved legible permanent design and shall be maintained by the owner or authorized agent. Action required - The occupant load of 20, as indicate on the plans, shall be posted in Meeting Room 103. This will be verified on inspection.
Fire Plan Review Approved 06/03/2011 06/06/2011
Mike Weisenborn
Address numbers required
Corrective Action Required
06/02/2011

2006 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). ACTION REQUIRED: Address all doore leading into the occupancy as the same address, verified at inspection
Portable fire extinguishers - general
Corrective Action Required
06/02/2011

2006 IFC 906.2 - General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10. ACTION REQUIRED: Provide a minimum of (1) 2A10B:C extinguisher, verified at inspection
Internal Plan Review (Res) Rejected 05/17/2011 05/17/2011
Mike Weisenborn
Building Plan Review Rejected 05/17/2011 05/17/2011
Mike Weisenborn
Misc
Corrective Action Required
05/17/2011

Adequate mechanical, electrical and plumbing plans have not been provided. Action required - Provide complete plans for the plumbing, electrical and mechanical work which have been sealed by an engineer.
Misc
Corrective Action Required
05/17/2011

The plans do not provide complete accessiblitlity details for the restrooms. Action required - Provide details for all required grab bars, clearances and fixture installation.
Bldg - Accessibility - Point of sale and service counters 1109.12.3
Corrective Action Required
05/17/2011

2006 IBC 1109.12.3 - Point of sale and service counters. Where counters are provided for sales or distribution of goods or services, at least one of each type provided shall be accessible. Where such counters are dispersed throughout the building or facility, accessible counters shall also be dispersed. Action required - Provide an accessible sales and service counter.
Misc
Corrective Action Required
05/17/2011

The plans indicate that pedistal sinks are to be installed in the restrooms but details showing how they meet accessiblity requirements are not provided. Action required - Provide additional information.
Misc
Corrective Action Required
05/17/2011

Information on the fireplace being installed have not been provided. Action required - Provide manufactures specifications and installation requirements.
Bldg - Doors - Door hardware
Corrective Action Required
05/17/2011

2006 IBC 1008.1.8.1 - Hardware. Door handles, pulls, latches, locks and other operating devices on doors required to be accessible by Chapter 11 shall not require tight grasping, tight pinching or twisting of the wrist to operate. Action required - Provide information on the door hardware to be installed.
Bldg - Glazing - Human impact loads
Corrective Action Required
05/17/2011

2006 IBC 2406.1 - Human impact loads. Individual glazed areas, including glass mirrors, in hazardous locations as defined in Section 2406.3 shall comply with Sections 2406.1 through 2406.1.4. Action required - Indicate location of required safety glazing.
Misc
Corrective Action Required
05/17/2011

I am unable to locate details on the wall constuction. Action required - Provide additional information.
Zoning Review Approved 05/17/2011 05/16/2011
Chris Hughey
Fire Plan Review Approved 05/17/2011 05/12/2011
Mike Weisenborn
Address numbers required
Corrective Action Required
05/12/2011

2006 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). ACTION REQUIRED: Address all doore leading into the occupancy as the same address, verified at inspection
Portable fire extinguishers - general
Corrective Action Required
05/12/2011

2006 IFC 906.2 - General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10. ACTION REQUIRED: Provide a minimum of (1) 2A10B:C extinguisher, verified at inspection
Historical Preservation Review Approved 05/17/2011 05/09/2011
Mike Weisenborn
License Tax Codes Approved 05/17/2011 05/09/2011
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for Change of Tenant $265.53 $265.53 Paid 06/06/2011
8331507-Sewer Connection Fee $120.00 $120.00 Paid 06/06/2011
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Rough Mechanical Inspection - Commercial Failed 6/9/2011 at 12:00 AM 06/09/2011
Misc
Corrective Action Required
06/09/2011
FURNACE TO BE RELOCATED TO PROVIDE 30"W x 36" DEEP MINIMUM CLEARANCE IN FRONT OF ELECTRICAL SERVICE PANEL
Underslab Electrical Inspection - Commercial Passed 6/14/2011 6/14/2011 at 12:00 AM 06/14/2011
All Rough Inspection - Commercial Not Ready 6/21/2011 at 12:00 AM 06/21/2011
Misc
Corrective Action Required
06/21/2011
WORK IN PROGRESS ABOVE CEILING AND IN-WALL. REQUEST INSPECTION WHEN READY.
All Rough Inspection - Commercial Partial 6/23/2011 6/23/2011 at 12:00 AM 06/23/2011
Misc
Corrective Action Required
06/21/2011
WORK IN PROGRESS ABOVE CEILING. REQUEST INSPECTION WHEN READY.
All Rough Inspection - Commercial Passed 7/25/2011 (8:00 to 5:00) 7/25/2011 at 12:00 AM 07/25/2011
Misc
Resolved
07/25/2011
WORK IN PROGRESS ABOVE CEILING. REQUEST INSPECTION WHEN READY.
Miscellaneous Inspection Partial 8/22/2011 08/22/2011
Misc
Partial Correction
08/22/2011
COURTESY PRE-FINAL OBSERVATIONS
Occupancy Inspection - Codes Commercial Failed 8/26/2011 at 12:00 AM 08/26/2011
Misc
Corrective Action Required
08/26/2011
ADDRESS IDENTIFICATION OF GAS SERVICE ENTRY: WHERE TWO OR MORE SERVICES ARE GROUPED HANG ADDRESS-STAMPED MEDALLIONS ON LOAD SIDE PIPES.
Misc
Corrective Action Required
08/26/2011
ADDRESS LABELING OF ELECTRICAL SERVICE METER/DISCONNECT: APPLY PERMANENT ADDRESS STICKER
Misc
Corrective Action Required
08/26/2011
SEAL HOLES, PENETRATIONS, ANNULAR SPACES IN EXTERIOR WALL AND SOFFIT (AT PIPE, CONDUIT, CABLES…)
Misc
Corrective Action Required
08/26/2011
PIPING OF WATER HEATER TPR DISCHARGE: PIPE MATERIAL MUST BE RATE FOR HIGH TEMPERATURE; MUST PIPE DIRECTLY TO FLOOR DRAIN OR FLOOR -- NOT TO PLASTIC PAN
Misc
Corrective Action Required
08/26/2011
UNUSED OPENING AT ELECTRICAL JUNCTION BOX @ EAST MECH RM NW CORNER REQUIRES PLUG
Misc
Corrective Action Required
08/26/2011
WATER PIPE SUPPORT FLANGE BEHIND WATER HEATER @ EAST MECH RM NOT ANCHORED TO WALL
Misc
Corrective Action Required
08/26/2011
WATER UTILITES DEPARTMENT MAY REQUIRE TESTING INFO FOR BACKFLOW PREVENTION DEVICES -- CARD PROVIDED FOR BEN HASKAMP
Misc
Corrective Action Required
08/26/2011
RESOLVE FIRE DEPARTMENT ISSUES
Occupancy Inspection - Fire Temporary C of O 8/26/2011 at 12:00 AM 08/26/2011
Miscellaneous Inspection Passed 8/29/2011 at 12:00 AM 08/29/2011
Misc
Resolved
08/29/2011
COURTESY PRE-FINAL OBSERVATIONS
Rough Mechanical Inspection - Commercial Passed 8/29/2011 at 12:00 AM 08/29/2011
Misc
Resolved
08/29/2011
FURNACE TO BE RELOCATED TO PROVIDE 30"W x 36" DEEP MINIMUM CLEARANCE IN FRONT OF ELECTRICAL SERVICE PANEL
Occupancy Inspection - Codes Commercial Failed 8/29/2011 at 12:00 AM 08/31/2011
Misc
Resolved
08/29/2011
ADDRESS IDENTIFICATION OF GAS SERVICE ENTRY: WHERE TWO OR MORE SERVICES ARE GROUPED HANG ADDRESS-STAMPED MEDALLIONS ON LOAD SIDE PIPES.
Misc
Resolved
08/29/2011
ADDRESS LABELING OF ELECTRICAL SERVICE METER/DISCONNECT: APPLY PERMANENT ADDRESS STICKER
Misc
Resolved
08/29/2011
SEAL HOLES, PENETRATIONS, ANNULAR SPACES IN EXTERIOR WALL AND SOFFIT (AT PIPE, CONDUIT, CABLES…)
Misc
Corrective Action Required
08/26/2011
PIPING OF WATER HEATER TPR DISCHARGE: PIPE MATERIAL MUST BE RATE FOR HIGH TEMPERATURE; MUST PIPE DIRECTLY TO FLOOR DRAIN OR FLOOR -- NOT TO PLASTIC PAN
Misc
Corrective Action Required
08/26/2011
UNUSED OPENING AT ELECTRICAL JUNCTION BOX @ EAST MECH RM NW CORNER REQUIRES PLUG
Misc
Corrective Action Required
08/26/2011
WATER PIPE SUPPORT FLANGE BEHIND WATER HEATER @ EAST MECH RM NOT ANCHORED TO WALL
Misc
Corrective Action Required
08/26/2011
WATER UTILITES DEPARTMENT MAY REQUIRE TESTING INFO FOR BACKFLOW PREVENTION DEVICES -- CARD PROVIDED FOR BEN HASKAMP
Misc
Corrective Action Required
08/26/2011
RESOLVE FIRE DEPARTMENT ISSUES
Misc
Corrective Action Required
08/29/2011
REFRIGERANT PIPING OBSTRUCTS WATER METER BEHIND BUILDING
Occupancy Inspection - Codes Commercial Temporary C of O 8/31/2011 at 12:00 AM 08/31/2011
Misc
Resolved
08/31/2011
PIPING OF WATER HEATER TPR DISCHARGE: PIPE MATERIAL MUST BE RATE FOR HIGH TEMPERATURE; MUST PIPE DIRECTLY TO FLOOR DRAIN OR FLOOR -- NOT TO PLASTIC PAN
Misc
Resolved
08/31/2011
UNUSED OPENING AT ELECTRICAL JUNCTION BOX @ EAST MECH RM NW CORNER REQUIRES PLUG
Misc
Resolved
08/31/2011
WATER PIPE SUPPORT FLANGE BEHIND WATER HEATER @ EAST MECH RM NOT ANCHORED TO WALL
Misc
Corrective Action Required
08/29/2011
REPORT OF TESTING OF BACKFLOW PREVENTION DEVICES TO BE PROVIDED TO WATER UTILITES DEPARTMENT -- ATTENTION BEN HASKAMP
Misc
Resolved
08/31/2011
RESOLVE FIRE DEPARTMENT ISSUES
Occupancy Inspection - Fire Passed 9/7/2011 at 12:00 AM 09/07/2011
Occupancy Inspection - Codes Commercial Full C of O 9/7/2011 at 12:00 AM 09/07/2011
Misc
Resolved
09/07/2011
REPORT OF TESTING OF BACKFLOW PREVENTION DEVICES TO BE PROVIDED TO WATER UTILITES DEPARTMENT -- ATTENTION BEN HASKAMP
Documents & Images
Date Uploaded File Type Document Name
05/17/2011 Letter Plan Review Conditions
06/06/2011 Letter Plan Review Conditions
06/06/2011 Letter Building Permit
06/09/2011 Letter Inspection Summary
06/09/2011 Letter Inspection Summary
06/14/2011 Letter Inspection Summary
06/21/2011 Letter Inspection Summary
06/23/2011 Letter Inspection Summary
07/25/2011 Letter Inspection Summary
08/26/2011 Letter Inspection Summary
08/31/2011 Letter Temporary Certificate of Occupancy
09/07/2011 Letter Field Certificate of Occupancy
09/08/2011 Letter Final Certificate of Occupancy
06/27/2013 Letter Fire Building Plan Review
06/27/2013 Letter Fire Loss Reduction Form
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home