Summary
PL2025071
Alura Apartments - Private Sewer and Water
Engineering Plan Review
Engineering Plan Review
In Plan Review
03/31/2025
Engineering Review for Alura Apartments Private Sewer and Water lines
Locations
Contacts
Jeff Bartz, Address:OWN, Inc, Phone:(816) 777-0400  
Intrinsic Development, L.L.C., Address:3622 Endeavor Ave., Ste. 101  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Corrections 03/31/2025 03/31/2025
Sue Pyles, P.E.
Corrective Action Required
03/31/2025

Sheet C200: • The proposed private water line will require backflow vaults at each connection with the public main. • Please label the service lines in a consistent manner. • Clarify how the proposed entrances will be constructed.
Corrective Action Required
03/31/2025

Sheets C300-C303: • Why are pipe sizes shown twice in the flowline information in Profile view? Please revise. • Easements are shown for the proposed sanitary sewer. Will they be a private easement or will it be handled as on the overall Discovery Park development? Please provide additional information and revise as necessary. • Please extend the view enough to show the entire service line to Bldgs 2, 4, and 5. • Much of the proposed sanitary sewer is deep. Please investigate options to shallow it up. Options could include adjusting drops and slopes or possible use of an outside drop MH or others similar.
Corrective Action Required
03/31/2025

Sheet C300: Please extend the Proposed Grade line all the way to the MH in Profile view.
Corrective Action Required
03/31/2025

Sheet C302: • Please relocate overlapping flowline information at MH B1 in Profile view for clarity. • Please relocate overlapping building label for Bldg 10 in Plan view. • Please include missing storm sewer crossings between MHs B1 & B3 in Profile view. • Please provide information for MH B4 in Profile view.
Corrective Action Required
03/31/2025

Sheet C305: Blank sheet.
Corrective Action Required
03/31/2025

Sheet C306: If this table is the only thing on this sheet, please enlarge somewhat for readability.
Corrective Action Required
03/31/2025

Sheet C400: • Please relocate overlapping building label for Bldg 2 in Plan view. • 3 valves are required at tees. Please add at the connection to the existing water line and at the connection at Sta. 17+49.
Corrective Action Required
03/31/2025

Sheet C401: • Please relocate overlapping callout information near Bldg. 7 in Plan view for clarity. • 3 valves are required at tees. Please add at the connection at Sta. 30+89.
Corrective Action Required
03/31/2025

Sheet C402: • Is there a specific reason the bend at Sta. 35+65 isn’t made with 2-45 degree bends like all of the others? • There is no sanitary service line crossing near Sta. 34+95 as is shown in both Plan and Profile views. • 3 valves are required at tees. Please add at the connection at Sta. 32+87.
Corrective Action Required
03/31/2025

Sheet C403: • Please extend the pipe to each end in Profile view. • Please adjust the Sta. 13+49 callout in Plan view so the last line isn’t cut off.
Corrective Action Required
03/31/2025

Sheet C404: Please extend the pipe to the end in the Profile view.
Corrective Action Required
03/31/2025

Sheets C500-C501: Is pavement patching anticipated during sanitary sewer construction? If not, please remove the standard detail.
Hearings

There are no hearings for this planning application.

Documents & Images
Date Uploaded File Type Document Name
03/31/2025 Plans Private Sewer and Water Plans_Rev0_PL2025071
03/31/2025 Letter DE-Comment Letter (Engineering Plans)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home