Summary
PL2024250
Final Plat - Oldham Village First Plat Lots 1-13 & Tracts A-D
Final Plat
Final Plat
Recorded
09/26/2024
OLDHAM INVESTORS LLC
The first of two final plats for Oldham Village master development. Lots 1-13
Locations
Contacts
OLDHAM INVESTORS LLC, Address:1700 132ND ST STE 150  
ENGINEERING SOLUTIONS, Address:50 SE 30TH ST, Phone:(816) 623-9888  
CHILDERS REMINGTON, Address:410 SW JEFFERSON ST  
Reviews
Review Type Outcome Est. Completion Date Completed
Planning Review Approved with Conditions 05/07/2025 05/08/2025
Hector Soto Jr.
Corrective Action Required
05/08/2025

CC&Rs. Submit a copy of CC&Rs for staff to review that said document contains the required common property language from UDO Section 4.290.
Corrective Action Required
05/08/2025

ROW TO BE VACATED. Revise the note labeled on the existing portion of SW Jefferson St that is to be vacated to read, "Ex. R/W to be vacated by Ord #10103. See note No. 10". Also, revise the end of Note 10 from "...vacated by separate document" to "...vacated by Ord #10103."
Corrective Action Required
05/08/2025

TITLE BLOCK. Add the missing words "First Plat" in the plat title block reference to the complete plat name. It currently just reads "Oldham Village, Lots 1-12...).
Corrective Action Required
05/08/2025

PRIVATE DRIVES. Add a label of "Private Street" to the private drive name labels of SW Fieldhouse Crossing, SW Oldham Crossing and SW Jefferson Crossing.
Engineering Review Approved with Conditions 05/07/2025 05/06/2025
Gene Williams, P.E.
DE C&O #01 Eng Plans – FP/PP
Corrective Action Required
05/06/2025

All required engineering plans and studies, including water lines, sanitary sewers, storm drainage, streets and erosion and sediment control shall be submitted along with the final plat and approved prior to the approval of the final plat. All public infrastructure must be substantially complete, prior to the issuance of any building permits.
DE C&O #03 Eng & Insp Fees
Corrective Action Required
05/06/2025

All Engineering Plan Review and Inspection Fees shall be paid prior to approval of the associated engineering plans and prior to the issuance of any site development permits or the start of construction (excluding land disturbance permit).
DE C&O #04 Cert FA or Escrow
Corrective Action Required
05/06/2025

All subdivision-related public improvements must have a Certificate of Final Acceptance prior to approval of the final plat, unless security is provided in the manner set forth in the City's Unified Development Ordinance (UDO) Section 7.340. If security is provided, building permits may be issued upon issuance of a Certificate of Substantial Completion of the public infrastructure as outlined in Article 3, Division V, Sections 3.540 and 3.550 and Article 3, Division IV, Section 3.475 of the UDO, respectively.
DE C&O #06 Land Disturbance
Corrective Action Required
05/06/2025

A Land Disturbance Permit shall be obtained from the City if groundbreaking will take place prior to the issuance of a site development permit, building permit, or prior to the approval of the Final Development Plan / Engineering Plans.
DE C&O #07 Easements
Corrective Action Required
05/06/2025

All permanent off-site easements, in a form acceptable to the City, shall be executed and recorded with the Jackson County Recorder of Deeds prior to the issuance of a Certificate of Substantial Completion or approval of the final plat. A certified copy shall be submitted to the City for verification.
DE C&O #12 Cut & Fill
Corrective Action Required
05/06/2025

Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
DE C&O #13 ADA Sidewalk Ramps
Corrective Action Required
05/06/2025

All ADA sidewalk ramps shall be constructed by the developer at the time the street is constructed.
DE C&O #14 Common Area Sidewalks
Corrective Action Required
05/06/2025

All sidewalks adjacent to a common area tract, unplatted land or any land where no structure is intended to be built, and is required, shall be constructed by the developer at the time the street is constructed.
DE Commercial Detention Basin
Corrective Action Required
05/06/2025

The applicant shall submit and the City shall accept an “As-built / As-graded” detention basin plan prior to issuance of any occupancy permit for the proposed development.
Planning Review Corrections 04/28/2025 04/29/2025
Hector Soto Jr.
Corrective Action Required
04/29/2025

STREET NAMES. 1) The east-west segment of the "7" road shall have the name changed from SW Fieldhouse Dr to SW Oldham Xing (Xing representing an abbreviation of Crossing). 2) The north-south segment of the "7" road shall have the name changed from SW Jefferson St to SW Jefferson Xing. 3) The street name suffix for SW Fieldhouse Dr contained within Tract D shall be changed to Xing, so the named private drive is SW Fieldhouse Xing.
Corrective Action Required
04/29/2025

ADDRESSES. 1) Update the street name portion of the labeled addresses for Lots 8-10 and Tract C to reflect the correct street name of SW Jefferson Xing, not Jefferson St. 2) Add an additional label to make it clear that Tract D is addressed as 241 SW Oldham Pkwy. 3) Staff has re-sent all draft address to our Fire Dept and GIS group to get final approval. Any further address revisons will be provided, if necessary.
Corrective Action Required
04/29/2025

CITY SIGNATURE BLOCK. Update the Planning Commission Secretary's name from Terry Trafton to Charles E. Touzinsky, III.
Engineering Review Corrections 04/28/2025 04/28/2025
Gene Williams, P.E.
DE C&O #01 Eng Plans – FP/PP
Resolved
04/28/2025

A ten (10) foot sidewalk easement is shown, but according to the engineering plans, it appears the area to the north of the retention basin and south of the retaining wall is too steep to install a ten (10) foot sidewalk in accordance with ADA standards. Suggest a meeting between Development Services, Parks, and the consultant. Even though the sidewalk is being deferred to the future, a concept plan showing its feasibility is required. Correction required.
DE C&O #03 Eng & Insp Fees
Resolved
04/28/2025

It is unclear how the future ten (10) foot sidewalk will connect to Pleasant Lea Park to the west. Suggest a meeting between Development Services, Parks, and the consultant. Correction required.
DE C&O #04 Cert FA or Escrow
Resolved
04/28/2025

Linework is vague east of Tract A in regard to the ten (10) foot sidewalk. Cleanup required.
DE C&O #06 Land Disturbance
Resolved
04/28/2025

All required engineering plans and studies, including water lines, sanitary sewers, storm drainage, streets and erosion and sediment control shall be submitted along with the final plat and approved prior to the approval of the final plat. All public infrastructure must be substantially complete, prior to the issuance of any building permits.
DE C&O #07 Easements
Resolved
04/28/2025

All Engineering Plan Review and Inspection Fees shall be paid prior to approval of the associated engineering plans and prior to the issuance of any site development permits or the start of construction (excluding land disturbance permit).
DE C&O #13 ADA Sidewalk Ramps
Resolved
04/28/2025

All subdivision-related public improvements must have a Certificate of Final Acceptance prior to approval of the final plat, unless security is provided in the manner set forth in the City's Unified Development Ordinance (UDO) Section 7.340. If security is provided, building permits may be issued upon issuance of a Certificate of Substantial Completion of the public infrastructure as outlined in Article 3, Division V, Sections 3.540 and 3.550 and Article 3, Division IV, Section 3.475 of the UDO, respectively.
Corrective Action Required
04/28/2025

Review the public infrastructure plans and add easements that are missing, including the easement to serve the new sanitary sewer line serving the landlocked lot to the south.
Corrective Action Required
04/28/2025

Review public infrastructure plans and widen the sanitary sewer easement as shown in the public sanitary sewer plans.
Corrective Action Required
04/28/2025

Review the public infrastructure plans and add the public utility easement for the water line serving the landlocked lot to the south.
Planning Review Approved with Conditions 01/28/2025 01/29/2025
Hector Soto Jr.
Corrective Action Required
01/29/2025

ADDRESSES. Addresses for both the 1st and 2nd plat will be provided under separate cover.
Corrective Action Required
01/29/2025

PRIVATE STREET/DRIVE NAMES. After continued internal discussion regarding addressing, the drive leading to the fieldhouse (SW Fieldhouse Xing) may not be needed after all because the fieldhouse is likely to be addressed off of SW Oldham Pkwy in order to maintain consistency with addressing for the adjacent lots on the south/west side of SW Oldham Pkwy. A final determination on the need for SW Fieldhouse Xing as a named private drive will be determined once addressing is finalized.
Engineering Review Corrections 01/28/2025 01/23/2025
Gene Williams, P.E.
Corrective Action Required
01/23/2025

A ten (10) foot sidewalk easement is shown, but according to the engineering plans, it appears the area to the north of the retention basin and south of the retaining wall is too steep to install a ten (10) foot sidewalk in accordance with ADA standards. Suggest a meeting between Development Services, Parks, and the consultant. Even though the sidewalk is being deferred to the future, a concept plan showing its feasibility is required. Correction required.
Corrective Action Required
01/23/2025

It is unclear how the future ten (10) foot sidewalk will connect to Pleasant Lea Park to the west. Suggest a meeting between Development Services, Parks, and the consultant. Correction required.
Corrective Action Required
01/23/2025

Linework is vague east of Tract A in regard to the ten (10) foot sidewalk. Cleanup required.
DE C&O #01 Eng Plans – FP/PP
Corrective Action Required
01/23/2025

All required engineering plans and studies, including water lines, sanitary sewers, storm drainage, streets and erosion and sediment control shall be submitted along with the final plat and approved prior to the approval of the final plat. All public infrastructure must be substantially complete, prior to the issuance of any building permits.
DE C&O #03 Eng & Insp Fees
Corrective Action Required
01/23/2025

All Engineering Plan Review and Inspection Fees shall be paid prior to approval of the associated engineering plans and prior to the issuance of any site development permits or the start of construction (excluding land disturbance permit).
DE C&O #04 Cert FA or Escrow
Corrective Action Required
01/23/2025

All subdivision-related public improvements must have a Certificate of Final Acceptance prior to approval of the final plat, unless security is provided in the manner set forth in the City's Unified Development Ordinance (UDO) Section 7.340. If security is provided, building permits may be issued upon issuance of a Certificate of Substantial Completion of the public infrastructure as outlined in Article 3, Division V, Sections 3.540 and 3.550 and Article 3, Division IV, Section 3.475 of the UDO, respectively.
DE C&O #06 Land Disturbance
Corrective Action Required
01/23/2025

A Land Disturbance Permit shall be obtained from the City if groundbreaking will take place prior to the issuance of a site development permit, building permit, or prior to the approval of the Final Development Plan / Engineering Plans.
DE C&O #07 Easements
Corrective Action Required
01/23/2025

All permanent off-site easements, in a form acceptable to the City, shall be executed and recorded with the Jackson County Recorder of Deeds prior to the issuance of a Certificate of Substantial Completion or approval of the final plat. A certified copy shall be submitted to the City for verification.
DE C&O #13 ADA Sidewalk Ramps
Corrective Action Required
01/23/2025

All ADA sidewalk ramps shall be constructed by the developer at the time the street is constructed.
DE C&O #14 Common Area Sidewalks
Corrective Action Required
01/23/2025

All sidewalks adjacent to a common area tract, unplatted land or any land where no structure is intended to be built, and is required, shall be constructed by the developer at the time the street is constructed.
GIS Plat Review No Comments 01/28/2025 01/21/2025
Kathy Kraemer
Planning Review Corrections 01/15/2025 01/16/2025
Hector Soto Jr.
Corrective Action Required
01/16/2025

COMMON AREA. See Development Engineering comment regarding conflicting references between a property owners association and homeowners association as it relates to ownership and maintenance responsibilities.
Corrective Action Required
01/16/2025

PRIVATE STREET/DRIVE NAMES. After additional internal discussion to assist in addressing and to help with emergency response efficiency, the City needs each of the 7-road legs to have an assigned name. Similarly, the private drive leading to the fieldhouse will also be assigned a name. The north-south leg of the 7-road shall be named SW Jefferson Xing. The east-west leg of the 7-road shall be named SW Oldham Xing. The drive leading to the fieldhouse shall be named SW Fieldhouse Xing.
Corrective Action Required
01/16/2025

ADDRESSES. Addresses for both the 1st and 2nd plat will be provided under separate cover.
Engineering Review Corrections 01/15/2025 01/15/2025
Gene Williams, P.E.
Corrective Action Required
01/15/2025

Dedication language states the property owners association will be responsible for maintenance of common area tracts, but in the subsequent sentence, the homeowner's association is listed as the responsible party. Reconcile and correct, as there will be only one entity responsible for ongoing maintenance and ownership. Correction required.
Corrective Action Required
01/15/2025

A ten (10) foot sidewalk is labeled along the retaining wall and Tract A. It is not clear how this sidewalk will be able to connect to the park due to the retaining wall. Correction required.
Corrective Action Required
01/15/2025

A twenty (20) foot utility easement is shown bisecting Lot 1 from east to west. Since this storm line will be private, remove the utility easement. Correction required.
Corrective Action Required
01/15/2025

An easement along the entire west side of the subdivision is still shown, despite the storm line being private within it. Remove the easement to the extent the storm line does not conflict with the easement. Correction required.
GIS Plat Review Corrections 01/15/2025 01/10/2025
Kathy Kraemer
Corrective Action Required
01/09/2025

The eastern ROW line for Oldham is STILL not correct. The street centerline is correct this version, as I drew from the NW corner of this roadway. However, the east line is still not right...using the new ITB it goes awry about 80 ft in. It does not follow the dark ROW line...it actually follows a bit on the second line next to it. These curves actually follow the LIGHT black line, but not the DARK BLACK ROW line. I think these are flat out not the right curve data. It needs to be for the dark black ROW line.
Corrective Action Required
01/09/2025

information is covered up along the east ROW line of Oldham (in the area with all the problems on lot 5). Please fix.
Engineering Review Corrections 01/03/2025 01/03/2025
Gene Williams, P.E.
Corrective Action Required
01/03/2025

Refer to previous applicant letter comment #1. You are showing the detention basin (i.e., Tract A) to be owned and maintained by the owner of Lot 1. Staff will not support the ownership and maintenance of this detention basin tract to an individual lot owner. It should be owned and maintained by the property owner's association. Correction required.
Corrective Action Required
01/03/2025

Refer to comment #2 in previous applicant letter. Sanitary sewer easements are still not shown. Refer to comment #2 in the previous applicant letter for further details. Correction required.
GIS Plat Review Corrections 12/31/2024 12/31/2024
Kathy Kraemer
Corrective Action Required
12/30/2024

The curve on Oldham Pkwy still isn't right. IDK if its a non-tangent curve or the radius is wrong. I can draw the west ROW lines according to the plat's dir/dim with accuracy, but the centerline and the east ROW line are off. I can try to draw from the north point of Oldham, but need an ITB on both the centrline and the eastern ROW line
Corrective Action Required
12/31/2024

The eastern ROW line for Oldham is not correct. When I try to draw the reversing curve near Lot 5 (512/88.97 and 488/42.24) it is way off and doesn't follow plat line. If I draw them as compound curves, it's worse. It appears that maybe all these radius/distances do not refer to lot lines. The whole western part of lot 5 is not accurate.
Corrective Action Required
12/31/2024

Please mark overall distance on the east ROW line of Oldham on Lot 5A and 6
Corrective Action Required
12/31/2024

Please use hashmarks to indicate measurement start and stop, and please remove lines and dir/dim info where they overlap (ex west lot line for lot 5 and those multiple curves).
Corrective Action Required
12/31/2024

Please double check the south lot line of Lot 5. It states 349.77, but it actually measures ~344.77
Planning Review Corrections 12/31/2024 12/30/2024
Hector Soto Jr.
Corrective Action Required
12/30/2024

APPLICATION. Submit a completed and signed application and Ownership Authorization form.
Corrective Action Required
12/30/2024

COMMON AREA - CC&RS. Submit a copy of the CC&Rs for the proposed development for review that includes the required common property language from UDO Section 4.290. The plat shall not be released for recording until such time as the CC&Rs have been submitted and reviewed by staff for compliance. No immediate is required for this comment.
Corrective Action Required
12/30/2024

COMMON AREA - TRACT A. A note on the plat states that ownership and maintenance of Tract A, which is the site of a stormwater detention basin, is tied to the ownership of Lot 1. It is staff's understanding that Lot 1 will be owned by the adjacent church, with future intent for parking expansion. It appears that the Tract A detention basin serves most of the lots in the subject first plat. Please clarify/confirm if the intent is for Tract A to be owned and maintained by the ownership of Lot 1 rather than the property owners association (POA) for the Oldham Village development. And if so, provide the justification for this approach.
Traffic Review No Comments 12/31/2024 12/27/2024
Erin Ralovo
Corrective Action Required
12/27/2024

Plat still shows a 5 FT sidewalk between Jefferson and the Fieldhouse lot. This should be a 10 ft Shared Use path.
Corrective Action Required
12/27/2024

There should be a 10 FT shared use path across the Fieldhouse lot and connecting to the neighboring homes. Please show on the Plat.
GIS Plat Review Corrections 12/17/2024 12/18/2024
Kathy Kraemer
Corrective Action Required
12/12/2024

Plat still does not close. I believe the error is on the curve along lots 8, 9, 10. First, an accurate georeference to coordinates revealed that that whole line from coord 3 to coord 2 had a dimension problem. I pulled the previous plat for these parcels, Lelands Commercial Park, and I see the radius along that curve is 1352.39, with an original length of 390.75 I added up that whole eastern curve (between coord 3 and 2)and lot dimensions don't equal overall length (79.36+151.38+252.11=482.85, not 490.71 which is 8.66 off). It definitely appeared the measurements on lot 10 weren't correct, and I was able to determine that the 79.36 dimension is more like 88.02, a difference of 8.66 When I edit that curve radius to 1352.39 (to match the previous curve) and length of 491.51 (after correcting the measurements), the plat closes.
Corrective Action Required
12/12/2024

Please provide distances on the northern portion of Oldham (dist=78.15) on either side of the street centerline
Corrective Action Required
12/17/2024

None of the curves seem right on either Jefferson or Oldham. When I draw the centerlines, the curves veer off. For example, on the east edge of Oldham, the first tangent curve R=350/41.34 aligns to the georeferenced image, but continuing west with R=350/496.86, the curve is too wide; it veers almost 14 feet off the centerline and towards that road's west ROW. If I change the radius to a smaller number and continue on,then the curve at the north (R=550) is also off both in curve radius (too small) and length is (~5 feet short). Jefferson is similar when drawing the centerline from the southeastern plat corner, the curve radius is too large on both of the curves, and the length is too long by over 10ft
Corrective Action Required
12/18/2024

Please use hashmarks to indicate where dimensions start and stop, as this plat is very busy and it is hard to determine lengths without them.
Corrective Action Required
12/18/2024

On the NE ROW of Oldham, there are 2 curves: R=489 and R=512. Can you please confirm if the 512 is a reverse curve to the 489 or if they both go in the same direction?
Traffic Review Corrections 12/17/2024 12/17/2024
Erin Ralovo
Corrective Action Required
12/17/2024

The sidewalk from Jefferson Street West to Lot 2 should be a 10 FT shared use path and a sidewalk connection should be shown into the adjoining neighborhood.
Engineering Review Corrections 12/17/2024 12/17/2024
Gene Williams, P.E.
Corrective Action Required
12/17/2024

Tract A dedication language on the plat is ambiguous. In the first sentence, it states Tracts A through D are to be owned and maintained by the property owner's association. The next sentence states Tract A (i.e., the detention basin tract) shall be owned and maintained by the owner of Lot 1. Concise language shall be used to show who owns and maintains this tract. Correction required.
Corrective Action Required
12/17/2024

There are no sanitary sewer easements shown on the plat despite the fact they are needed for this project. Show the location of all exclusive sanitary sewer easements using the sanitary sewer plans as a guide. Ensure the callout matches what is shown on the dedication language (i.e., "S.E." or "SANITARY SEWER EASEMENT") Correction required.
Planning Review Approved with Conditions 12/17/2024 12/17/2024
Hector Soto Jr.
Corrective Action Required
12/16/2024

APPLICATION. Submit a completed and signed application and Ownership Authorization form.
Corrective Action Required
12/16/2024

UTILITY EASEMENTS. Label and dimension the east-west easement that bisects Lot 1 and extends onto Lot 3.
Corrective Action Required
12/16/2024

ACCESS EASEMENTS. 1) Add a note to the plat referencing the CC&Rs for dedication of cross-access easements. 2) Provide a copy of the CC&Rs for review of the cross-easement dedication language.
Corrective Action Required
12/17/2024

BUILDING LINES. Show, label and dimension a 20' building line along the SW Oldham Pkwy frontage of Lots 10 and 12.
Corrective Action Required
12/17/2024

COMMON AREA - CC&RS. 1) Submit a copy of the CC&Rs for the proposed development for review that includes the required common property language from UDO Section 4.290. The plat shall not be released for recording until such time as the CC&Rs have been submitted and reviewed by staff for compliance. 2) The common area dedication paragraph has conflicting language. One sentence states that Tracts A-D will be owned and maintained by the HOA. The next sentence states that Tract A ownership and maintenance responsibilities shall run with the ownership of Lot 1.
Corrective Action Required
12/17/2024

CITY SIGNATURE BLOCK. Add the name of Terry Trafton to the Planning Commission Secretary signature line.
Corrective Action Required
12/17/2024

EXISTING RIGHT-OF-WAY. There is an east-west segment of right-of-way that extends west of the current SW Jefferson St alignment just south of the alignment of the short segment of SW Oldham Pkwy that "T"s into M-291 Hwy. Show, label and dimension said section of right-of-way to be vacated and label it as "to be vacated".
Planning Review Corrections 11/26/2024 11/26/2024
Grant White
Corrective Action Required
11/12/2024

APPLICATION. Submit a completed and signed application and Ownership Authorization form. Additionally, the application fee has not yet been paid.
Corrective Action Required
11/12/2024

LEGAL DESCRIPTION. 1) In the third line of the metes and bounds description, the listed bearing distance of 371.44' does not match the labeled distance of 371.41' on the drawing. 2) Provide a copy of the legal description in Word format.
Corrective Action Required
11/12/2024

SIDEWALKS. Darken the linework and text showing and calling out the proposed 5' and 10' sidewalks along the proposed roadways.
Corrective Action Required
11/12/2024

UTILITY EASEMENTS. 1) Show, label and dimension all proposed easements. None are shown on the drawing. 2) The plat includes a Sanitary Sewer Easement dedication paragraph, but no sanitary sewer easement (S.E) is shown on the drawing. Remove the dedication paragraph if no specific sanitary sewer easement will be dedicated as part of the subject plat.
Corrective Action Required
11/12/2024

ACCESS EASEMENTS. Show and dedicate all cross-access easements needed to serve the development on the subject plat.
Corrective Action Required
11/12/2024

ERRANT LINEWORK. What do the dashed lines at the southeast corner of Lot 13 represent?
Corrective Action Required
11/12/2024

BUILDING LINES. Show, label and dimension all proposed building lines on the proposed lots.
Corrective Action Required
11/12/2024

COMMON AREA - CC&RS. Submit a copy of the CC&Rs for the proposed development for review that includes the required common property language from UDO Section 4.290. The plat shall not be released for recording until such time as the CC&Rs have been submitted and reviewed by staff for compliance.
Corrective Action Required
11/12/2024

CITY SIGNATURE BLOCK. Change the name of Josh Johnson to Aimee Nassif, AICP, and the listed title to Deputy Director of Development Services.
Corrective Action Required
11/12/2024

EXISTING RIGHT-OF-WAY. Show, label and dimension the existing SW Jefferson St and SW Oldham Pkwy right-of-way boundaries that are proposed to be vacated and label them as "to be vacated".
Engineering Review Corrections 11/25/2024 11/25/2024
Gene Williams, P.E.
Corrective Action Required
11/25/2024

Minimum ten (10) foot general utility easement required along all street frontage, unless greater width necessary to accommodate utilities. Correction required.
Corrective Action Required
11/25/2024

Tract A is for detention of stormwater, and as such, shall include the standard language for stormwater detention tract. It should "stand out" from the other tracts due to this special designation. Corrections required. (P.S., please contact me for the special dedication language for stormwater dedication tract language if you do not have it).
Corrective Action Required
11/25/2024

Easments for the sanitary sewer line appear to be missing in several locations. Exclusive easement required in these instances. Correction required.
Corrective Action Required
11/25/2024

Easements shall be shown along private streets where public utilities are shown on the plans. General utility easements are required. Correction required.
Corrective Action Required
11/25/2024

Easements for stormwater shall be dedicated where needed. See stormwater plans for placement of these easements. Please dedicate a general utility easement for these. Correction required.
GIS Plat Review Corrections 11/13/2024 11/14/2024
Kathy Kraemer
Corrective Action Required
10/31/2024

Calls with issues: The very first call after POB is inconsistent between description and drawing (length). The call between coord 8 and 9 is inconsistent (missing length). Missing a call in description between coord 4 and 3. Call after ctl pt 3 is inconsistent dwg vs description (NWvNE)
Corrective Action Required
10/31/2024

Plat does not close. It is about 10ft off. The line along reconfigured Oldham Pkwy appears short, although I can't tell if it is the curve length between ctl pt 2 and POB,the straight distance N43-39-15W (484.93), or the N44-17-15W (122.21). When georeferenced, though, it seems likely that the curve is short; the curve ends ~11ft before the eastern line of lot 5 starts.
Corrective Action Required
11/14/2024

Curve on SW Oldham is wrong. Either the radius is wrong on the tangent curve, or it is not a tangent curve.
Corrective Action Required
11/14/2024

Please mark the dimensions on each side of the centerline of Jefferson St (near ctl pt 5)
Corrective Action Required
11/14/2024

Radius missing from dwg on Jefferson St, the part within lot 13 (221.32) Also, dimension wrong on SW Jefferson: it cannot be 350 ft when all the other like lines are 150 ft
Corrective Action Required
11/14/2024

Please provide ITB on SW Oldham curves: R=393.42 (after N70-42-39E, ITB probably NW) R=377.95 (after N70-42-39E, but ITB probably SE) R=600.00 west side of road after S68-55-47W, ITB probably SE) R=631.51 east side of road after S68-55-47W, ITB probably SE)
Corrective Action Required
11/14/2024

Lot 2 missing correct dimension at NE corner. Cannot be 559 ft
Corrective Action Required
11/14/2024

Lot 10 missing a lot dimension along the south lot line: S87-50-52E.
Corrective Action Required
11/14/2024

Lot 17 east line dimension is incorrect; 245.03 is the total length of the line that includes tract B. West line is also wrong 310.54 is total length includes tract B
Corrective Action Required
11/14/2024

Lot 5: the curve near Oldham and Tract C seems off. It seems like it needs a larger radius like 24.00 to follow the georeferenced drawing.
Corrective Action Required
11/14/2024

Lot 1 missing a dimension in the NE corner near POB
Corrective Action Required
11/14/2024

Please double check the line between tract A and lot 11: The dimension seems more like 240.81
Corrective Action Required
11/14/2024

Please use hashmarks to indicate where dimensions stop and start, particularly on curves. It's very hard to verify dimensions without them.
Corrective Action Required
11/14/2024

A lot of this plat is in current ROW, whilst dedicating ROW for reconfig Oldham and Jefferson. Are there recorded documents vacating this ROW? I am not sure where MoDot owns ROW and where we own ROW based on ours or JaCo's maps, so any vacations would have to be based on ownership: JaCo/LSMO vacation and any MoDot vacations
Fire Review No Comments 11/13/2024 11/07/2024
Jim Eden
Traffic Review Corrections 11/13/2024 11/07/2024
Erin Ralovo
Corrective Action Required
11/07/2024

Sidewalks and Mutli-use paths should be shown on the plat.
Fees
Paid Fees Amount Paid Owing Date Paid
Final Plat fee $889.00 $889.00 Paid 12/03/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Planning Commission Meeting 01/09/2025 5:00 PM Council Chambers 01/09/2025 05:00 PM
Agenda Item
Approved
01/09/2025
City Council Ordinance 1st Reading 01/21/2025 6:00 PM Council Chambers 01/21/2025 06:00 PM
Agenda Item
Approved
City Council Ordinance 2nd Reading 05/20/2025 6:00 PM Council Chambers 05/20/2025 06:00 PM
Agenda Item
Approved
05/20/2025
Documents & Images
Date Uploaded File Type Document Name
09/26/2024 Plans FINAL PLAT_Rev 0_PL2024250
11/26/2024 Letter Applicant Letter_Rev 0_PL2024250
12/03/2024 Receipt Receipt_PL2024250
12/10/2024 Plans FINAL PLAT_Rev 1_PL2024250
12/10/2024 Letter CITY COMMENT RESPONSE_Rev 1_PL2024250
12/18/2024 Letter Applicant Letter_Rev 1_PL2024250
12/20/2024 Letter CITY COMMENT RESPONSE_Rev 2_PL2024250
12/20/2024 Plans FINAL PLAT_Rev 2_PL2024250
01/02/2025 Letter Staff Report_PL2024250
01/03/2025 Letter Applicant Letter_Rev 2_PL2024250
01/08/2025 Plans FINAL PLAT_Rev 3_PL2024250
01/13/2025 Ordinance/Resolution Ordinance
01/14/2025 Letter Declaration of Covenants Restrictions and Easements_PL2024250
01/15/2025 Application Form Signed application and ownership form_PL2024250
01/16/2025 Letter Applicant Letter_Rev 3_PL2024250
01/20/2025 Plans FINAL PLAT_Rev 4_PL2024250
01/29/2025 Letter Applicant Letter_Rev 4_PL2024250
03/04/2025 Agreement (executed) MHTC approval_Oldham Pkwy city reliquishment
04/21/2025 Plans FINAL PLAT_Rev 5_PL2024250
04/29/2025 Letter Applicant Letter_Rev 5_PL2024250
04/30/2025 Plans FINAL PLAT_Rev 6_PL2024250
05/06/2025 Agreement (executed) Performance Bond- Public-Executed_Oldham Village
05/08/2025 Letter FP Applicant Letter
07/21/2025 Routing Sheet Final Plat Signature Routing
08/29/2025 Recorded Document Recorded_Oldham Village First Plat Lots 1-12 & Tracts A-D
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home