Review Type |
Outcome |
Est. Completion Date |
Completed |
Building Codes Review
|
No Comments
|
09/13/2023
|
09/06/2023
|
|
Joe Frogge
|
|
MISC
Light pole base detail is incomplete. Specify pier depth and any other relevant dimensions.
8/4/23 - Not addressed
|
|
|
Traffic Review
|
No Comments
|
09/13/2023
|
09/06/2023
|
|
Scott Ready
|
|
|
Fire Review
|
No Comments
|
09/13/2023
|
09/06/2023
|
|
Scott Ready
|
|
|
Engineering Review
|
Approved with Conditions
|
09/13/2023
|
09/06/2023
|
|
Scott Ready
|
|
DE Commercial Detention Basin
Corrective Action Required
The applicant shall submit and the City shall accept an “As-built / As-graded” detention basin plan prior to issuance of any occupancy permit for the proposed development.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee of $6,766.91 (which is based on 3% of the total infrastructure cost) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit.
|
|
|
Planning Review
|
No Comments
|
09/13/2023
|
09/06/2023
|
|
Scott Ready
|
|
|
Planning Review
|
No Comments
|
08/07/2023
|
08/07/2023
|
|
Shannon McGuire
|
|
|
Building Codes Review
|
Corrections
|
08/02/2023
|
08/04/2023
|
|
Joe Frogge
|
|
MISC
Corrective Action Required
Light pole base detail is incomplete. Specify pier depth and any other relevant dimensions.
8/4/23 - Not addressed
|
|
|
Engineering Review
|
Approved with Conditions
|
08/04/2023
|
08/04/2023
|
|
Sue Pyles, P.E.
|
|
DE Commercial Detention Basin
Corrective Action Required
The applicant shall submit and the City shall accept an “As-built / As-graded” detention basin plan prior to issuance of any occupancy permit for the proposed development.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee of $6,766.91 (which is based on 3% of the total infrastructure cost) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit.
|
|
|
Fire Review
|
No Comments
|
08/02/2023
|
07/26/2023
|
|
Scott Ready
|
|
|
Traffic Review
|
No Comments
|
08/02/2023
|
07/26/2023
|
|
Scott Ready
|
|
|
Planning Review
|
Corrections
|
07/12/2023
|
07/19/2023
|
|
Shannon McGuire
|
|
Corrective Action Required
North Arrow – Please check the orientation of the north area on sheet 13 of 14. It is pointing in the wrong direction.
|
|
Corrective Action Required
Land Area – In addition to acres please add the area of land in square feet to the property description on sheet 1 of 14.
|
|
Corrective Action Required
Oil & Gas Wells – Please show the location of all oil and/or gas wells within the subject property. If none are present please add a note stating such and cite your source of information.
|
|
Corrective Action Required
Parking lot lighting - light fixtures on properties within or adjoining residential uses and/or districts shall not exceed 15 feet in height within the perimeter area. For purpose of this standard, the perimeter area shall be measured 100 feet from the property line closest to the residential use and/or district. Outside the perimeter area, the overall height may be increased to 20 feet, measured to the top of the fixture from grade. As this property is located with in a residential district (RP-4) The parking lot lighting is limited to 15 feet in height.
|
|
Corrective Action Required
Island width - Tree planting areas shall be no less than 10 feet in width. No tree shall be located less than 4 feet from the back of curb. Some of the islands are not wide enough to accommodate trees as proposed on the landscaping plan. Please increase the width of these islands to meet the code requirements.
|
|
Corrective Action Required
Parking setback - Parking lots shall be set back a minimum 6 feet from the side or rear property line when not part of shared parking and/or cross access. The parking stalls along the north property line do not meet this requirement. Deviation from this requirement will require a PDP to seek Council approval.
|
|
Corrective Action Required
No. of Accessible Parking Spaces – Please provide information on the total number of standard and ADA parking stalls provided for the site as a whole. It is possible that additional ADA stall may be required.
|
|
|
Building Codes Review
|
Corrections
|
07/12/2023
|
07/13/2023
|
|
Joe Frogge
|
|
MISC
Corrective Action Required
Light pole base detail is incomplete. Specify depth and any other relevant dimensions.
|
|
|
Traffic Review
|
No Comments
|
07/12/2023
|
07/12/2023
|
|
Erin Ralovo
|
|
|
Engineering Review
|
Corrections
|
07/12/2023
|
07/12/2023
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
Submit an Engineer's Estimate of Probable Construction Costs.
|
|
Corrective Action Required
Submit the SWPPP and a copy of the MDNR Land Disturbance Permit.
|
|
Corrective Action Required
Show location of all oil/gas wells, or indicate none are present, and cite the source.
|
|
Corrective Action Required
Sheet 1:
• Revise General Note 21 to reflect the correct City.
• Remove the approval signature block for the City. A stamp will be provided electronically when approved.
|
|
Corrective Action Required
Include the following note on any profile sheet applicable: “Compacted Fill shall be placed to a minimum 18” above the top of the pipe prior to installation.” Show and label the limits of the compacted fill placement in the Profile view. Use hatching for clarity.
|
|
Corrective Action Required
I’d like to discuss the overall detention approach to gain a better understanding. In looking at it, I can’t clearly see how the 100-year overflow will be able to flow across the parking lot without ponding at the curb inlets deeper than is safe. No comments are being made on the detention design at this time pending that discussion.
|
|
|
Fire Review
|
No Comments
|
07/12/2023
|
07/12/2023
|
|
Jim Eden
|
|
|