Planning Application Status

PL2023051




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2023051
Blackwell Reserve - Public Street, Storm and Final Grade
Engineering Plan Review
Engineering Plan Review
Approved
03/01/2023
RESIDENCES AT BLACKWELL LLC
Locations
Contacts
RESIDENCES AT BLACKWELL LLC, Address:21 SE 29TH TER  
GRIFFIN RILEY PROPERTIES, Address:21 SE 29TH TERRACE, Phone:(816) 366-7900  
SCHLAGEL & ASSOCIATES, Address:14920 W 107TH ST, Phone:(913) 492-5158  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review No Comments 04/01/2025 03/27/2025
Gene Williams, P.E.
Engineering Review Approved with Conditions 02/03/2025 02/03/2025
Gene Williams, P.E.
Corrective Action Required
02/03/2025

As-graded plan required prior to issuance of any occupancy permit. The as-graded plan shall be submitted, and the City shall review prior to acceptance. Informational comment.
Engineering Review No Comments 09/22/2023 09/21/2023
Gene Williams, P.E.
Traffic Review No Comments 09/22/2023 09/08/2023
Scott Ready
Engineering Review Corrections 07/13/2023 07/13/2023
Gene Williams, P.E.
Corrective Action Required
07/13/2023

Please refer to comment #1 in the previous applicant letter. During our telephone conversation, it was understood there was going to be a discussion concerning the prohibition of fences in the rear yard to prevent flooding, and in particular, there was going to be discussion concerning the use of open wrought iron fences or other fences that will pass stormwater. The main concern is the density of this development, and the modifications that were granted during the Preliminary Development Plan to allow for the increased density of this development. The long swale along the western and northern boundary of the project is concerning, since there are no additional underground systems to collect and convey stormwater.
Corrective Action Required
07/13/2023

We are still recommending additional inlets and underground piping to mitigate the concerns discussed above. This would pertain to the western property boundary as well as the northern property boundary, where the swale is shown being installed very close to buildings.
Traffic Review No Comments 07/13/2023 07/12/2023
Erin Ralovo
Engineering Review Corrections 05/24/2023 06/02/2023
Gene Williams, P.E.
Corrective Action Required
06/02/2023

The Master Drainage Plan was submitted in response to the previous applicant letter. However, there are issues with the Master Drainage Plan as follows: 1) MBOEs should be called-out, not MLOs since the City of Lee's Summit does not recognize or define an MLO, 2) all lots should include an MBOE due to the density of the development, 3) MBOEs shall be a minimum of 2.0 feet above the calculated 100 year water surface elevation, 4) it would appear at least one (1) field inlet and associated piping is required west of Lot 19, and one (1) field inlet and associated piping west of Lot 2, 5) it would appear additional field inlets are required along the northern swale to collect and convey stormwater to the east, and 6) sideyard swales should be specifically called-out on the Master Drainage Plan due to the density.
Corrective Action Required
06/02/2023

The private fire access road geometry looks acceptable, but there are no other details such as drainage, grading, etc. for the private fire access road. Please provide these details in the resubmittal.
Corrective Action Required
06/02/2023

Swale sections shown on the Master Drainage Plan should be shown explicitly from the start of the swale to the end, with cross-sections along intervals to be selected by the engineer. Please update.
Corrective Action Required
06/02/2023

Lot corner finish elevations shall be shown for each lot within the project. Please update and revise.
Corrective Action Required
06/02/2023

Is the placement of swales within such a small distance from structures a good idea? There is concern the swales are too close to the proposed structures, especially those shown on Lots 1, 4, 7, 10, 13, 16, 19, 22, 25, 28, and 31. It appears the proposed structures on these lots will be within 5 feet of the swale bottom. Please evaluate and revise if appropriate.
Traffic Review No Comments 05/24/2023 05/24/2023
Susan Barry, P.E.
Engineering Review Corrections 03/21/2023 03/28/2023
Gene Williams, P.E.
Corrective Action Required
03/28/2023

A stormwater memorandum shall be required which describes the stormwater detention being provided outside the limits of the plat. This is required for documentation purposes, and shall describe why detention is not being constructed for this portion of the project, but rather, shall be provided by other adjacent portions of the project.
Corrective Action Required
03/28/2023

Informational Comment: It is our understanding that a second street access point is required with a new connection to Blue Pkwy. just west of the roundabout. This will change the geometry of the overall street plan, as well as the water line plans and the sanitary sewer plans.
Corrective Action Required
03/28/2023

Profile Views of Storm Lines: Please show the hydraulic grade line for the design storm event on the profile view of the storm lines. If the system cannot manage the 100 year event without surcharging (i.e., defined as being less than 6 inches from the throat of an inlet), an overflow route shall be established and minimum building opening elevations shall be established for all habitable structures along the overflow route. The opening elevations shall be a minimum of 2.0 feet above the 100 year water surface elevation in this instance.
Corrective Action Required
03/28/2023

A typical section view of the pavement shall be provided for the pavement, with stationing shown for beginning and end. The typical section shall meet the requirements shown in the Design and Construction Manual for construction of streets.
Corrective Action Required
03/28/2023

Sheet 13: ADA-accessbile ramps shall be detailed with: 1) runiing slope callouts not to exceed 7.5% design slope, 2) cross-slope callouts not to exceed 1.5%, 3) ADA-accessible route across stop-controlled intersection with a minimum of 5 foot width and 1.5% cross-slope. Please revise as appropriate.
Corrective Action Required
03/28/2023

Private alley appears to be shown without curb and gutter. Curb and gutter should be shown for the private alleys. Please revise as appropriate.
Corrective Action Required
03/28/2023

Informational Comment: If the development is being platted as separate lots, a Master Drainage Plan shall be required. The Master Drainage Plan is normally a part of the street and stormwater plans. Further discussion is being held about the applicability of this development being in the form of separate lot ownership, and hence may affect the requirement for a separate Master Drainage Plan.
Corrective Action Required
03/28/2023

Area inlets are called-out within the private alley. There does not appear to be a detail within the plans for an "Area Inlet". The City has a standard detail for a field inlet, but this does not appear appropriate for an alley. Please review and revise as appropriate, and ensure there are sufficient details contained in the plans for construction.
Corrective Action Required
03/28/2023

Field inlet 1001: This field inlet was called-out on Sheet 18 without any corresponding callouts for the number and cardinal direction of openings. Please callout the openings for this field inlet.
Corrective Action Required
03/28/2023

The swale along the west side of the property which begins at approximately lot 11 and ends at the aforementioned field inlet is long. Details concerning this swale, such as flow rate, depth of flow, and vertical distance to building openings were not provided. This information is typically shown on the Master Drainage Plan discussed previously, but regardless of whether a Master Drainage Plan is required or not, this swale shall be designed with a minimum 2.0 foot freeboard between the 100 year water surface elevation and any building opening along the swale. Please evaluate and revise as appropriate.
Corrective Action Required
03/28/2023

The same comment above also applies to the swale along the north side of the development. Please evaluate and revise as appropriate.
Corrective Action Required
03/28/2023

Turf reinforcement mat should be shown for all swales described above. Please revise as appropriate.
Corrective Action Required
03/28/2023

Depending upon how this development is platted, sidewalks along "lot lines" may be required during construction rather than individual builders. The notes on the plans state the sidewalks will be constructed by others unless otherwise noted. Please evaluate and revise as appropriate.
Corrective Action Required
03/28/2023

A trenching and backfill detail appeared to be missing. Please provide a trenching and backfill detail for the storm lines, and ensure the new standard of 12 inches aggregate over the top of pipe is shown.
Corrective Action Required
03/28/2023

It appears some of the stationing for storm sewer structures were missing. Please ensure the plans show the stationing on the revised plans.
Corrective Action Required
03/28/2023

Sheet 5: The drainage map shows the limits of "Onsite 4" ending at the west property line. Is there any drainage from offsite areas that will contribute to the flows within the western or northern swales? It is difficult to determine from the plans as the offsite contours are not labelled. Please evaluate and review, and revise if appropriate.
Corrective Action Required
03/28/2023

The same comment as above applies to the northern property line. The drainage area appears to abruptly terminate at the property line. Are there any offsite contributors to flow within the northern swale? Please evaluate and review, and revise if appropriate.
Corrective Action Required
03/28/2023

Informational Comment: An itemized and sealed Engineer's Estimate of Probable Construction Costs shall be required prior to formal approval. The Engineering Plan Review and Inspection Fee is based on this estimate.
Traffic Review Approved with Conditions 03/21/2023 03/21/2023
Brad Cooley, P.E., RSPI
Corrective Action Required
03/21/2023

Street name signs should be a mix of upper and lower case letters, per City standard details.
Hearings

There are no hearings for this planning application.

Documents & Images
Date Uploaded File Type Document Name
03/07/2023 Plans 22-093 STREET AND STORM - REV0 - 2023_03_03
03/28/2023 Letter DE-Comment Letter (Engineering Plans)
05/10/2023 Plans 22-093 STREET AND STORM - REV1 - 2023_05_05
05/10/2023 Letter Response to DE-Comment Letter (Engineering Plans) Public Street and Storm Sewer dated 3-28-2023
06/02/2023 Letter DE-Comment Letter (Engineering Plans)
06/28/2023 Plans 22-093 PUBLIC STREET AND STORM - REV2 - 2023_06_27
06/28/2023 Engineer Report/Study 22-102 - Blackwell Final Stormwater Management Plan - Rev3
06/28/2023 Letter Response to DE-Comment Letter (Engineering Plans) Public Street and Storm Sewer dated 6-2-2023
07/13/2023 Letter DE-Comment Letter (Engineering Plans)
09/08/2023 Plans 22-093 - BLACKWELL RESERVE - PUBLIC STREET AND STORM - REV4 - 2023_09_06
09/08/2023 Engineers Estimate 22-097 - BLACKWELL RESERVE - PUBLIC STREET AND STORM - EOPC 2023_09_06
09/08/2023 Letter Response to DE-Comment Letter (Engineering Plans) Public Street and Storm Sewer dated 7-13-2023
09/21/2023 Approved Plans STAMPED PLANS APPROVED
09/21/2023 Activity Document FeeWorksheetReserveBlackwellStreetStormMDP
09/21/2023 Email STKY APPROVAL CONDITIONS
01/27/2025 Plans 22-093-SS-PLOT-PLAN-PHASE 1-GROUP 2
02/19/2025 Approved Plans Approved Final Grading Plan Lots 1 -12 Reserve at Blackwell
03/25/2025 Plans 22-093-SS-PLOT-PLAN-PHASE 1-GROUP 3_REV 0_PL2023051
03/25/2025 Plans 22-093-SS-PLOT-PLAN-PHASE 1-GROUP 4_REV 0_PL2023051
03/25/2025 Plans 22-093-SS-PLOT-PLAN-PHASE 1-GROUP 5_REV 0_PL2023051
04/08/2025 Plans 22-093-SS-PLOT-PLAN-PHASE 1-GROUP 6_REV 0_PL2023051
04/08/2025 Approved Plans Approved Final Grading Plan Lots 48 -59 Reserve at Blackwell
04/08/2025 Approved Plans Approved Final Grading Plan Lots 13 - 16 and Lots 43 - 47 Reserve at Blackwell
04/08/2025 Approved Plans Approved Final Grading Plan Lots 60 -72 Reserve at Blackwell
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home