Summary
PL2022019
Town Centre Lot 1 - Mass Grading
Engineering Plan Review
Engineering Plan Review
Approved
01/20/2022
WHD MANAGEMENT LLC
Locations
Contacts
WHD MANAGEMENT LLC, Address:PO BOX 1059  
DAVIDSON ARCHITECTURE & ENGINEERING, Address:4301 INDIAN CREEK PKWY, Phone:(913) 451-9390  
Jon Prueter, Address:Davidson Architecture & Engineering, Phone:(913) 451-9390  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review No Comments 03/16/2022 03/16/2022
Sue Pyles, P.E.
Engineering Review Corrections 02/03/2022 02/02/2022
Gene Williams, P.E.
Corrective Action Required
02/01/2022

Retaining walls appear to be slightly within public easements. Retaining wall or any portion of geogrid or tie-backs, and footings are a "Non-Alloweed" use of the easement according to the current Encroachment Policy adopted by the City.
Corrective Action Required
02/01/2022

Location, material, and sizing of the water transmission main existing along the west side of the project was missing. This transmission main shall be shown on the plans.
Corrective Action Required
02/01/2022

Transmission main location will be impacted by cut/fill. Maximum depth of cover is 7 feet, and minimum depth of cover is 3.5 feet. The vertical location in the form of a profile view shall be presented. Please provide the method used to determine the depth of the transmission main in the affected areas, as as-builts may not be the most suitable method. It is possible Water Utilities will require potholing or other direct methods for vertical location of the line.
Corrective Action Required
02/02/2022

Sheet C2.1: Drainage swale 2-2 is shown in the plan view, but the typical section view at bottom of sheet does not match the callout. In addition, no other section views were shown for the swale despite the different geometry at different locations along the swale. Recommend several sections be called-out, with different section views for each. In any case, all must match what is called-out on the plan view versus the section view.
Corrective Action Required
02/02/2022

The water transmission main is crucial to Water Utilities. Ensure there is no conflict with the retaining walls, as Water Utilities will require a substantial buffer between the retaining walls and the transmission main. Please show the location of this transmission main on the plans.
Corrective Action Required
02/02/2022

General Note: The note concerning contacting Development Services Inspections 48 hours prior to construction commencement is not correct. Please revise to read "A prec-construction meeting shall be scheduled between Contractor and Development Services Inspections with a minimum of 48 hours notice. Please contact 816-969-1200 to schedule this pre-construction meeting."
Corrective Action Required
02/02/2022

Erosion Control Note #1: The erosion control note did not mention the construction of the basin. This is a critical element of the plan, and shall be discussed within the notes.
Corrective Action Required
02/02/2022

Are there any areas on this project where turf reinforcement mat (TRM) would be appropriate? It does not appear any TRM was called-out for this project, and it is unclear how this plan will limit off-site erosion and sediment from leaving the site without it.
Corrective Action Required
02/02/2022

All retaining wall designs with walls greater than 2.5 feet including the footing shall be submitted to Development Services for review and approval.
Corrective Action Required
02/02/2022

Sediment basin design is incomplete and based on "hunch" estimates of volume and flows. I see the summary design table on the last sheet of the plans, but no site-specific design parameters are presented. Please complete, and provide a new design if the calculations show a larger basin is necessary. Drainage area shall include any off-site contributors to flow.
Corrective Action Required
02/02/2022

Sheet C2.2: Why isn't the sediment basin being constructed first? I realize the pond needs to be removed, but shouldn't the sediment basin be installed as the first measure of erosion and sediment control?
Corrective Action Required
02/02/2022

The discharge location of the sediment basin appears to be lacking in terms of design. Sufficient energy dissipation measures shall be installed, and sufficient distance shall be maintained between the discharge point and the adjacent property. Provide design calculations for any energy dissipation measures, and ensure there is no adverse impact to adjacent property.
Corrective Action Required
02/02/2022

Two (2) separate swales are located toward the east side of the project, each in a north/south orientation. Neither swale was labeled, and neither swale included cross-sections at key locations. In addition, two (2) separate swales are also located toward the west side of the project in a north/south orientation. These additional swales were neither labeled nor detailed in the form of a section view. Please see previous comments concerning the other swale bisecting the project in an east/west fashion. The same comments apply to these swales.
Corrective Action Required
02/02/2022

It shall be noted that no review of a final stormwater detention report was conducted since no such report was provided. It is possible that the sediment basin shall require significant modification if being converted into a permanent stormwater detention facility after the skimmer assembly is removed. In other words, the volume of the basin as well as the allowable release rates may differ significantly than allowed by the proposed sediment basin design. Finally, no review was conducted on the 0.5 feet freeboard requirements of KCAPWA Section 5600 from the nominal 100 year WSE and the emergency spillway, and the 1.0 feet freeboard requirement between the clogged condition/zero available storage 100 year WSE and the top of dam.
Corrective Action Required
02/02/2022

Public utilities such as water main near the southeast portion of the project may be affected by grading. It is difficult to determine, however, since the contours are crowded, and there are discrepancies in what is being showed for sanitary sewer sewer service versus what we are showing on GIS. Please review and revise as appropriate, as it is possible the water main along the road will be affected by grading activities. The City's requirements are no more than 7 feet of cover over water mains, and no less than 3.5 feet. Sanitary sewer requirements are different, but we are not showing the presence of a public sanitary sewer main along the roadway, and this conflicts with the drawings.
Hearings

There are no hearings for this planning application.

Documents & Images
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home