Review Type |
Outcome |
Est. Completion Date |
Completed |
Engineering Review
|
No Comments
|
12/04/2020
|
11/25/2020
|
|
Loic Nguinguiri, E.I.
|
|
|
Engineering Review
|
Corrections
|
10/16/2020
|
10/15/2020
|
|
Loic Nguinguiri, E.I.
|
|
Corrective Action Required
Please include a FEMA National Flood Hazard information note.
|
|
Corrective Action Required
Please show location of all oil/gas wells, or indicate none are present, and cite the source.
|
|
Corrective Action Required
On sheet C403, one discharging storm pipe with FES and rip rap appears to look significantly larger than its counterpart on the plan; please revise. Unless there is a specific reason, feel free to use a similar icon size to represent FES + rip rap throughout the plans.
|
|
Corrective Action Required
Please revise staging chart activities to match the proposed work shown on the plan(s) for each project stage. (e.g. A5 and A6 leaders on sheet C404 are misrepresented on the plan)
|
|
Corrective Action Required
As shown in ESC-03, J-hooks are required within the ESC plan. Given the silt fence 100’ maximum runs for J-hooks, please locate the needed J-hooks on the plan.
|
|
Corrective Action Required
Please remove non-applicable item from the legend.
|
|
Corrective Action Required
Please provide an Engineer’s Opinion of Probable Construction Cost (EOOPCC) sheet, listing cost estimates for the proposed work shown on the ESC set of plans only.
|
|
Corrective Action Required
The spillway width shown in the Sediment Trap 1 Design Summary does not match the Plan view. Please revise as needed.
|
|
Corrective Action Required
Please show construction standard detail ESC-08, instead of ESC-02.
|
|
Corrective Action Required
Comments on the Street, Stormwater, and Master Drainage Plan are being provided by separate cover. Please ensure the comments on the Street, Stormwater, and Master Drainage Plan are also reflected in the Mass Grading and Erosion and Sediment Control Plans for this project.
|
|
Corrective Action Required
Please provide a Missouri DNR permit.
|
|
Corrective Action Required
Please make sure to include a final restoration plan.
|
|
|