Review Type |
Outcome |
Est. Completion Date |
Completed |
Planning Review
|
No Comments
|
03/03/2020
|
03/24/2020
|
|
Joshua Johnson
|
|
|
Fire Review
|
No Comments
|
03/01/2020
|
03/02/2020
|
|
Mike Weisenborn
|
|
|
Engineering Review
|
No Comments
|
03/03/2020
|
02/27/2020
|
|
Gene Williams, P.E.
|
|
DE C&O #01 Eng Plans – FP/PP
Corrective Action Required
Please add a note concerning stormwater detention being provided for each lot, in accordance with the Master Drainage Plan. Ongoing maintenance and ownership should also be described in this note.
|
|
DE C&O #02 Master Drainage Plan
Corrective Action Required
Please show a general outline of the location of each detention basin on the plat. A note may be added which references the approved Master Drainage Plan, and discussing the need to construct during the building permit process.
|
|
DE C&O #03 Eng & Insp Fees
Corrective Action Required
All required engineering plans and studies, including water lines, sanitary sewers, storm drainage, streets and erosion and sediment control shall be submitted along with the final plat and approved prior to the approval of the final plat. All public infrastructure must be substantially complete, prior to the issuance of any building permits.
|
|
DE C&O #04 Cert FA or Escrow
Corrective Action Required
A Master Drainage Plan (MDP) shall be submitted and approved in accordance with the City’s Design and Construction Manual for all areas of the development, including all surrounding impacted areas, along with the engineering plans for the development. The MDP shall address drainage level of service issues on an individual lot basis.
|
|
|
Traffic Review
|
No Comments
|
03/01/2020
|
02/26/2020
|
|
Michael Park
|
|
|
Planning Review
|
Corrections
|
01/30/2020
|
01/31/2020
|
|
Jennifer Thompson
|
|
Legal Description
Corrective Action Required
Please submit an electronic copy of the legal description in Microsoft Word document.
|
|
Corrective Action Required
Provide the single-family residential compatibility form.
|
|
Corrective Action Required
Label the addresses as follows:
Lot 1: 518 NW Main St.
Lot 2: 514 NW Main St.
Lot 3: 510 NW Main St.--existing
Lot 4: 508 NW Main St.
Lot 5: 504 NW Main St.
Lot 6: 500 NW Main St.
|
|
|
Engineering Review
|
Approved with Conditions
|
01/30/2020
|
01/30/2020
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
Please add a note concerning stormwater detention being provided for each lot, in accordance with the Master Drainage Plan. Ongoing maintenance and ownership should also be described in this note.
|
|
Corrective Action Required
Please show a general outline of the location of each detention basin on the plat. A note may be added which references the approved Master Drainage Plan, and discussing the need to construct during the building permit process.
|
|
DE C&O #01 Eng Plans – FP/PP
Corrective Action Required
All required engineering plans and studies, including water lines, sanitary sewers, storm drainage, streets and erosion and sediment control shall be submitted along with the final plat and approved prior to the approval of the final plat. All public infrastructure must be substantially complete, prior to the issuance of any building permits.
|
|
DE C&O #02 Master Drainage Plan
Corrective Action Required
A Master Drainage Plan (MDP) shall be submitted and approved in accordance with the City’s Design and Construction Manual for all areas of the development, including all surrounding impacted areas, along with the engineering plans for the development. The MDP shall address drainage level of service issues on an individual lot basis.
|
|
DE C&O #03 Eng & Insp Fees
Corrective Action Required
All Engineering Plan Review and Inspection Fees shall be paid prior to approval of the associated engineering plans and prior to the issuance of any infrastructure permits or the start of construction (excluding land disturbance permit).
|
|
DE C&O #04 Cert FA or Escrow
Corrective Action Required
All subdivision-related public improvements must have a Certificate of Final Acceptance prior to approval of the final plat, unless security is provided in the manner set forth in the City's Unified Development Ordinance (UDO). If security is provided, building permits may be issued upon issuance of a Certificate of Substantial Completion of the public infrastructure as outlined in Section 1000 of the City's Design and Construction Manual.
|
|
DE C&O #08 Changes to MDP
Corrective Action Required
A restriction note shall be included on the final plat stating: “Individual lot owner(s) shall not change or obstruct the drainage flow paths on the lots, as shown on the Master Drainage Plan, unless specific application is made and approved by the City Engineer."
|
|
|
Fire Review
|
No Comments
|
01/30/2020
|
01/29/2020
|
|
Jim Eden
|
|
|
Traffic Review
|
No Comments
|
01/28/2020
|
01/28/2020
|
|
Michael Park
|
|
|
Traffic Review
|
Corrections
|
12/27/2019
|
12/30/2019
|
|
Michael Park
|
|
Corrective Action Required
Provide a note regarding limits of no access to Orchard for Lot 6.
|
|
|
Planning Review
|
Corrections
|
12/27/2019
|
12/30/2019
|
|
Mike Weisenborn
|
|
Legal Description
Corrective Action Required
Please submit an electronic copy of the legal description. Microsoft Word document or selectable text PDF are the preferred file formats. The legal description can be emailed to the planner's email address above.
|
|
Corrective Action Required
Provide the single-family residential compatibility form.
|
|
Corrective Action Required
Remove Vincent E. Brice's name from the GIS title block. Jackson County prefers it doesn't reference a specific person.
|
|
Corrective Action Required
Label the varying widths of the sanitary sewer easement within Lot 1.
|
|
Corrective Action Required
In the sidewalk paragraph reference the NW and NE orientation for Orchard St and Main St, respectively.
|
|
Corrective Action Required
Addresses will be forthcoming.
|
|
Corrective Action Required
See engineering comment regarding the sidewalk comment.
|
|
|
Engineering Review
|
Corrections
|
12/27/2019
|
12/26/2019
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
An existing sidewalk is shown to the north, but we are not showing the existence of any sidewalk in this area. Please verify.
|
|
Corrective Action Required
Note 8 is not applicable. It was our understanding that a property owner's association was not being formed, and that the individual detention pits were going to be maintained by the individual lot owners.
|
|
|
Fire Review
|
No Comments
|
12/27/2019
|
12/17/2019
|
|
Jim Eden
|
|
|
GIS Review
|
No Comments
|
12/27/2019
|
12/12/2019
|
|
Kathy Kraemer
|
|
|