Planning Application Status

PL2019245




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2019245
CHIPMAN & DONOVAN INTERSECTION - TRAFFIC SIGNAL IMPROVEMENTS
Engineering Plan Review
Engineering Plan Review
Approved
07/25/2019
Locations
Contacts
Emery Sapp & Son Construction Co., Address:140 Walnut Street , Phone:(816) 221-3500  
ANDERSON ENGINEERING INC, Address:941 W 141ST TERRACE SUITE A, Phone:(816) 777-0400  
Reviews
Review Type Outcome Est. Completion Date Completed
Traffic Review Approved with Conditions 09/23/2019 09/23/2019
Michael Park
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Plan inconsistencies and errors must be corrected on the as-build drawings. The pavement markings shown on sheet C101 are correct, but incorrectly shown/referenced on sheet TC101. The signal shown on sheet TC101 is correct, but incorrectly shown/referenced on sheet C101.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

Sheet TC101, Signal Plan, shall be to scale.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Corrective Action Required
09/23/2019

A complete and thorough review of plan details, notes and quantities has not been completed to expedite approvals; which may result in necessary material or design modifications (signal pole and mast arm or geometric design impacts not anticipated). These modifications and/or minor quantity revisions are subject to the City's acceptance of construction. These changes, if applicable, will be shown on the as-build drawings.
Engineering Review Corrections 08/08/2019 08/08/2019
Michael Park
Corrective Action Required
08/08/2019

Refer to Traffic Comments
Traffic Review Corrections 08/08/2019 08/08/2019
Michael Park
Miscellaneous Correction
Corrective Action Required
08/08/2019

R10-12 Signs Located on the Mast Arms should be positioned to the left of the outboard signal head (and five section head).
Miscellaneous Correction
Corrective Action Required
08/08/2019

Show the Power Source and Power Supply Disconnect/Meter Cabinet (PUP Unit) on the plans.
Miscellaneous Correction
Corrective Action Required
08/08/2019

Add Fiber Optic Pull Box to the Legend
Miscellaneous Correction
Corrective Action Required
08/08/2019

Optional: The 3" Conduit between Pull Boxs and 4' Pedestals (Push Button) with 1-2c cable may be 2" Conduit.
Miscellaneous Correction
Corrective Action Required
08/08/2019

Scale on Sheet 6 is incorrect. Verify Mast Arm Lengths shown on plans and quantity tables are correct.
Miscellaneous Correction
Corrective Action Required
08/08/2019

Sheet 3 (C101). Existing Street Name Signs and Post at Donovan shall also be removed with Stop Sign (Upon Operational Traffic Signal). Street Name Signs will be on the signal mast arms.
Miscellaneous Correction
Corrective Action Required
08/08/2019

Street Lighting: The street light system modifications and impacts have not been adequately addressed in the plans. The existing street light in the median along Chipman on the west side of the intersection appears in conflict (obstructs visibility) with the proposed signal mast arm/head for Pole 4. The proposed street lights on Signal Pole 8; street light replacements, 240V, 250W LED Fixture on 30' Pole for the existing street lights at the same location may not be equivalent to existing 480 high voltage, 250W HPS Fixture on 40' Pole (design documentation needed as noted below). Consider removing both existing street light poles and the installation of street light pull boxes (intercepting the existing conduit and cable/circuit) and reconnecting the existing system with new conduit and cable between these pull boxes to nearest adjacent street lights to keep the existing system connected with the installation of an independent lighting system on the signal for the intersection following City standards and specifications. Alternatively, the street light in conflict could be relocated west (behind the signal) with new concrete foundation, pull box, etc. and connection to the existing conduit and cable/circuit towards the east (with new pull box intercepting the system that is disconnected by removal of street light at location of Pole 8). However, this would not address the issue of one light in the corridor on separate circuit/power supply with the signal and the existing lighting system cannot be routed through the proposed signal due to 480V. Lighting calculations should be submitted for review in association with the plan in support of the plan and design criteria (as well as comparison to existing lighting levels).
Miscellaneous Correction
Corrective Action Required
08/08/2019

Consider moving Head 31 to the pole (approximately 2' north of center lane) with R10-12 Sign on Pole. Head 31 would be changed to vertical 5-section head. Then move Street Name Sign on mast arm closer to the pole.
Miscellaneous Correction
Corrective Action Required
08/08/2019

Signs D3-1 and D3-1B Should be NW Donovan Rd, not NW Ward Rd. Verify S.F. for these Mast Arm Street Names in the Sign Table.
Miscellaneous Correction
Corrective Action Required
08/08/2019

Fiber Optic (FO) Plan and Interconnect: Plans need more detail for construction. Plan should include note(s) regarding FO Pull Box 6, intercept existing FO, splice enclosure, SFP, installation, splicing details, etc. Some of the FO wiring construction, splicing and installation information may be shown on the wiring plan. Include all necessary materials in the interconnect equipment table. Wireless Radio's shown for interconnect are not necessary at Chipiman & Donovan since interconnect will be FO. Interconnect will utilize the proposed FO and existing FO that runs along Chipman between Douglas and Ward (48 Count Single Mode FO).
Miscellaneous Correction
Corrective Action Required
08/08/2019

Signal system should be InSync for coordination compatibility with existing system(s) along Chiopman and adjacent intersection at Ward/Chipman. Add applicable cabinet equipment, revise detection system and add processor. The proposed controller is still good, but needs to be noted NTCIP and firmware 4.57f (unless otherwise directed by City) for compatibility with TranSuite ATMS.
Hearings

There are no hearings for this planning application.

Documents & Images
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home