Review Type |
Outcome |
Est. Completion Date |
Completed |
Planning Review
|
No Comments
|
05/06/2019
|
05/07/2019
|
|
Hector Soto Jr.
|
|
|
Fire Review
|
Approved with Conditions
|
05/06/2019
|
05/03/2019
|
|
Mike Weisenborn
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code.
Standpipe connections are required in the stairwells.
|
|
|
Traffic Review
|
No Comments
|
05/06/2019
|
05/03/2019
|
|
Mike Weisenborn
|
|
|
Building Codes Review
|
No Comments
|
05/06/2019
|
05/03/2019
|
|
Mike Weisenborn
|
|
|
Engineering Review
|
Approved with Conditions
|
05/06/2019
|
05/02/2019
|
|
Gene Williams, P.E.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Contact the Field Engineering Inspector at (816) 969-1200 at least 48 hours prior to the onset of construction.
|
|
DE Contact ROW Inspector
Corrective Action Required
Prior to any activities within the right-of-way that are not directly associated with a specific infrastructure or building permit, a separate right-of-way permit may be required. Contact a Right-of-Way Inspector at (816) 969-1800 to obtain the required permit.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $30,897.58
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
DE C&O #12 Cut & Fill
Corrective Action Required
Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
|
|
|
Engineering Review
|
Approved with Conditions
|
04/19/2019
|
04/22/2019
|
|
Mike Weisenborn
|
|
DE Engineers Estimate
Corrective Action Required
The plans show additional storm lines being installed as part of this project. The estimate is required to include any stom lines greater than (i.e., but not including) 6 inches in diameter, including any roof drain. Please add this information to the estimate previously provided and provide a signed and sealed copy.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Contact the Field Engineering Inspector at (816) 969-1200 at least 48 hours prior to the onset of construction.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
|
Fire Review
|
Complete
|
04/19/2019
|
04/19/2019
|
|
Mike Weisenborn
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code.
Standpipe connections are required in the stairwells.
|
|
|
Planning Review
|
Corrections
|
04/19/2019
|
04/15/2019
|
|
Hector Soto Jr.
|
|
Corrective Action Required
EXTERIOR MATERIALS. The pre-finished MBCI Masterline - 16 Wall Panel System material shown on the elevations will need to have the optional embossed finish in order to meet City ordinance for approved materials. The standard smooth finish for this product is not allowed.
|
|
|
Building Codes Review
|
No Comments
|
04/19/2019
|
04/15/2019
|
|
Joe Frogge
|
|
|
Traffic Review
|
No Comments
|
04/19/2019
|
04/12/2019
|
|
Michael Park
|
|
|
Engineering Review
|
Approved with Conditions
|
04/11/2019
|
04/12/2019
|
|
Mike Weisenborn
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs was missing from the resubmittal. The Engineering Plan Review and Inspection Fee will be calculated at a later date pending receipt of this estimate.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Contact the Field Engineering Inspector at (816) 969-1200 at least 48 hours prior to the onset of construction.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
DE C&O #06 Land Disturbance
Corrective Action Required
A Land Disturbance Permit shall be obtained from the City if ground breaking will take place prior to the issuance of an infrastructure permit, building permit, or prior to the approval of the Final Development Plan.
|
|
|
Planning Review
|
Approved with Conditions
|
04/11/2019
|
04/11/2019
|
|
Hector Soto Jr.
|
|
Corrective Action Required
Provide three (3) additional copies of the architectural plans that were recently submitted. Resubmittals require 6 copies of plans, but only 3 were previously provided.
|
|
|
Building Codes Review
|
No Comments
|
04/11/2019
|
04/11/2019
|
|
Joe Frogge
|
|
|
Fire Review
|
Complete
|
04/11/2019
|
04/10/2019
|
|
Jim Eden
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code.
Standpipe connections are required in the stairwells.
|
|
|
Traffic Review
|
No Comments
|
04/11/2019
|
04/09/2019
|
|
Michael Park
|
|
|
Building Codes Review
|
No Comments
|
09/25/2018
|
03/13/2019
|
|
Mike Weisenborn
|
|
|
Planning Review
|
Corrections
|
03/13/2019
|
03/13/2019
|
|
Hector Soto Jr.
|
|
Corrective Action Required
ARCHITECTURE.
- Submit the most recent version of the building elevations for all sides of the building.
- Label the proposed exterior building material colors and provide a colored rendering.
- Dash in the location of the roof-top units (RTUs) on the building elevations to the extent possible. RTUs shall be fully screened from view by using parapet walls on all sides of a height at least equal to the height of the RTUs.
The response from the engineer on the civil engineering resubmittal indicates that this requested information will be provided under separate cover by the architect.
|
|
Corrective Action Required
PHOTOMETRICS.
- Provide a photometric plan in accordance with Article 7 of the UDO.
- Provide cut sheets of all exterior light fixtures for review for compliance with the requirements of Article 7 of the UDO.
The response from the engineer on the civil engineering resubmittal indicates that this requested information will be provided under separate cover by the architect.
|
|
Corrective Action Required
TRASH ENCLOSURE. Provide a trash enclosure detail. The enclosure shall be constructed of masonry walls and a solid steel gate painted a color that is compatible with the enclosure walls and building it serves.
The response from the engineer on the civil engineering resubmittal indicates that this requested information will be provided under separate cover by the architect.
|
|
|
Engineering Review
|
Approved with Conditions
|
03/13/2019
|
03/13/2019
|
|
Gene Williams, P.E.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs was missing from the resubmittal. The Engineering Plan Review and Inspection Fee will be calculated at a later date pending receipt of this estimate.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Contact the Field Engineering Inspector at (816) 969-1200 at least 48 hours prior to the onset of construction.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
DE C&O #06 Land Disturbance
Corrective Action Required
A Land Disturbance Permit shall be obtained from the City if ground breaking will take place prior to the issuance of an infrastructure permit, building permit, or prior to the approval of the Final Development Plan.
|
|
|
Traffic Review
|
No Comments
|
03/13/2019
|
03/12/2019
|
|
Michael Park
|
|
|
Fire Review
|
Approved with Conditions
|
03/13/2019
|
03/11/2019
|
|
Jim Eden
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code.
Standpipe connections are required in the stairwells.
|
|
Knox Locks
IFC 506.1 - Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type listed in accordance with UL 1037, and shall contain keys to gain necessary access as required by the fire code official. 506.1.1 Locks. An approved lock shall be installed on gates or similar barriers when required by the fire code official.
A knox box shall be provided on the building over the FDC.
|
|
|
Building Codes Review
|
No Comments
|
03/13/2019
|
03/11/2019
|
|
Joe Frogge
|
|
|
Planning Review
|
Corrections
|
09/25/2018
|
09/25/2018
|
|
Hector Soto Jr.
|
|
Corrective Action Required
FLOOR AREA RATIO (FAR). The maximum allowable FAR in the PI zoning district is 1.0. The submitted plans have an FAR of 1.13. Staff does not have the authority to approve the proposed FAR. Approval of the proposed FAR requires City Council approval through a public hearing process.
|
|
Corrective Action Required
ADA PARKING SIGN. Specify sign type R7-8 as identified in the MUTCD on the sign detail on Sheet 5.1).
|
|
Corrective Action Required
PARKING SPACE DIMENSIONS. The minimum parking space width is 9'. Because of the plan scale of Sheet C1.0, it is not clear that all of the spaces on the north side of the building meet the minimum 9' width. The 9' width is measured from the face of the curb. It appears that the dimensions may measure to the back of curb.
|
|
Corrective Action Required
PROPERTY LINE INFORMATION. Label the correct property line dimesions and bearings for Lot 1 on Sheet C1.0.
|
|
Corrective Action Required
DRIVEWAY IMPROVEMENTS. Use a heavier line weight to more clearly identify the limits of the private drive to be constructed with this project.
|
|
Corrective Action Required
ARCHITECTURE.
- To meet the requirements for horizontal and vertical breaks, building offsets shall be incorporated on the west and east elevations to break up the expansive wall planes.
- Provide a color perspective in order to better evaluate compliance with the architectural requirements for horizontal and vertical breaks.
- Label the proposed exterior building material colors and provide a colored rendering.
- The architectural drawings submitted with this application appears to have decreased the amount of brick used on the exterior from that shown on the rendering presented to the City Council as part of the special use permit application approval process. Revise the plans to increase the use of brick to more closely match the previously presented colored rendering.
- The number and sizes of windows on the submitted architectural plans are signifcantly fewer in number and size from that depicted on the rendering presented to the City Council as part of the special use permit approval.
- It appears the proposed metal wall material is a smooth-finished shadow wall panel. City ordinance does not allow the use of smooth-finished metal in this part of the city. The use of metal panels requires an engineered rough-textured metal panel system. Provide a material sample of the proposed metal panels for review.
- Dash in the location of the roof-top units (RTUs) on the building elevations to the extent possible. RTUs shall be fully screened from view by using parapet walls on all sides of a height at least equal to the height of the RTUs.
|
|
Corrective Action Required
PHOTOMETRICS.
- Provide a photometric plan in accordance with Article 7 of the UDO.
- Provide cut sheets of all exterior light fixtures for review for compliance with the requirements of Article 7 of the UDO.
|
|
Corrective Action Required
LANDSCAPING. Staff does not have authority to approve the landscaping modifications requested on Sheet L1.0. Modifications can only be approved by the City Council through a public hearing under a preliminary development plan application.
|
|
Corrective Action Required
PARKING LOT SETBACK. The parking lot on the north end of the lot shall be set back a minimum 6.5' from the north property line.
|
|
Corrective Action Required
TRASH ENCLOSURE. Provide a trash enclosure detail. The enclosure shall be constructed of masonry walls and a solid steel gate painted a color that is compatible with the enclosure walls and building it serves.
|
|
|
Traffic Review
|
No Comments
|
09/25/2018
|
09/25/2018
|
|
Mike Weisenborn
|
|
|
Engineering Review
|
Corrections
|
09/25/2018
|
09/25/2018
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
Please show the aggregate base extending a minimum of one (1) foot beyond the back of curb for the concrete-paved areas.
|
|
Corrective Action Required
An itemized and sealed Engineer's Estimate of Probable Construction Costs should accompany your final submittal drawings. The Engineering Plan Review and Inspection Fee is based on this estimate, and calculated at 3% of the total. Items to include in the estimate include: 1) storm lines greater than 6 inches in diameter, 2) storm structures, 3) sanitary sewer connection, 4) concrete paving and subgrade, 5) curb and gutter, 6) grading to establish proper drainage, 7) additional water lines greater than 2 inches, that were not shown on previous plans, and 8) erosion and sediment control/final restoration.
|
|
|
Fire Review
|
Approved with Conditions
|
09/25/2018
|
09/20/2018
|
|
Jim Eden
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code.
Standpipe connections are required in the stairwells.
|
|
Knox Locks
Corrective Action Required
IFC 506.1 - Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type listed in accordance with UL 1037, and shall contain keys to gain necessary access as required by the fire code official. 506.1.1 Locks. An approved lock shall be installed on gates or similar barriers when required by the fire code official.
A knox box shall be provided on the building over the FDC.
|
|
|