Summary
PL2016195
Bob Sight Quick Lane
Commercial Preliminary Development Plan
Commercial Preliminary Development Plan
Approved
10/21/2016
TRD REAL ESTATE LLC
Locations
Contacts
DAVIDSON ARCHITECTURE & ENGINEERING, Address:4301 INDIAN CREEK PKWY, Phone:(913) 451-9390  
DAVIDSON ARCHITECTURE & ENGINEERING, Address:4301 INDIAN CREEK PKWY, Phone:(913) 451-9390  
TRD REAL ESTATE LLC, Address:607 NW BLUE PARKWAY  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Approved with Conditions 12/06/2016 12/06/2016
Christina Stanton
DE C&O #01 Eng Plans – FDP/PDP
Corrective Action Required
12/06/2016

All required engineering plans and studies, including water lines, sanitary sewers, storm drainage, streets and erosion and sediment control shall be submitted along with the final development plan. All public infrastructure must be substantially complete, prior to the issuance of any certificates of occupancy.
DE C&O #03 Eng & Insp Fees
Corrective Action Required
12/06/2016

All Engineering Plan Review and Inspection Fees shall be paid prior to approval of the engineering plans and prior to the issuance of any infrastructure permits or the start of construction (excluding land disturbance permit).
DE C&O #06 Land Disturbance
Corrective Action Required
12/06/2016

A Land Disturbance Permit shall be obtained from the Public Works Department if ground breaking will take place prior to the issuance of an infrastructure permit or prior to the approval of the Final Development Plan / Engineering Plans.
DE C&O #11 Pavement Thickness
Corrective Action Required
12/06/2016

Private pavement sections shall either follow Article 12 of the UDO or Table LS-2 or LS-3 of the Design & Construction Manual for pavement thickness and base requirements.
DE C&O #12 Cut & Fill
Corrective Action Required
12/06/2016

Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
Planning Review No Comments 12/06/2016 12/06/2016
Christina Stanton
Traffic Review No Comments 12/06/2016 12/06/2016
Michael Park
Fire Review Approved with Conditions 12/06/2016 11/25/2016
Jim Eden
Code Statement
Corrective Action Required
11/25/2016

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code.
Engineering Review Corrections 11/04/2016 11/04/2016
Gene Williams, P.E.
Corrective Action Required
11/04/2016

The domestic water service is shown in a commercial driveway entrance. Please move the water service and meter outside of the driveway.
Corrective Action Required
11/04/2016

If interior fire hydrant(s) are needed, then these should be shown on a private fire line, with a backflow vault installed near the property line outside of any public easement, and on the private side.
Traffic Review No Comments 11/04/2016 11/03/2016
Michael Park
Fire Review Corrections 11/04/2016 10/31/2016
Jim Eden
Code Statement
Corrective Action Required
10/31/2016

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code (IFC). For information only. The quantity of stored new and used lubricants shall comply with the IFC Chapter 50 and 57.
Hydrants
Corrective Action Required
10/31/2016

IFC 507.5.1- Where a portion of the facility or building hereafter constructed or moved into or within the jurisdiction is more than 300 feet from a hydrant on a fire apparatus access road, as measured by an approved route around the exterior of the facility or building, on-site fire hydrants and mains shall be provided where required by the fire code official. Action required: Show the location of accessible hydrants. Action required: Show the location of an accessible hydrant.
Misc.
Corrective Action Required
10/31/2016

903.2.9.1 Repair garages. An automatic sprinkler system shall be provided throughout all buildings used as repair garages in accordance with Section 406.8 of the International Building Code, as shown: 1. Buildings having two or more stories above grade plane, including basements, with a fire area containing a repair garage exceeding 5,000 square feet . 2. Buildings no more than one story above grade plane, with a fire area containing a repair garage exceeding 5,000 square feet. 3. Buildings with repair garages servicing vehicles parked in basements. 4. A Group S-1 fire area used for the repair of commercial trucks or buses where the fire area exceeds 5,000 square feet (464 m2). Action required: The building is required to have an automatic sprinkler system.
FDC
Corrective Action Required
11/01/2016

IFC 903.3.7- Fire department connections. The location of fire department connections shall be approved by the fire code official. Connections shall be a 4 inch Storz type fitting and located within 100 feet of a fire hydrant, or as approved by the code official. Action required: Show the location of the FDC and provide a hyran.t
Planning Review Corrections 11/04/2016 10/26/2016
Christina Stanton
Corrective Action Required
10/26/2016

Lighting. All outdoor lighting shall utilize full cut-off lenses per Section 7.220.B of the UDO. In addtion, provide a photometric plan to show lighting location, height and uniformity ratio information as required per Sections 7.230 and 7.250.F of the UDO.
Corrective Action Required
10/26/2016

Signage. Call out the signage information for those signs located above the service bays. In addition, provide the materials and colors proposed for the monument sign.
Corrective Action Required
10/26/2016

Provide the percentage of metal panels proposed for the elevations.
Corrective Action Required
10/26/2016

Parking Lot Screening. Provide parking lot screening per Section 14.120 of the UDO.
Corrective Action Required
10/28/2016

Four-Sided Architecture. Vertical elements shall be incorporated into the east elevation to break up the expanse of wall.
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Commercial Preliminary Development Plan fee $1,800.00 $1,800.00 Paid 10/21/2016
9110076-Legal Notice Publishing Charge $165.00 $165.00 Paid 10/21/2016
9110076-Legal Notice Publishing Charge $165.00 $165.00 Paid 10/21/2016
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Planning Commission Meeting 12/13/2016 05:00 PM Council Chambers 12/13/2016 05:00 PM
Public Hearing Review
Approved
12/13/2016
City Council Ordinance 01/05/2017 06:15 PM Council Chambers 01/05/2017 06:15 PM
Public Hearing Review
Pending
01/05/2017
Documents & Images
Date Uploaded File Type Document Name
10/21/2016 Receipt Receipt for transaction: 2016-006517
10/21/2016 Letter Routing Sheet
11/07/2016 Letter Applicant Letter - Dev. Apps (DRCP)
11/21/2016 Letter Resubmittal Routing Sheet
12/06/2016 Letter PL2016195 Bob Sight Quick Lane TIA
12/07/2016 Plans 16192 A1-1-A1.1
12/07/2016 Plans 16192 A1-1-L1.1
12/07/2016 Plans 16192 A2-1-A3.1
12/07/2016 Plans 16192C1-C1.1 Site Plan
12/07/2016 Plans 16192C1-C1.2 Utility Plan
12/07/2016 Plans 16192C1-C1.3 Demo Plan
12/07/2016 Plans 16192C2-C2.1 Grading & Erosion
12/07/2016 Plans Bob Sight PDP response letter
12/07/2016 Plans Bob Sight Quick Lane Lighting 33 degrees
12/07/2016 Plans Bob Sight Quick Lane Lighting AGi32
01/06/2017 Ordinance PL2016-195 PDP Bob Sight Quick Lane
01/10/2017 Ordinance ORDINANCE #8065
01/15/2017 Letter Applicant Letter - Dev. Apps (DRCP)
03/29/2018 Email Withdrawn Email
09/10/2019 Bob Sight Quick Lane
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home