Review Type |
Outcome |
Est. Completion Date |
Completed |
Fire Review
|
Approved with Conditions
|
07/07/2014
|
07/08/2014
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
Fire Department- All building and life safety issues shall comply with the 2012 International Fire Code and local amendments as adopted by the City of Lee’s Summit.
|
|
|
Traffic Review
|
No Comments
|
07/07/2014
|
07/07/2014
|
|
Michael Park
|
|
|
Planning Review
|
No Comments
|
07/07/2014
|
07/03/2014
|
|
Hector Soto Jr.
|
|
|
Engineering Review
|
Approved with Conditions
|
07/07/2014
|
06/30/2014
|
|
Gene Williams, P.E.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Public Works Review and Inspection Fee of $58,238.80 (which is based on 3% of the total infrastructure cost plus a water test inspection fee) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit from the Codes Administration Department.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Contact Public Works Inspections at (816) 969-1800 at least 48 hours prior to the onset of construction.
|
|
DE Contact ROW Inspector
Corrective Action Required
Contact a Right-of-Way Inspector at (816) 969-1800 prior to any land disturbance within the right-of-way. These activities may require a permit.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
PW Public Improvements TIFF CD's (DELETE)
Corrective Action Required
Any public improvements will require two (2) CD ROMs with the plans in TIFF format.
|
|
PW Submit Land Disturbance (DELETE)
Corrective Action Required
Submit a Land Disturbance Permit application and the required attachments to the Erosion Control Specialist prior to any land disturbance activities that are to occur prior to obtaining a building permit from the Codes Administration Department. Approval of these plans does not constitute approval of the erosion control plan. Contact Barton Reese at (816) 969-1800 for new land disturbance permitting details.
|
|
Corrective Action Required
Please be aware that the City will not provide the water meter vault as indicated on the plans. This vault will need to be designed and supplied by the applicant.
|
|
|
Planning Review
|
Corrections
|
06/06/2014
|
06/06/2014
|
|
Hector Soto Jr.
|
|
Corrective Action Required
TRASH ENCLOSURE DOORS. Cedar planks are shown on the enclosure detail on Sheet A6.01. Wood is not an allowed material for this purpose. Trash enclosure doors shall be solid steel painted to be compatible with the enclosure walls and buildings it is to serve. This comment was made on the original submittal, but a revised plan sheet was not resubmitted. Provide a plan sheet showing the required revision.
This is the same comment from the previous staff review letter dated 5/20/14. The response letter from RIC dated 5/28/2014 stated that this comment would be addressed under separate cover from the architect. No revised plans have been submitted to date.
|
|
|
Fire Review
|
Approved with Conditions
|
06/06/2014
|
06/05/2014
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
Fire Department- All building and life safety issues shall comply with the 2012 International Fire Code and local amendments as adopted by the City of Lee’s Summit.
|
|
Imposed Loads
Corrective Action Required
Fire Department- IFC 503.2.3 Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
|
|
|
Engineering Review
|
Corrections
|
06/06/2014
|
06/05/2014
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
Please refer to Engineering Review comment #7 dated May 20, 2014. Fire access lanes require an additional one (1) inch of base course as specified in the Unified Development Ordinance Article 12. In addition, the locations of the the fire access lanes were not shown. A report dated May 28, 2014 from Ian Dillon, P.E. at Ollson Associates stated that "our pavement design for the New Longview Apartements project consists of 7 inches of asphaltic pavement over 12 inches of reconditioned subgrade." As discussed previously, Public Works will only consider a pavement design if it can be demonstrated that it will meet or exceed the requirements contained within the Unified Development Ordinance Article 12. The report does not appear to meet this requirement.
|
|
Corrective Action Required
A revised Engineer's Estimate of Probable Construction Costs should be provided which includes the thicker asphatlic concrete pavement required by the Unified Development Ordinance Article 12.
|
|
|
Traffic Review
|
No Comments
|
06/06/2014
|
06/03/2014
|
|
Michael Park
|
|
|
Fire Review
|
Approved with Conditions
|
05/19/2014
|
05/27/2014
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
Fire Department- All building and life safety issues shall comply with the 2012 International Fire Code and local amendments as adopted by the City of Lee’s Summit.
|
|
Sprinkler System
Fire Department- An automatic fire sprinkler (suppression) system is required in accordance with the 2012 International Fire Code.
903.2.1.2 Group A-2.
An automatic sprinkler system shall be provided for Group A-2 occupancies where one of the following conditions exists:
1.The fire area exceeds 5,000 square feet (464 m2).
2.The fire area has an occupant load of 100 or more.
3.The fire area is located on a floor other than a level of exit discharge serving such occupancies.
Based on review of the building permit plans and discussion by the reviewer with the project architect , the indicated use of the clubhouse includes banquets/parties with an occupant load of greater than 100. The building shall be provided with an automatic fire sprinkler system and appurtenances such as, FDC, fire main, alarm notification ,and a fire hydrant within 100 feet of the FDC.
May 27, 2014 Per Brad Haymond with Northpoint, The entire space is not rented out or leased for special events such as banquets or parties. The space meets the requirements of a Group A3 Occupancy and a sprinkler system will not be required as part of this project.
|
|
Imposed Loads
Corrective Action Required
Fire Department- IFC 503.2.3 Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
|
|
|
Fire Review
|
Corrections
|
04/23/2014
|
05/27/2014
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
Fire Department- All building and life safety issues shall comply with the 2012 International Fire Code and local amendments as adopted by the City of Lee’s Summit.
|
|
Misc.
There have not been any changes on the FDP addressing comments from the PDP. I recommend scheduling a meeting to go over the corrections that need to be made on the project.
|
|
FDC's
Fire Department- A fire hydrant shall be located within 100 feet of the fire department connection (FDC).
The FDC's shall be located on the fronts of the building next to fire department access lanes. Typically there is only one FDC per building. Please indicate the number and locations of sprinkler rooms and fire mains to each of the buildings.
|
|
Water Flow
Fire Department- IFC 507.1 An approved water supply capable of supplying the required fire flow for fire protection shall be provided to premises upon which facilities, buildings or portions of buildings are hereafter constructed or moved into or within the jurisdiction.
Water mains shall be sized and connected to a public water supply to provide water flow requirements in accordance with IFC Table B105.1.
Provide fire flow calculations for the single connection main provided for the project.
|
|
Marking
Fire Department- IFC 505.3 Where required by the fire code official, approved signs or other approved notices shall be provided for fire apparatus access roads to identify such roads or prohibit the obstruction thereof. Signs or notices shall be maintained in a clean and legible condition at all times and be replaced or repaired when necessary to provide adequate visibility.
Fire lanes and required access to hydrants and FDC's shall be marked.
|
|
Knox Box
Corrective Action Required
Fire Department- IFC 506.1 Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. An approved lock shall be installed on gates or similar barriers when required by the fire code official.
A Knox Box shall be provided for each building.
|
|
Imposed Loads
Corrective Action Required
Fire Department- IFC 503.2.3 Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
|
|
Hydrants
Provide a hydrant along the fire access lane between Buildings 5 and 6 to maintain average spacing as intended by IFC Table C105.1.
|
|
Misc.
Corrective Action Required
D105.2 Width. Aerial fire apparatus access roads shall have a minimum unobstructed width of 26 feet (7925 mm), exclusive of shoulders, in the immediate vicinity of the building or portion thereof.ty gates in accordance with Section 503.6, and an unobstructed vertical clearance of not less than 13 feet 6 inches (4115 mm).
Fire lanes parallel to the buildings shall have a driveable surface of 26 feet. The drawings are including the sidewalk in front of the buildings. Provide clarification.
|
|
|
Planning Review
|
Corrections
|
05/19/2014
|
05/20/2014
|
|
Hector Soto Jr.
|
|
Corrective Action Required
TRASH ENCLOSURE DOORS. Cedar planks are shown on the enclosure detail on Sheet A6.01. Wood is not an allowed material for this purpose. Trash enclosure doors shall be solid steel painted to be compatible with the enclosure walls and buildings it is to serve. This comment was made on the original submittal, but a revised plan sheet was not resubmitted. Provide a plan sheet showing the required revision.
|
|
Corrective Action Required
LIGHT FIXTURES. All exterior light fixtures shall have full cut-offs so as to direct light downward and so the light source is not visible from off the property. The proposed fixture called out as "SL1" does not meet the full cut-off requirement. This comment was made on the original submittal, but a revised plan sheet was not resubmitted. Provide a copy of plan sheets (ME2.01 and ME2.02) showing the required revision.
|
|
|
Engineering Review
|
Corrections
|
05/19/2014
|
05/19/2014
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
Sheet C3: The existing fire hydrant located at the NW Kessler Dr. entrance is labeled as "relocate hydrant clear of sidewalk if necessary". This fire hydrant and valve are within the limits of the sidewalk/ADA-accessible ramp and will need to be moved. Please show their new locations, including the valve and fire hydrant. Ensure they are within the right of way or an easement. If this is not possible, a separate easement may be dedicated by a separate document.
|
|
Corrective Action Required
Sheet C13: The same comment as discussed above (i.e., Engineering comment #1) applies to this sheet. Please revise as appropriate. The valve should also be moved clear of the sidewalk.
|
|
Corrective Action Required
Sheet C13: What is the plan for the existing junction box near the entrance at NW Kessler Dr.? Please keep in mind that the maximum cross slope across the driveway at this entrance is 2.0%, and it is doubtful that this junction box can remain "as-is" without modification.
|
|
Corrective Action Required
Sheet C14: Please see comment #3 above concerning the modification of the existing junction box. Please describe the work to be done on this sheet.
|
|
Corrective Action Required
Sheet C14: Is there a junction box at the northeast entrance to Kessler Dr.? The same comment that applies to the junction box to the west applies to this additional junction box. It is likely this box will need to be relocated out of the ADA-accessible ramp, and the elevation will need to be adjusted as appropriate. Please note what will be done at this location.
|
|
Corrective Action Required
Sheet C14: There are instances where it appears the domestic water service is connected to the fire line. To reduce the likelihood of this occurring, please provide a separate domestic water line plan as Sheet C14a (or equivalent), and remove the domestic water service from Sheet C14. Alternatively, you may use a different lineweight to distinguish between the two.
|
|
Corrective Action Required
Fire access lanes are subject to a different requirement for pavement thickness than drive aisles and parking stalls. The difference is that fire access lanes require a 6 inch base course rather than a 5 inch base course (i.e., for a total of 8" of asphaltic concrete pavement on a prepared subgrade). Please change the detail accordingly, and please show the locations of fire access lanes on the site layout plan.
|
|
Corrective Action Required
Engineer's Estimate of Probable Construction Costs dated 5/6/2014: A vault was missing from the 8" backflow preventor assembly. Typically, the estimated costs for this item based on previous projects has been between $7,500 and $10,000. The fire hydrant unit price was low based on previous projects. The paving subgrade preparation work item did not appear to include the area beneath the curb and gutter and one (1) foot beyond the back of curb. A separate unit price should be included for the fire lane access (i.e., the 8" asphaltic concrete pavement section). Finally, junction box modifications were not included.
|
|
|
Traffic Review
|
No Comments
|
05/19/2014
|
05/16/2014
|
|
Michael Park
|
|
|
Planning Review
|
Corrections
|
04/23/2014
|
04/24/2014
|
|
Hector Soto Jr.
|
|
Corrective Action Required
STREET NAME. Longview Blvd is mis-identified as View High Drive on Sheets C1 and C2.
|
|
Corrective Action Required
INTERNAL SIDEWALK. The plans do not reflect the extention of a sidewalk to the detention pond to provide access for its use a passive recreation area.
|
|
Corrective Action Required
PAVEMENT. Parking lot pavement shall be designed to meet the minimum design standards under Section 12.120.F of the UDO.
|
|
Corrective Action Required
ACCESSIBLE PARKING SIGNS.
- The plans show all accessible parking spaces being marked with a painted symbol on the pavement. But it isn't clear that they will all be posted with signage. Every accessible parking space shall be identified by a sign, mounted on a pole or other structure, located between 36 inches and 60 inches above the ground, measured to the bottom of the sign.
- Specify accessible parking sign type R7-8 (white background, green text and blue wheelchair symbol) on the detail on Sheet C33.
|
|
Corrective Action Required
TRASH ENCLOSURE DOORS. Cedar planks are shown on the enclosure detail on Sheet A6.01. Wood is not an allowed material for this purpose. Trash enclosure doors shall be solid steel painted to be compatible with the enclosure walls and buildings it is to serve.
|
|
Corrective Action Required
LANDSCAPE PLAN. Provide a count of each of the proposed planting material species listed on Sheets L1 and L2.
|
|
Corrective Action Required
LIGHT FIXTURES. All exterior light fixtures shall have full cut-offs so as to direct light downward and so the light source is not visible from off the property. The proposed fixture called out as "SL1" does not meet the full cut-off requirement.
|
|
|
Engineering Review
|
Corrections
|
04/23/2014
|
04/24/2014
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
Cover Sheet: General Note 1 should be revised to read "...all construction shall follow the City of Lee' Summit Design and Construction Manual as adopted by Ordinance 5813. Where discrepancies exist between the Final Development Plan and the Design and Construction Manual, the Design and Construction Manual shall govern."
|
|
Corrective Action Required
Sheet C2: The legend in the upper right hand side of the sheet references various pavement types, but the plan view does not show any of these proposed pavement types. Please revise to show these pavement types. Please be aware that parking aisles and drive aisles are considered the same for purposes of the Unified Development Ordinance (UDO) Chapter 12 pavement requirements. The only difference in pavement thickness as shown in the UDO Chapter 12 would be for fire access lanes (which were also not shown on the general layout view).
|
|
Corrective Action Required
Sheet C2: View High Drive is mislabeled. This should be labeled as "SW Longview Blvd."
|
|
Corrective Action Required
Sheet C2: All driveway entrances must be constructed with KCMMB concrete mix from the edge of the existing pavement to the right of way line. Please label accordingly.
|
|
Corrective Action Required
Sheet C2: The locations of existing fire hydrants along Kessler Drive are difficult to see. Please clearly show the locations of the fire hydrants by enlarging the symbols.
|
|
Corrective Action Required
Sheet C2: The water lines along Kessler Drive are only partially shown. Please provide the locations of the water lines along Kessler Drive, including water line on the north side of Kessler Drive and the water lines serving the fire hydrants on the south side of Kessler Drive.
|
|
Corrective Action Required
Sheet C3: Sidewalk widths should be noted.
|
|
Corrective Action Required
Sheet C8: It appears the detention basin is being enlarged and will no longer fit within the boundary of the detention basin tract. Is there a way to enlarge the basin without adding to the existing footprint? Would a retaining wall along the east side of the basin be possible?
|
|
Corrective Action Required
Sheet C14: There appears to be a discrepancy in the location of the existing water line on Kessler Drive. In addition, there appear to be existing public fire hydrants on the south side of Kessler Drive which are difficult to see. Please show the entire length of the existing water line and size along Kessler Drive, and also show the existing crossings feeding the existing fire hydrants.
|
|
Corrective Action Required
Sheet C14: The interior water lines are shown, but it is not clear which one is the fire line, and which one is the domestic water line. For instance, there is a domestic water service line feeding the clubhouse which appears to be connected to a fire line. This is prohibited. These lines cannot be connected together in any fashion since the domestic water line should only be connected to the 3" meter, and they should be clearly labeled to avoid any confusion.
|
|
Corrective Action Required
Sheet C14: All interior water service, fire lines, sanitary sewers, and stormwater structures and lines should be clearly labeled with the word "PRIVATE".
|
|
Corrective Action Required
Sheet C14: The backflow vault and backflow assembly which serves the private fire line is shown connecting to the existing water line within the intersection of Kessler Drive and SW Tower Park Drive. This is not allowed since it will involve removal and repair of pavement within the right of way. Rather than changing the geometry of this connection point and boring under the street, the fire line could be connected to the existing public water main which serves the existing public fire hydrant on Kessler Drive. A tee should be shown cut into the water line prior to the valve serving the fire hydrant, and a valve should be shown prior to the backflow vault. This valve would denote the end of the public water line.
|
|
Corrective Action Required
Sheet C14: Sizes of all waterlines and sanitary sewer lines should be shown.
|
|
Corrective Action Required
Sheet C17: It appears that a k factor of 1.25 for the 1% annual chance event is shown, but 1.15 was actually used in the calculations. This is based on a spot check of several calculations within the table. Please check all calculations and perform a re-design as necessary.
|
|
Corrective Action Required
Sheet C18: It appears that the profile view of Junction Box A12 should be labeled as A13. Please check and revise as appropriate.
|
|
Corrective Action Required
Sheet C18: Please call out the toe wall section at the end of the flared end section. This should be shown on all sheets where a flared end section is specified. Please include a toe wall detail on the detail sheets.
|
|
Corrective Action Required
All stormwater sheets: Please clarify the stormwater system as "PRIVATE" either by a label, or revision to the title of the sheet.
|
|
Corrective Action Required
Sanitary sewer plan and profile sheets: Please clarify that the system is private either by using labels or revising the title of the sheet.
|
|
Corrective Action Required
Sheet C29: The existing detention basin is not a sediment basin. Please correct by using the word "existing detention basin."
|
|
Corrective Action Required
Sheet C30: Silt fence is shown, but it is difficult to determine where it will be placed. Please show the silt fence with a darker lineweight, and/or show the development in the background as a lighter lineweight to distinguish the silt fence from other features.
|
|
Corrective Action Required
Sheet C30: Since the detention area is being proposed for a temporary sediment basin, details concerning the temporary outlet structure should be provided. The detention basin should also be labeled as "temporary sediment basin."
|
|
Corrective Action Required
Sheet C30: In general, silt fence should be installed along contour lines, with the ends curled upward. This does not appear to be shown.
|
|
Corrective Action Required
Sheet C31: Please include notes concerning the removal of silt fence, the removal of inlet protection, the removal of silt within the temporary sediment basin, and the removal of the temporary outlet structure.
|
|
Corrective Action Required
Sheet C32: Typical pavement sections do not appear to follow the Unified Development Ordinance (UDO) Article 12. Please see UDO Article 12 for specific requirements. Please note that parking aisles and drive aisles are treated the same for purposes of pavement design.
|
|
Corrective Action Required
Sheet C32: A detail should be provided for the temporary sediment basin outlet structure.
|
|
Corrective Action Required
Sheet C32: The driveway detail should be corrected to show 8" of KCMMB mix concrete.
|
|
Corrective Action Required
Sheet C32: Please remove the "Sidewalk Ramp Details" from the sheet. This detail is no longer used. It will be sufficient to note the general location and general geometry of the ADA-accessible ramp(s) on the Final Development Plan where needed. Please note that the use of truncated domes or other tactile warning devices are not allowed on private entrances.
|
|
Corrective Action Required
Please note that Planning and Codes Administration will require a retaining wall design by a registered engineer in the State of Missouri.
|
|
Corrective Action Required
Please note that geogrid, footings, or other elements of the retaining wall(s) cannot encroach into the right of way or public easements.
|
|
Corrective Action Required
Sheet C35: A "Concrete Low Flow Channel" detail is shown, but it is not clear where this is being proposed. Please note the City does not allow concrete-lined low flow channels within detention basins or swales.
|
|
Corrective Action Required
Sheet C39: The sediment fence detail shows the old method of trench and fill for silt fence. The City requires the use of machine-laid silt fence. Please remove this detail from the Final Development Plan. It will be sufficient to reference the use of machine-laid silt fence on the plan view.
|
|
Corrective Action Required
Sheet C39: Straw bales are not allowed in the City of Lee's Summit, and hence this detail should be removed.
|
|
Corrective Action Required
Sheet C2: Please note where the sidewalks will be constructed along Longview Road from the roundabout to the west. The entire sidewalk must be constructed as part of the Final Development Plan.
|
|
Corrective Action Required
An applicant meeting is recommended since it appears there are several items which might be better to discuss in person.
|
|
Corrective Action Required
A sealed Engineer's Estimate of Probable Construction Costs should accompany your final submittal drawings. The Engineering Plan Review and Inspection Fee is based on this estimate, and is calculated at 3% of the total construction cost plus a nominal water sample collection and observation fee of $100 per sample. Items to include in the itemized estimate include: 1) storm sewer lines and structures, 2) sanitary sewer lines and structures, 3) waterlines, 4) paving and subgrade preparation, 5) curb and gutter, 6) public sidewalks, 7) subgrade preparation beneath curb and gutter, 8) grading to establish proper drainage, 9) grading for parking lot and driveways, 10) driveway approaches, 11) fire hydrants, 12) backflow vault and backflow assembly, 13) valves, tees, fittings, and thrust blocks, 14) ADA-accessible ramps, 15) detention basins, 16) erosion and sediment control including final restoration, and 17) all other site work necessary to complete the project.
|
|
|
Traffic Review
|
Corrections
|
04/23/2014
|
04/14/2014
|
|
Michael Park
|
|
Corrective Action Required
Can the four parking spaces on the north side of the West Longview Road Drive Entrance be moved towards the east about 4' to align with the parking spaces on the south side of the same driveway/isle?
|
|
Corrective Action Required
Why is the South Longview Road Drive Entrance offset approx. 5' from Ovation? These intersections should align.
|
|
Corrective Action Required
Could a sidewalk connection between the sidewalk along the east property line and the east-facing buildings/development be provided? Or at least a sidewalk connection of the eastern parking lot area to the buildings be provided to give residents an option to access the building areas from afar parking without having to use the parking lot and drive isles as pedestrian routes? Recommend sidewalk from the east property line sidewalk to Building 4 along one side of the drive isle where the "future" connection is shown to the east.
|
|
Corrective Action Required
Could bike racks be included on-site for residents? A bike rack near each building and adjacent to the clubhouse is recommended.
|
|
Corrective Action Required
Sidewalk connecting Buildings 2 & 5 to Buildings 3 & 6 (as well as the common area east of Buildings 3 & 6) is recommended; perhaps through the island areas centered between all four of the aforementioned buildings.
|
|
Corrective Action Required
The portion of asphalt path along the South Longview Road Driveway Access within City right-of-way should be concrete and ADA compliant.
|
|
Corrective Action Required
Recommend the installation of stop signs at each driveway approach to the public roadway (Kessler and Longview).
|
|
|