Permit Application Status

PRSUBD20251122


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSUBD20251122
Public Infrastructure
In Plan Review
TRAILS OF PARK RIDGE LLC
DEVELOPMENT COMPLETE
Storm Sewer Replacement
03/27/2025
Locations
Contacts
TRAILS OF PARK RIDGE LLC, Address:3170 NE CARNEGIE DR STE 400  
Matthew J Schlicht, Address:50 SE 30th Street, Phone:(816) 623-9888  
  
  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review - Street and Storm Approved with Conditions 04/10/2025 04/07/2025
Sue Pyles, P.E.
DE Contact Field Eng. Inspector
Corrective Action Required
04/04/2025

Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
DE Engineers Estimate
Corrective Action Required
04/04/2025

.The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee of $198.07 (which is based on 3% of the total infrastructure cost) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permitThe Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $xxx.xx
Fees
Paid Fees Amount Paid Owing Date Paid
None $0.00 $0.00 $0.00
Outstanding Fees Amount Paid Owing Date Paid
9110081-Paved Surface Inspection Fee $28.50 $0.00 $28.50 Not Paid
9110068-Storm Fee $171.07 $0.00 $171.07 Not Paid


$199.57    Add Fees to My Cart
Inspections

There are no inspections for this permit application.

Documents & Images
Date Uploaded File Type Document Name
03/27/2025 Plans Storm Sewer Plans_Rev0_PRSUBD20251122
04/02/2025 Plans Storm Sewer Plans_Rev1_PRSUBD20251122
04/04/2025 Approved Plans APPROVED - Trails of Park Ridge 2nd Plat
04/07/2025 Engineers Estimate Cost Estimate
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home