Permit Application Status

PRSUBD20225624


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSUBD20225624
Public Infrastructure
Substantial Completion
HFI 463 WARD LLC
DEVELOPMENT COMPLETE
WHATABURGER M150 - PUBLIC WATER
11/08/2022
09/01/2023
Locations
Contacts
HFI 463 WARD LLC, Address:463 SW WARD RD  
PINNACLE CONSTRUCTION GROUP LLC, Address:8355 MELROSE DR, Phone:(816) 412-5855  
HFI WHATA LLC, Address:1401 N MADISON ST  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 05/08/2023 08/30/2023
Dawn Bell
Fees
Paid Fees Amount Paid Owing Date Paid
91100C9-Water Insp Fee $1,415.55 $1,415.55 Paid 11/28/2022
9110072-Water Test Fee $400.00 $400.00 Paid 11/28/2022
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 11/28/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Punch List Inspection Pending 5/7/2024
Site Visit Partial 12/19/2023
Misc
Informational
12/05/2023
12-5-23 Dustin A, No activity today for us at this time. 12-19-23 Dustin A, Sewer pipe has been dropped off. Depending on the weather this week , they may start on service line depending on delivery of there grease trap. 12-21-23 Dustin A, Scheduled a partial sewer on service. 12-21-23 Dutch recalled and canceled inspection due to the contractor not being ready. 1-17-24 Dustin A, No activity today . Contractor thought about starting storm, but must have decided not to . when went back by there was not outside contractor on site . 1-18-24 Dustin A, Conditions have not changed, nobody is performing work for our department.
Water Line - Construction Inspection Partial 02/08/2024
Misc
Informational
02/08/2024
2-8-24 Dustin A, Started doing the street crossing on hollywood and summit crest.
Water Line - Construction Inspection Partial 02/16/2024
Misc
Informational
02/16/2024
2-8-24 Dustin A, Water is installed in hollywood, flowable fill is installed with concrete cap. 2-15-24 Dustin A, The T on hollywood was installed as well as the t for the hydrant.
Water Line - Hydrostatic Test Passed 2/26/2024 2/26/2024 02/26/2024
Misc
Informational
02/26/2024
2-26-24 Dustin A. Hydrostatic passed
Water Line - Construction Inspection Partial 02/26/2024
Misc
Informational
02/16/2024
2-8-24 Dustin A, Water is installed in hollywood, flowable fill is installed with concrete cap. 2-15-24 Dustin A, The T on hollywood was installed as well as the t for the hydrant. 2-22-24 Dustin A, Water line extension is ran to bout 10 ft from existing. Ready for hydrostatic and chlorine test. 3-12-24 Dustin A, Meter pit was installed . Poly was ran from building
Water Line - Coliform Test 1 Passed 03/11/2024
Misc
Informational
03/11/2024
2-28-24 Dustin A, passed
Water Line - Coliform Test 2 Passed 03/11/2024
Misc
Informational
03/11/2024
3-1-24 Dustin A, Passed
Water Line - Coliform Test 2 Passed 03/11/2024
Water Line - Construction Taps Removed Passed 03/11/2024
Misc
Informational
03/11/2024
3-11-24 Dustin A, Passed
Erosion Control Inspection Passed 06/19/2024
Misc
Informational
06/19/2024
6-19-24 Dustin A, freshly graded , waiting for sod\seed
Grading/Excavation/Fill Inspection Passed 7/3/2024 7/3/2024 07/03/2024
Water Line - Construction Inspection Passed 07/03/2024
Misc
Informational
02/26/2024
2-8-24 Dustin A, Water is installed in hollywood, flowable fill is installed with concrete cap. 2-15-24 Dustin A, The T on hollywood was installed as well as the t for the hydrant. 2-22-24 Dustin A, Water line extension is ran to bout 10 ft from existing. Ready for hydrostatic and chlorine test.
Site Visit Complete 07/03/2024
Misc
Informational
12/19/2023
12-5-23 Dustin A, No activity today for us at this time. 12-19-23 Dustin A, Sewer pipe has been dropped off. Depending on the weather this week , they may start on service line depending on delivery of there grease trap. 12-28-23 Dustin A, No Activity for our dept . 1-16-24 Dustin A, No activity due to weather
Water Line - Hydrostatic Test Passed 07/03/2024
Water Line - Coliform Test 1 Passed 07/03/2024
Water Line - Coliform Test 2 Passed 07/03/2024
Documents & Images
Date Uploaded File Type Document Name
11/28/2022 Receipt Receipt for transaction:2022-009163
12/01/2022 Approved Plans Whataburger Public Water Plans Approved 12 01 22
09/01/2023 Letter DE-Permit
12/19/2023 Letter INSPECTION SUMMARY
12/21/2023 Letter INSPECTION SUMMARY
02/08/2024 Letter INSPECTION SUMMARY
02/16/2024 Letter INSPECTION SUMMARY
02/26/2024 Letter INSPECTION SUMMARY
02/26/2024 Letter INSPECTION SUMMARY
03/01/2024 WO#3HB0107 - City of Lees Summit
03/04/2024 Whataburger passed 2nd sample
03/11/2024 const tap plug
03/11/2024 Letter INSPECTION SUMMARY
03/11/2024 Letter INSPECTION SUMMARY
03/11/2024 Letter INSPECTION SUMMARY
03/11/2024 Letter INSPECTION SUMMARY
03/14/2024 Letter INSPECTION SUMMARY
05/07/2024 Letter DE-Certificate of Substantial Completion Single Lot
05/07/2024 Letter DE-Punch List
06/19/2024 Letter INSPECTION SUMMARY
06/19/2024 Letter INSPECTION SUMMARY
07/03/2024 Letter INSPECTION SUMMARY
07/03/2024 Letter INSPECTION SUMMARY
07/03/2024 Letter INSPECTION SUMMARY
07/03/2024 Letter INSPECTION SUMMARY
07/03/2024 Letter INSPECTION SUMMARY
03/18/2025 Affidavit
04/15/2025 Security Document Maintance Bond
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.