Summary


PRSUBD20222088
Public Infrastructure
Issued
CLAYTON PROPERTIES GROUP, INC
DEVELOPMENT COMPLETE
RETREAT AT BAILEY FARMS 1ST PLAT - FULL PUBLIC INFRUSTURE DEVELOPMENT FOR RETREAT AT BAILEY FARMS 1ST PLAT
05/16/2022
01/19/2024
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
SCHLAGEL & ASSOCIATES, Address:14920 W 107TH ST, Phone:(913) 492-5158  
EMERY SAPP AND SONS INC, Address:2301 I-70 DR NW, Phone:(573) 445-8331  
Anthony Nosbush, Address:140 Walnut, Ste 101  
DOMAIN TIMBERLAKE MULTISTATE LLC, Address:590 MADISON AVE FL 13TH  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 05/16/2022 01/19/2024
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $6,649.59 $6,649.59 Paid 12/15/2023
91100C9-Water Insp Fee $4,082.52 $4,082.52 Paid 12/15/2023
9110072-Water Test Fee $800.00 $800.00 Paid 12/15/2023
9110068-Storm Fee $3,833.28 $3,833.28 Paid 12/15/2023
9110081-Street Inspections $5,355.52 $5,355.52 Paid 12/15/2023
9110071-Site Grading Fee $3,944.09 $3,944.09 Paid 12/15/2023
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 12/15/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Grading/Excavation/Fill Inspection Pending
Sanitary - Material Verification Pending
Install Street and Stop Signs Pending
Pavement-Aggregate Base Pending
Pavement-Stabilized Subgrade Pending
Sanitary Sewer Construction Inspection Pending
Misc
Informational
08/07/2024
7-29-24 BR Contractor (ESS) installed 110' of 8'' PVC pipe heading to MH K-4. 08-06-24 Tuesday JMJ Continued with installation of 8" SDR-26 PVC pipe. Approximately 145' and 6 laterals 4" PVC around 40' to 45'. Contractor poured 4 ditch checks on K line. 08-07-24 Wednesday JMJ Contractor set MH K-6 and poured inverts K-3, & K-4. Contractor backfilled and grade sanitary main and structure.
Sanitary Sewer - Vacuum Pending
Misc
Informational
09/27/2024
9-27-24 BR Contactor (ESS) test MH K-3, MH K-4, MH K-5, MH M-1, MH K-7 passed MH K-6 failed.
Water Line - Construction Inspection Pending
Misc
Informational
09/30/2024
9-30-24 BR Contractor (ESS) installed 300' of 8'' water main line 8 from Sta. 1+50 - Sta. 4+26
Water Line - Coliform Test 1 Pending
Pavement-Curb Construction Pending
Misc
Informational
10/25/2024
10-25-24 BR Contractor poured concrete curbs on SE Vantage Point Dr., SE Windbreak Dr.
Pavement-Surface Pending
Misc
Informational
11/12/2024
11-12-24 BR Contractor installed 5'' of KCMMB A-3 asphalt base on Windbreak Dr. & SE Vantage Point Dr. with 3rd party inspector (Ideker Inc.) getting 94 - 96 compaction.
Sanitary Sewer - Air Test Pending
Sanitary Sewer - Mandrel Pending
Sanitary Sewer - Vacuum Pending
Sanitary Sewer - Air Test Pending
Sanitary Sewer - Mandrel Pending
Sanitary Sewer - Vacuum Pending
Sanitary Sewer - Air Test Pending
Sanitary Sewer - Mandrel Pending
Sanitary Sewer - Vacuum Pending
Sanitary Sewer - Air Test Pending
Sanitary Sewer - Mandrel Pending
Sanitary Sewer - Vacuum Pending
Water Line - Hydrostatic Test Pending
Erosion Control Inspection Pending
Misc
Informational
03/04/2025
1-26-25 BR Erosion control is up and working order. 2-4-25 BR Erosion control is up and working order. 2-20-25 BR Erosion control is up and working order. 3-4-25 BR Erosion control is up and working order.
Sanitary Sewer - Air Test Passed 09/10/2024
Misc
Informational
09/10/2024
09/09/24 Monday JMJ air test passed B12-B13.
Sanitary Sewer - Mandrel Passed 9/25/2024 9/25/2024 09/25/2024
Misc
Informational
09/25/2024
9-25-24 BR Contractor (ESS) preformed mandrel test on MH M-1 to MH K-5, MH K-5 to MH K-6, MH K-6 to MH K-7, MH K-5 to MH K-4, MH K-4 to MH K-3 pass
Sanitary Sewer - Air Test Passed 9/27/2024 9/27/2024 09/27/2024
Misc
Informational
09/27/2024
9-27-24 BR Contractor (ESS) tested MH K-7 to MH K-6, MH K-6 to MH K-5, MH K-5 to MH M-1, MH K-5 to MH K-4, MH K-4 to MH K-3 pass
Water Line - Hydrostatic Test Passed 10/17/2024 10/17/2024 10/17/2024
Misc
Informational
10/17/2024
10-17-24 BR Contractor (ESS) preformed a hydrostatic test on 8'' water main at 150 psi.
Sanitary Sewer - Vacuum Passed 10/17/2024 10/17/2024 10/17/2024
Misc
Informational
09/27/2024
9-27-24 BR Contactor (ESS) test MH K-3, MH K-4, MH K-5, MH M-1, MH K-7 passed MH K-6 failed. 10-17-24 BR Contractor (ESS) test MH K-6 pass.
Pavement-Surface Partial 11/12/2024 11/12/2024 11/12/2024
Misc
Informational
11/12/2024
11-12-24 BR Contractor installed 5'' of KCMMB A-3 asphalt base on Windbreak Dr. & SE Vantage Point Dr. with 3rd party inspector (Ideker Inc.) getting 94 - 96 compaction.
Pavement-Proof Roll Passed 11/8/2024 11/8/2024 11/12/2024
Misc
Informational
11/12/2024
11-8-24 BR Contractor preformed a poof roll on Windbreak Dr. & SE Vantage Point Dr.
Pavement-Curb Construction Passed 10/28/2024 10/28/2024 12/04/2024
Misc
Informational
10/25/2024
10-25-24 BR Contractor poured concrete curbs on SE Vantage Point Dr., SE Windbreak Dr. 10-28-24 BR Contractor have to correct several storm boxes before pouring more concrete do to storm boxes are to high and need to be cut down to meet curb level. 12-3-24 BR All curb and gutters installed.
Sanitary Sewer Construction Inspection Passed 11/25/2024 11/25/2024 12/04/2024
Misc
Informational
08/07/2024
7-29-24 BR Contractor (ESS) installed 110' of 8'' PVC pipe heading to MH K-4. 08-06-24 Tuesday JMJ Continued with installation of 8" SDR-26 PVC pipe. Approximately 145' and 6 laterals 4" PVC around 40' to 45'. Contractor poured 4 ditch checks on K line. 08-07-24 Wednesday JMJ Contractor set MH K-6 and poured inverts K-3, & K-4. Contractor backfilled and grade sanitary main and structure. 8-9-24 BR Contractor (ESS) installed 100' of 8'' PVC pipe from MH K-6 to MH K-7 with MH K-7 structure installed. 8-21-14 BR Contractor (ESS) installed 115' of 8" PVC pipe from MH K-5 to MH M-1 with structure installed and 50' of services wyes. 11-25-24 BR Contractor framed up and rebar manholes diamond. Also poured 8'' 4k KCMMB concrete around manholes.
Sanitary Sewer Construction Inspection Passed 8/6/2024 8/6/2024 12/04/2024
Misc
Informational
08/06/2024
7-29-24 BR Contractor (ESS) installed 110' of 8'' PVC pipe heading to MH K-4. 08-06-24 JMJ Continued with installation of 8" SDR-26 PVC pipe. Approximately 145' and 6 laterals 4" PVC around 40' to 45'. Contractor poured 4 ditch checks on K line.
Sanitary Sewer Construction Inspection Passed 8/6/2024 8/6/2024 12/04/2024
Misc
Informational
07/29/2024
7-29-24 BR Contractor (ESS) installed 110' of 8'' PVC pipe heading to MH K-4. 08-06-24 JMJ Continued with installation of 8" SDR-26 PVC pipe. Approximately 145' and 6 laterals 4" PVC around 40' to 45'.
Sanitary Sewer Construction Inspection Passed 8/5/2024 8/5/2024 12/04/2024
Misc
Informational
07/29/2024
7-29-24 BR Contractor (ESS) installed 110' of 8'' PVC pipe heading to MH K-4. 8-1-24 BR Contractor (ESS) installed 150' of 8'' PVC pipe to MH K-4 with MH K-4 structure installed. 8-5-24 BR Contractor (ESS) installed 300' of 8'' PVC pipe from MH K-4 to MH K-5 with MH K-5 structure installed.
Water Line - Construction Inspection Passed 10/4/2024 10/4/2024 12/04/2024
Misc
Informational
09/30/2024
9-30-24 BR Contractor (ESS) installed 300' of 8'' water main line 8 from Sta. 1+50 - Sta. 4+26 10-1-24 BR Contractor (ESS) installed 300 of 8'' water main on line 8 to connection to existing water main with sleeve installed at Sta. 0+05. Fire hydrant assembly is installed at Sta. 1+25. 8x8 tee is installed to connect to water line 12 to water line 8. 10-3-24 BR Contractor (ESS) installed 500' of 8'' water main from Sta. 9+00 - Sta. 5+40 on water line 12 and installed temp fire hydrant. Also contractor installed water main on line 10 to fire hydrant assembly. 10-4-24 BR Contractor (ESS) installed 300' of 8'' water main from Sta. 10+00 - Sta. 12+32 and install fire hydrant at end of water main. Backing blocks was poured on all tee's and fire hydrant assembly.
Erosion Control Inspection Partial 3/4/2025 3/4/2025 03/04/2025
Misc
Informational
03/04/2025
1-26-25 BR Erosion control is up and working order. 2-4-25 BR Erosion control is up and working order. 2-20-25 BR Erosion control is up and working order. 3-4-25 BR Erosion control is up and working order.
Documents & Images
Date Uploaded File Type Document Name
12/15/2023 Receipt Receipt for transaction: 2023-009134
12/14/2023 Approved Plans WATER STAMPED CONSTRUCTION PLANS
12/14/2023 Activity Document FeeWorksheetRetreatBaileyWater
04/26/2022 Engineers Estimate 21-133-Retreat - EOPC(REV0)
12/14/2023 Activity Document FeeWorksheetRetreatBaileySanitary
12/14/2023 Approved Plans SANITARY STAMPED CONSTRUCTION PLANS
12/14/2023 Activity Document FeeWorksheetRetreatBaileyStreetStormMDP
12/14/2023 Engineers Estimate 21-133-Retreat - Cost Estimate(REV3)
12/14/2023 Approved Plans STREET, STORM AND MDP STAMPED CONSTRUCTION PLANS
04/26/2022 Engineers Estimate 21-133-Retreat - EOPC(REV0)
07/29/2024 Letter INSPECTION SUMMARY
08/02/2024 Letter INSPECTION SUMMARY
08/02/2024 Letter INSPECTION SUMMARY
08/05/2024 Letter INSPECTION SUMMARY
08/05/2024 Letter INSPECTION SUMMARY
08/06/2024 Letter INSPECTION SUMMARY
08/07/2024 Letter INSPECTION SUMMARY
08/07/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/21/2024 Letter INSPECTION SUMMARY
08/21/2024 Letter INSPECTION SUMMARY
09/10/2024 Letter INSPECTION SUMMARY
09/25/2024 Letter INSPECTION SUMMARY
09/27/2024 Letter INSPECTION SUMMARY
09/27/2024 Letter INSPECTION SUMMARY
09/30/2024 Letter INSPECTION SUMMARY
10/01/2024 Letter INSPECTION SUMMARY
10/01/2024 Letter INSPECTION SUMMARY
10/03/2024 Letter INSPECTION SUMMARY
10/03/2024 Letter INSPECTION SUMMARY
10/04/2024 Letter INSPECTION SUMMARY
10/04/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/25/2024 Letter INSPECTION SUMMARY
10/28/2024 Letter INSPECTION SUMMARY
11/12/2024 Letter INSPECTION SUMMARY
11/12/2024 Letter INSPECTION SUMMARY
11/25/2024 Letter INSPECTION SUMMARY
11/25/2024 Letter INSPECTION SUMMARY
11/25/2024 Letter INSPECTION SUMMARY
11/25/2024 Letter INSPECTION SUMMARY
12/04/2024 Letter INSPECTION SUMMARY
12/04/2024 Letter INSPECTION SUMMARY
12/04/2024 Letter INSPECTION SUMMARY
12/04/2024 Letter INSPECTION SUMMARY
12/04/2024 Letter INSPECTION SUMMARY
12/04/2024 Letter INSPECTION SUMMARY
12/04/2024 Letter INSPECTION SUMMARY
12/04/2024 Letter INSPECTION SUMMARY
12/04/2024 Letter INSPECTION SUMMARY
12/04/2024 Letter INSPECTION SUMMARY
12/04/2024 Letter INSPECTION SUMMARY
01/02/2025 Letter INSPECTION SUMMARY
03/04/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home