Summary


PRSUBD20221588
Public Infrastructure
Final Acceptance
DEVELOPMENT COMPLETE
Pergola Park 5th Plat - Final Plat. Off-Site Sanitary.
04/19/2022
09/19/2022
10/26/2023
Locations
Contacts
RUSSELL PEARSON, Address:3152 GRANDSTAND CIR, Phone:(913) 735-9861  
Scott Ready, Phone: 8169691225  
DAVID RINNE, Address:SCHLAGEL ASSOCIATES  
BUILDER'S STONE & MASONRY LLC, Address:9801 Legler Rd., Phone:(913) 764-4446  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 04/19/2022 04/20/2022
Scott Ready
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $158.25 $158.25 Paid 04/22/2022
91100C8-Sanitary Sewer Insp Fees $5,117.25 $5,117.25 Paid 05/06/2022
$5,275.50
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sanitary Sewer Construction Inspection Partial 08/15/2022
Misc
Informational
08/15/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES
Sanitary Sewer Construction Inspection Partial 08/15/2022
Misc
Informational
08/15/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES
Erosion Control Inspection Partial 08/15/2022
Misc
Informational
08/15/2022
Erosion control measures installed and functioning. 8/15/22 ES
Sanitary Sewer Construction Inspection Partial 08/16/2022
Misc
Informational
08/15/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES
Site Visit Partial 08/17/2022
Misc
Informational
08/17/2022
No work being done due to rain. 8/16/22 ES
Sanitary Sewer Construction Inspection Partial 08/17/2022
Misc
Informational
08/16/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES
Sanitary Sewer Construction Inspection Partial 08/18/2022
Misc
Informational
08/17/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES
Sanitary Sewer Construction Inspection Partial 08/19/2022
Misc
Informational
08/18/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES
Sanitary Sewer Construction Inspection Partial 08/22/2022
Misc
Informational
08/19/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Sanitary Sewer Construction Inspection Partial 08/22/2022
Misc
Informational
08/22/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
08/22/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES
Sanitary Sewer Construction Inspection Partial 08/23/2022
Misc
Informational
08/22/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
08/22/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES
Erosion Control Inspection Partial 08/23/2022
Misc
Informational
08/15/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES
Erosion Control Inspection Partial 08/23/2022
Misc
Informational
08/23/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES
Sanitary Sewer Construction Inspection Partial 08/25/2022
Misc
Informational
08/23/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
08/23/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES
Site Visit Partial 08/25/2022
Misc
Informational
08/17/2022
No work being done due to rain. 8/16/22 ES Bair Excavating had a skid steer with mulcher clearing out areas back into the woods for access to install sanitary line A. 8/24/22 ES
Sanitary Sewer Construction Inspection Partial 08/25/2022
Misc
Informational
08/25/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
08/25/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES
Site Visit Partial 08/25/2022
Misc
Informational
08/25/2022
No work being done due to rain. 8/16/22 ES Bair Excavating had a skid steer with mulcher clearing out areas back into the woods for access to install sanitary line A. 8/24/22 ES Bair Excavating continued clearing brush and smaller treed areas to make access for sanitary sewer install. 8/25/22 ES
Sanitary Sewer Construction Inspection Partial 08/29/2022
Misc
Informational
08/25/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
08/25/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Sanitary Sewer Construction Inspection Partial 08/29/2022
Misc
Informational
08/29/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
08/29/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
08/29/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES
Erosion Control Inspection Partial 08/29/2022
Misc
Informational
08/23/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES
Sanitary Sewer Construction Inspection Partial 08/29/2022
Misc
Informational
08/29/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
08/29/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
08/29/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES
Sanitary Sewer Construction Inspection Partial 09/02/2022
Misc
Informational
08/29/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
08/29/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
08/29/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 ES
Sanitary Sewer Construction Inspection Partial 09/02/2022
Misc
Informational
09/02/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
09/02/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
09/02/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 ES
Sanitary Sewer Construction Inspection Partial 09/02/2022
Misc
Informational
09/02/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
09/02/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
09/02/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES
Erosion Control Inspection Partial 09/06/2022
Misc
Informational
08/29/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES
Sanitary Sewer Construction Inspection Partial 09/09/2022
Misc
Informational
09/02/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
09/02/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
09/02/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES
Grading/Excavation/Fill Inspection Partial 09/09/2022
Misc
Informational
09/09/2022
Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES
Erosion Control Inspection Partial 09/12/2022
Misc
Informational
09/06/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES Erosion control measures installed, intact, and functioning. 9/12/22 ES
Site Visit Partial 09/12/2022
Misc
Informational
08/25/2022
No work being done due to rain. 8/16/22 ES Bair Excavating had a skid steer with mulcher clearing out areas back into the woods for access to install sanitary line A. 8/24/22 ES Bair Excavating continued clearing brush and smaller treed areas to make access for sanitary sewer install. 8/25/22 ES CFS was onsite performing compaction testing between MH A-2 and A-3 and began working onto the onsite areas. 9/9/22 ES
Sanitary Sewer Construction Inspection Partial 09/19/2022
Misc
Informational
09/09/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
09/09/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
09/09/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed.
Erosion Control Inspection Partial 09/26/2022
Misc
Informational
09/12/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES Erosion control measures installed, intact, and functioning. 9/12/22 ES Erosion control installed, intact and functioning. 9/26/22 ES
Sanitary Sewer Construction Inspection Partial 09/28/2022
Misc
Informational
09/19/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
09/19/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
09/19/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Grading/Excavation/Fill Inspection Partial 09/28/2022
Misc
Informational
09/09/2022
Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Erosion Control Inspection Partial 10/03/2022
Misc
Informational
09/26/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES Erosion control measures installed, intact, and functioning. 9/12/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES
Grading/Excavation/Fill Inspection Partial 10/07/2022
Misc
Informational
09/28/2022
Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES Adam's crew working on grading site. 10/7/22 ES
Erosion Control Inspection Partial 10/11/2022
Misc
Informational
10/03/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES Erosion control measures installed, intact, and functioning. 9/12/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES
Sanitary - Material Verification Partial 10/11/2022
Misc
Informational
10/11/2022
Had 25 sticks of 8" zinc coated ductile iron pipe delivered from WinWater. This will be for the offsite sanitary line going under the spillway. 10/10/22 ES
Erosion Control Inspection Partial 10/19/2022
Misc
Informational
10/11/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES Erosion control measures installed, intact, and functioning. 9/12/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES
Grading/Excavation/Fill Inspection Partial 10/19/2022
Misc
Informational
10/07/2022
Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES Adam's crew working on grading site. 10/7/22 ES Bair crew working on grading site. Schlagel onsite verifying elevations on installed structures. 10/18/22 ES
Site Visit Partial 10/19/2022
Misc
Informational
09/12/2022
No work being done due to rain. 8/16/22 ES Bair Excavating had a skid steer with mulcher clearing out areas back into the woods for access to install sanitary line A. 8/24/22 ES Bair Excavating continued clearing brush and smaller treed areas to make access for sanitary sewer install. 8/25/22 ES CFS was onsite performing compaction testing between MH A-2 and A-3 and began working onto the onsite areas. 9/9/22 ES Schlagel onsite staking for water lines and verifying installed structure elevations. 10/18/22 ES
Erosion Control Inspection Partial 10/28/2022
Misc
Informational
10/19/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES Erosion control measures installed, intact, and functioning. 9/12/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event on 10/24, erosion control measures holding. Did have some residual silt make its way to the lake through newly constructed storm structures. 10/25/22 ES
Sanitary Sewer Construction Inspection Partial 10/28/2022
Misc
Informational
09/28/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
09/28/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
09/28/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
10/28/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES
Erosion Control Inspection Partial 10/31/2022
Misc
Informational
10/28/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES Erosion control measures installed, intact, and functioning. 9/12/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event on 10/24, erosion control measures holding. Did have some residual silt make its way to the lake through newly constructed storm structures. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES
Sanitary Sewer Construction Inspection Partial 10/31/2022
Misc
Informational
10/28/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
10/28/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
10/28/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
10/28/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES
Sanitary - Material Verification Partial 10/31/2022
Misc
Informational
10/11/2022
Had 25 sticks of 8" zinc coated ductile iron pipe delivered from WinWater. This will be for the offsite sanitary line going under the spillway. 10/10/22 ES Have 8" SDR26 pipe and MH Structures for A-1 on site as well as butyl wrap and concrete riser rings. 10/31/22 ES
Erosion Control Inspection Partial 11/08/2022
Misc
Informational
10/31/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES Erosion control measures installed, intact, and functioning. 9/12/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event on 10/24, erosion control measures holding. Did have some residual silt make its way to the lake through newly constructed storm structures. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. Measures held up to rain even from 11/4, had conversation with crews about keeping mud off of existing roads. 11/7/22 ES
Sanitary Sewer Construction Inspection Partial 11/14/2022
Misc
Informational
10/31/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
10/31/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
10/31/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
10/31/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES
Erosion Control Inspection Partial 11/14/2022
Misc
Informational
11/08/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES Erosion control measures installed, intact, and functioning. 9/12/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event on 10/24, erosion control measures holding. Did have some residual silt make its way to the lake through newly constructed storm structures. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. Measures held up to rain even from 11/4, had conversation with crews about keeping mud off of existing roads. 11/7/22 ES Erosion control measures installed, intact, and functioning. With snow coming tonight/tomorrow did readdress issues with mud on roadways. 11/14/22 ES
Erosion Control Inspection Partial 11/21/2022
Misc
Informational
11/14/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES Erosion control measures installed, intact, and functioning. 9/12/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event on 10/24, erosion control measures holding. Did have some residual silt make its way to the lake through newly constructed storm structures. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. Measures held up to rain even from 11/4, had conversation with crews about keeping mud off of existing roads. 11/7/22 ES Erosion control measures installed, intact, and functioning. With snow coming tonight/tomorrow did readdress issues with mud on roadways. 11/14/22 ES Erosion control measures installed, intact, and functioning. 11/21/22 ES
Sanitary Sewer Construction Inspection Partial 11/28/2022
Misc
Informational
11/14/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
11/14/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
11/14/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
11/14/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water.
Sanitary Sewer Construction Inspection Partial 11/29/2022
Misc
Informational
11/28/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
11/28/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
11/28/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
11/28/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow. They plan to start forming up for concrete collars soon.
Sanitary Sewer Construction Inspection Partial 11/29/2022
Misc
Informational
11/29/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
11/29/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
11/29/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
11/29/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon.
Sanitary Sewer Construction Inspection Partial 11/30/2022
Misc
Informational
11/29/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
11/29/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
11/29/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
11/29/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed.
Sanitary Sewer Construction Inspection Partial 12/01/2022
Misc
Informational
11/30/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
11/30/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
11/30/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
11/30/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line.
Sanitary Sewer Construction Inspection Partial 12/01/2022
Misc
Informational
12/01/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/01/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/01/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/01/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping.
Grading/Excavation/Fill Inspection Partial 12/02/2022
Misc
Informational
10/19/2022
Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES Adam's crew working on grading site. 10/7/22 ES Bair crew working on grading site. Schlagel onsite verifying elevations on installed structures. 10/18/22 ES 12-2-22 RH. Contractor continues to build up fill on top of the encased pipe to build the spill way. Fill is being compacted in and rip rap will be added.
Sanitary Sewer Construction Inspection Partial 12/05/2022
Misc
Informational
12/01/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/01/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/01/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/01/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1.
Sanitary Sewer Construction Inspection Partial 12/06/2022
Misc
Informational
12/05/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/05/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/05/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/05/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1. 12-6-22 RH. Contractor is working on Manhole A-2 today. They will be stacking it out and filling in around it due to the location next to the lake and a possible fall in due to the lake.
Sanitary Sewer Construction Inspection Partial 12/07/2022
Misc
Informational
12/06/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/06/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/06/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/06/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1. 12-6-22 RH. Contractor is working on Manhole A-2 today. They will be stacking it out and filling in around it due to the location next to the lake and a possible fall in due to the lake. 12-7-22 RH. Contractor continues from Manhole A-2 toward A-1. A-2 was stacked out yesterday. Ditch checks will be poured today between exciting MH and MH A-1.
Sanitary Sewer Construction Inspection Partial 12/08/2022
Misc
Informational
12/07/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/07/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/07/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/07/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1. 12-6-22 RH. Contractor is working on Manhole A-2 today. They will be stacking it out and filling in around it due to the location next to the lake and a possible fall in due to the lake. 12-7-22 RH. Contractor continues from Manhole A-2 toward A-1. A-2 was stacked out yesterday. Ditch checks will be poured today between exciting MH and MH A-1. 12-8-22 RH. Contractor continues to install pipe form A-2 to A-1.
Sanitary Sewer Construction Inspection Partial 12/09/2022
Misc
Informational
12/08/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/08/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/08/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/08/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1. 12-6-22 RH. Contractor is working on Manhole A-2 today. They will be stacking it out and filling in around it due to the location next to the lake and a possible fall in due to the lake. 12-7-22 RH. Contractor continues from Manhole A-2 toward A-1. A-2 was stacked out yesterday. Ditch checks will be poured today between exciting MH and MH A-1. 12-8-22 RH. Contractor continues to install pipe form A-2 to A-1. 12-9-22 RH. Contractor continues to dig and place pipe between A-2 and A-1. Backfilling is also being completed as pipe is placed.
Erosion Control Inspection Partial 12/12/2022
Misc
Informational
11/21/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES Erosion control measures installed, intact, and functioning. 9/12/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event on 10/24, erosion control measures holding. Did have some residual silt make its way to the lake through newly constructed storm structures. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. Measures held up to rain even from 11/4, had conversation with crews about keeping mud off of existing roads. 11/7/22 ES Erosion control measures installed, intact, and functioning. With snow coming tonight/tomorrow did readdress issues with mud on roadways. 11/14/22 ES Erosion control measures installed, intact, and functioning. 11/21/22 ES 12-12-22 RH. Erosion control is up and in working order.
Sanitary Sewer Construction Inspection Partial 12/12/2022
Misc
Informational
12/09/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/09/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/09/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/09/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1. 12-6-22 RH. Contractor is working on Manhole A-2 today. They will be stacking it out and filling in around it due to the location next to the lake and a possible fall in due to the lake. 12-7-22 RH. Contractor continues from Manhole A-2 toward A-1. A-2 was stacked out yesterday. Ditch checks will be poured today between exciting MH and MH A-1. 12-8-22 RH. Contractor continues to install pipe form A-2 to A-1. 12-9-22 RH. Contractor continues to dig and place pipe between A-2 and A-1. Backfilling is also being completed as pipe is placed. 12-12-22 RH. Contractor continues to place pipe from A-2 to A-1. Backfilling over pipe as they place.
Sanitary Sewer Construction Inspection Partial 12/14/2022
Misc
Informational
12/12/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/12/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/12/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/12/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1. 12-6-22 RH. Contractor is working on Manhole A-2 today. They will be stacking it out and filling in around it due to the location next to the lake and a possible fall in due to the lake. 12-7-22 RH. Contractor continues from Manhole A-2 toward A-1. A-2 was stacked out yesterday. Ditch checks will be poured today between exciting MH and MH A-1. 12-8-22 RH. Contractor continues to install pipe form A-2 to A-1. 12-9-22 RH. Contractor continues to dig and place pipe between A-2 and A-1. Backfilling is also being completed as pipe is placed. 12-12-22 RH. Contractor continues to place pipe from A-2 to A-1. Backfilling over pipe as they place. 12-14-22 RH. Contractor continues to place pipe from A-2 to A-1.
Sanitary Sewer Construction Inspection Partial 12/15/2022
Misc
Informational
12/14/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/14/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/14/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/14/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1. 12-6-22 RH. Contractor is working on Manhole A-2 today. They will be stacking it out and filling in around it due to the location next to the lake and a possible fall in due to the lake. 12-7-22 RH. Contractor continues from Manhole A-2 toward A-1. A-2 was stacked out yesterday. Ditch checks will be poured today between exciting MH and MH A-1. 12-8-22 RH. Contractor continues to install pipe form A-2 to A-1. 12-9-22 RH. Contractor continues to dig and place pipe between A-2 and A-1. Backfilling is also being completed as pipe is placed. 12-12-22 RH. Contractor continues to place pipe from A-2 to A-1. Backfilling over pipe as they place. 12-14-22 RH. Contractor continues to place pipe from A-2 to A-1. 12-15-22 RH. Pipe continues to be lad towards A-1 from A-2.
Sanitary Sewer Construction Inspection Partial 12/16/2022
Misc
Informational
12/15/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/15/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/15/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/15/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1. 12-6-22 RH. Contractor is working on Manhole A-2 today. They will be stacking it out and filling in around it due to the location next to the lake and a possible fall in due to the lake. 12-7-22 RH. Contractor continues from Manhole A-2 toward A-1. A-2 was stacked out yesterday. Ditch checks will be poured today between exciting MH and MH A-1. 12-8-22 RH. Contractor continues to install pipe form A-2 to A-1. 12-9-22 RH. Contractor continues to dig and place pipe between A-2 and A-1. Backfilling is also being completed as pipe is placed. 12-12-22 RH. Contractor continues to place pipe from A-2 to A-1. Backfilling over pipe as they place. 12-14-22 RH. Contractor continues to place pipe from A-2 to A-1. 12-15-22 RH. Pipe continues to be lad towards A-1 from A-2. 12-16-22 RH. Contractor is just backfilling sanitary line between A-2 to A-1. No pipe will be laid today.
Sanitary Sewer Construction Inspection Partial 12/17/2022
Misc
Informational
12/16/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/16/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/16/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/16/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1. 12-6-22 RH. Contractor is working on Manhole A-2 today. They will be stacking it out and filling in around it due to the location next to the lake and a possible fall in due to the lake. 12-7-22 RH. Contractor continues from Manhole A-2 toward A-1. A-2 was stacked out yesterday. Ditch checks will be poured today between exciting MH and MH A-1. 12-8-22 RH. Contractor continues to install pipe form A-2 to A-1. 12-9-22 RH. Contractor continues to dig and place pipe between A-2 and A-1. Backfilling is also being completed as pipe is placed. 12-12-22 RH. Contractor continues to place pipe from A-2 to A-1. Backfilling over pipe as they place. 12-14-22 RH. Contractor continues to place pipe from A-2 to A-1. 12-15-22 RH. Pipe continues to be lad towards A-1 from A-2. 12-16-22 RH. Contractor is just backfilling sanitary line between A-2 to A-1. No pipe will be laid today. 12-17-22 JMJ Contractor continues to install pipe from A-2 to A-1 Approximately 60’ of 8” sanitary sewer pipe. Contractor is dealing with the slow excavation because of depth of pipe install, hardshell soil, and water needing to be pump.
Sanitary Sewer Construction Inspection Partial 12/20/2022
Misc
Informational
12/17/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/17/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/17/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/17/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1. 12-6-22 RH. Contractor is working on Manhole A-2 today. They will be stacking it out and filling in around it due to the location next to the lake and a possible fall in due to the lake. 12-7-22 RH. Contractor continues from Manhole A-2 toward A-1. A-2 was stacked out yesterday. Ditch checks will be poured today between exciting MH and MH A-1. 12-8-22 RH. Contractor continues to install pipe form A-2 to A-1. 12-9-22 RH. Contractor continues to dig and place pipe between A-2 and A-1. Backfilling is also being completed as pipe is placed. 12-12-22 RH. Contractor continues to place pipe from A-2 to A-1. Backfilling over pipe as they place. 12-14-22 RH. Contractor continues to place pipe from A-2 to A-1. 12-15-22 RH. Pipe continues to be lad towards A-1 from A-2. 12-16-22 RH. Contractor is just backfilling sanitary line between A-2 to A-1. No pipe will be laid today. 12-17-22 JMJ Contractor continues to install pipe from A-2 to A-1 Approximately 60’ of 8” sanitary sewer pipe. Contractor is dealing with the slow excavation because of depth of pipe install, hardshell soil, and water needing to be pump. 12-20-22 RH. Contractor continues to install pipe between A-2 to A-1. Progress is slow due to depth.
Erosion Control Inspection Partial 12/20/2022
Misc
Informational
12/12/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES Erosion control measures installed, intact, and functioning. 9/12/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event on 10/24, erosion control measures holding. Did have some residual silt make its way to the lake through newly constructed storm structures. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. Measures held up to rain even from 11/4, had conversation with crews about keeping mud off of existing roads. 11/7/22 ES Erosion control measures installed, intact, and functioning. With snow coming tonight/tomorrow did readdress issues with mud on roadways. 11/14/22 ES Erosion control measures installed, intact, and functioning. 11/21/22 ES 12-12-22 RH. Erosion control is up and in working order. 12-20-22 RH. Erosion control is up and in working order.
Sanitary Sewer Construction Inspection Partial 12/21/2022
Misc
Informational
12/20/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/20/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/20/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/20/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1. 12-6-22 RH. Contractor is working on Manhole A-2 today. They will be stacking it out and filling in around it due to the location next to the lake and a possible fall in due to the lake. 12-7-22 RH. Contractor continues from Manhole A-2 toward A-1. A-2 was stacked out yesterday. Ditch checks will be poured today between exciting MH and MH A-1. 12-8-22 RH. Contractor continues to install pipe form A-2 to A-1. 12-9-22 RH. Contractor continues to dig and place pipe between A-2 and A-1. Backfilling is also being completed as pipe is placed. 12-12-22 RH. Contractor continues to place pipe from A-2 to A-1. Backfilling over pipe as they place. 12-14-22 RH. Contractor continues to place pipe from A-2 to A-1. 12-15-22 RH. Pipe continues to be lad towards A-1 from A-2. 12-16-22 RH. Contractor is just backfilling sanitary line between A-2 to A-1. No pipe will be laid today. 12-17-22 JMJ Contractor continues to install pipe from A-2 to A-1 Approximately 60’ of 8” sanitary sewer pipe. Contractor is dealing with the slow excavation because of depth of pipe install, hardshell soil, and water needing to be pump. 12-20-22 RH. Contractor continues to install pipe between A-2 to A-1. Progress is slow due to depth. 12-21-22 RH. Contractor continues to lay pipe to A-1. Progress is slow due to rock and and depth of trench.
Erosion Control Inspection Partial 12/27/2022
Misc
Informational
12/20/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES Erosion control measures installed, intact, and functioning. 9/12/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event on 10/24, erosion control measures holding. Did have some residual silt make its way to the lake through newly constructed storm structures. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. Measures held up to rain even from 11/4, had conversation with crews about keeping mud off of existing roads. 11/7/22 ES Erosion control measures installed, intact, and functioning. With snow coming tonight/tomorrow did readdress issues with mud on roadways. 11/14/22 ES Erosion control measures installed, intact, and functioning. 11/21/22 ES 12-12-22 RH. Erosion control is up and in working order. 12-20-22 RH. Erosion control is up and in working order. 12-27-22 RH. Erosion control is up and in working order.
Sanitary Sewer Construction Inspection Partial 12/27/2022
Misc
Informational
12/21/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/21/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/21/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/21/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1. 12-6-22 RH. Contractor is working on Manhole A-2 today. They will be stacking it out and filling in around it due to the location next to the lake and a possible fall in due to the lake. 12-7-22 RH. Contractor continues from Manhole A-2 toward A-1. A-2 was stacked out yesterday. Ditch checks will be poured today between exciting MH and MH A-1. 12-8-22 RH. Contractor continues to install pipe form A-2 to A-1. 12-9-22 RH. Contractor continues to dig and place pipe between A-2 and A-1. Backfilling is also being completed as pipe is placed. 12-12-22 RH. Contractor continues to place pipe from A-2 to A-1. Backfilling over pipe as they place. 12-14-22 RH. Contractor continues to place pipe from A-2 to A-1. 12-15-22 RH. Pipe continues to be lad towards A-1 from A-2. 12-16-22 RH. Contractor is just backfilling sanitary line between A-2 to A-1. No pipe will be laid today. 12-17-22 JMJ Contractor continues to install pipe from A-2 to A-1 Approximately 60’ of 8” sanitary sewer pipe. Contractor is dealing with the slow excavation because of depth of pipe install, hardshell soil, and water needing to be pump. 12-20-22 RH. Contractor continues to install pipe between A-2 to A-1. Progress is slow due to depth. 12-21-22 RH. Contractor continues to lay pipe to A-1. Progress is slow due to rock and and depth of trench. 12-27-22 RH. Contractor is digging out where they will be placing MH A-1. Contractor is hopping to finish sanitary tie in today or tomorrow.
Sanitary Sewer Construction Inspection Partial 12/28/2022
Misc
Informational
12/27/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/27/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/27/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/27/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1. 12-6-22 RH. Contractor is working on Manhole A-2 today. They will be stacking it out and filling in around it due to the location next to the lake and a possible fall in due to the lake. 12-7-22 RH. Contractor continues from Manhole A-2 toward A-1. A-2 was stacked out yesterday. Ditch checks will be poured today between exciting MH and MH A-1. 12-8-22 RH. Contractor continues to install pipe form A-2 to A-1. 12-9-22 RH. Contractor continues to dig and place pipe between A-2 and A-1. Backfilling is also being completed as pipe is placed. 12-12-22 RH. Contractor continues to place pipe from A-2 to A-1. Backfilling over pipe as they place. 12-14-22 RH. Contractor continues to place pipe from A-2 to A-1. 12-15-22 RH. Pipe continues to be lad towards A-1 from A-2. 12-16-22 RH. Contractor is just backfilling sanitary line between A-2 to A-1. No pipe will be laid today. 12-17-22 JMJ Contractor continues to install pipe from A-2 to A-1 Approximately 60’ of 8” sanitary sewer pipe. Contractor is dealing with the slow excavation because of depth of pipe install, hardshell soil, and water needing to be pump. 12-20-22 RH. Contractor continues to install pipe between A-2 to A-1. Progress is slow due to depth. 12-21-22 RH. Contractor continues to lay pipe to A-1. Progress is slow due to rock and and depth of trench. 12-27-22 RH. Contractor is digging out where they will be placing MH A-1. Contractor is hopping to finish sanitary tie in today or tomorrow. 12-28-22 RH. Contractor placed MH A-1. 80’ of line needs to be installed and line will be complete.
Sanitary Sewer Construction Inspection Partial 12/29/2022
Misc
Informational
12/28/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/28/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/28/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/28/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1. 12-6-22 RH. Contractor is working on Manhole A-2 today. They will be stacking it out and filling in around it due to the location next to the lake and a possible fall in due to the lake. 12-7-22 RH. Contractor continues from Manhole A-2 toward A-1. A-2 was stacked out yesterday. Ditch checks will be poured today between exciting MH and MH A-1. 12-8-22 RH. Contractor continues to install pipe form A-2 to A-1. 12-9-22 RH. Contractor continues to dig and place pipe between A-2 and A-1. Backfilling is also being completed as pipe is placed. 12-12-22 RH. Contractor continues to place pipe from A-2 to A-1. Backfilling over pipe as they place. 12-14-22 RH. Contractor continues to place pipe from A-2 to A-1. 12-15-22 RH. Pipe continues to be lad towards A-1 from A-2. 12-16-22 RH. Contractor is just backfilling sanitary line between A-2 to A-1. No pipe will be laid today. 12-17-22 JMJ Contractor continues to install pipe from A-2 to A-1 Approximately 60’ of 8” sanitary sewer pipe. Contractor is dealing with the slow excavation because of depth of pipe install, hardshell soil, and water needing to be pump. 12-20-22 RH. Contractor continues to install pipe between A-2 to A-1. Progress is slow due to depth. 12-21-22 RH. Contractor continues to lay pipe to A-1. Progress is slow due to rock and and depth of trench. 12-27-22 RH. Contractor is digging out where they will be placing MH A-1. Contractor is hopping to finish sanitary tie in today or tomorrow. 12-28-22 RH. Contractor placed MH A-1. 80’ of line needs to be installed and line will be complete. 12-29-22 RH. Contractor has 60’ of pipe left from A-1 to connect to exciting Sanitary MH but due to the depth of trench and water work is going slow.
Sanitary Sewer Construction Inspection Partial 01/03/2023
Misc
Informational
12/29/2022
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
12/29/2022
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
12/29/2022
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
12/29/2022
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1. 12-6-22 RH. Contractor is working on Manhole A-2 today. They will be stacking it out and filling in around it due to the location next to the lake and a possible fall in due to the lake. 12-7-22 RH. Contractor continues from Manhole A-2 toward A-1. A-2 was stacked out yesterday. Ditch checks will be poured today between exciting MH and MH A-1. 12-8-22 RH. Contractor continues to install pipe form A-2 to A-1. 12-9-22 RH. Contractor continues to dig and place pipe between A-2 and A-1. Backfilling is also being completed as pipe is placed. 12-12-22 RH. Contractor continues to place pipe from A-2 to A-1. Backfilling over pipe as they place. 12-14-22 RH. Contractor continues to place pipe from A-2 to A-1. 12-15-22 RH. Pipe continues to be lad towards A-1 from A-2. 12-16-22 RH. Contractor is just backfilling sanitary line between A-2 to A-1. No pipe will be laid today. 12-17-22 JMJ Contractor continues to install pipe from A-2 to A-1 Approximately 60’ of 8” sanitary sewer pipe. Contractor is dealing with the slow excavation because of depth of pipe install, hardshell soil, and water needing to be pump. 12-20-22 RH. Contractor continues to install pipe between A-2 to A-1. Progress is slow due to depth. 12-21-22 RH. Contractor continues to lay pipe to A-1. Progress is slow due to rock and and depth of trench. 12-27-22 RH. Contractor is digging out where they will be placing MH A-1. Contractor is hopping to finish sanitary tie in today or tomorrow. 12-28-22 RH. Contractor placed MH A-1. 80’ of line needs to be installed and line will be complete. 12-29-22 RH. Contractor has 60’ of pipe left from A-1 to connect to exciting Sanitary MH but due to the depth of trench and water work is going slow. Contractor completed line today.
Erosion Control Inspection Partial 01/03/2023
Misc
Informational
12/27/2022
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES Erosion control measures installed, intact, and functioning. 9/12/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event on 10/24, erosion control measures holding. Did have some residual silt make its way to the lake through newly constructed storm structures. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. Measures held up to rain even from 11/4, had conversation with crews about keeping mud off of existing roads. 11/7/22 ES Erosion control measures installed, intact, and functioning. With snow coming tonight/tomorrow did readdress issues with mud on roadways. 11/14/22 ES Erosion control measures installed, intact, and functioning. 11/21/22 ES 12-12-22 RH. Erosion control is up and in working order. 12-20-22 RH. Erosion control is up and in working order. 12-27-22 RH. Erosion control is up and in working order. 1-3-23 DP. Erosion control is up and in working order.
Erosion Control Inspection Partial 01/30/2023
Misc
Informational
01/03/2023
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES Erosion control measures installed, intact, and functioning. 9/12/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event on 10/24, erosion control measures holding. Did have some residual silt make its way to the lake through newly constructed storm structures. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. Measures held up to rain even from 11/4, had conversation with crews about keeping mud off of existing roads. 11/7/22 ES Erosion control measures installed, intact, and functioning. With snow coming tonight/tomorrow did readdress issues with mud on roadways. 11/14/22 ES Erosion control measures installed, intact, and functioning. 11/21/22 ES 12-12-22 RH. Erosion control is up and in working order. 12-20-22 RH. Erosion control is up and in working order. 12-27-22 RH. Erosion control is up and in working order. 1-3-23 DP. Erosion control is up and in working order. 1-30-23 RH. Eroison contorl is up and in working order.
Sanitary Sewer Construction Inspection Passed 02/07/2023
Misc
Informational
01/03/2023
Bair Excavating had MH A-2 hole dug and base set using shoring and trench boxes. 8/12/22 ES Bair Excavating began digging out from MH A-2 to start laying pipe. 8/15/22 ES Bair Excavating laid 2 sticks of 8” pipe and were looking to get 2-3 more in before leaving. 8/15/22 ES Bair excavating laying pipe and installed first wye north of MH A-2. 8/17/22 ES Bair Excavating laying pipe, had 3 sticks in and almost to second wye. 8/18/22 ES Bair Excavating continued laying, had laid 7 sticks of pipe today. 8/18/22 ES Bair Excavating had a trench collapse, had to pull 6 sticks of pipe out to get lined back up. Capped pipe at end before rain started and began backfilling trench that was still open. 8/19/22 ES
Misc
Informational
01/03/2023
Bair Excavating worked on putting riser on first service line north of MH A-2 and backfilling. Wye was turned up at a 45 and street 45 put on to make 9’ rise and 9’ run off of 45 bend to 1.3% flow line. They were working on getting the equipment set back up to start digging out the area of pipe that had been removed at end of last week. 8/22/22 ES Bair Excavating installed 6 sticks of pipe including 2nd wye connection from MH A-2(7’ rise 10’ of pipe out for stub). Spoke with Troy and Adam both about making sure we get anodes and tracer wire ran out from stubs. 8/23/22 ES Bair Excavating had to pull out a couple of sticks of pipe again due to another wall falling in as they moved trench box. Reinstalled these sticks along with the 3rd wye connection from MH A-2 and capped. 8/24/22 ES Bair Excavating installed pipe up to MH A-3 including final wye connection on this section of A line. 8/25/22 ES Bair began backfilling between MH A-2 and MH A-3. Capped outlet of MH A-3. 8/26/22 ES
Misc
Informational
01/03/2023
Bair Excavating began laying pipe out from MH A-3 had first stick in during the morning. 8/29/22 ES Bair had 6 sticks of pipe in before storms stopped construction. They were working on backfilling trench. 8/29/22 ES Bair continued working on Line A towards MH A-4. 8/30/22 Bair Excavating working on running anodes and tracer wire from stub lines and backfilling. 9/1/22 ES Bair Excavating working on laying sewer tape and backfilling along all lines that have been put in. 9/2/22 ES Bair Excavating pipe crew worked on backfilling areas along A line. Mike from CFS was onsite doing compaction testing. 9/9/22 ES 9-19-22 RH. Sanitary continues to be placed. MH A-6 was placed today and contractor continues to dig toward MH A-7. Compaction was started on Line A but until concrete is poured no more fill was placed. Adam's crew began backfilling Storm line 800 as well as the areas down towards the lake. Compacting with large roller. 9/28/22 ES
Misc
Informational
01/03/2023
Met with Schlagel, Bair excavating, and Water Utilities about sanitary sewer crossing from basin below dam. Came to agreement that existing berm is not at the level it needs to be and once construction on this section of line is completed berm will need to be reconstructed with at least 1' +/- of fill over concrete encased dip and then larger rock placed over top and new rip-rap going into existing stream to cut erosion. 10/27/22 ES Troy's crew began working on poly wrapping ductile iron pipe. They will begin construction on the final legs of this after water on 5th plat is completed. Also spoke with Troy/Lafe and Sue about the ditch checks that are called out in the plans along the offsite main. Lafe was going to get in contact with Schlagel about the requirements for these or options outside of concrete/flow fill. 10/31/22 ES Troy's crew worked on pumping out area around MH A-2 in preparation to start laying pipe from A-1 to A-2 and also from existing MH to A-1. 11/14/22 ES 11-28-22 RH. Troys crew is fixing pip placed due to trench filling with water. The pipe was moved due to the water. 11-28-22 RH. Troy’s crew continues dig out trench and fix outflow from retention pond to stop trench from flooding where sanitary is being installed. They plan to start forming up for concrete collars soon. 11-29-22 RH. Troy’s crew had fixed issue with pipe and re dug the trench for the sanitary line at station 46.55 to 1+18.55. The 8” zinc coated piping was formed up with rebar surrounding the pipe for encasement due to the drainage channel going over the sanitary encasement. Concrete is being planned to be poured at 2pm. Trench still needed pumping rest of rebar installed. Water was pumped out and all rebar was placed. Contractor then poured concrete for concrete encasement. 12-1-22 RH. Crew continues to work on dam around the encased piping. They are filling and compacting to finish work around sanitary line. Crew continued to lay pipe after the encase piping. 12-2-22 RH. Crew laid pipe after encased pipe to station 3+14. More work to continue Monday. 12-5-22 RH. Crew plans to continue to lay pipe until they get to Manhole A-1. 12-6-22 RH. Contractor is working on Manhole A-2 today. They will be stacking it out and filling in around it due to the location next to the lake and a possible fall in due to the lake. 12-7-22 RH. Contractor continues from Manhole A-2 toward A-1. A-2 was stacked out yesterday. Ditch checks will be poured today between exciting MH and MH A-1. 12-8-22 RH. Contractor continues to install pipe form A-2 to A-1. 12-9-22 RH. Contractor continues to dig and place pipe between A-2 and A-1. Backfilling is also being completed as pipe is placed. 12-12-22 RH. Contractor continues to place pipe from A-2 to A-1. Backfilling over pipe as they place. 12-14-22 RH. Contractor continues to place pipe from A-2 to A-1. 12-15-22 RH. Pipe continues to be lad towards A-1 from A-2. 12-16-22 RH. Contractor is just backfilling sanitary line between A-2 to A-1. No pipe will be laid today. 12-17-22 JMJ Contractor continues to install pipe from A-2 to A-1 Approximately 60’ of 8” sanitary sewer pipe. Contractor is dealing with the slow excavation because of depth of pipe install, hardshell soil, and water needing to be pump. 12-20-22 RH. Contractor continues to install pipe between A-2 to A-1. Progress is slow due to depth. 12-21-22 RH. Contractor continues to lay pipe to A-1. Progress is slow due to rock and and depth of trench. 12-27-22 RH. Contractor is digging out where they will be placing MH A-1. Contractor is hopping to finish sanitary tie in today or tomorrow. 12-28-22 RH. Contractor placed MH A-1. 80’ of line needs to be installed and line will be complete. 12-29-22 RH. Contractor has 60’ of pipe left from A-1 to connect to exciting Sanitary MH but due to the depth of trench and water work is going slow. Contractor completed line today.
Sanitary Sewer - Air Test Passed 02/07/2023
Misc
Informational
02/07/2023
2-7-23 RH. Air test was performe on A-1 to Origianl Passed A-2 to A-1 Passed A-2 to A-3 Passed
Sanitary Sewer - Vacuum Passed 02/07/2023
Misc
Informational
02/07/2023
2-27-22 RH. Vaccum was tested for Manholes A-1 Passed A-2 Passed
Sanitary Sewer - Mandrel Partial 02/21/2023
Misc
Informational
02/21/2023
2-21-23 RH. Contractor is blowing string through line to pull mandral later today.
Sanitary Sewer - Mandrel Partial 02/21/2023
Misc
Informational
02/21/2023
2-21-23 RH. Mandral was pulled through Exciting MH to MH A-1 Passed MH A-1 to MH A-2 MH A-2 to MH A-3
Sanitary Sewer - Mandrel Partial 02/21/2023
Misc
Informational
02/21/2023
2-21-23 RH. Mandral was pulled through Exciting MH to MH A-1 Passed MH A-1 to MH A-2 Passed MH A-2 to MH A-3
Sanitary Sewer - Mandrel Partial 02/21/2023
Misc
Informational
02/21/2023
2-21-23 RH. Mandral was pulled through Exciting MH to MH A-1 Passed MH A-1 to MH A-2 Passed MH A-2 to MH A-3. Mandral got stuck going through.
Erosion Control Inspection Partial 2/22/2023 2/22/2023 02/22/2023
Misc
Informational
01/30/2023
Erosion control measures installed and functioning. 8/15/22 ES Erosion control measures installed, intact, and functioning. 8/22/22 ES Erosion control measures installed, intact, and functioning. 8/29/22 ES Erosion control measures installed, intact, and functioning. 9/6/22 ES Erosion control measures installed, intact, and functioning. 9/12/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event on 10/24, erosion control measures holding. Did have some residual silt make its way to the lake through newly constructed storm structures. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. Measures held up to rain even from 11/4, had conversation with crews about keeping mud off of existing roads. 11/7/22 ES Erosion control measures installed, intact, and functioning. With snow coming tonight/tomorrow did readdress issues with mud on roadways. 11/14/22 ES Erosion control measures installed, intact, and functioning. 11/21/22 ES 12-12-22 RH. Erosion control is up and in working order. 12-20-22 RH. Erosion control is up and in working order. 12-27-22 RH. Erosion control is up and in working order. 1-3-23 DP. Erosion control is up and in working order. 1-30-23 RH. Eroison contorl is up and in working order. 2-22-23 RH. Erosion Control is up and in working order.
Sanitary Sewer - Mandrel Partial 3/13/2023 3/13/2023 03/13/2023
Misc
Informational
02/21/2023
2-21-23 RH. Mandral was pulled through Exciting MH to MH A-1 Passed MH A-1 to MH A-2 Passed MH A-2 to MH A-3. Mandral got stuck going through. 3-13-23 PS Contractor working on flushing lines and doing test pull of MH A-2 to MH A-3. There is obstruction in line preventing pull
Sanitary Sewer - Mandrel Partial 03/31/2023
Misc
Informational
03/13/2023
2-21-23 RH. Mandral was pulled through Exciting MH to MH A-1 Passed MH A-1 to MH A-2 Passed MH A-2 to MH A-3. Mandral got stuck going through. 3-13-23 PS Contractor working on flushing lines and doing test pull of MH A-2 to MH A-3. There is obstruction in line preventing pull 3-31-23 RH. Contractor is flushing line today between MH A-2 to A-3. They will pull mandral after.
Sanitary Sewer - Mandrel Passed 4/4/2023 4/4/2023 04/04/2023
Misc
Informational
03/31/2023
2-21-23 RH. Mandral was pulled through Exciting MH to MH A-1 Passed MH A-1 to MH A-2 Passed MH A-2 to MH A-3. Mandral got stuck going through. 3-13-23 PS Contractor working on flushing lines and doing test pull of MH A-2 to MH A-3. There is obstruction in line preventing pull 3-31-23 RH. Contractor is flushing line today between MH A-2 to A-3. They will pull mandral after. 4-4-23 RH. Mandral passed through A-2 to A-3.
Install Street and Stop Signs Partial 6/7/2023 6/7/2023 06/07/2023
Misc
Informational
06/07/2023
6-7-23 DP. Streetwise is currently installing necessary signs
Sanitary Sewer - Camera Test Partial 6/21/2023 6/21/2023 06/21/2023
Misc
Informational
06/21/2023
6-21-23. Water is currently working on performing their camera inspection.
Sanitary Sewer - Camera Test Partial 6/23/2023 6/23/2023 06/23/2023
Misc
Informational
06/21/2023
6-21-23. Water is currently working on performing their camera inspection. 6-23-23 DP. Camera test had problem areas that need attention. Bair was already on site this morning fixing issues of Mastic in Manholes, grouting the cracked riser ring and squaring up steps in manholes. They will be fixing the required sags in the pipe. Ryan and I met the developer, Russel along with Lafe from Bair on site this morning to discuss different scenarios. Crew has dropped off sewer pipe on site in preparation for fixing required issues and i'll update plan of action once all scenario's are ironed out.
Install Street and Stop Signs Passed 9/1/2023 9/1/2023 09/01/2023
Misc
Informational
06/07/2023
6-7-23 DP. Streetwise is currently installing necessary signs 9-1-23 DP. Street signs have been installed and are accepted.
Sanitary - Material Verification Passed 09/01/2023
Misc
Informational
10/31/2022
Had 25 sticks of 8" zinc coated ductile iron pipe delivered from WinWater. This will be for the offsite sanitary line going under the spillway. 10/10/22 ES Have 8" SDR26 pipe and MH Structures for A-1 on site as well as butyl wrap and concrete riser rings. 10/31/22 ES
Sanitary Sewer - Camera Test Passed 9/1/2023 9/1/2023 09/01/2023
Misc
Informational
06/23/2023
6-21-23. Water is currently working on performing their camera inspection. 6-23-23 DP. Camera test had problem areas that need attention. Bair was already on site this morning fixing issues of Mastic in Manholes, grouting the cracked riser ring and squaring up steps in manholes. They will be fixing the required sags in the pipe. Ryan and I met the developer, Russel along with Lafe from Bair on site this morning to discuss different scenarios. Crew has dropped off sewer pipe on site in preparation for fixing required issues and i'll update plan of action once all scenario's are ironed out. 9-1-23 DP. Water signed off on all sewer. Passed.
Site Visit Complete 9/1/2023 9/1/2023 09/01/2023
Misc
Informational
10/19/2022
No work being done due to rain. 8/16/22 ES Bair Excavating had a skid steer with mulcher clearing out areas back into the woods for access to install sanitary line A. 8/24/22 ES Bair Excavating continued clearing brush and smaller treed areas to make access for sanitary sewer install. 8/25/22 ES CFS was onsite performing compaction testing between MH A-2 and A-3 and began working onto the onsite areas. 9/9/22 ES Schlagel onsite staking for water lines and verifying installed structure elevations. 10/18/22 ES
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home