Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Sanitary - Material Verification
|
Pending
|
|
|
|
Install Street and Stop Signs
|
Pending
|
|
|
|
Pavement-Aggregate Base
|
Pending
|
|
|
|
Pavement-Stabilized Subgrade
|
Pending
|
|
|
|
Punch List Inspection
|
Pending
|
|
|
|
Grading/Excavation/Fill Inspection
|
Pending
|
|
|
|
Pavement-Curb Construction
|
Pending
|
|
|
|
|
Misc
|
Pavement-Surface
|
Pending
|
|
|
|
|
Misc
|
Water Line - Construction Inspection
|
Pending
|
|
|
|
|
Misc
|
Water Line - Hydrostatic Test
|
Pending
|
|
|
|
Erosion Control Inspection
|
Pending
|
|
|
|
|
Misc
|
Water Line - Coliform Test 2
|
Pending
|
|
|
|
Grading/Excavation/Fill Inspection
|
Partial
|
|
|
05/01/2024
|
|
Misc
|
Sanitary Sewer - Mandrel
|
Passed
|
10/17/2024
|
10/17/2024
|
10/17/2024
|
|
Misc
|
Sanitary Sewer - Air Test
|
Passed
|
10/17/2024
|
10/17/2024
|
10/17/2024
|
|
Misc
|
Sanitary Sewer - Vacuum
|
Passed
|
9/17/2024
|
9/17/2024
|
10/17/2024
|
|
Misc
|
Pavement-Proof Roll
|
Passed
|
11/12/2024
|
11/12/2024
|
11/12/2024
|
|
Misc
|
Pavement-Surface
|
Partial
|
11/12/2024
|
11/12/2024
|
11/12/2024
|
|
Misc
|
Pavement-Curb Construction
|
Passed
|
10/28/2024
|
10/28/2024
|
12/04/2024
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Passed
|
7/25/2024
|
7/25/2024
|
12/04/2024
|
|
Misc
|
Storm Sewer Construction Inspection
|
Passed
|
7/29/2024
|
7/29/2024
|
12/04/2024
|
|
Misc
|
Water Line - Construction Inspection
|
Passed
|
12/5/2024
|
12/5/2024
|
12/09/2024
|
|
Misc
|
Water Line - Hydrostatic Test
|
Passed
|
1/2/2025
|
1/2/2025
|
01/02/2025
|
|
Misc
|
Water Line - Construction Inspection
|
Passed
|
1/17/2025
|
1/17/2025
|
01/22/2025
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
3/4/2025
|
3/4/2025
|
03/04/2025
|
|
Misc
|
Water Line - Coliform Test 1
|
Passed
|
3/13/2025
|
3/13/2025
|
03/13/2025
|
|
Misc
|
Water Line - Coliform Test 2
|
Partial
|
3/13/2025
|
3/13/2025
|
03/13/2025
|
|
Misc
|