Permit Application Status

PRSUBD20202616


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSUBD20202616
Public Infrastructure
Final Acceptance
CLAYTON PROPERTIES GROUP INC
DEVELOPMENT COMPLETE
OSAGE 1ST PLAT - M-150 & PRYOR ROAD IMPROVEMENTS
08/27/2020
09/17/2020
03/08/2024
Locations
Contacts
CLAYTON PROPERTIES GROUP INC, Address:120 SE 30TH ST  
EMERY SAPP AND SONS INC, Address:2301 I-70 DR NW, Phone:(573) 445-8331  
OSAGE HOMES ASSOCIATION INC, Address:120 SE 30TH ST  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 08/27/2020 08/27/2020
Dawn Bell
Fees
Paid Fees Amount Paid Owing Date Paid
9110068-Storm Sewer Inspection Fee $362.55 $362.55 Paid 09/08/2020
9110081-Paved Surface Inspection Fee $5,545.32 $5,545.32 Paid 09/08/2020
9110071-Site Grading Fee $2,205.44 $2,205.44 Paid 09/08/2020
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Storm Sewer Construction Inspection Partial 09/24/2020
Misc
Informational
09/24/2020
John DiMauro 9/24/2020 2:07 PM The ESS crew is installing the culvert crossing section of line. The crew currently has approx 40’ ft of the RCP pipe installed. Photos are uploaded.
Pavement-Proof Roll Failed 04/12/2021
Miscellaneous Correction
Informational
04/12/2021
Had pumping over the fire hydrant crossing . We are going to let it dry out and try later today. It was minimal pumping.
Pavement-Proof Roll Passed 04/13/2021
Miscellaneous Correction
Informational
04/12/2021
Had pumping over the fire hydrant crossing . We are going to let it dry out and try later today. It was minimal pumping.
PW-Misc
Informational
04/13/2021
Still was a little soft, contractors dug up soft area and let air out over night. Installed 4 “ extra of base asphalt over soft spot. We let it sit and for a coupl;e hours and then did another proof roll that was good.
Street - Wedge Lift Passed 04/14/2021
Misc
Informational
04/14/2021
Asphalt base was installed for pryor road. The asphalt wedge lift was also installed after cooling down to 140 degrees. this was done on 4/13. today the existing surface was milled out and is ready for 2" of surface asphalt to be installed in the morning when temperatures get to 50 degrees.
Street - Surface Course Partial 04/15/2021
Misc
Informational
04/15/2021
It is 10:06 and the truck says it is 51 degrees and my phone says 48.I am giiving seal o matic the okay to start surface paving at 10:30. The will be installing 2 “ of type 5-6 surface from a50 HWY to Napa Valley Dr on Pryor Rd. The tester will be oiut at 11 to take a sampkle behind the paver and take samples.
Street - Surface Course Partial 4/15/2021 04/15/2021
Misc
Informational
04/15/2021
It is 10:06 and the truck says it is 51 degrees and my phone says 48.I am giiving seal o matic the okay to start surface paving at 10:30. The will be installing 2 “ of type 5-6 surface from a50 HWY to Napa Valley Dr on Pryor Rd. The tester will be oiut at 11 to take a sampkle behind the paver and take samples.
Misc
Informational
04/15/2021
Finishing the last load for surface. The tester was out and has done the testing for the surface asphalt. I will make a final check in the morning.
Documents & Images
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide: