Permit Application Status

PRRES20252080


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20252080
Building Permit - Residential
Issued
NEW SINGLE FAMILY
NEW HOUSE - UNFINISHED BASEMENT - ROOF TRUSSES - COVERED PATIO STOP WORK ORDER generated on 07/24/2025 12:00 AM by username 'Mitchell Schwarz'. STOP WORK ORDER removed on 08/13/2025 12:00 AM by username 'Mitchell Schwarz'.
05/19/2025
05/22/2025
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
Summit Homes, Address:120 SE 30th St, Phone:(816) 434-5074 Ext:320  
BRUCER@SUMMITHOMESKC.COM  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Development Fee $2,285.00 $2,285.00 Paid 05/22/2025
Right of Way Permit Fee $85.00 $85.00 Paid 05/22/2025
Residential Excise Tax Fee $1,022.72 $1,022.72 Paid 05/22/2025
Water Tap Fee $3,973.00 $3,973.00 Paid 05/22/2025
Water Meter Fee $748.03 $748.03 Paid 05/22/2025
Valuation Fee New Single Family $1,321.42 $1,321.42 Paid 05/22/2025
Outstanding Fees Amount Paid Owing Date Paid
Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid


$75.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Driveway Inspection Pending
Plot Plan Inspection Pending
Occupancy Inspection - Codes Residential Pending
Erosion Control Inspection Residential Pending
Footing Inspection - Residential Passed 6/16/2025 6/16/2025 06/16/2025
Sewer Service Inspection - R Passed 6/16/2025 6/16/2025 06/16/2025
Water Service Inspection - R Passed 6/17/2025 6/17/2025 06/17/2025
Underslab Plumbing Inspection - Residential Passed 6/18/2025 6/18/2025 06/18/2025
Erosion Control Inspection Residential Failed 7/21/2025 7/21/2025 07/21/2025
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
07/21/2025
07/21/25 Jamie S, Erosion control needs to be established. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Erosion Control Inspection Residential Failed - Stop Work 7/24/2025 7/24/2025 07/24/2025
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
07/21/2025
07/21/25 Jamie S, Erosion control needs to be established. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
07/24/2025
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. EROSION CONTROL STILL NOT IN COMPLIANCE. SILT FENCE DOWN IN MULTIPLE AREAS. MAINTAIN OVERGROWN VEGETATION STOP WORK ISSUED -
Erosion Control Inspection Residential Partial 8/13/2025 8/13/2025 08/13/2025
DCM3 ESC REQUIRED 2 DAY
Resolved
08/13/2025
07/21/25 Jamie S, Erosion control needs to be established. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
DCM2 ESC DEFICIENT INSTALLATION
Resolved
08/13/2025
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. EROSION CONTROL STILL NOT IN COMPLIANCE. SILT FENCE DOWN IN MULTIPLE AREAS. MAINTAIN OVERGROWN VEGETATION STOP WORK ISSUED -
Electrical Service Inspection Failed 8/15/2025 8/15/2025 08/15/2025
Misc
Corrective Action Required
08/15/2025
Provide approved connection for ufer ground connections -install bonding screw at panel main disconnect
Gas Service Inspection - Residential Not Ready 8/15/2025 8/15/2025 08/15/2025
Misc
Corrective Action Required
08/15/2025
-Ufer bonding clamp at ufer not approved. -no gauge for pressure test
G2417.4.1 Test Pressure
Corrective Action Required
08/15/2025
INSPECTION, TESTING AND PURGING. AMENDED 7-945. The test pressure to be used shall be not less than one and one-half times the proposed maximum working pressure, but not less than 10 psig (68.9kPa) irrespective of design pressure. For welded piping, and for piping carrying gas at pressures in excess of fourteen (14) inches water column pressure, the test pressure shall not be less than 60 psig. Where the test pressure exceeds 125 psig (862 kPa gauge), the test pressure shall not exceed a value that produces a hoop stress in the piping greater than 50 percent of the specified minimum yield strength of the pipe.
All Rough Inspection - Residential Failed 8/15/2025 8/15/2025 08/15/2025
Miscellaneous Correction
Corrective Action Required
08/15/2025
-strap top plate where lapped less than 24” E garage wall -fire block kitchen/stairwell wall in furr down -maximum 2 NM through each top plate penetration. See pwdr room. Check throughout -fire block pdwr room wall to garage wall furr down -rear walls not framed to cspf specifications -uncover covered front porch -protect dryer vent at top plate. Protection shall extend 2” bellow top plate -solid block sheathing breaks where sheathing does not extend to top plate throughout 2nd floor(nail according at exterior and to top plate) -proving blocking under kitchen island -plans call for (3) 2x6 at rear basement under beam each side -use approved connector for ufer ground connections -install bonding screw at main disconnect -no pressure at gas line
Electrical Service Inspection Passed 8/25/2025 8/25/2025 08/25/2025
Misc
Corrective Action Required
08/15/2025
Provide approved connection for ufer ground connections -install bonding screw at panel main disconnect
Gas Service Inspection - Residential Passed 8/25/2025 8/25/2025 08/25/2025
Misc
Resolved
08/25/2025
-Ufer bonding clamp at ufer not approved. -no gauge for pressure test
G2417.4.1 Test Pressure
Resolved
08/25/2025
INSPECTION, TESTING AND PURGING. AMENDED 7-945. The test pressure to be used shall be not less than one and one-half times the proposed maximum working pressure, but not less than 10 psig (68.9kPa) irrespective of design pressure. For welded piping, and for piping carrying gas at pressures in excess of fourteen (14) inches water column pressure, the test pressure shall not be less than 60 psig. Where the test pressure exceeds 125 psig (862 kPa gauge), the test pressure shall not exceed a value that produces a hoop stress in the piping greater than 50 percent of the specified minimum yield strength of the pipe.
All Rough Inspection - Residential Passed 8/25/2025 8/25/2025 08/25/2025
Miscellaneous Correction
Resolved
08/25/2025
-strap top plate where lapped less than 24” E garage wall -fire block kitchen/stairwell wall in furr down -maximum 2 NM through each top plate penetration. See pwdr room. Check throughout -fire block pdwr room wall to garage wall furr down -rear walls not framed to cspf specifications -uncover covered front porch -protect dryer vent at top plate. Protection shall extend 2” bellow top plate -solid block sheathing breaks where sheathing does not extend to top plate throughout 2nd floor(nail according at exterior and to top plate) -proving blocking under kitchen island -plans call for (3) 2x6 at rear basement under beam each side -use approved connector for ufer ground connections -install bonding screw at main disconnect -no pressure at gas line
Documents & Images
Date Uploaded File Type Document Name
05/19/2025 BY #1340 - PERMIT APP
05/20/2025 Approved Plans APPROVED PLANS
05/20/2025 Plot Plan APPROVED PLOT PLAN
05/20/2025 Approved Plans APPROVED TRUSS LAYOUT
05/20/2025 Approved Plans APPROVED TRUSS PACKET
05/22/2025 Permit Codes Residential Plan Review
05/22/2025 Permit DS Building Permit
05/22/2025 Receipt Receipt for transaction:2025-003708
06/12/2025 M L Crose 1221 SE Cronin St LSMO Footing Inspection Report Page 1 of 2
06/12/2025 M L Crose 1221 SE Cronin St LSMO Footing Inspection Report Page 2 of 2
06/16/2025 Letter INSPECTION SUMMARY
06/16/2025 Letter INSPECTION SUMMARY
06/17/2025 Letter INSPECTION SUMMARY
06/18/2025 Letter INSPECTION SUMMARY
07/21/2025 Letter INSPECTION SUMMARY
07/24/2025 Letter Stop Work Order
08/13/2025 Letter INSPECTION SUMMARY
08/15/2025 Letter INSPECTION SUMMARY
08/15/2025 Letter INSPECTION SUMMARY
08/15/2025 Letter INSPECTION SUMMARY
08/25/2025 Letter INSPECTION SUMMARY
08/25/2025 Letter INSPECTION SUMMARY
08/25/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.